Handbook Amie
Handbook Amie
2006-07
Managing Director
Dakshin Haryana bijli Vitran Nigam
Vidyut Sadan, Vidyut Nagar, Hisar
1
TABLE OF CONTENTS
Sl. particulars Page
No. No.
i Introduction 3
x Directory of officers 59
xi Remuneration Details 68
2
Chapter -1
Introduction
3
Chapter –2 (Manual-1)
Particulars of Organisation,
Functions and duties
4
circles Gurgaon, Hisar and Narnaul include two districts each i.e.
Hisar and Fatehabad, Gurgaon and Mewat and Mahendragarh
and Rewari respectively.
The Dakshin Haryana Bijli Vitran Nigam Ltd. has
been constituted as a company under the provisions of the
Companies Act- 1956 in public sector and is a Government
Company within the meaning of Companies Act, 1956. It was
given license for power distribution in nine districts of Southern
part of Haryana on 04-11-2004.
The Nigam supplies power to its over 18.25 lac
consumers of different categories through distribution network of
130 substations of 33 KV level, about 1600 feeders of 11 KV
level and 68700 distribution transformers of different levels.
The jurisdiction of the Nigam is sprawled over an
area of 24208 square kilometres having geographical variations
from water logged plane areas to undulating sand dunes of the
Thar Desert. The area of sand dunes is a single crop area while
in plane areas farmers take two to three crops in a year including
water-guzzling crops like rice and wheat. Irrigation of crops is
largely dependent on electricity run tube wells. The region has a
density of eight electricity run tubewells per square kilometre
area. The Nigam serves 1.20 crore population of 3,348 villages.
The DHBVN is endeavouring to improve the quantity and quality of
power supply to its consumers. During the financial year 1999-2000 (the year of
creation of the DHBVN), only 63,308 lakh units (LU) of energy was available for
the area now comprising the DHBVN which increased to 95,900 LU during the
year 2005-2006. The consumption grew at an average annual rate of about 11
percent since the year 1999-2000 which contributed to progress of the State and
increased revenue in flows. The falling trend of industrial consumption recorded
in the earlier years has reversed. The agriculture sector in its area could pierce
5
through a medley of adverse factors, like failure of Monsoons, only because of
sufficient and qualitative power.
Revenue has shown a remarkable upward trend during the period
2000 -2001 to 2005-2006 and has increased by over 72 per cent. The revenue
(The amount of bills raised), which was Rs.1340 crores during the year 2000 -
2001, has increased to about Rs 2400 crores during 2005-06. The annual
Percentage increase in revenue assessed has been about 14.5 per cent as
compared to 1999-2000.
The Faridabad Operation Circle is probably the first Operation
Circle in India that came in profit.
Various schemes were launched for improving consumer metering,
billing and collections. Simultaneously, for improving the customer satisfaction,
many facilities have been given to the consumers like bill collection through
commercial banks, post offices and mobile cash collection vans, distribution of
bills through courier system in towns and through village Chowkidar and ex-
servicemen in Villages, resolution of customer billing disputes and complaints.
Bijli Suvidha Kendras (BSK) have been set at all district head quarters in
first phase, which works like call centres for redressal of complaints of
consumers relating to power supply round the clock. It is planned to extend the
BSK facility in other towns in second phase and to all villages in third phase.
Customer Care Centres are also being set up at all operation circle offices. A
Customer Care Centre is already operational in the Vidyut Sadan at Hisar.
6
ELECTRICITY BILL ARREARS WAIVER SCHEME
The Government of Haryana took a historic and courageous decision on
June 16 last to waive off arrears of electricity bills of domestic and agriculture
consumers in rural areas. In the area of DHBVN, the response of consumers
to the scheme has been enthusiastic. About 3.25 lac defaulter consumers
have already started paying their current electricity bills taking the benefit of
the scheme.
Later, the DHBVN extended the benefits of electricity bill waiver
scheme to Panchayat tubewells, village community centres and Chaupals
also as these consumers are being given power supply under domestic
supply category. Since the scheme is meant for rural domestic and
agriculture consumers and these consumers are under domestic category of
consumers they become entitled for benefits of the bill waiver scheme.
The facility of reconnection of permanent disconnected tubewell and
domestic connections in rural area is also made available upto March 31,
2005 under the bills waiver scheme. Under the scheme, permanently
disconnected domestic and agricultural consumers of rural area, who were
defaulters as on June 16, 2005, can apply for reconnection by depositing
consumption security (CS), meter cost and reconnection fees. They will not be
charged minimum monthly charges for the period of disconnection prior to
June 16. In case a consumer desires, he will be allowed to pay cost of meter
in ten installments.
In case of tubewell connections, the fee of reconnection has also been
reduced drastically. A fee of only Rs.1000/- for disconnected consumer for
less than six months period and only Rs.2000/- where the period of
disconnection is more than 6 months will be charged. Where the High
Tension/Low Tension (HT/LT) lines are required to be erected, the
reconnection shall be allowed by charging only 50 per cent of the cost of
erection of the lines. Rest of the 50 per cent of the cost would be borne by the
7
DHBVN. The cost of augmentation of transformer or installation of new
transformer would be borne by the DHBVN.
NEW CONNECTIONS
Special efforts were made to accelerate the pace of releasing new
connections. The plan of setting up Consumer Care Centre would facilitate
consumers to get connection with out delay. A scheme was launched to give
domestic and non-domestic connections on spot by holding camps in selected
villages. Aim of this scheme is to dissuade the people of using electricity
through illegal kundi connections and to provide a regular electricity
connection to villagers without any delay and fatigue. New domestic and non-
domestic connections in the area of the DHBVN are being released within 15
days period. Special efforts have been made to accelerate the pace of
releasing agriculture connections. Where the number of pending connections
is high, the work is being got done on turnkey basis.
Label2
Label1
24 HOUR POWER SUPPLY TO VILLAGES
The DHBVN has decided to give 24 hour power supply, on urban mode,
to those villages and settlements in town areas which have 33 KV substations
located within their boundary or which fall within two kilometre area from the
substation of 33 KV or above level. However, entire cost of erection of feeder,
8
including the cost of terminal equipment at the substation, will be borne by the
Panchayats or the consumers.
Such villages or towns would be given the facility of power supply from
urban feeders if 90 per cent or more consumers are paying their electricity
bills.
It is planned to segregate the feeders supplying power to rural areas
from the feeders supplying power to urban areas so as to give reliable power
supply to rural areas.
9
STRENGTHENING DISTRIBUTION SYSTEM
The Nigam realized that excessive length and over loading of 11 KV
feeders are the major reasons of low voltage and interruptions in power
supply. To over come the problem and to give uninterrupted power supply at
proper voltage up to tail of electricity feeders, the DHBVN rehabilitated 242
feeders of 11 KV level by dividing each feeder into 2 or 3 feeders and
renovating complete system. These feeders have been divided into 556
feeders of proper load and length.
Rehabilitation of 35 feeders of 11 KV level, augmentation of conductor of
80 feeders and erection of 123 new 11 KV feeders are planned to be
completed in near future, thus, strengthening the distribution system to a
considerable level which would be sufficient even to meet the demand to be
increased in near future also.
Complete power distribution system in a number of towns is being
renovated under different schemes so as to increase the reliability of power
supply. To make power supply system interruptions free, the DHBVN set up
15000 power distribution transformers of different capacities and augmented
the capacity of 291 existing pole mounting substations during last over six
years. The Nigam plans to install about 4200 new distribution transformers in
the system and replace 1500 existing transformers of lower capacity with
those of higher capacity. Electricity distribution lines of a length of over 1600
kilometres are under construction.
To strengthen power distribution system in rural area to give
electricity connections in all house holds in villages, including hamlets, and to
provide free connections to rural people living below poverty line, the DHBVN
have sent a number of schemes for each district worth about Rs.100 crores to
the Government of India for approval under the Rajiv Gandhi Gramin
Vidyutikaran Yojna. The schemes of an amount of Rs. 29 crores for the
districts of Sirsa and Bhiwani have already been sanctioned by the
Government of India.
10
Operation Innovations- Distribution Action Plan
The Nigam aims to develop into an efficient and successful electricity
distribution company by introducing innovative new technologies, adopting
efficient process and systems, emulating best practices in the sector and
providing best services/added value to its consumers.
The current distribution network is a legacy of the past. There have been
several innovations and new practices in the utility business, which has
helped improve operational performance and provide quality supply of
electricity to the consumers. It is the endeavor of the power distribution
corporation to adopt best practices in the sector.
The Nigam would adopt a bottom up planning process to identify
requirements for renovation & modernization (R&M) and addition of new
capacity in the network. The key initiatives to improve the operational
performance and service parameters for quality and reliable supply of
electricity are discussed below:-
Modernization of Low Tension Distribution System (LTDS): The LTDS
has many shortcomings like high technical loss, voltage drop due to
inadequate maintenance, system overloading /load unbalancing etc. The
present network of the company is primarily based on LTDS (over 60 %).
Therefore, to improve the efficiency in addition to LTDS modernization
program; preventive & scheduled maintenance, maintenance of safety
and earthing system, maintenance of distribution transformers, provision
of adequate breakers and fuses etc. shall be undertaken on priority basis.
11
Introduction of High Voltage Distribution System
It is a policy of the DHBVN to increase High Tension portion of the
distribution system as it has lower technical losses compared to the Low
Tension system. (HVDS): HVDS has a lower technical loss than LTDS.
Also it reduces the non-technical losses by preventing unauthorized use of
electricity. The Nigam plans to introduce HVDS, to reduce AT&C losses
especially in areas with high losses. HVDS would also ensure accurate
and universal metering of all connected consumers.
Demand Side Management (DSM): With increasing load, inadequate
generation capacity addition and higher peak load requirement, DSM has
become an urgent necessity for utilities. The key objective of the DSM is
to manage the load in such a way that the load curve is flattened.
Successful implementation of DSM would require detailed understanding
of the load curve (intra day and seasonal) of the Nigam and thereafter
introduction of tactical and strategic measures to provide incentives to
consumers for shifting/reducing load from peak load to base load.
The Nigam plans to introduce Time of Day (ToD) tariff and meters to all
possible categories, whereby industrial High Tension (HT) & Low Tension
(LT) consumers, large commercial & large residential consumers would be
assessed on ToD basis over the next few years. The Nigam also plans to
segregate agricultural feeders to assist in shifting of agricultural load to off
peak time and promote energy efficiency measures like the usage of
capacitors amongst agricultural consumers. For effective DSM in the
agricultural areas, switchable capacitors and single-phase transformer
system are being planned.
12
In addition to the above technical measures, public awareness program
shall be initiated to promote energy efficient appliances like chloro fluro
lamps, especially in public street lightings. Different means of publicity are
being used to create awareness for energy efficiency. It is planned to
introduce prepaid metering system to motivate consumers to conserve
electricity
13
Duties of the DHBVN
14
15. Electrification of hamlets and to provide free electricity connections to the
people living below poverty line under Rajiv Gandhi Gramin Vidyutikaran
Yojna.
16. To give free connections to poor and down trodden under Kutir Jyoti
Programme to achieve the target of 20 point programme.
15
ORGANISATIONAL STRUCTURE OF DHBVNL
Chairperson
Managing Director
DGM - IT/MIS & Monitoring Vigilance & Security
MGR - IT/MIS
Xen - Operations Monitoring Company Secretary
.
Chief Accounts Officer Medical Officer
16
CE - Planning, Design &
Construction
Financial Advisor
17
Office of Chairman
The Office of the Managing Director, DHBVN is located in Nigam’s head office
Vidyut Sadan, Vidyut Nagar at Hisar. Personal staff of the MD includes a Sr. Private
Secretary, a private assistant and a clerk. While, Dy. General Manager (IT), Company
Secretary, Manager (Monitoring) report directly to the Managing Director. The MD is
assisted by three whole time directors viz. Director (Operations), Director (Projects), and
Director (Commercial), Finance and Regulatory Affairs) and General Manager (HR and
Admn.).
Director (Projects): His office is located in Vidyut Sadan, Vidyut Nagar, Hisar. He
generally controls Planning, design and construction works in addition to material
management. He is assisted by two Chief Engineers, each for Material Management
and Planning, Design and Construction and four Superintending Engineers.
Director (Commercial, Finance and Regulatory Affair) : His office is located in Shakti
Bhawan at Panchkula and generally looks after the finance related issues of all the
Haryana Power Utilities.
Director (Operations): His office is located in Vidyut Sadan, Vidyut Nagar, Hisar. He
controls his organisation through Chief Engineer, Operation Zone- Hisar, Chief
Engineer, Operation Zone- Delhi, Superintending Engineer, Metering and Protection
and Superintending Engineer system Operations and Energy Audit.
The Operation Zone Hisar comprises of three operation Circles namely
Operation Circle Sirsa, Operation Circle Hisar and Operation Circle Bhiwani. The
Operation Zone Delhi comprises of Operation Circle Narnaul, Operation Circle Gurgaon
and Operation Circle Faridabad. Each operation circle is headed by a Superintending
Engineer.
18
DHBVN VISION
It is a right time for Haryana to further accelerate the pace of economic growth to become
number-I state of India. The growth graph can rise only upon the foundations that the
infrastructure sector, particularly the power sector, can and must provide.
To give a strong base to the agricultural, industrial and economic growth of Haryana, the
Dakshin Haryana Bijli Vitran Nigam (DHBVN) is committed to set new benchmarks in
standards of corporate performance through the pursuit of operational and financial excellence. It
aspires to be the best distribution company in India by enhancing its technological leadership and
consumer satisfaction. Nevertheless, to provide quality electricity-supply-service to consumers in
most effective and efficient manner at reasonable tariff through continuous innovations is
considered to be the strongest factor of consumer satisfaction. The DHBVN has also to uphold
the guiding principle of trust, integrity and transparency in all aspects of interactions and
dealings. Sound financial health also finds prominent place on its agenda.
Focus on:
19
• Cent per cent metering, including metering of tubewell connections.
• Shifting of meters to out side consumers’ premises.
• Abating theft/pilferage and misuse of electricity with the involvement of public.
• Stringent punitive action against unscrupulous people committing theft of power.
Focus on:
Focus on:-
20
Focus on:-
Focus on:-
• Evolving participatory management to enable workers and managers discuss vital issues
together and work hand in hand towards common goals.
• Persistent drive for increase in revenue and reduction in costs.
• To encourage ideas, talent and value system.
• To train manpower for upgradation of knowledge.
• To promote a work culture that fosters individual growth, team spirit and creativity to
overcome challenges and attain goals.
• Circles to act as profit centres; buy the power they require, pay for it and meet their
expanses through their own income.
Focus on:
• Bijli Suvidha Kendras (Call Centres) having connected rural areas also.
• Web based availability of each and every information (Information publishing).
• Information facilitation counters/ consumer helpline centres at sub-divisional level.
• Web based database publishing.
• Development of IT within the organisation.
• Lesser paper office.
• Connectivity of workforce to Internet and encouraging usage of I.T. tools right down to
their home level also.
• E-billing and on line payment, ATM type cash collection centres.
21
• Providing means of communication of latest technology to maximum number of
employees.
• E – tendering.
• Net work mapping.
• Data logging.
• Remote meter reading.
• Electricity distribution automation.
DHBVN VALUES :
The DHBVN and its employees affirm and commit themselves to dedication to duty, integrity
and honesty, transparency in work, cost consciousness, openness to suggestions and feedback
from all stake holders and consumers. We are connected to consumers by more than electricity
lines and believe in leading by example in consumer satisfaction. We are proud being creators of
base for over all development of Haryana and India.
22
Chapter-3 (Manual-2)
Powers:
Managing Director, Chief Engineers, Superintending Engineers,
Executive Engineers, Assistant Executive Engineers, Assistant
Engineers, Chief Accounts Officers, Chief Auditor, Financial Advisers
etc. have been delegated powers for carrying different works and a
book titled ‘Delegation of Powers’ containing all detailed information
in this regard has been published separately. In addition, Haryana &
Punjab PWD(B&R) specifications , Haryana Schedule of Rates and
Indian Standards Codes are also used in carrying out a number of
works.
2 Manuals for general terms and conditions for civil, mechanical,
electrical works: This Book contains rules, regulations, terms &
conditions for carrying the different civil works, mechanical works and
electrical works and for awarding contract for different works like
construction of buildings, roads, substations, transmission and
distribution lines etc. A Book has been published separately.
3. Purchase Manual : In the purchase regulations, N.I.T., floating for
purchase of different material for D.H.B.V.N. , its officers have been
given different powers, details of which is given in purchase
regulations. The manual is published separately.
23
4. Store Manual: The material purchased by DHBVN such as
transformers, meters, conductor, oil, capacitors, breakers, panels etc. is
receiving in its stores and, through stores, it is sent to respective offices.
Unusable or obsolete material/equipment is returned by the field offices
to the store. The store authority completes process of auction of such
material and equipments. To regulate these activities, the powers and
duties of officers have been given in this regulation book which has
been published separately.
5. Sales Manual :- This book contains sales circulars, pertaining to rules,
regulations, terms & conditions on power tariff and other charges,
release of new connections, acceptance of load, load rating, meter
reading, bill preparations, bill collections, power theft cases,
installation of maintenance of metering equipments, revenue matters,
and different schemes on consumer motivation. A book has been
published separately.
Duties of Officers
The Dakshin Haryana Bijli Vitran Nigam is managed by Board of
Directors appointed by the Government of Haryana. The present
composition of Board of Directors is as follows:-
1. Lt. Gen.(Retd.) Onkar S. Lohchab- Chairman
2. Sh.Vijayendra Kumar, IAS - Managing Director
3. Sh.P.K.Dass, IAS Director
4 Smt.Jyoti Arora, IAS - Director
5 Sh.M.K.Sharma - Director
6. Sh. R. K. Goel Director
Managing Director :
The Managing Director is vested with the powers of managing over all
affairs of Dakshin Haryana Bijli Vitran Nigam under the
superintendence and control of Board of Directors.
24
He fixes targets for different officers and offices and analyses their
performance. The Managing Director keeps liaison with the State
Government, Haryana Regulatory Electricity Commission, other
Haryana Power Utilities, World Bank, Power Financial Corporation,
Rural Electrification Corporation etc.
Director/Operation
Besides his contribution in decision making by participating in the
meetings of Board of Directors and Whole Time Directors, the
Director/Op. looks after the work of electricity supply in the area of
D.H.B.V.N.
He also looks after the work of issuing Sales Circulars and instructions
on different aspects of power distribution and instructions relating to
dispatch of material and bifurcation and trifurcation of electricity
feeders. The Director/Op. Coordinate with the Power Utilities from
whom the DHBVN purchase the electricity.
Director/Projects
In addition to his contribution in decision making and policy
formulation by participating in the meetings of Board of Directors and
Whole Time Directors, the Director/Projects looks after the work of
Planning , expansion and augmentation of power transformers,
distribution transformers, designing work and construction of Planning
& Design system.
He also looks after the work of Planning and Maintenance of 33KV
substations release of HT Tubewell connections on Turn Key Basis,
and Planning and execution of any new scheme. Besides this, he looks
after the important work of Material Management also.
25
Chief Engineer/Material Management
1. Chief Engineer/M.M. is holding the charge of material management of
the D.H.B.V.N.
2. He prepares the annual requirement of different type of material
required in new construction, maintenance of all installations and day-
do-day operation of power supply.
3. He purchases material and distributes in field offices through stores as
per their requirement and availability of material.
4. He is assisted by the offices of Two Superintending Engineers/MM and
Controller of Stores.
Chief Engineer/PD&C:
1. Chief Engineer/PD&C pay head to the work of planning, designing and
construction of power transmission and distribution system.
2. He prepares annual plans for the construction and augmentation of
33KV substations their feeding lines, construction and rehabilitation of
11KV feeders and setting up of additional distribution transformers.
3. He prepares the plans and schemes under different Projects of Central
Government Projects like Accelerated Power Development and
Reforms Program, Rajiv Gandhi Vidyutikaran Yojna, NABARD
Project, National Capital Rigion Development Project, World Bank
Projects, Rural Electrification Corporation Projects, etc.
4. He prepares annual outlay for development activities.
5 He carries the construction works of 33 KV substations, augmentation
of 33 KV substations, erection of 33 KV and 11 KV new lines and
bifurcation of 11 KV existing feeders.
6. He is assisted in his work by Superintending Engineer/Const,
Superintending Engineer/Planning and S.E./Design.
General Manager/Commercial:
26
1. The G.M./Comml. looks after the work of commercial performance of
DHBVN.
2. He prepares Sales Circulars and instructions on different aspects of
operation of electricity supply.
3. He prepares Annual Revenue Report of D.H.B.V.N. for submitting to
Haryana Electricity Regulatory Commission.
4. He also supervises the work of system operation all over the area of
DHBVN and issue power supply regulatory measures in consultation
with the Haryana Power Generation Corporation, the Haryana Vidyut
Prasaran Nigam, the Bhakra Beas Management Board the Haryana
Power Grid Corporation of India Ltd., etc.
General Manager/HR&Admn
1 Financial scrutiny of property returns up to the ranks of S.E.
2 Different administrative matters, including pension, GPF, sanction of
leave, Leave encashment, No Demand Certificates, retention of
residence, etc. of class-II and class - I officers.
3 Change of cadre of non-gazetted staff.
Superintending Engineer/Admn.
1. Human Resources development.
2. Promotion, transfers, posting, leave and preparation of seniority list of
all officers and ministerial staff of H.O Cadre.
3. Disciplinary action including framing and disposing off of the charge
sheets against the officers and employees of DHBVN.
4. Issuance of administrative orders.
5. Recruitment of officers and officials and formation of Recruitment
policies.
27
6 Acceptance of claims/Pension and gratuity etc. against Ex-gratia /
Compassionate and Retirement.
7. Work relating to Industrial relations and cases pending in Labour
Courts.
8. Monitoring and defending of court cases in all civil courts and
Consumer Protection Forums.
9. To maintenance public relations for the DHBVN by way of two way
persuasive communication through all possible means of
communications.
10 Publication of all type of advertisements of DHBVN including Tender
notices, public notices and display advertisements.
11. Publicity for the DHBVN through exhibitions and hoardings.
12 Organisation of Seminars and Field functions.
13. Maintenance of Vidyut Sadan the Head Office of DHBVN and Vidyut
Nagar Residential Colony.
14. Welfare activities for employees like entertainment, Sports and Medical
facilities.
15. Training to employee.
16. Industrial relations, Unions
17. Staff /employee grievances resolutions.
18. Staff Set up.
19. Grant of medical claims, Higher grades & increments.
20. Court cases related to service matters.
21 Maintenance of Vehicles of DHBVN.
22
Manager/PR
1 To create a favourable opinion by highlighting achievements.
2 To inform consumers or public through press releases, announcements
and advertisements on planned shut downs/outages/ low frequency.
3 To educate public on conservation of electricity, safe use of electricity,
optimum/rational use of electricity.
28
4 Liaison with media.
5 To organise seminars, radio talks, press conferences, TV programmes,
exhibitions, etc.
6 To bring out PR publications.
7 To cover field ceremonial programmes and publicity thereof.
8 To cover and organise Bijli Sabhas for redressal of complaints.
9 Feedback to the management and concerned organisation.
10 Value added service.
11 To issue rebuttals, clarifications on doubts and countering rumours.
12 Publicity of different schemes of the DHBVN.
13 Anti-theft advocacy.
14 Involvement of community leaders and other stakeholders in Nigam's
affairs, particularly for sending message to public.
15 Publication of all types of advertisements of the DHBVN, including
NITs, Public Notices, Auction Notices and publicity oriented display
advertisements and to handle bills thereof and payment.
16 Internal communication.
17 Entertainment activities and cultural programmes.
Financial Adviser/HQ
1. Raising of long term finance and working capital finance from
Financial Institutions and Banks.
2. Daily cash management, Fund transfer and monitoring of revenue.
3. Budget and Planning- Annual Budget, Business Plan, Five Year Plan,
CAPEX, ARR etc.
4. Financial concurrence on proposals and functions relating to Materials
Management.
5. Setting & monitoring monthly targets of revenue collection and review
of MS reports relating to revenue matters- Assessment, CGL &
Arrears.
29
6. Monitoring of Bill collecting Agencies.
7. Bank reconciliation & IBA reconciliation for revenue collection &
remittances from field offices.
8.
Chief Accounts Officer
1. Maintenance & finalization of Accounts.
2. Advising field staff on accounting policies and procedures.
3. Insurance matters.
4. Subsidy claims and information to Govt./DHBVN.
5. Maintenance of Cash & Bank Book and payment to suppliers
/contractors, repayment to Finance Institutions, staff related liabilities
and other expenditure payments including statutory payments.
6. Processing & Passing of invoices of suppliers/contractors for A/T
Work Order placed by corporate Office and maintenance of registers &
Suspense Accounts.
7. Accounting & Reconciliation of power purchase bills, Energy
Accounting & review of T& D Loss.
8. Submitting claims to DHBVN/Govt. for various subsidies like
Agriculture, Water Works, Nagar Palika etc.
9. Income Tax: Tax Audit, TDS, filling return of income, Assessment,
Appeal, Fringe benefit tax and tax planning.
10. Compliance of various provisions of Sales Tax Act and Rules including
Professional Tax, Service Tax etc.
11. Corporate Taxation – Income Tax, Sales Tax, Service Tax, Professional
Tax.
12 Disbursement of pay and allowances of all officers and non-gazetted
establishment of Head Office.
13 Finalization of pension cases of all the retired employees of the
DHBVN.
14 Monitoring of Material at Site Accounts.
15 Management of trusts for pension and GPF.
30
16 Controls the cadre of sectional officers, divisional accountants/revenue
accountants.
Chief Auditor
1. Chief Auditor is the Head of Internal Audit such as Revenue Audit and
Works Audit which covers audit of expenditure and payments.
2. To follow up various Audit Reports prepared by R.A.O. and A.G.
Office on the functioning of various field as well as Head Offices.
3. To provide all necessary information to the Government on matters
relating to meetings of the Committee on Public Undertakings (COPU).
4. To monitor and direct several audit parties spread
5. Pre-audit of payment, purchase/works orders and Trial Balance
6 Ensuring implementation of overall policy of the Company relating to
procedural aspect and internal control procedures.
7. Internal Audit, Statutory audit, CAG Audit, PUC matters and PAC
reports.
8. Advising field staff of internal audit procedure.
9. To control the functions of the establishment section dealing in
sanctioning of E.L., GPF Advance etc. and extension of field cadre
UDCs working in Audit Parties.
31
Company Secretary: He is reporting to the Managing Director of the
Nigam and looking after the following activities:-
1. Convening Board Meetings & taking follow up action on the decision
taken.
2. Convening Shareholders' Meetings.
3. Convening Meetings of Whole Time Directors, Audit, & Bijli Suvidha
Kendra Committee Meetings.
4. Compliance of all statutory requirements under the companies Act,
1956.
5. Setting up of Bijli Suvidha Kendras (BSK).
6. Monitoring of Announcements made by Chief Minister of Haryana.
7. Other Projects relating to Regulatory Performance Management
Consumer Billing, I.T. Meter Readings, Bill Distribution, etc.
whenever required.
32
Superintending Engineer/Metering & Protection
1. Periodical testing of CT operated LT connections and CVT PT
operated HT connections.
2. Besides, periodical checking, of all the 33KV substations including
working of feeder meters.
3. Pre-commissioning and commissioning of new 33KV substation as
well as testing of power transformers in case of augmentation or
replacement of damaged power transformers.
4. To attend the fault of Industries having CTPT operated meters.
5. To attend emergency break down in respect of 33KV substations.
6 In addition to above, since for the last four months, the target of
detection of theft of electricity has been fixed for the M&P
organization.
33
3. The Chief Engineer/Op. Office receives annual plans, plans for
expansion of transmission and distribution system, augmentation of the
system and maintenance of the system.
4. Annual requirements of funds and material sent by the field office to
the Head Office also route through the office of C.E./Op.
5. Chief Engineer/Op. Hisar is the cadre controlling authority of all
technical employees upto the rank of Junior Engineer-I, hence looks
after the work of promotion, posting and transfer, leave, charge-sheets,
enquiry and punishments etc.
34
4. New Distribution network.
5. Rural Electrification schemes.
6. Loss reduction measures.
7. Installation checking.
8. Work contracts.
9. Procurement of decentralized items.,
10. Project Planning and monitoring etc.
11. HR and Establishment activities.
12. Arrangement of funds as per annual requirement of field offices.
13. Preparing annual budget and annual requirement of material for their
circles.
14. Holding Bijli Sabha to listen and redress the complaint of the
consumers.
15. Sanctioning new connections and load extension from ___ KW upto
____ KW in respect of all category of consumers.
16 Administrative and technical sanction for maintenance of distribution
system upto 11KV level.
17 Participating in Operation Review Meeting at different levels and is
responsible for making coordination between the field offices and the
Head Office.
18 Coordinating between the district administration and DHBVNL field
offices.
19 To check power theft and unscrupulous activities.
35
3. Monitoring regular power supply within the jurisdiction of their
respective operation division.
4. Checking power theft and unscrupulous activities.
5. Loss reduction measures.
6. Procurement of decentralized items.
7. Revenue monitoring.
8 Approval of new connections and extension of load for the connections
from 50 KW to 500 KW.
9. Supervision and monitoring of preparation of new plans.
10. HR & Establishment activities.
11. Coordinating between the district administration and DHBVNL field
offices.
12 Holding Bijli Sabha to listen and redress the complaint of the
consumers.
13 Installation checking.
14 Work contracts.
15 Analysis and supervision of all commercial activities in the division
including revenue monitoring.
36
5. To sanction financial and technical estimate for new connections of all
categories of consumers upto load of 50 KW.
6. Preparation of financial and technical estimates and plans for
augmentation and extension and maintenance of distribution system.,
7. Carrying the activities of meter reading bill preparation, distribution,
cash collection etc.
8. Checking of consumer meters and issuance and implementation of
MCO
9. Vigilant inspection of power supply and distribution system, including
metering equipment.
10. Keeping account of electricity consumption by the consumers.
11 Cash Book and Cash Handling.
12. Loss reduction measures.
13. Installation checking.
14. New distribution works.
15. Work contracts.
16. Bill correction.
17 Energy billing and collection.
18. Site survey and distribution design.
19. Project planning and implementation etc.
37
Chapter - 4 (Manual - 3)
38
17 Inter-state agreements executed between various companies.
18 Minutes of Committee Meetings, Board Meetings and Shareholders
General Meeting.
19 Statutory Books and Registers maintained by the Corporation.
20 Other miscellaneous daily files maintained by the staff members.
39
Chapter - 5 (Manual - 4)
40
shedding, release of new connections; water works connections, augmentation
and expansion of distribution system, etc.
41
Khula Darbar: Khula Darbars are arranged by Deputy Commissioners and Sub
Divisional Officers (Civil) in which officials of the DHBVN participate and resolve
the issues raised by individuals or representatives of public in regard with
electricity service.
42
43
44
Chapter - 6 (Manual - 5)
45
24 Sales Manual
25 Cash books
26 Memorandum & Articles of Association
27 Minutes of meetings of Board, Whole time Directors, Committees, etc.
28 Minutes of Annual General Meeting of Share Holders
29 Seniority lists for connections
30 Meter Reading Books
31 Service Connection Order
32 Ledgers of consumers accounts
33 Meter Change Order Book
34 Complaint registers
35 Consumer files
46
The Boards, Councils, Committees and other bodies
consisting of two or more persons constituted as its
part or for the purpose of its advice, and as to
whether meetings of those boards, councils, committees
and other bodies are open to the public, or minutes of
such meetings are accessible for public:
The Dakshin Haryana Bijli Vitran Nigam is a subsidiary of Haryana Vidyut Prasaran
Nigam Ltd. which in turn is a wholly company of Government of Haryana. DHBVN is
run and controlled by its shareholders through a Board of Directors appointed by it. The
Government of Haryana holds 16.63 equity share Capital of DHBVN while the rest is
held by HVPN. Shareholders are the owners of the Company and have all the powers
given to them under the companies Act. The Company convenes Annual General
Meeting of its shareholders every year for approval of appointment of statutory Auditors
& their remuneration, Dividend etc. & other matters requiring shareholders' approval.
A number of committees are constituted by the Board of Directors or other competent
authority for purchases or execution of works which include Whole Time Directors,
Audit Committee, High Power Purchase Committee, Nigam's Purchase Committee, -----
---------------------
1) The minutes of meetings of the shareholders of the company are open for inspection
during working hours of the company to any member (Shareholder) of the Company.
2) Any member (Shareholder) of the Company can have a copy of the minutes of
meetings of shareholders.
3) No person is allowed to have inspection or copy of minutes of meetings of the Board
of Directors or any of its committee.
4) The meetings of the Board of Directors, Shareholders, Whole Time Directors and
other internal committee meetings of the Company are not open to the public.
47
The DHBVN is responsible for reliable and affordable power distribution to residential
areas, commercial centres, streetlights, water works, bulk consumers, railway tracks,
agriculture and industries. Major function areas of DHBVN are as under:
Chapter - 8 (Manual - 7)
48
The names, designations and other particulars of the
Public Information Officers
The officers who are given the responsibilities for the task of public information
as per the Right to Information Act - 2005
Head Office:
49
(Op) Dabwali 226083 227945 Dabwarl (Sirsa)i
9. Sh. Veer Bhan, 01664- 01664- -do-
Xen City Bhiwani 242801 242821
10. Sh.S.C.Garg, Xen 01664- 01664- S/U Divn
S/U Bhiwani 242340 242802 DHBVN Bhiwani
11. Sh.Y.K.B..Sharma, 01250-- 01250-- DHBVN, Dadri
Xen (Op) Dadri 220142 220143 (Bhiwani)
12. Sh.B.S.Boora, Xen 01662- 01662- Vidyut Sadan,
M&P, Hisar 220299 221969 Vidyut Nagar,
Hisar
13. Sh.Balbir Singh, 01664- 01664- DHBVN, Bhiwani
Xen, M&P, Bhiwani 244136 244126
50
Nuh Stand,
DHBVN,
Nuh
6. Sh J.B. Mudgil, 0129- 0129- -do-
Xen. (Op) Fbd 2233377 4100390
7. Sh.R.N.Garg, Xen 0129-- 0129- Op. Divn.
Old Faridabad 2286251 2225465 DHBVN,
Old
Faridabad
8. Sh Sudhir 0129-- ---- Op. Divn.
Chhabra, Xen 2446449 DHBVN,
Ballabgarh Ballabgar
h
(Faridaba
d)
9. Sh.Balwant Singh 01275-- 01275-- DHBVN,
Chauhan Xen (Op) 252105 252705 Palwal
Palwal
10. Sh.D.S. Doodi , 01282— 01282-- Singhana
Xen (Op) NNL 251347 251348 Road,
Narnaul
11. Sh.V.P.Gupta, Xen 01285-- 01285-- Dadri
(Op) Mohindergarh 220281 220381 Road,Mah
endragarh
12. Sh S.S.Yadav Xen 01274-- 01274-- DHBVN,
(Op) Rewari 254762 253754 Jhajjar
Road,
Rewari
13 Sh.P C Gupta, Xen 01274— 01274— Nand
(Op) Dharuhera 242103 242104 Rampur
Bass
Road,
Dharuher
a
14. Sh.SubhashDeswa 0124- 0124- DHBVN,
lXEN, M&P GGN 2340245 5085083 Gurgaon
15. Sh.H.S.Rana, Xen, 0129- 0129- DHBVN,
M&P Faridabad 2230945 2238287 Faridabad
16 Sh..A.K.,Singal, 0124- 0124- SCO 1 to
Xen Const. 2384758 2326333 4, HUDA
Gurgaon Complex,
Gurgaon
17 Sh.S.K.Sachdeva, 0124- 0129- Old Power
Xen Const.Fbd 2443234 2439763 House
Colony,
Faridabad
51
18. Sh. S.K.Sehgal, 0129— 0129— DHBVN,
Xen C/S B/Garh 2234357 2237972 Ballabgar
h
52
Chapter - 9 (Manual - 8)
Decision Making Process in the company for following areas are generally
described as under:
1. Delegation of Power
2. Sales Manual
3. Store Manual
4. Purchase Manual
5. Revenue Manual
6. Terms and Conditions of power supply
7. Different orders of HERC
8. Tariff for supply of electricity
9. Citizen Charter
10. Standard of performance
11. Works Manual and General Conditions of Contract for Works
12. Employees service rules and regulations
13. Pb. Civil Services Rules Vol. I, II, III
14. Departmental Financial Rules
15. Punjab Financial Rules
16. Public Works Departmental Code
17. Accounts Code Vol. III
18. EPF Regulations
19. Punishment and Appeal Regulations
53
20. Manual of Instructions
21. Pb. Budget Manual
Procurement of material:
Work Execution:
For the execution of work, the details of work to be executed is gathered from
field offices, compiled at divisions/ Circle Offices / Head Office. Administrative
approval is given to the works to be executed as per necessity and priority and
tenders are invited. On receipt of the tenders, the same are evaluated and after
approval of the competent authority, as per Delegation of Powers, the work order
is placed with the party.
54
Chapter-10 (Manmual-9)
55
Sh.M.P.Jain, AEE Civil Mtc. 01662-220122 -do-
Sh.V.K.Sareen, Dy. Secy.T&M 01662-220314 01662-222539 -do-
Sh R.K.Aggarwal, C.E/MM 01662-220761 01662- 222900 -do-
&GM/HR&A ,Hisar.
Sh.V.K.Jain, SE/MM-1 01662-220897 0129-5002534 -do-
Sh. B.R.Nehra, SE/MM-II 01662-220232 ----------- -do-
Sh.V.K.Johar, GM/Comml. 01662-223067 01662- 220242 -do-
56
Sh. S.K.Sehgal, Xen C/S B/Garh 0129—2234357 0129—2237972 DHBVN, Ballabgarh
Sh R.K.Batra , Xen.Vigilance 01662—220283 01662—250877 Vidyut Sadan, Vidyut Nagar,
01662—246611 Hisar
Hisar
Sh.Sanjeev Chopra, 0124—2384757 DHBVN, Gurgaon.
Xen.Vigilance,Gurgaon
Sh ------------------, Xen Vig. 0129—2231604 DHBVN, Faridabad
Faridabad
Sh. R.C.Sapra, CE (Op) Delhi 011--28313780 011-28313781 Shakur Basti, Power Hosue,
Rohtak Road, Delhi
Sh. P.D.Sanduja, PA 011—28313780 0124-2328476 -do-
Sh.D.S.Yadav, SE(Op) Gurgaon 0124—2322427 0124-2340987 Power House Colony,
Mehrauli Road, Gurgaon
Sh.A.K.Jain, Xen City Gurgaon 0124—2320971 0124—2302810 -do-
Sh.R.S. Hooda, SDO New 0124-2253684 Near Blue Bell School,
Colony, Gurgaon Sector-4, Gurgaon.
Sh. S.K.Sharma, SDO City-I GGN 0124-2320821 0129-5000453 Gurdwara Road, near Kamla
Nehru Park, Gurgaon
Sh.J.C.Bali, SDO City-II GGN 0124-2322338 0124-2254275 Laxmi Bazar, Gurgaon
Sh. S.S.Sangwan, SDO Ind/Area 0124-2382364 0124-2335287 Sector -31, HUDA Complex
Market, Gurgaon
Sh. O.P.Ahlawat, Xen S/U GGN 0124—2382363 0124—2225608 -do-
Ramesh Verma, SDO OCC 0124-2384755 0124-2323283 -do-
Gurgaon
Sh.S.P.Dagar SDO South City Sector-46, Gurgaon
GGN
Sh.Manoj Yadav, SDO 0124-2343317 0124-2305288 Near Maruti Factory, Gurgaon
Maruti.GGN
Sh.S.L.Gupta, SDO, F/Nagar 0124-2375233 0124-2375213 DHBVN, Farukh Nagar
(Gurgaon)
Sh.Anil Goyal, SDO, Udyog Vihar 0124-2340194 0124-2316606 Near Maruti Factory, Gurgaon
Sh.Satvir Singh SDO, 0124-2361238 0124-2361221 DHBVN, Badshahpur
Badshahpur (Gurgaon)
Sh.Om Singh Xen OCC GGN 0124-2382365 0124-2321197 Sector31, Gurgaon
57
Sh. Daljit Singh, SDO Manesar 0124-2337209 0124- 2337211 DHBVN, Manesar, Gurgaon
Sh.Rajeev Sharma, SDO Tauru 01267- 287328 01267-282313 DHBVN Tauru
Sh. Sachin Yadav, SDO Pataudi. 0124-2671064 0124-2671070 DHBVN, Pataudi
Sh.R.N. Gupta, SDO Bhodakalan 0124-2379527 0124-5036102 DHBVN, Bhodakalan
Sh.S.S.Dalal, Xen (Op) Sohna 0124--2362344 0124--2362333 DHBVN, Sohna
Sh.D.K.Goel, SDO, Sohna 0124-2362355 0124-2395140 DHBVN, Sohna
R. P. Relatia, XEN, Nuh Near Bus Stand,DHBVN, Nuh
Sh.Sat Prakash, SDO,Nuh 01267-271233 01267-271233 DHBVN, Nuh
Sh. R.P.Gupta, SDO, Punhana 01268-272238 01268-272440 DHBVN, Punhana
Sh. M.U. Khan, SDO, P/Zhirka 01268-277239 01268-277248 DHBVN, Ferozpur Zhirka
Sh.Uddai Singh JE Nagina 01268-273225 DHBVN, Nagina
Sh.S.K. Aggarwal, SE(Op) 0129--2233277 0129-2283333 DHBVN, Sector- 23,
Faridabad
Faridabad
Control Room at Faridabad 0129-2235252 -do-
Sh J.B. Mudgil, Xen. (Op) Fbd 0129-2233377 0129-4100390 -do-
Sh.Shambir Singh, SDO 0129-2415693 0129-2444111 Op. S/D No.I, DHBVN,
No.1,Fbd Faridabad
Sh.P.K. Chauhan, SDO No.2, Fbd 0129-2417432 0129-2420040 Op. S/D No.II, DHBVN,
Faridabad.
Sh.Neeraj Khandekar, SDO 0129-2233396 0129-2231055 Op. S/Divn.No.3, Faridabad.
No.3,Fbd
Sh.J.C. Bisla, SDO No.5,Fbd 0129-2412492 0129-2230983 Op. S/D No.5, Faridabad.
Sh.A.S.Jaiswal,SDO Jawahar 0129-2470141 DHBVN Jawahar Colony
colony
Faridabad.
58
Sh.R.N.Garg, Xen Old 0129--2286251 0129-2225465 Op. Divn. DHBVN, Old
Faridabad Faridabad
Sh.K.D. Bansal, SDO No.4, Fbd 0129-2412547 0129-5518370 Op. S/D No.4, DHBVN,
Faridabad.
Sh-------------------- SDO East 0129-2288001 0129-2244989 Op.S/D (East) DHBVN,
Fbd Faridabad.
Sh.Shanti Prakash, SDO West, 0129-2292980 0129-2211305 Op. S/D (West) DHBVN,
Fbd Faridabad.
Sh.K.C.Agrawal, SDO 0129-2275541 0129-2227610 Op.S/D M/Road, Faridabad.
M/Road,Fbd
Sh.Kuldip Attri , SDO Kheri Kalan 0129-2229337 0129-2302709 DHBVN, Kheri Kalan
(Faridabad )
Sh Sudhir Chhabra, Xen 0129--2446449 ---- Op. Divn. DHBVN,
Ballabgarh Ballabgarh (Faridabad)
Sh.Inderjeet Yadav, SDO I/A 0129-2244317 0129-2311288 Industrial Area S/D, DHBVN,
B/Garh Ballabgarh
Sh.Mukesh Gupta, SDO Pali 0129-2470301 0129-2444000 Op.S/D DHBVN, Pali
(Faridabad)
Sh.Vikas Mohan, SDO City-1 0129-2247257 0129-2231055 Op. City-I S/D DHBVN,
B/Garh Ballabgarh
Sh.S.S.Kantura, SDO City-II 0129-2241293 0129-2311228 Op City-II S/D DHBVN,
B/Garh Ballabgarh
Sh.Naveen Verma, SDO S/U 0129-2232948 S/U S/D DHBVN, Ballabgarh
B/Garh
Sh., NL Chawla, SDO Badraula 0129-2401240 0129-2285593 Op.S/D DHBVN, Badraula
(Faridabad)
Sh.Vijay Kumar, SDO Chhainsa 0129-2209217 0129-2209231 DHBVN, Chhainsa (Faridabad)
Sh.Balwant Singh Chauhan Xen 01275--252105 01275--252705 DHBVN, Palwal
(Op) Palwal
Sh.Prem Singh, SDO City Palwal 01275-252215 01275-252097 DHBVN, Palwal
Sh.N.L.Dube,SDO S/U Palwal 01275-252107 01275-252707 -do-
Sh.HD Sharma, SDO Hathin 01275-261391 DHBVN, Hathin
Sh.AK Goel, SDO Hodel 01275-235521 01275-235616 DHBVN, Hodel
Sh., SDO Hassanpur 01275-271225 01275-271275 DHBVN, Hassanpur
Sh.K.G.Yadav, SE(Op) Narnaul 01282--251296 01282--251109 DHBVN, Mahendragarh
Road, Narnaul
Sh.D.S. Doodi , Xen (Op) NNL 01282—251347 01282--251348 Singhana Road, Narnaul
Sh.Amit Kamboj , SDO City NNL 01282-251291 01282-251252 Shivaji Nagar, Narnaul.
Sh., S.K.Mathur,SDO S/U 01282-251219 01282-251262 Nizampur Road, Narnaul.
Narnual
Sh.S.S.Rawat, SDO Ateli 01282-272582 01282-276585 Rewari Road,. Ateli
59
Sh.S.K.Keshav, SDO 01282-278436 01282-278242 Kotputli Road, Nangal
N/Chaudhary
Chaudhary
60
Sh.R.K.Aggarwal, CE (Op) Hisar 01662-220616 01662-223110 DHBVN, Vidyut Nagar, Hisar
Sh.M.L.Goyal, SE(Op) Hisar 01662-232629 01662- DHBVN, Rajgarh Road,
Hisar.
Sh.K.K.Gupta, Xen.OP-I, Hisar 01662-237853 ------- -do-
Sh.Anil Sharma, SDO Model 01662-221665 01662-248283 DHBVN, Vidyut Nagar, Hisar
Town
Sh.Dalbir Singh,, SDO City,Hisar 01662-237882 -- DHBVN, Double Phatak, -do-
Sh.Vinod Poonia, SDO Civil Line 01662-237548 01662-251627 -do-
Sh.R.A.Bansal, Xen.(Op)-II,HSR 01662-234324 01662-221428 DHBVN, Rajgarh Road, Hisar.
Sh.A.K.Bhanot, SDO, Satrod 01662-220074 01662-220369 DHBVN, Vidyut Nagar, Hisar.
Sh. Rajender Sabarwal,SDO, 01693-242064 01693-242094 DHBVN, Barwala (Hisar)
Barwala
Sh.S.S.Rai, SDO, Adampur 01669-242268 01669-242052 DHBVN, Adampur(Hisar)
Sh. Dalbir Singh, JE Agroha 01669-281138 01669-220030 DHBVN, Agroha (Hisar)
Sh. Jai Singh, JE Balsamad 01662-264427 --- DHBVN, Balsamand (Hisar)
Sh. V.K.Bhardwaj, Xen. (Op) 01663-254142 01663-254045 DHBVN, Bhiwani Road, Hansi
Hansi
Sh. R.S.Malik, SDO City Hansi 01663-254048 01663-254183 -do-
Sh.K.S.Pannu, SDO S/U Hansi 01663-259200 01663-254318 -do-
Sh.S.S.Siwach,SDO Mundhal 01254-235232 --- DHBVN, Mundhal
Sh.Anupam Katiyar, SDO 01663-233223 01663-233231 DHBVN, Narnaund
Narnaund
Parveen Aora, JE Sub 01663-289238 DHBVN, Umra
Office,Umra
Sh.A.K.Virdhi, Xen.(Op) Tohana 01692-220060 01692-220393 DHBVN, Hisar Road, Tohana
Sh. B.S.Gill, SDO City Tohana 01692-230030 01692-230468 Op. City S/D DHBVN, Tohana
Sh.Krishan Sarup, SDO S/U 01692-230467 01692-220440 Op. S/U S/D DHBVN, Tohana
Tohana
Sh. Shemsher Singh, SDO 01693-233079 01693-233063 DHBVN, Uklana
Uklana
Sh.S.P. Bhatia, SDO, Jakhal 01667-252240 -- DHBVN, Jakhal
Sh.Raj Singh, SDO Bhuna 01693-242038 01693-242083 DHBVN, Bhuna
Sh.D.S.Rathee, 01667-220070 01667-220119 Power House, Fatehabad.
Xen.(Op)Fatehabad
61
Sh.O.P.Mehta, SDO S/U 01667-220988 01667-220644 Op. S/U S/D Fatehabad.
Fatehabad
Sh.I.S.Mor, SDO City Ratia 01697-250036 01697-250043 Op.City S/D Ratia
Sh.Jai Pal Singh, SDO S/U Ratia 01697-250283 01697-250284 S/U S/D Ratia(Fatehabbad)
Sh., R.S.Beniwal, SDO Bhattu 01692-252235 01692-252257 DHBVN, Bhattu (Fatehabad)
Sh.Kitab Singh, JE, Badopal 01667-285244 01667-223351 DHBVN, Badopal (Fatehaba)
Sh.D.S.Malhan, SE(Op) Sirsa 01666—238400 01666—238401 DHBVN, Barnala Road, Sirsa
Sh. R.K. Jain , Xen City Sirsa 01666—238405 01666—238478 DHBVN, Near Bus Stand,
Sirsa
Sh. Shiv Raj Singh, SDO City 01666-238407 01666-238408 -do-
Sirsa
Sh.C.B.Gaba, SDO I/A Sirsa 01666--238409 01666-238438 -do-
Sh.Bhim Sain, SDO Panjuana 01666-252536 01666-252537 DHBVN, Panjuana (Sirsa)
Sh. S.S.Kumar, SDO Ding 01666-273884 01666-273885 DHBVN, Ding(Sirsa)
Sh. B.S.Khatri, SDO 01666-274315 ------------------- DHBVN, Madhosinghana
Madhosinghana (Sirsa)
Sh. Mehta Xen S/U Sirsa 01666--238403 01666--238404 DHBVN, Baranala Road,
Sirsa
Sh.Sukhbir Singh,SDO S/U Sirsa 01666-238410 01666-238411 -do-
Sh. Mani Ram SDO Nathusari 01666-256138 01666-245582 DHBVN, Nathusari (Sirsa)
Sh. M.L.Sukhija, SDO Rania 01698-250346 01698-250345 DHBVN, Rania.(Sirsa)
Sh.S.K.Singh, SDO Ellenabad 01698-220049 01698-221340 DHBVN, Ellenabad (Sissa)
Sh.S.K.Nain, SDO Jiwannagar 01698-272992 01698-272254 DHBVN, Jiwan Nagar (Sirsa)
01698-238444
Sh.R.K.Soda, Xen (Op) Dabwali 01668-226083 01668--227945 DHBVN, Dabwarl (Sirsa)i
Sh.M.R.Sachdeva, SDO Dabwali 01668-227173 01668-226905 -do-
Sh. S.L.Mehta, SDO Chautala 01668-250253 01668-227048 DHBVN, Asakhera (Sirsa)
Sh. B.K.Rajan, SDO Kalanwali 01696-222005 01696-222003 DHBVN, Kalanwali (Sirsa)
Sh. K.S.Behl, SE(Op) Bhiwani 01664--243491 01664- 243131 Old Power House Colony,
DHBVN, Bhiwani.
Sh. Veer Bhan, Xen City Bhiwani 01664- 242801 01664- 242821 -do-
Sh. Mahavir Singh, SDO City 01664-242805 01664-242805 Op. City S/D DHBVN, Bhiwani
BWN
Sh. ,Y.K.B.Sharma SDO S/U No.I 01664-242803 01664-242091 Op. S/U No.I S/D DHBVN,
Bhiwani
Sh., S.S.Sangwan, SDO S/U -II 01664-242109 01664-242804 Op. S/U No.II S/D DHBVN,
Bhiwani.
Sh.Sanjay Ranga, SDO 01254-233030 01254-233040 DHBVN, Bawani Khera
Bawanikhera
(Bhiwani)
Sh.V.P.Yadav , SDO Tosham 01253-258284 01253-258184 DHBVN Tosham (Bhiwani)
Sh.S.C.Garg, Xen S/U Bhiwani 01664- 242340 01664- 242802 S/U Divn DHBVN Bhiwani
62
Sh. H.C.Saini, SDO Jui 01664- 262532 01664-262545 DHBVN, Jui (Bhiwani)
Sh. Virender Kumar, SDO, 01252-258246 01252-258242 DHBVN, Loharu (Bhiwani)
Loharu
Sh.Rud Singh, SDO Digwa Jattan 01252-257746 -------- DHBVN, Digawa Jattan
(Bhiwani)
Sh.Virender Singh Lamba, SDO 01255-265235 01255-265357 DHBVN, Bahal (Bhiwani)
Behl
Sh. Rathi , SDO Sewani 01255-277322 01255-277333 DHBVN, Siwani (Bhiwani)
Sh.Y.K.B..Sharma, Xen (Op) 01250--220142 01250--220143 DHBVN, Dadri (Bhiwani)
Dadri
Sh.H.R, Jain, SDO City Dadri 01250-220024 01250-220144 -do-
Sh.Hari Dutt, SDO S/U Dadri 01250-220493 01250-220577 -do-
Sh.J.B.Yadav, SDO Sanjarwas 01250-286538 01250-286534 DHBVN, Sanjarwas (Bhiwani)
Sh.O.P.Chahal, SDO Jhojukalan 01250-263044 01250-263066 DHBVN, Jhojukalan (Bhiwani)
Sh. H.C.Saini, SDO Badhra 01252-253166 ---- DHBVN, Badhra (Bhiwani)
Manmohan Singh, SDO Atelakan. 01250-298238 ---- DHBVN, Atela Kalana
(Bhiwani)
63
Chapter - 11 (Manual - 10)
64
KAPIL DEV BANSAL AE 14300 0 7150 200 300 26705
KISHORE KUMAR XEN 18700 300 9350 100 300 34641
SHARMA
M.K. RELHAN XEN 19100 0 9550 100 0 35777
M.L. KALRA XEN(U/S) 19100 300 9550 100 0 32402
MUKET BEHARI VASHIST SE 19550 400 9775 100 0 35983
M.L. GOEL SE 19100 0 9550 100 0 34767
M.L. GOEL SE 19550 0 9775 100 0 35583
MUKESH GUPTA AEE 16700 200 8350 100 300 30911
M.M.GUPTA AEE 16300 0 8150 0 300 29885
M.R. SACHDEVA AEE 15500 0 7750 0 300 28683
N.L. DUBEY AEE 11300 0 5650 0 0 21280
NAVIN KUMAR AEE 15900 0 7950 200 300 29609
NARDEEP KUMAR AE 12275 200 6138 200 300 24490
O.P.AHLAWAT XEN 17900 0 8950 100 0 32839
O.P. MEHTA AE 15900 0 7950 0 300 29409
O.P. SALUJA AEE 15900 200 7950 100 300 29459
PARVESH CHANDER XEN 18700 0 9350 0 0 33941
P.P.MITTAL AEE 15100 0 7550 200 300 27961
R.K.MONGA XEN 17500 300 8750 100 150 34015
R.K.SEHGAL XEN 18700 0 9350 200 0 34201
R.K.YADAV XEN 18700 300 9350 100 300 34641
R.P.MADAN SE 19550 400 9775 100 300 36363
R.C.SAPRA SE 20000 400 10000 100 0 36800
RATTAN LAL SUPDT 11275 200 5638 200 150 22275
S.S. DALAL XEN 19100 0 9550 0 0 34667
SUBHASH CHANDER XEN 19100 0 9550 100 0 34767
GARG
DR. SANYOGITA M.O. 17500 0 10000 100 75 36475
S.S. YADAV XEN 17900 0 8950 0 0 31837
S.K. AGGARWAL SE 19550 0 9775 100 0 35833
S.K. KASHIV AEE 16700 0 8350 0 0 30311
SATYA VIR YADAV AE 14300 0 7150 0 300 26334
SMT.VEENA VOHRA XEN 18700 0 9350 100 0 34041
V.K. SINGLA SE 19550 400 9775 100 300 36533
VIJAY KUMAR JOHAR SE 20000 400 10000 100 0 36800
Y.K.B. SHARMA AEE 16300 0 8150 100 300 30235
V.P. GUPTA XEN 18700 0 9350 0 300 35741
VIPON CHANDA XEN 17500 300 8750 100 150 34563
V.K. BHARDWAJ XEN 18700 0 9350 0 0 33941
TARA CHAND KANSAL AE 15500 200 7750 100 300 28733
VIR BHAN XEN 17100 0 8550 0 0 31037
V. D.KAUSHIK MGR/I.R 14250 400 7125 100 150 27274
Y.S. GULIA LO 10375 200 5188 100 150 19281
V.K.GARG SE 19100 400 9550 100 222 35389
VINOD KUMAR SDO 12275 0 6138 0 300 22580
DR. RIETA MITTAL MO 17900 0 10200 100 75 37961
RAKESH KUMAR SODHA XEN 17100 0 8550 0 0 31287
R.N.GARG XEN 17100 0 8550 200 0 32497
R.C. YADAV AEE 12600 0 6300 0 0 23119
RAMESH KUMAR VERMA AEE 15900 0 7950 0 150 29009
R.K.JAIN XEN 17100 0 8550 0 0 36950
RAJ PAL RELATIYA XEN 18700 0 9350 0 0 33941
RAVINDER SINGH AE 16300 0 8150 0 300 30135
RAJINDER SINGH AEE 15900 200 7950 100 300 29459
R.S. GUPTA AE 13250 0 6625 200 300 24799
R.L. KAMBOJ XEN 18700 400 9350 100 0 34441
65
RANDEEP SINGH AE 15100 200 7550 100 300 28007
S.K. SACHDEVA XEN 18700 0 9350 200 0 35401
SUBHASH DESWAL XEN 16300 0 8150 100 0 30445
S.K.CHOPRA XEN 17100 0 8550 100 300 31437
SUDHIR CHHABRA XEN 17100 0 8550 200 0 31237
S.S YADAV AEE 16300 0 8150 100 300 30745
SUSHIL KUMAR MATHUR AEE 15900 0 7950 200 300 29663
SANT SINGH KUMAR AEE 15900 0 7950 0 150 29259
S.N. AGGARWAL AEE 15900 0 7950 0 0 26642
SATISH KUMAR SHARMA AE 12275 0 6138 0 0 22530
R.N.GUPTA AE 10200 0 5100 0 0 18763
R.K.BATRA XEN 17900 300 8950 100 300 34199
INDERJIT AEE 14300 0 7150 200 300 27965
BRAJINDER SINGH AEE 8150 0 4075 96 0 15138
S.S. SANGWAN AE 10975 0 5488 100 300 20570
KRISHAN SWAROOP AE 9650 0 4825 0 150 17915
KAPOOR SINGH SRAO 13875 400 6938 100 300 26044
INDER SINGH MOR AE 8825 0 4413 0 0 19197
JAGBIR SINGH KADIAN SR.A.O. 13875 400 6938 100 300 26234
N.L. CHAWLA AE 9925 0 4963 0 0 18074
P.C. GUPTA FA/HQ. 19100 400 9550 100 300 35467
MAHABIR SINGH AEE 10325 0 5163 200 150 19910
NAVEEN KAPOOR COMP.SE 17100 0 8550 100 300 31437
CY.
ASHOK KUMAR BHANOT AE(T) 9650 0 4825 100 300 18165
SANJEEV SHANKAR RAI AE 9375 200 4688 200 300 18566
SATYA PARKASH AE(T) 8000 200 4000 200 0 15170
PARMOD KUMAR AEE 10325 0 5163 200 150 20390
RANBIR SINGH AE 9375 0 4688 0 150 17166
FAHIM RAZA NAQVI AE(T) 8550 200 4275 100 0 16068
S.K. SINGH AE 9375 0 4688 0 0 17266
ANUPAM KATIAR AE 9650 0 4825 100 300 18165
RAMESH KUMAR SR.A.O 13500 400 6750 100 150 25153
SHARMA
NEERAJ KHANDEKAR AE 10325 0 5163 100 300 19390
SHYAMBIR AE 9375 0 4688 200 150 17616
M.G. WADHWA SR. A.O. 15375 400 7688 100 300 29556
SMT. VINEETA SINGH AEE 15900 0 7950 100 300 29259
PREM SINGH AE 8000 0 4000 0 150 14920
SURINDER SINGH AE 8550 0 4275 0 150 15668
V.K. JAIN SE 19100 400 9550 100 300 35467
S.S BANGA XEN 15900 300 7950 200 0 30444
R.K. KHUDIA SR.A.O 13500 400 6750 100 300 25303
B.K. BHATIA SE 20000 400 10000 100 300 37100
OM SINGH XEN 18700 0 9350 100 0 35904
SUBE SINGH SIWACH AE 10200 0 5100 0 150 18663
GHANSHYAM DASS SE 20000 400 10000 100 300 37100
R.N.BANSAL XEN 19100 300 9550 100 150 35277
B.S.BOORA XEN 19100 0 9550 100 0 34767
V.P. THUKRAL A.E.E. 16700 200 8350 100 300 30911
J.B.MUDGIL XEN 17900 0 8950 200 0 32939
G.C.RAWAL SR.P.S 13500 400 6750 100 300 25625
D.S.YADAV SE 19550 0 9775 100 0 35608
RAJ KUMAR AE 8550 0 4275 0 0 15518
M.L.ROHILA AE 12275 0 6138 200 300 24290
R.V.BARI Sr.A.O. 13125 400 6563 100 300 24622
V.K.SAREEN XEN 18700 300 9350 100 300 34741
66
BHUSHAN KUMAR AE 10325 0 5163 0 150 19140
RANJAN
SURINDER SINGH AE 8275 0 4138 100 150 12220
MANOJ KUMAR AEE 10325 0 5163 100 75 21995
RAJENDER KUMAR AE 5163 0 2582 0 0 14090
SABHARWAL
KESAR CHAND US 13125 400 6563 100 300 25436
O.P.MUDGIL UNDER 13125 400 6563 200 300 24972
SECY.
HARI DUTT AE 9375 200 4688 100 300 17866
R.A.BANSAL XEN 18700 0 9350 100 0 34041
BALWAN SINGH HOODA SR.P.S. 13125 400 6563 100 150 24544
V.K. SETH XEN 19100 300 9550 100 300 35367
RAJA RAM SHARMA AE 15100 0 7550 200 300 28735
R.R. GOYAL XEN 17900 300 8950 100 150 34049
M.L. MUTREJA AE 9100 200 4550 100 150 17217
O.P.SHARMA A.O 9925 0 4963 100 75 18439
PARDEEP KR. CHAUHAN AE 9375 0 4688 200 0 17216
KAPIL K. MARWAHA C/AUDIT 19550 0 9775 100 300 35883
OR
C.S. ARORA AEE 16300 200 8150 200 300 31795
RAM MEHAR SINGH AE 8000 0 4000 100 0 14620
RAJESH KUMAR SHARMA A.O. 10000 0 5000 100 300 18550
S.C.AGGARWAL A.O 10000 0 5000 100 150 19160
RAJENDER SINGH AE 10475 0 5238 100 300 19467
HOODA
M.K.VERMA AE 0 0 0 0 0 0
HEM RAJ SINGH RANA XEN 18700 0 9350 200 0 34141
H.R.JAIN AE 12125 0 6063 0 150 22407
A.K.GOYAL AE 8825 0 4413 0 150 16478
M.K.SHARMA DIR./(OP) 22925 250 11463 100 0 41959
J.C.BALI AE 10025 0 5013 100 150 18446
PIRTHI SINGH SPORTS 8900 0 4450 100 150 16404
OFFICER
D.P.SINGH SUPDT. 9900 200 4950 200 300 20179
S.S.LOHAN AE 8800 0 4400 0 0 16222
RAM NIWAS AE 8550 0 4275 0 150 15668
SULEKHAN SUPDT. 10375 200 5188 100 75 19456
M. S. JAKHAR AE 8000 0 4000 0 150 14670
0 0 0 0 0 0
PIARE LAL SUPDT. 10100 200 5050 100 300 18932
H.R. KUMAR PS 10825 200 5413 100 300 20248
N.D.SHARMA SUPDT. 10300 200 5150 100 150 19145
R.S.MALIK AE 8000 0 4000 100 300 17850
PREM KUMAR SUPDT. 10300 200 5150 100 300 19545
S.C.DUREJA SUPDT. 10300 200 5150 100 150 19145
S.P.SHARMA AE 10475 0 5238 100 150 19263
S.L.GUPTA AE 8550 0 4275 0 0 15768
M.P.JAIN AE 10475 200 5238 100 300 19671
DAYA NAND KHATKAR AE(T) 8275 0 4138 100 0 15120
MADAN LAL SUKHIJA AE(T) 8275 0 4138 0 150 15420
MANJU CHAUDHARY AE(T) 8275 200 4138 100 0 15320
MANOJ KUMAR AE(T) 8000 0 4000 100 0 15565
AMIT KAMBOJ AE(T) 8275 0 4138 0 150 15865
ASHUTOSH Kr. PANCHAL AE(T) 8275 200 4138 100 150 17043
OM BIR AE(T) 8275 0 4138 100 150 16215
JITENDER SINGH AE(T) 8275 0 4138 200 150 15670
JOGINDER SINGH AE(T) 8000 0 4000 0 75 15670
67
JAGDISH CHANDER JAIN AE(T) 8275 0 4138 100 150 15270
JAI DEEP AE(T) 8275 200 4138 100 150 12940
JOGINDER HOODA AE(T) 8275 0 4138 100 0 15120
KULDEEP ATRI AE(T) 8275 0 4138 0 150 15420
SATISH KUMAR AE(T) 8275 200 4138 100 150 15470
SANKALP PARIHAR AE(T) 8275 200 4138 100 150 16165
SHIV RAJ SINGH AE(T) 8000 0 4000 0 0 14770
RANJAN RAO AE(T) 8275 0 4138 100 0 15120
CHANDER SHEKHAR AE(T) 8275 200 4138 100 150 15720
VED PARKASH AE(T) 8275 200 4138 100 150 15470
VINOD KUMAR PUNIA AE(T) 8275 0 4138 100 150 15520
BHIM SAIN AE(T) 8000 0 4000 0 150 22758
VIJENDRA SINGH AE(T) 8275 0 4138 0 0 19593
VIKAS MOHAN AE(T) 8275 0 4138 200 150 16755
VIJAY PAUL AE(T) 8275 0 4138 0 0 18020
MS REKHA AE(T) 8275 0 4138 100 150 20422
RAJESH NINANIYA AE(T) 8275 200 4138 100 0 15570
R.K.GOEL GM 20400 0 10200 100 0 37126
SACHIN YADAV AE(T) 8275 0 4138 0 150 18420
SATYAVEER AE(T) 8000 0 4000 0 150 14670
SUKHBIR KAMBOJ AE(T) 8275 0 4138 100 150 15520
SHAMSHER SINGH AE(T) 8000 0 4000 0 0 15670
SANJAY AE(T) 8275 0 4138 0 0 15270
PARVEEN YADAV AE(T) 8275 0 4138 100 150 17527
D.S.HOODA AE 8450 0 4225 100 0 16197
S.S.RAWAT AE 8000 0 4000 200 0 14720
J.C.BISLA AE 8000 0 4000 200 150 15120
S.K.SINGLA AE 10200 0 5100 100 150 19523
VIJAYENDRA KUMAR IAS MD 13500 500 6750 100 0 25353
P.D.SHARMA AE/CIVIL 11575 200 5788 200 0 21409
C.L.MONGA P.S. 10600 200 5300 100 150 19761
ZILE SINGH AE 8000 200 4000 100 150 15220
AVINASH YADAV AE(T) 8000 0 4000 0 150 14920
RAJNISH GARG AEE 14300 200 7150 100 300 26805
R.S.MALIK AE 8000 0 4000 0 0 14520
NARESH KAKKAR AE(T) 8000 0 4000 100 0 14620
D.P.TYAGI AE 10100 0 5050 200 0 19119
P.R.MEHTA A.O. 9500 0 4750 100 150 18563
S.S.MEHTA A.O. 9700 0 4850 100 150 18616
SADHU RAM SUPDT. 10100 150 5050 100 150 18732
ANIL KUMAR BULAN A.O. 6654 145 3327 96 145 12463
JAIVIR SINGH A.O. 6900 150 3450 100 150 13174
D.P.SINGH TANWAR A.O. 8500 150 4250 100 150 15864
RAM MEHAR SUPDT. 10300 150 5150 100 150 19149
M.P.SHARMA A.O. 8300 150 4150 100 150 15465
M.S.MALIK SUPDT. 10300 150 5150 100 150 19149
MAHABIR PARSHAD SUPDT. 10300 150 5150 100 150 19167
R.K.AGGARWAL C.E. 20400 0 10200 100 0 37201
D.K.GOEL AE 10500 0 5250 0 0 57354
Total 3E+06 23745 2E+06 22092 33817 6E+06
68
Schedule of Staff of Dakshin Haryana Bijli Vitran Nigam Limited
Sr. Designation of the post Pay scale No. of sanctioned posts
No.
Management PMT TMP Total
1 Managing Director 0 1 1
2 Director Finance 0 1 1
3 Director OP 0 1 1
4 Director Project 0 1 1
5 Part Time Directors 0 2 2
A Employees 0 6 6
OFFICERS
1 GM/Administration 18400-500-22400 0 1 1
2 GM/Commercial 18400-500-22400 0 1 1
3 Chief Engineer 18400-500-22400 1 3 4
(Planning, MM & Op. Zones).
4 FA/Hqrs. 15950-450-20000+400SP - 1 1
5 C.A.O./FA&CAO(MM 15950-450-20000 - 2 2
)
6 Chief Auditor 15950-450-20000 - 1 1
7 SE/Admn. 15950-450-20000+400SP - 1 1
8 SE 15950-450-20000+400SP (For 3 13 16
working in Head Office only)
9 C.O.S. 15950-450-20000 - 1 1
10 Executive Engineer 14700-400-18700+300SP (For Head 16 40 56
Office)
11 XEN(Monitoring)/Dy.S 14700-400-18700+400SP - 2 2
ecretary
12 Company Secretary 14700-400-18700 - 1 1
13 Chief Security Officer 12750-375-16500 1 - 1
14 Sr. A.O. 12750-375-16500+400SP - 10 10
15 Sr. Pvt. Secretary 12750-375-16500+400SP - 2 2
16 P.S. 7450-225-11500 0 2 2
17 Admn. Officer/Under 12750-375-16500+400SP 1 5 6
Secretary
18 Accounts Officer 9025-325-14550 - 12 12
19 AE/AEE 57 119 176
(i) 8000-275-10200-EB-275-13500
(ii) 10000-325-15200 after 5 years of regular satisfactory service as
AE/AEE
(iii) 14300-400-18300 after 12 years of regular satisfactory service as
AE/AEE
20 Medical Officer/Sr. M.O. - 7 7
(i) 8000-275-10200-EB-275-13500
(ii) 10000-325-15200 after 5 years regular satisfactory service of
MO/Sr.MO
(iii) 14300-400-18300 after 12 years service.
21 Law Officer 7450-225-9025-EB-225- - 3 3
11500+200 SP
22 Superintendent (HO) 7450-225-9025-EB-225- 3 11 14
11500+200 SP
23 A.L.O. 6500-200-8500-EB-200- - 3 3
10500+150 SP
24 Sports Officer 6500-200-8500-EB-200- - 1 1
10500
25 Manager IR 12750-375-16500 - 1 1
26 Manager PR 12750-375-16500 - 1 1
Total Officers 82 250 332
NON GAZETTED
69
1 Section Officer 6500-200-8500-EB-200- 2 23 25
10500+150SP
2 RA/Acctt./IA 5500-175-8300-EB-175- 12 88 100
9000+75 SP (HO)
3 Acctt-cum-H.Clerk 5500-175-8300-EB-175- 2 - 2
9000+100SP (For cash
handling)
4 Circle Supdt. 6500-200-8500-EB-200- 3 5 8
10500
5 Dy. Supdt. 6500-200-8500-EB-200- 3 2 5
10500+150SP
6 Assistant (HO) 5500-175-8300-EB-175- 14 48 62
9000+60SP
7 Head Clerk (Divnl.) 5500-175-8300-EB-175- 12 18 30
9000+100SP
8 Head Clerk (Circle Office) 5500-175-8300-EB-175-9000 - 3 3
9 Circle Assistant 5450-150-6950-EB-150-8000 5 10 15
10 Commercial Asstt./Asstt.Acctts. 5000-150-7100-EB-150-8000 39 79 118
11 UDC (HO) 4625-125-6000-EB-125- 5 54 59
7250+50SP(HO)
12 UDC (Field) 4625-125-6000-EB-125-7250 218 354 572
13 LDC (HO) 4000-100-4800-EB-100- 12 54 66
6000+40TA & 40SP (HO)
14 LDC(Field)/Cashier 4000-100-4800-EB-100- 549 587 1136
6000+80SP
15 Meter Reader 4000-100-4800-EB-100-6000 239 291 530
16 Bill Distributor 3050-85-3950-EB-85-4590 161 206 367
17 Head Mistress (Middle School) 5500-175-8300-EB-175-9000 - 1 1
18 B.Ed. Teacher 5500-175-8300-EB-175-9000 - 6 6
19 J.B.T. Teacher 4500-125-6000-EB-125-7000 - 13 13
20 P.T.I. 4500-125-6000-EB-125-7000 - 1 1
21 Metrun/Nurse 4500-125-6000-EB-125-7000 - 1 1
22 DMA 4000-100-4800-EB-100- - 1 1
6000+30SP(HO)
23 Havildar (HO) 2750-70-3800-EB-75- 1 12 13
4400+75SA+30SP(HO)
24 Havildar (Field) 2750-70-3800-EB-75- 3 5 8
4400+75SA
25 Daftri (Field) 2750-70-3800-EB-75- 3 4 7
4400+30SP
26 Head Safai Karamchari (Field) 2750-70-3800-EB-75- - 1 1
4400+65SA+30SP
27 Safai Karamchari (HO) 2650-65-3300-EB-70- - 1 1
4000+65SA+30SP (HO)
28 Safai Karamchari (Field) 2650-65-3300-EB-70- - 56 56
4000+65SA
29 Peon (HO) 2650-65-3300-EB-75- 6 107 113
4000+40SA+30SP (HO)
30 Peon (Field) 2650-65-3300-EB-75- 200 143 343
4000+40SA
30 Peon-cum-Mate 2650-65-3300-EB-75- - 4 4
4000+40SA
28 Safai Karamchari-cum-Ckd. 2650-65-3300-EB-70- - 2 2
4000+65SA
29 Chowkidar (HO) 2650-65-3300-EB-70- - 2 2
4000+65SA+30SP
30 Chowkidar (Field) 2650-65-3300-EB-70- 99 109 208
4000+65SA+30SP
31 Sewerman 2650-65-3300-EB-70- - 14 14
4000+65SA+30SP (HO)
32 Pump Driver 4000-100-4800-EB-100-6000 - 8 8
70
33 A.P.D. 2750-70-3800-EB-75-4400 - 11 11
34 Mali 2650-65-3300-EB-70- - 69 69
4000+30SP(HO)
35 Washarman 2650-65-3300-EB-70-4000 - 1 1
36 Crane Driver 4500-125-6000-EB-125-7000 - 6 6
+300SP(HO)+150SP(Other)
37 Driver (HO) 4500-125-6000-EB-125-7000 - 18 18
+300SP(HO)+150SP(Other)
38 Driver (Field) 4500-125-6000-EB-125-7000 80 175 255
+300SP(HO)+150SP(Other)
39 T.T. Driver 4500-125-6000-EB-125-7000 1 7 8
+300SP(HO)+150SP(Other)
40 Cleaner 2750-70-3800-EB-75-4400 1 14 15
41 Work Superviser 4500-125-6000-EB-125-7000 - 3 3
42 Cook 2650-65-3300-EB-70- - 2 2
4000+30SA+30SP (HO)
43 Chowkidar-cum-Cook 2650-65-3300-EB-70- 3 3 6
4000+40SA
44 Personal Assistant 6500-200-8500-EB-200- - 10 10
10500+150SP
45 Sr. Scale Stenographer 5500-175-8300-EB-175- 3 16 19
9000+60SP (HO)
46 Jr. Scale Stenographer 5000-150-7100-EB-150- 16 55 71
8000+40SP
47 Steno Typist 4000-100-4800-EB-100- - 21 21
6000+100SP
48 Data Entry Operator 4000-100-4800-EB-100-6000 - 18 18
+ 60SP(HO)
49 Hindi Translator 5000-150-7100-EB-150-8000 - 2 2
50 Jr. Photographer 4500-125-6000-EB-125-7000 - 1 1
51 Security Officer 5500-175-8300-EB-175- 3 - 3
9000+35KA
52 Security Havildar 4500-125-6000-EB-125- 5 8 13
7000+30KA
53 Security Guard 3050-85-4325-EB-100- 52 42 94
5325+22KA
54 Inspector (Vigilance) 5000-150-7100-EB-150-8000 - 6 6
55 Vigilance Sub-Inspector On deputation - 7 7
56 A.S.I. On deputation - 3 3
57 Head Constable On deputation - 9 9
58 Constable On deputation - 15 15
59 Pharmacist 5000-150-7100-EB-150-8000 - 12 12
60 Attendant 2650-65-3300-EB-70-4000 - 1 1
Total Non-gazetted/Non-technical Staff. 1753 2845 4598
71
NON GAZETTED STAFF
(TECH.)
1 Asstt. Store Officer 6500-200-8500-EB-200-10500 3 2 5
2 Head Store Keeper 5450-150-6950-EB-150-8000 3 1 4
3 Store Keeper 4500-125-6000-EB-125-7000 6 4 10
4 Asstt. Store Keeper 4000-100-4800-EB-100-6000 2 - 2
5 Store Munshi 4000-100-4800-EB-100-6000 - 15 15
6 Store Attendant 2650-65-3300-EB-70-4000+30SP(HO) 21 73 94
7 Stock Verifier 5500-175-8300-EB-175-9000 - 1 1
8 Chief Draftsman 6500-200-8500-EB-200-10500 1 2 3
9 Circle Head Draftsman 6500-200-8500-EB-200-10500 3 5 8
10 Divnl. Head Draftsman 5500-175-8300-EB-175-9000 15 21 36
11 Draftsman 5000-150-7100-EB-150-8000 16 71 87
12 Jr. Engineer (Civil) 6000-175-8450-EB-175-9500 + 60SP(HO) 12 12 24
13 Jr. Engineer-1 6700-200-8500-EB-200-10500 39 79 118
14 Jr. Engineer 6000-175-8450-EB-175-9500 + 115 256 371
100SP(HO)
15 Foreman 5500-175-8300-EB-175-9000 - 3 3
16 Asstt. Foreman 5000-150-7100-EB-150-8000 267 378 645
17 Lineman 4500-125-6000-EB-125-7000 1257 1247 2504
18 Asstt. Lineman 4000-100-4800-EB-100-6000 3223 2819 6042
19 Cable Jointer 5500-175-8300-EB-175-9000 1 - 1
20 Work Mate/T.Mate 2650-65-3300-EB-70-4400 1 52 53
21 S/Stn. Attendant 5000-150-7100-EB-150-8000 31 201 232
22 ASSA 4000-100-4800-EB-100-6000 76 396 472
23 Shift Attendant 4000-100-4800-EB-100-6000 118 330 448
24 Instrument Mechanic - 1 1
25 Meter Mechanic 4000-100-4800-EB-100-6000 6 10 16
26 Sr. Technician 4625-150-6000-EB-125-7250 - 1 1
27 Electrician 4500-125-6000-EB-125-7000 - 2 2
28 Technician Grade-1 4500-125-6000-EB-125-7000 - 10 10
29 Technician Grade-II 4000-100-4800-EB-100-6000 1 3 4
30 Helper Grade-I 2650-65-3300-EB-70-4400 - 23 23
72
Chapter-12 (Manual-11)
ANNUAL PLAN
FOR
2006 - 07
Power demand in Haryana has increased manifold over the past few years, and
the existing infrastructure has become over stretched to meet this demand.
Though the planning at various stages has been taking place over the years, it is
evident from the progress achieved so far that substantial head way could not be
made due to paucity of funds. Nigam had to look towards other financial
institutions for financial assistance. With the launching of Accelerated Power
Development & Reforms Program by the Ministry of Power during the year 2000-
01, other institutions like NABARD, NCR Planning Board, REC & PFC also came
forward to provide assistance at easier terms. Accordingly, various system
improvement schemes have been planned thereafter. In order to speed up the
progress of works, the concept of getting the jobs executed on turnkey basis was
introduced. Initially, problems were faced in getting the proper vendors
developed and in finalizing various terms & conditions of contract. This may have
caused initial delays in kicking off the projects, but now the things have started
picking up, and we expect to achieve significant achievement in the coming
years.
Important aspect of power planning has been that it has been tried to take
33 KV lines as near to the load center as possible. Therefore, quite a large
73
number of 33 KV sub stations have come up during financial year 2005-06 and
many more will be coming up during next few years. Apart from these, it was also
planned to bifurcate all the over loaded and lengthy 11 KV feeders in rural as well
as urban areas. As a follow up action, 242 feeders have already been bifurcated
into 556 feeders of proper load and length since July 1999, and work on 35 other
feeders to divide in to 79 feeders is in progress.
Apart from the above, which have become more or less routine system
improvement works, some innovative schemes have also been envisaged like
computerized data logging at substations, consumer indexing, setting up of Bijli
Suvidha Kendras etc. for better planning & reliability, energy audit & consumer
satisfaction. Bijli Suvidha Kendras have already become functional at all district
head quarters and it is proposed to set up such centralized complaint centers at
all the other small towns in second phase. If arrangement of funds does not
become a problem, scenario is bound to change and we expect an overall
improvement in the existing electrical net work. It is hoped that even the
consumer at the tale end of a feeder will get proper voltage and an un-interrupted
power throughout.
74
Before reviewing the plan proposals during 2005-06, let us have a look at break-
up of the revised outlay:
Sr.No. Particulars Proposed outlay (Rs. in lacs)
1. Normal Development 1929.00
2. System Improvement -
3. APDRP-II 2477.00
4. NABARD 500.00
5. HVDS (APDRP new Scheme) 0.00
6. Rajiv Gandhi Vidyutikaran Yojna 0.00
7. Separation of the rural feeder from mixed urban feeder 0.00
8. Area Load Dispatch Centre (ALDC) 0.00
Total 4906.00
75
Following distribution works have been completed during the
current financial year 2005-06 under system improvement schemes funded under APDRP,
NABARD, REC, PFC and NCR Planning Board:
33 kV Lines (New)
Name of line Circle Length of line
76
of 33kV S/Stn Memra
Augmentations of 33 kV Substation
Sr.no. 33 KV Sub-Stns. Circle District Augmentation (MVA Addition Date
(MVA)
1 Jatusana–II(JC-II) Narnaul M.garh 5 to 6.3/8 3 28.4.05
2 Siswal Hisar Hisar Addl. 4 4 11.5.05
3 Lehrian Hisar Hisar Addl. 5 5 26.5.05
4 Arya Nagar Hisar Hisar Addl.4 i.e. 6.3/8+4 4 28.5.05
5 Siwani Bhiwani Bhiwani 4 to 6.3 2.3 11.6.05
6 Buthan Hisar Fatehabad 6.3 to 10/12.5 6.2 16.6.05
7 Teliwara Hisar Fatehabad 4 to 5 1 21.6.05
8 Farwain Sirsa Sirsa 4 to 6.3/8 4 11.7.05
9 Pirthala Hisar Fatehabad Addl. 4 4 12.7.05
10 Bhuna Hisar Fatehabad 4 to 6.3 2.3 15.7.05
11 Degoh Hisar Fatehabad 4 to 6.3/8 4 17.8.05
12 132 KV Kosli Narnaul Rewari 4 to 5 1 6.9.05
13 Gudiyani(JC-I) Narnaul Rewari Addl.5 5 26.9.05
14 Rozkameo Gurgaon Gurgaon Addl.4 4 5.10.05
15 Ganga Sirsa Sirsa 4 to 6.3 2.3 27.10.05
16 Berla Bhiwani Bhiwani Addl. 5 5 31.10.05
17 Kadma Bhiwani Bhiwani Addl. 5 i.e. 2x5+5 5 25.11.05
18 Rudrol Bhiwani Bhiwani Addl. 5 5 14.1.06
19 Mithi (Temp.) Bhiwani Bhiwani 2 to 4 2 19.1.06
TOTAL CAPACITY ADDED 69.1
77
Spill Over Works from FY 2005-06
Sr.No. Name of S/Stn. Circle Length of line Capacity
_______________________________________km________MVA___
1 I. A. Narnaul Narnaul 0.10 1x6.3/8 33/11
78
12. Mazra Kalan Sirsa 2x4 33/11
T-Off from 132 KV S/S 2.2Km
Mohindergarh to Kauine
79
Augmentation of 33 KV Sub-Stations
6. Service Connections
a) General 60000 Nos.
b) Tube wells 3500 Nos.
c) Industrial 2000 Nos.
80
ANNUAL PLAN ALLOCATION FOR 2006-07
A nos. of improvement schemes have been formulated for execution during the
year 2006-07, which include the spill over works from the financial year 2005-06, and
accordingly a financial provision has been made in the proposed outlay for the year 2006-
07. Schemes have been formulated against financial assistance from APDRP (MOP),
NABARD, NCR Planning Board, PFC, REC and State Plan. However, while assessing
the requirement of funds from State, other than the Normal Development, only that
percentage of project cost sanctioned by NABARD has been taken into account that is to
be borne by the Nigam. Under REC loan schemes, 100% finance is provided by the REC
Ltd., and as such, nothing is required under the State Plan funds. However, an additional
head is required to be included for the projects covered under financial assistance from
National Capital Region Planning Board while finalizing the outlay under State Annual
Plan. NCR PB provides only 75% of the project cost and the rest 25% is to be arranged
by the Utility. A provision of this 25% is required to be made in the outlay as is being
done in case of the projects covered under NABARD. An abstract attached as Annexure-
A depicts the total position of project proposals, that have been proposed to be executed
after arranging funds from different agencies, clearly indicating the Nigam’s share
required to be met with from the State Plan funds.
However, the following table shows the proposed outlay for the year 2006-07 that
has been prepared on the basis of funds allocation conveyed by the Finance Department,
Haryana.
Sr.No. Particulars Proposed outlay (Rs. in lacs) 1.
Normal Development 1000.10
2. System Improvement -
3. APDRP-II 1564.00
4. NABARD 50.00
5. HVDS (APDRP new Scheme) 600.00
6. Rajiv Gandhi Vidyutikaran Yojna 500.00
7. Separation of the rural feeder from mixed urban feeder 600.00
8. Area Load Dispatch Centre (ALDC) 430.00
9. Segregation of tubewell load from rural domestic 500.00
Total 5244.00
81
New Sub Stations & Lines
82
S/Stn., Badhra
83
from Ch-Dadri-II
20 Chhapar Bhiwani 8.2 KM 1x6.3/8 33/11
132 KV S/Stn. Atela Kalan
8.2 KM 33 KV line from Atela Kalan.
21. Jamalpur Shekhon Hisar 8 KM 1x6.3/8 33/11
132 KV S/Stn. Tohana
8 KM 33 KV line from Tohana.
22. Bhirdana Hisar 0.5 KM 1x6.3/8 33/11
132 KV S/Stn. Aherwan
Existing 33 KV Aherwan-Bhuthan
line shall be utilized for feeding this
S/Stn. on Upgradation of 33 KV
S/Stn. Bhuthan to 132 KV level.
84
Augmentations
Sr.No. Name of S/Stn. Name of T/F Voltage Capacity
Circle Capacity Ratio Addition
MVA KV MVA
85
33 kV Lines (New)
86
MAIN FEATURES OF STATE PLAN 2006-07
A provision of Rs.5244.00 lacs have been made in the State Plan under
various heads as mentioned below:
A Normal Development Program
Strengthening of distribution system in Haryana is a thrust area. Works are
being executed for improvement and strengthening of distribution system to take
up the load growth, to reduce technical and non technical distribution losses and
to ensure reliable power supply to consumers at appropriate voltage. Provision of
Rs. 1000 lacs has been made under this program during the annual plan 2006-07.
B APDRP
A provision of Rs. 1564 lacs has been made under APDRP-II for carrying
out developmental works in Faridabad and Hisar Operation Circles and the towns
of Sirsa, Bhiwani and Rewari.
C NABARD
To accommodate Nigam’s share i.e. 10% under RIDF-VII, 25% under
RIDF-VIII and 5% under RIDF-IX of the Nigam in the projects sanctioned under
NABARD Financial Assistance Scheme, a provision of Rs. 50.00 lacs has been
made under the State Plan.
D Implementation of High Voltage Distribution System (HVDS)
Benefits of the scheme are as under:
1. Helps in reduction of ATC (Aggregated Technical & Commercial) losses.
2. Reliable & uninterrupted Power Supply to the consumers. Thereby increasing
consumer satisfaction level.
3. Improvement in voltage of distribution system.
4. Reduced transformer damage rate.
5. Less trippings and breakdowns of distribution system.
This will help in proper accounting of energy for urban and rural areas
separately and in implementing the power regulatory measures properly. It will also be
useful for projections of future load growth for urban and rural sectors separately.
A provision of Rs.600.00 lacs has been made under the State Plan.
87
F Area Load Dispatch Centre (ALDC)
This scheme will help in proper energy accounting and load side
management.
A provision of Rs.430.00 lacs has been made under the State Plan.
This scheme has been introduced for electrification of rural area. Under
this scheme, all the RHH including BPL connections are to be released in addition
to the strengthening of distribution system.
A provision of Rs.500.00 lacs has been made under State Plan.
This scheme has been introduced for giving 24 hours supply to villages for
light purpose.
A provision of Rs.500.00 lacs has been made under State Plan.
88
ASSESSMENT OF FINANCIAL RESOURCES FOR THE FY 2005-
06(REVISED)
(All
figures are in Cr.)
Source of L S Consu O T
r. capital/Name of oan ubsidy/ mers wn otal
No Financial Inst. Grant/ Contribution Funds
Equity
Ministry of Power - - - - -
(GOI) through State Plan
(APDRP-II Scheme)
REC Ltd. 2 - - - 2
(APDRP Scheme)(Non- 2.42 2.42
APDRP)
PFC Ltd. 2 - - - 2
(APDRP-II 8.76 8.76
Scheme)(Non-APDRP)
NCR Planning 8 - - 2 1
Board (NCR Scheme-II) .37 .88 1.25
NABARD - - - - -
(APDRP Schemes)(Non-
APDRP)
P.M.G.Y. - - - - -
Normal - 2 - - 2
Development 5.39 5.39
Grand Total 5 2 - 2 8
9.55 5.39 .88 7.82
89
DETAIL OF PLAN & NON-PLANNED EXPENDITURE DURING
FY 2005-06 (Revised)
(All figures in Cr.)
PLANNED EXPENDITURE
1. Distribution
B) SYSTEM IMPROVEMENT -
D) A.P.D.R.P. -
E) N.A.B.A.R.D. -
2. Rural Electrification
F) P.M.G.Y. -
TOTAL 25.39
NON-PLANNED EXPENDITURE
90
ASSESSMENT OF FINANCIAL RESOURCES FOR THE FY 2006-
07
(All figures are in
Cr.)
Source of L S Consu O T
r. capital/Name of Financial oan ubsidy/ mers wn otal
No Inst. Grant/ Contribution Funds
Equity
Ministry of Power 1 - - - 1
(GOI) through State Plan 2.38 2.38
(APDRP-II Scheme)
REC Ltd - - - - -
(APDRP-II) - - - - -
(Non-
APDRP)
PFC Ltd. (APDRP- - - - - -
II) - - - - -
(Non-
APDRP)
NCR Planning 1 - - 3 1
Board 1.25 .75 5.00
(NCR Scheme-II)
NABARD
(APDRP Schemes) - - - - -
(Non-APDRP) 0 - - - 0
.50 .500
Normal - 1 - - 1
Development 0.00 0.000
Rajiv Gandhi - 2 - 3 3
Gramin Vidyutikaran 7.00 .00 0.000
Yojna
High Voltage - 6 - - 6
Distribution System .00 .000
Separation of Rural - 6 - - 6
Sector from mixed Urban .00 .000
91
Feeder
A.L.D.C. - 1 - - 1
0 0.00 0.000
Segregation of - 4 - - 4
1 tubewell load from rural .30 .300
domestic
R.E.C. System 1 - - - 1
2 Improvement GP:IF 8.030 8.030
Rashtriya Sam - 3 - - 3
3 Vikas Yojna .50 .500
Total 4 6 6 1
2.16 6.80 .75 15.71
92
DETAIL OF PLAN & NON-PLANNED EXPENDITURE DURING
FY 2006-07
(All
figures in Cr.)
PLANNED EXPENDITURE
1. Distribution
B) SYSTEM IMPROVEMENT -
D) A.P.D.R.P. -
E) N.A.B.A.R.D. 00.500
F) H.V.D.S. 06.000
TOTAL 36.800
NON-PLANNED EXPENDITURE
93
Budget proposal for the financial year 2006-07 and Revised Estimates for
the financial year 2005-06.
The revised budget estimates for the financial year 2005-06 have been
prepared after taking into account the actual receipts and expenditure for 6
months i.e. from 1-4-2005 to 30-9-2005 and projections for the remaining period
of the current financial year 2005-06. The Budget estimates for the financial year
2006-2007 have also been prepared on the basis of demand received from the
accounting units/circles and keeping in view the financial projection taken in ARR
for the year 2006-07, filed with the HERC. The same are discussed as under:-
2. POWER PURCHASES:
(Units in MU)
Sr. Particulars 2004-2005 Original Actuals Revised Budget
No. ACTUALS Budget for 4/05 to estimates Estimates
(Audited) estimate 9/05 (Ist 2005-2006 For 2006-
for 2005- six 2007
2006 months)
1 2 3 4 5 6
1 Power Purchased
i Total power 10026.89 11335.00 5463.31 11047.39 12393.02
purchased from
HVPNL (mu)
ii Less distribution 3280.51 3400.50 1770.75 3474.93 3779.87
losses (mu)
iii Percentage of 32.72 30.00 32.41 31.46 30.50
losses
iv Net Power 6746.38 7934.50 3692.56 7572.46 8613.15
available for sale
94
UHBVNL & DHBVNL, as decided by the State Govt. for allocation of RE subsidy
for the financial year 2005-06 & 2006-07. The budget demands of RE subsidy
for 2005-06 & 2006-07 have been kept as Rs.430.60 Crores + Rs.20.68 Crores
for Voluntarily Load Disclosure Scheme and Rs.517.37 Crores respectively.
WORKING RESULTS:-
(Rs. in Crores)
Sr. Particulars 2004-2005 Budget Actual for Revised Budget
No. ACTUALS estimate 4/05 to 9/05 estimates Estimates
(audited) 2005-2006 2005-2006 2006-2007
(original)
1 2 3 4 5 6 7
3(1) Revenue Receipt
i Sale of power 1855.00 2152.40 1035.39 2107.33 2320.10
ii Misc. Receipt 53.07 50.59 33.90 74.67 85.03
iii RE Subsidy from
State Govt.:-
a) By cash - - - - -
b) By adjustment 380.00 419.03 230.09 451.28 568.74
Total revenue 2288.07 2622.02 1299.38 2633.28 2973.87
receipt
95
Net interest & 34.17 43.29 17.56 37.65 49.61
financial charges
7 Commercial (202.74) (-)322.65 (-)17.66 (-)56.67 3.13
profit/loss (-)
8 Transferred to 11.88 - - - -
Regulatory
Assets (Net)
9 Prior period (1.21) - (0.45) (-)0.90 -
charges (Net)
Profit/(Loss) (192.07) (-)322.65 (-)18.11 (-)57.57 3.13
Circle-wise and Head Office Unit wise details of revenue receipt and expenditure
have been prepared and annexed with memorandum. The Division-wise distribution will
be shown in the Annual Financial Statement for the guidance of all D.D.Os/Executive
Authorities, after approval of budget proposal.
4. CASH DEFICIT:-
(Rs.in crores)
Sr. Particulars Original Budget Revised estimate Budget
No. Estimates 2005-2006 Estimates
2005-2006 2006-2007
1 2 3 4 5
1 Revenue Receipt
i-a) Sale of power 2152.40 2107.33 2320.10
b) Less revenue expected to be 129.14 126.44 139.21
in arrears(unrealized) (6%)
c) Net realization (a-b) 2023.26 1980.89 2180.89
ii Misc. Receipt 50.59 74.67 85.03
iii RE subsidy from State Govt.
:-
a) By cash - - -
b) By adjustment 419.03 451.28 568.74
Total revenue receipt 2492.88 2506.84 2834.66
2. Rev. Expenditure
i Power Purchased 2550.31 2262.27 2539.50
ii O&M expenses 26.26 24.29 28.49
iii Employees cost 208.64 220.75 214.74
iv Admn. & Gen.expenses 15.51 26.44 28.03
v Other debits 23.02 31.01 7.28
vi Contingency reserve 3.51 3.28 3.84
Total revenue Exp. 2827.25 2568.04 2821.88
3. Interest & Finance Charges 50.79 45.98 54.96
4 Repayment of loans to Financial Institutions
i) IDBI/SIDBI - - -
ii) REC 8.92 10.45 9.82
iii) PFC 3.03 2.64 4.50
iv) Govt. loan 4.14 5.78 7.02
96
Others 208.15 168.20 196.23
Sub Total 224.24 187.07 217.57
5 Total Revenue Expenditure 3102.28 2801.09 3094.41
+ Debt servicing(3+4)
6 Cash Deficit(1-5) (-)609.40 (-)294.25 (-)259.75
7 Loan for working capital 200.00 215.00 200.00
8 Net Deficit/Surplus (-)409.40 (-)79.25 (-)59.75
The DHBVNL is paying all power purchase bills to HVPNL, out of the
revenue to avail all admissible rebate being allowed by Central Power Utilities.
The arrears of HVPNL are being paid @ 1.5% of the arrears per month.
97
Total 121.33 104.73 133.06
The Misc. receipt during the financial year 2005-06 includes income from
surcharge equivalent to 20% of assessment value on the basis of norms allowed
by HERC subject to its actual realization and the same base has been adopted
for the financial year 2006-07.
The above results are without giving effect of FSA which is now introduced
@ 3P/Kwh and further to be paid to HPGCL against Power Purchase.
98
Chapter -13 (Manual -12)
99
Objectives of APDRP:
Hisar Circle:
Faridabad Circle:
100
the project cost of 7 no. Towns, namely Rewari, Bhiwani, Sirsa,
Hisar-II, Fatehabad, Tohana and Hansi has been sanctioned. Under DPR of
Rs. 44.05 Cr. Out of which Rs.22.04 Cr. has been spent up to 31.12.05 and the
remaining work of installation of consumer meter, feeder meter etc. is in
progress.
R.G.G.V.Y.:
101
additional T/Fs, HT/LT lines will be covered under this scheme and the tenders
are being called by the respective SEs (OP) Circles. The scheme is likely up to
completed in next two years.
102
Chapter - 14 (Manual - 13)
The Dakshin Haryana Bijli Vitran Nigam does not grant any concession,
permission or authorisation.
103
Chapter-15 (Mannual-14)
104
VOLTAGE VARIATIONS,
The Nigam shall maintain the voltages at the point of commencement of supply to
a consumer within the limits stipulated hereunder, with reference to declared
voltage:
*In the case of low voltage, +6% and -6%
• In the case of high voltage, +6% and -9%
• In the case of Extra High Voltage, +10% and -12.5%.
The complaints in regard with voltage variation (LT + 6%, HV +6% & -9%,
EHV +10% & -12.5%) where expansion of distribution net work is not involved,
shall be attended within 4 hours in city and towns and within 8 hours in rural area.
If it requires augmentation of LT distribution system the work shall be completed
within a period of 60 days. In case the augmentation of H.T./EHT distribution
system is required, the work will take a period upto 180 days. Opening of neutral
& neutral voltage exceeding 2% of supply voltage shall take maximum time of 4
hours. The D.H.B.V.N. Shall, however, inform the complainant within 2 hours of
receipt of complaint, about the time to be taken for redressal of complaint.
HARMONICS
105
g. Inverters/power rectifiers.
h. Railway traction loads.
DHBVN can also measure the level of harmonics generation of any customer on
receipt of complaint from other affected consumer (s).
The DHBVN shall follow the Voltage and Current harmonics distortion limit as
specified by the Authority in the Grid Connectivity Standards applicable to the
Distribution System.
COMPLAINTS OF METERS AND METRING SYSTEM
The DHBVN shall regularly inspect, check and test the meters. However, the
periodicity of such inspection shall not be less than that as may be provided by
the Central Electricity Authority in their regulations on installation and operation
of the meters.
The Nigam shall inspect, check or test the meter within 7 days of receipt of fee
from the consumer for this purpose. The slow and fast meters and creeping or
stick meters shall be replaced within 7 days of its being so established on
checking. The brunt meters, if cause is attributed to consumer shall also be
replaced within 7 days. In all other cases, the brunt meters shall be replaced
within 24 hours.
SHIFTING OF METER AND SYSTEM:
The shifting of meter/service connection will be completed within 15 days after
receipt of request alongwith prescribed charges. The shifting of LT/HT lines and
transformer structure shall, however, take a time upto 45 days and 60 days
respectively.
COMPLAINTS PERTAINING TO BILLING:
Incase no additional information is required, the complaint shall be rectified
within 24 hours and if additional information is required, it shall take time upto 7
days.
Reconnection of supply following disconnection shall be within 6 hours of receipt
of payment from consumer in cities and towns and within 12 hours of receipt of
payment in rural area. The period to be taken in refund of Advance Consumption
Deposits/ Consumption Security, meter security is upto 30 days after receipt of
request. The No Due Certificate shall be given latest by 5 PM next day of receipt
of request.
106
RELIABLITY OF SYSTEM:
The DHBVN shall make the endeavor to cater continuous supply to its
consumers. It will have to match the reliability indices benchmarks set by the
Haryana Electricity Regulatory Commission from time to time.
SCHEDULE – I
107
Failure Rural Area Alternat
involving e
Power arrange
Transforme ment,
r/ to
Equipment restore
etc. the
supply
to the
affected
area, to
be
made
within
24 hrs.
108
- Where up- Within about the Rs. 100 per
likely time
9% gradation of 60 days day or part
to be taken
LT thereof in
EHV = for
distribution each case of
+10% redressal of
system is default to
required complaint each affected
& -12.5
% consumer
Where up- Within subject to a
gradation of 180 maximum of
High days Rs 3000/-
Tension/ EHT
distribution
system is
required
109
9 Application Release of Within one month of Rs. 200 for Automati
for new supply where receipt of application each day of c
connection/ service is complete in all respect default,
additional feasible from along with prescribed subject to
load/ existing charges Section 44 of
Temporary network Act and also
Connection subject to a
maximum of
Rs 3000/-.
110
1 Conversion from LT to HT charges default c
and vice-versa subject to a
maximum of
Rs 3000/-.
1 Issue of No Due Certificates Latest by 5PM next day Rs. 100 for To be
5 of receipt of request each day of claimed
default
subject to a
maximum of
Rs 3000/-.
111
Shifting of Within 60 days after
Transformer receipt of request
Structure along with prescribed
charges
SCHEDULE – II
2 Line Breakdowns Cities and Towns Within 8 hours (12 hrs. if 95%
pole gets broken)
112
Where up- Within 60 days 90%
gradation of LT
distribution system
is required
113
Agriculture Pump Within 30 days after 80%
Sets attaining seniority (The
no. of new connections
shall be limited to the
target fixed for the year)
114
1 Distribution Transformer Urban areas Shall not
7 failure rate exceed
5% p.a.
a) LT
system,
between
+6% to -
6%
b) HT
system
between
+6% to –
9%
c) EHT
system,
between
+10% to
12.5 %
115
1 shall be computed separately for urban and Commissio
rural feeders. n will lay
down the
a) Average number of interruptions in 11KV
standards
feeders.
separately
b) Average duration of interruptions in 11KV later on.
feeders
SCHEDULE – III
Rural Area
Rural Area
Rural Area
116
Transformer / Rural Area
Equipment etc.
Restoration of
supply
Opening of 99%
neutral and
neutral voltage
exceeding 2%
of supply
voltage
Replace
slow/fast
meters
117
Replace
creeping or
stuck meters
Replace burnt
meters if cause
not attributable
to consumer
Replace burnt
meters in all
other cases
Release of 95%
supply where
Distribution
Network
expansion /
Commissioning
of New Sub
Station required
for providing
connection
Agriculture 80%
Pump Sets
1 Redressal of If no 99%
2 consumer’s complaint additional
regarding billing information is
required
118
If additional 99%
information is
required
Shifting of LT
/ HT Lines
Shifting of
Transformer
Structure
119
within the
limits
stipulated
hereunder
a) LT
system,
between
+6% to -6%
b) HT
system,
between +
6% to -9%
c) EHT
system,
between
+10% to –
12.5%
120
Chapter 16 (Manual -15)
1. Structure of DHBVN
2. Detail data of DHBVN
3. Financial data of DHBVN
4. Financial Accounting of DHBVN
5. Revenue record and billing
6. Annual budget
7. Annual plan
8. Pay and salary details of employees
9. Sales manual
10. Citizen charter
11. Information necessary to publish under provisions of the Right to
Information Act - 2005.
12. Tender Notices
Note: The obsolete information is generally removed from the computer disk.
121
Chapter - 17 (Manual - 16)
122
Chapter 18 (Manual - 17)
Other useful information
NEW CONNECTION
Detail of Papers/Documents Required to be Submitted to Get New Connections
Sr. Category Documents to be deposited by the consumer for new
connection
1. Domestic/Non i) A&A form
domestic(DS/NDS ii) Passport size photograph of applicant
) iii) Registration deed/House Tax Notice from
Municipal Committee and copy of
allotment letter from
HUDA/HSIDC/Group Housing
Society/Housing Board/
iv) Consent of House Owner on the non-
judicial Stamp Paper worth Rs 15/-
alongwith Indemnity Bond shall be
submitted by tenant of the house if he
requests for new/separate connection.
v) Photo copy of Ration Card/Voter
Card/Pan No. /Driving Licence.
vi) Fitting Test Report by authorized
contractor.
i) A&A form
2. a) L.T. Industrial ii) Passport photograph of applicant
connection upto iii) Registration Deed/House Tax Notice
load of 20 K.W. from Municipal Commitee.
iv) A copy of allotment Letter fromHUDA-
B) Load above HSIDC.
20KW and upto 50 v) In case tenant applies for connection,the
KW for L.T. consent of the owner of House /Plot
industrial required on legal paper.
connection. vi) Photocopy of Ration Card. Voter
Card/PAN No. Driving License.
vii) A copy of partnership deed/
memorandum and articales of association.
viii) Declaration by applicant regarding
acceptance and following the rules &
condition of the Nigam, on the non
judicial Stamp Paper worth Rs.3/-
ix) Fitting test report by authorized
contractor.
123
3. H.T. Industrial i) A&A Form
connection above load of ii) Passport size photograph of applicant
50 K.W. iii) Registration Deed/House Tax Notice
form Municipal Committee/a copy of
allotment letter from HUDA/HSIDC
iv) In case applicant is tenant, consent of the
owner is required on legal paper.
v) Photocopy of Ration Card, Voter Card,
Pan No, Driving Licence, etc.
vi) Photo copy of the board of directors,
decision vide which applicant has been
authorized for signature.
vii) Drawing Map of the planning in which
spot for installlation of meter adjoining
the main door is shown.
viii) No Objection Certification from Water &
Air Pollution Control Board.
ix) Copy of partnership deed/Memorandum
& articles of Association and declaration
by applicant on non judical paper worth
Rs. 3/- regarding acceptance and
following the rules and conditions.
x) Fitting report by authorized contractor.
xi) Approval of Chief Electrical Inspector.
i) A&A From
4. Agriculture Tubewell ii) Passport size photograph of applicant
( A.P.) iii) Ownership of the land i.e. latest revenue
document (FARD)
iv) Photocopy of Ration Card/Voter/PAN
No./ Driving Licence.
v) Fitting Test Report by authorized
contractor.
124
2. Change of Within seven days after receipt of
ownership/change complete application.
of category.
3. Change of L.T. Within 30 days after receipt of
Single to L.T. dues/ prescribed amount.
three phase,
change of L.T.to
H.T. And change
of H.T. to L.T.
125
DETAIL OF APPLICABLE CHARGES FOR AVAILING NEW ELECTRIC CONNECTIONS
Category Processing Consumption Cost of Meter/Metering Equipment Service Development Charges if Other Charges
Charges Deposit Connection premises is situated in
Charges/ unauthorized area
Fixed Charges
DS Rs. 10 up Rs. 500 per Single Phase Rs. 650+50 Nil Rs. 15/sq-yd if total area of if the service line
to 2 KW KW. or Part Three Phase upto 10 KW premises is upto 100 sq-yd is more than 30
load and thereof Rs. 700+100 Rs. 25/sq-yd if total area of Mtr.
beyond Three Phase with MDI facility for premises is more than 100 then applicant has
two KW above 10 KW sq-yd to deposit the
load Rs. upto 35 KW Rs. 3850+100 unjustified
25 per For above 35 KW upto 50 KW cost of the
KW or LTCT connected three phase four wire estimate
part electronic meters. Rs. 4900
thereof LTCTs
limited to Upto 75/5 AMP Rs. 425x4= Rs. 1700
maximum Above 75/5 AMP Rs. 565x4= Rs.2270
Rs. HT Supply for loads above 50 KW
10,000/- Meter Rs. 6100
127
NDS -do- Rs. 1000 per 11KV CT Set 5/5 AMP. Rs.9540 Rs. 350 per Rs. 5000 in addition to If the length of
KW. 11KV CT Set 10/5 AMP. Rs. 8800 KW for Single Rs. 15/s1-yd if total area of new line
11KV CT Set 15/5 AMP. Rs. 8450 Phase Rs. 750 premises is upto 100sq-yd (including LT/HT
11KV CT Set 30/5 AMP. Rs. 5540 per Rs. 25/sq-yd if total area line or
11KV CT Set 35/5 AMP. Rs. 5540 KW for Three of cable) to be
11KV CT Set 40/5 AMP. Rs. 5350 Phase premises is more than provided is more
11KV CT Set 50/5 AMP. Rs. 5140 100sq-yd. than 300 Mtr.
11KV CT Set 60/5 AMP. Rs. 4650 then the additional
11KV CT Set 80/5 AMP. Rs. 5240 cost would be
11KV CT Set 100/5 AMP. Rs. 5240 chargeable @
11KV CT Set 150/5 AMP. Rs. 4440 Rs. 70 per Mtr. for
11KV CT Set 175/5 AMP. Rs. 4555 load upto 50 KW.
11KV CT Set 200/5 AMP. Rs. 4740 and Rs. 100 per
11KV CT Set 450/5 AMP. Rs. 3450 Mtr.
11KV CT Set 500/5 AMP. Rs. 3450 for load exceeding
11KV CT Set 1400/5 AMP. Rs. 4250 50 KW. No
11KV Oil Field PT Rs. 10800 component of
distribution
(For CTs & PTs Meters 2% Cost of substation
Meter/Metering equipment subject to a transformer to be
Minimum of Rs. 300/- to be charged for created is to be
installation of the same) charged
128
-do- Rs. 500 per installation of the same) Rs. 500 Per Rs. 10000 in addition to If the length of
LT KW. or part KW above new line
Industrial thereof Rs. 15/sq-yd if total area of (including LT/HT
Connection premises is up to 100 sq-yd line or cable)
Rs. 25/sq-yd if total area of to be provided is
premises more than 300
is more than 100 sq-yd. Mtr. then the
additional cost
would be
chargeable @ Rs.
70 per Mtr.
for load upto 50
KW. No
component of
distribution
substation
transformer to be
created is to be
charged
129
HT -do- Rs. 750 per Rs. 750 per No Charges If the length of
Connection KW or part KVA new HT line/cable
On 11 KV thereof (Service is to be provided
(One third of connection more than 300
the total ACD charges may Mtr. then the
may be be deposited at additional cost
deposited at the would be
the time of time of charged @ Rs. 100
submittion of compliance per Mtr.
the of demand
application. notice)
Balance two
third at the
time of
compliance of
demand
notice)
130
Bulk -do- Rs. 1000/- per Rs. 500 per In case of LT Supply If the length of
Supply KW or part KW Rs. 10000 in addition to new line
thereof Rs. 15/sq-yd if total area of (including LT/HT
premises upto 100 sq-yd line or cable)
Rs. 25/ sq-yd if total area to be provided is
of more than 300
premises is more than 100 Mtr. then the
sq-yd additional cost
In case of HT Supply No would be
Charge chargeable @ Rs.
70 per Mtr.
for load upto 50
KW and Rs. 100
per Mtr. for load
exceeding 50 KW.
No component of
distribution
substation
transformer to be
created is to be
charged
Agriculture -do- Rs. 100 per Rs. 20000 No Charges Rs. 7000 per sapn
Supply KW. of HT/LT line
would be
deposited
after preparation
of estimated when
demanded
131
Street light -do- Rs. 2000 per No Charges No Charges Full deposit cost
Supply KW or part of the estimated is
thereof to be deposited by
the applicant after
preparation of
estimated when
demanded
Temporary Four times the relevant No Charges No Charges Full deposit cost
Supply charges to be recovered of the estimate is
under normal category to be deposited by
applicant after
preparation of
estimate
132
TARIFF SUMMERY
Note: These tariffs are exclusive of the fuel cost adjustment as per HERC regulations.
2. Non-Domestic
All units 419 Rs. 120 upto 1 KW of
Connected load and Rs. 100
Per KW or part thereof in
Excess of 1 KW.
3. H.T. Industry
(70 KW and above) 409 (at 11 KV) Rs. 200 per KVA of the
397 (at 33 KV contract demand for general
385 (at 66/132 KV) HT industry and Rs. 250 per
377 (at 220 KV) KVA of the Contract
Demand for steel furnaces /
Rolling Mills, etc.
4. L.T.Industry
( less than 70 KW) 428 Rs.200 per KW
133
5. Agriculture Metered 25 paise per unit
Agriculture unmetered Rs. 35 per BHP per month
Minimum Charges Rs. 200 per BHP per year
6. Irrigation
Direct irrigation tubewells 400 Rs. 150 per BHP
Augmentation Canals 400 Rs. 150 per BHP
Lift irrigation 400 Rs. 150 per BHP
8. Bulk Supply
Domestic 419 (at LT) Rs. 200 per KW or part
Non-domestic 409 (at 11 KV) thereof.
& others 397 (at 33 KV)
385 (at 55/132 KV)
377 (at 220 KV)
NOTE:
1. Electricity Duty at the rate of 10 paise per unit is applicable on all categories of
consumers except lift irrigation, agriculture, village Chaupals,MITC Tubewells
and Augmentation Canals.
2. Fuel surcharge would be levied on all categories of consumers as approved by
HREC from time to time.
3. Municipal tax at the rate of 5 paise per unit is charged extra on consumers located
in Municipal areas.
134
SCHEDULE OF GENERAL CHARGES
Note: if the challenged meter is found to be incorrect, the credit of these charges will be
given to the consumer otherwise these will be forfeited.
3. Changing the meter or its position in the same premises at the request of the
consumer when no additional material is required:
135
5. Reconnection Charges
6. Fuse replacement
136
H E R C 'S T A R I F F O R D E R
TARIFFS
********
137
INSTRUCTION NO. 5.2
Schedule of Tariff for – Domestic Supply
(i) Availability
Available to consumers for lights, fans, domestic pumping sets and household
appliances in the following premises: -
i) Single private house/ flat.
ii) Hostel of Educational Institutions (including Mess/Canteen).
iii) Working Women’s hostels run by Red Cross and Social Welfare
Department.
iv) Anganwadi Workers’ training Centres set up by Indian Council for
Child Welfare.
v) Places of public worship such as Mandirs, Masjids, Churches,
Gurdwaras.
vi) Village Chaupal owned by Gram Panchayat/ Communities.
vii) Elementary School i.e. Government Primary and Middle Schools.
NOTE:
i) Private dwelling, in which space is occasionally used for the conduct of
business by a person residing therein, shall also be served under this
tariff.
ii) Where a portion of the dwelling is used regularly for the conduct of a
business, the consumption in that portion shall be separately metered and
billed under the appropriate Non-Domestic or Industrial power tariff. If
separate meters are not provided, the entire supply will be classified under
Non-Domestic supply.
iii) Resale of energy is strictly prohibited except where necessary permission/
exemption is granted by Haryana Electricity Regulatory Commission.
iv) A hostel shall be considered as one unit and billed without compounding.
The supply for residential quarters/ flats attached to the educational
institutions for staff-members shall not be compounded.
v) Any other part of the building excluding the place of worship like shops
and allied institutions attached to such places would be separately
138
metered and billed under non domestic tariff. In case separate connection
is not obtained the entire consumption shall be billed on non-domestic
schedule of tariff.
(ii) Character of Service.
A.C, 50 Cycles, single phase, 230 volts
A.C. 50 cycles, three phase, 400 volts (for load above 5 kW but upto 70 kW);
A.C. 50 cycles, three phase, 11000 volts or higher voltage (Above 70 kW).
iii) Tariff
First 40 units per month. 263 paise per Kwh.
Above 40 units per month upto 363 paise per Kwh.
300 Units per month
Above 300 units per month 428 paise per Kwh
iv) Fuel Surcharge Adjustment (FSA)
As per applicable charges calculated in accordance with the Haryana Electricity
Regulatory Commission (Tariff) Regulations, 1999 as amended from time to time.
v) Monthly Minimum Charges (MMC)
The monthly minimum charges (excluding service charges) will be as under :-
a) Upto 1 kW Rs. 60/-
b) Above 1 kW Rs. 60/- plus Rs. 40/- for every additional
kW in excess of 1 kW e.g., a consumer
having a connected load of 1.5 kW will
be assessed MMC of Rs. 80 per month.
vi) Payment.
In the event of the bi-monthly bill not being paid in full within the period specified
in the bill, a surcharge at the rate of 5% shall be levied for each billing cycle of 2
months on the unpaid amount of the bill until the amount is paid in full.
********
139
Available to consumers for lights, fans, appliances and small motors to all non-
residential premises such as: -
i) Business houses.
ii) Cinemas.
iii) Clubs
iv) Public offices.
v) Schools.
vi) Hospitals
vii) Hotels.
viii) Street lighting in Anaj Mandi.
ix) Single point street light connection to HUDA in cases where HUDA erects
its own complete street light system and undertakes to maintain the same.
NOTE.
Resale of energy is strictly prohibited except where necessary permission/
exemption is granted by Haryana Electricity Regulatory Commission.
Character of Service.
A.C, 50 Cycles, single-phase, 230 volts.
A.C, 50 Cycles three-phase, 400 volts, (for load above 5 kW but upto 70 kW).
A.C, 50 Cycles, three-phase, 11000 volts, or higher voltage (Above 70 kW)
(iii) Tariff.
419 paise per kwh.
(iv) Fuel Surcharge Adjustment (FSA)
As per applicable charges calculated in accordance with the Haryana Electricity
Regulatory Commission (Tariff) Regulations, 1999 as amended from time to time.
(v) Monthly Minimum Charges (MMC)
The monthly minimum charges (excluding service charges) will be applicable as
under: -
a) Upto 1 kW Rs. 120/-
b) Above 1 kW Rs. 120/- plus Rs. 100/- for every
additional kW in excess of 1 kW e.g. a
consumer having a connected load of
140
1.5 kW will be assessed MMC of Rs. 220
per month.
(vi) Payment.
In the event of the monthly/ bi-monthly bill not being paid in full within the period
specified in the bill, a surcharge at the rate of 2%/5 % shall be levied for each
billing cycle on the unpaid amount of the bill until the amount is paid in full.
********
141
factory will be separately metered and billed under schedule ‘DS’ for connections
having load above 20 kW but upto 70 kW.
(vi) Monthly Minimum Charges (MMC)
a. The monthly minimum charges (excluding service charges) shall be Rs.
120 per kW or part thereof for the connected load upto 20 kW and Rs.
150/- per kW or part thereof for the connected load exceeding 20 kW.
b. The industrial consumers seeking temporary disconnection of supply shall
submit their written requests giving therein specific reasons for the same
to SDO (OP)concerned at least one month in advance of the date from
which the disconnection is being sought. Such requests for a maximum
period of six months shall be examined and decided by concerned
Executive Engineer keeping in view the merits
of each case. The request for temporary disconnection beyond a period of
six months shall be referred by respective SEs
to concerned Chief Engineer (OP) for decision. While considering such
requests for temporary disconnections, the following guidelines are to be
kept in view: -
i) The consumer is not a defaulter of Nigam’s dues, whether disputed
or undisputed.
ii) The consumers seeking temporary disconnection under “Force
Majeure Clause” are not required to submit their requests one month in
advance as stipulated under above paragraph.
iii) The force Majeure Conditions for the purpose of this clause will
include only the following: -
a) Acts of God e.g. floods, Tempests, Earthquakes, Lightning.
b) Acts of Civil and Military Authorities e.g. Wars, Mutiny, Civil
commotion/disturbances, Riots.
c) Fires, Strikes, Lockouts.
Note : The disputes between partners, shortage of funds and raw materials etc.
will not be considered as Force Majeure reasons under this clause.
iv) The disconnections sought under Force Majeure reasons must be
142
supported by documentary evidence issued by concerned Civil
Authorities.
v) The Temporary Disconnection Order (T.D.C.O.) under Force Majeure
reasons can be allowed even beyond a continuous period of 12 months by
CE (OP) concerned. The CE (OP) will however, submit periodical report
after every six months relating to temporary disconnections allowed by
him to the Chief Engineer/Commercial of the Nigam.
vi) The requests for further-extension of temporary disconnection who have
been allowed TDCO for a period upto 12 months shall be considered only
after a minimum period of six months from the date upto which the last
disconnection was allowed. For example in case a consumer seeks
temporary disconnection for 12 months and the same is approved from
01.01.2005 to 31.12.2005 and if he applies for further extension the same
will not be allowed before 1st July, 2006. During the intervening period i.e.
for the period 1st January 2006 to 30th June 2006, he will be billed on
normal tariff as if there were no temporary disconnection.
vii) The industries, which are allowed temporary disconnection, will pay minimum
charges for one month following the month in which temporary disconnection has
been allowed and no MMC will be levied thereafter. Since MMC will be charged
for the first month of the TDCO, the consumer will be entitled for consuming
electricity equivalent to MMC in that billing month.
viii) Separate NDS connection
a) The existing or new LT industrial consumers can seek a separate single
phase NDS connection upto a load 5 kW on the same premises having
regular industrial connection for the purpose of meeting the requirement of
lighting etc. for offices, security, elevators, pumps etc. The consumer
through this connection shall not perform any industrial activity even
during temporary disconnection period of their regular industrial
connection.
b) This connection would be treated as a separate and distinct NDS
connection altogether from the regular industrial connection and will be
143
considered as a new connection.
c) This connection will be available to the consumer even during the
temporary disconnections of industrial connections.
d) The wiring and the connected load for this NDS connection will be
physically & distinctly separated from the wiring of the regular industrial
connection at all times & shall be connected to only lighting loads.
e) The shifting of load from this NDS connection to the regular industrial
connection will be treated as an act of un-authorized use of electricity and
will be treated as per applicable instruction /policy of the Nigam.
f) The Location of the metering arrangement for this NDS connection will be
separate from the metering arrangement of their industrial connection and
will not be tapped from the existing LT Industrial connection.
With the provision of a separate connection in the NDS category for
factory lighting purposes, the facility to consume upto 5% of the
monthly average consumption of preceding 6 months for factory
lighting is not available to the consumer. And while effecting the
TDCO of the LT industrial consumer the same shall be effected by
disconnecting / removing of all 3 phases.
(ix) In few cases, Nigam is not in a position to release separate NDS connection
as above due to non-availability of LT lines within a radius of 300 meters. In such
cases during the period of temporary disconnection beyond one month, the
consumption of industry for repair work and factory lighting, if any, upto 5% of the
monthly average consumption of preceding six months (or less, if 6 month
consumption is not available) will be charged at 200% of the normal tariff. In
case of excess consumption than the said limit of 5%, the temporary
disconnection facility shall be considered to have been withdrawn from that
month and the consumer shall be billed on normal tariff as if there were no
temporary disconnection.
(vii) Capacitor Surcharge
a. All the consumers are required to install shunt capacitors of adequate
rating and of ISI mark manufactured by the standard firms approved by
144
the Licensee. No new connection shall be released without installation of
such shunt capacitors. Rating of LT shunt capacitors required to be
installed on various sizes of motors shall be as under :-
Sr. Rating of KVAR rating of LT capacitors for
No. motors various R.P.M. of the Motors.
(BHP)
750 RPM 1000 RPM 1500
RPM
1 3 1 1 1
2 5 3 2 2
3 7.5 4 3 2
4. 10 5 4 3
5. 15 7 5 4
6. 20 9 7 5
7. 25 10 9 7
8. 30 12.5 10. 7.5
9. 40 15 12.5 10
10. 50 20 15 12.5
11. 60 22.5 17.5 15
12. 75 25 20 17.5
13. 90 30 25 20
14. 100 35 25 22.5
145
onwards shall be applied to the original sanctioned load plus the excess load till
complete papers along with Advance Consumption Deposit are submitted for
regularising such extension in connected load.
Where the MDI meters have been installed the charges shall be levied from the
month in which the excess load is recorded and shall be continued to be charged
till the excess connected load is got regularized or the intimation regarding
removal through test report is submitted.
Where category is changed i.e. load is found above 70 kW.
If there is a change of category from LT to HT due to unauthorized extension in
load recorded by the Maximum demand indicator or as per physical checking of
the inspecting officer, the consumer shall be charged HT tariff for that month with
LT Surcharge @ 25% along with penalty for unauthorized load @ Rs. 70/- per
kW. The MMC shall also be worked out on the extended load. In future, the
consumer shall be treated as a HT industrial Consumer having supply on LT with
provisional contract demand as 70 kW and shall be charged/ billed accordingly till
he shifts to HT or submits written intimation (through test report) of having
disconnected such unauthorized extended load. A notice to this effect shall also
be issued to the consumer by the concerned SDO immediately after the load is
found exceeded beyond 70 kW.
(ix) Payment.
In the event of the monthly bill not being paid in full within the time specified in
the bill, a surcharge of 2% shall be levied on the unpaid amount of the bill for
each 30 days successive period or part thereof until the amount is paid in full.
(x) Single Point Delivery.
The above tariff is based on the supply being given through a single delivery and
metering point and at a single voltage. Supply at other points or at other voltages
shall be separately metered and billed.
********
Schedule of Tariff for – H.T. Industrial And Steel Furnace Power Supply.
146
(i) Availability.
Available as primary power for load exceeding 70 kW to,
a) All industrial consumers.
b) Arc furnaces and mixed load of Arc furnaces and steel rolling mills.
c) For all other steel furnaces (including induction furnaces and stainless
steel furnaces), Steel Rolling Mills (including cold rolling/ re-rolling, steel/
stainless steel mills), mixed load of such steel furnaces and steel rolling
mills.
d) Flood de-watering pumping sets installed by the Govt.
e) Lift irrigation system installed by the Govt.
(ii) Character of Service.
A.C. 50 cycles, 3 phase 11 KV or higher voltage.
For Arc Furnaces & mixed load of Arc furnaces & Steel Rolling Mills, the voltage
of supply would be 33 KV and above, depending upon availability of bus voltage
at the feeding end substation, wherever possible at the discretion of the Nigam.
(iii) Tariff.
Energy Charges for
a) Industrial consumers Paise Note: For this
except Lift irrigation/ water 409 per purpose energy
works connection having kwh charges shall also
load above 70 kW include fuel
b) Lift irrigation/ water works Paise surcharge and
connection having load 400 per Peak Load
above 70 kW kwh Exemption
Charges.
Notes:
a) The above tariff covers supply at 11 KV. For supply at 3.3 KV and 400 Volts, a
surcharge of 10% and 25% respectively is leviable. For supply at 33 KV, the tariff
would be 397 paise per kwh; for supply at 66 KV or 132 KV, the tariff would be
385 paise per kwh; and for supply at 220 KV, the tariff would be 377 paise/ kwh
excepting such industry as may be covered in Note (b) below.
b) A surcharge of 15 paise per kwh on the above tariff shall be leviable for all Arc
furnaces mixed load of Arc furnaces and steel rolling mills, all other steel
furnaces (including induction furnaces and stainless steel furnaces). Steel
147
Rolling Mills (including cold rolling/ re-rolling steel/ stainless steel mills), mixed
load of such steel furnaces and steel rolling mills, which are being given supply
on 11 KV. For supply on 33 KV and above, no surcharge is leviable.
c) The demand for any month shall be defined as the highest average load
measured in kilovolt amperes during any thirty consecutive minute’s period of the
month.
d) In case supply has been given on H.T. but is metered on L.T. side, the energy
consumption of such consumers shall be increased by 3% of the recorded
consumption on account of transformation losses.
e) For new connections, all metering will be on HT side only.
(iv) Fuel Surcharge Adjustment (FSA)
As per applicable charges calculated in accordance with the Haryana Electricity
Regulatory Commission (Tariff) Regulations, 1999 as amended from time to time.
(v) Factory lighting and Colony Supply.
All consumption for bona-fide factory lighting including those of canteen and
Hospital, factory staff quarters, street lighting of the colony and the shopping
centre within the factory premises shall be included for the charge under the
above tariff.
(vi) Monthly Minimum Charges (MMC)
a) Monthly minimum charges (excluding service charges) shall be Rs. 250/-
per kVA of the contract demand in case of consumers as defined in (i) (b)
and (i) (c) above. The monthly minimum charges ( excluding service
charges) shall be Rs. 200/- per kVA of the contract demand in case of
other consumers defined therein i.e. (i) (a), (d) and (e).
b) The industrial consumers seeking temporary disconnection of supply shall
submit their written requests giving therein specific reasons for the same
to SDO (OP) concerned at least one month in advance of the date from
which the disconnection is being sought. Such requests for a maximum
period of six months shall be examined and decided by concerned
Superintending Engineer keeping in view the merits of each case. The
request for temporary disconnection beyond a period of six months shall
148
be referred by respective SEs to concerned Chief Engineer (OP)for
decision. While considering such requests for temporary disconnection,
the following guidelines are to be kept in view :-
i) The consumer is not a defaulter of Nigam’s dues, whether disputed or
undisputed.
ii) The consumers seeking temporary disconnection under “Force
Majeure Clause” are not required to submit their requests one
month in advance as stipulated under above paragraph.
iii) The Force Majeure Conditions for the purpose of this clause will
include only the following: -
a) Acts of God e.g. Floods, Tempests, earthquake, and lightning.
b) Acts of Civil and Military Authorities e.g. Wars, Mutiny, Civil
commotion/ disturbances, Riots.
c) Fires, Strikes, Lockouts.
Note : The disputes between partners, shortage of funds and raw materials etc.
will not be considered as Force Majeure reasons under this clause.
iv) The disconnections sought under Force Majeure reasons must be
supported by documentary evidence issued by concerned Civil
Authorities.
v) The Temporary Disconnection Order (T.D.C.O.) under force
Majeure reasons can be allowed even beyond a continuous
period of 12 months by CE (OP) concerned. The CE (OP) will,
however, submit periodical report after every six months relating
to temporary disconnections allowed by him to the Chief
Engineer/Commercial of the Nigam.
vi) The requests for further extension of temporary disconnection
who have been allowed T.D.C.O. for a period up to 12 months
shall be considered only after a minimum period of six months
from the date upto which the last disconnection was allowed, for
example in case a consumer seeks temporary disconnection for
12 months and the same is allowed from 01.01.2005 to
149
31.12.2005 and if he applies for further extension, the same will
not be allowed before 1st July, 2006 to 30th June 2006, he will be
billed on normal tariff as if there were no temporary disconnection.
vii) The industries, which are allowed temporary disconnection, will
pay minimum charges for one month following the month in which
temporary disconnection has been allowed and no MMC will be
levied thereafter. Since MMC will be charged for the first month of
the TDCO, the consumer will be entitled for consuming electricity
equivalent to MMC in that billing month.
viii) Separate NDS connection
a) The existing or new HT industrial consumers can
seek a separate single phase NDS connection upto a load 5 kW on
the same premises having regular industrial connection for the
purpose of meeting the requirement of lighting etc. for offices,
security, elevators, pumps etc. The consumer through this
connection shall not perform any industrial activity even during
temporary disconnection period of their regular industrial
connection.
b) This connection would be treated as a separate and distinct NDS
connection altogether from the regular industrial connection and will
be considered as a new connection.
c) This connection will be available to the consumer even during the
temporary disconnections of industrial connections.
d) The wiring and the connected load for this NDS connection will be
physically & distinctly separated from the wiring of the regular
industrial connection at all times & shall be connected to only
lighting loads.
e) The shifting of load from this NDS connection to the regular
industrial connection will be treated as an act of un-authorized use
of electricity and will be treated as per applicable instruction/ policy
of the Nigam.
150
f) The Location of the metering arrangement for this NDS connection
will be separate from the metering arrangement of their industrial
connection and will not be tapped from the existing HT Industrial
connection.
With the provision of a separate connection in the NDS category for
factory lighting purposes, the facility to consume upto 5% of the
monthly average consumption of preceding 6 months for factory
lighting is not available to the consumer. And while effecting the
TDCO of the HT industrial consumer, the same shall be effected by
disconnecting/ removing of all 3 phases.
ix) In few cases, Nigam is not in a position to release separate NDS
connection as above due to non-availability of LT lines within a radius of
300 meters. In such cases during the period of temporary disconnection
beyond one month, the consumption of industry for repair work and factory
lighting, if any, upto 5% of the monthly average consumption of preceding
six months (or less, if 6 month consumption is not available) will be
charged at 200% of the normal tariff. In case of excess consumption than
the said limit of 5%, the temporary disconnection facility shall be
considered to have been withdrawn from that month and the consumer
shall be billed on normal tariff as if there were no temporary disconnection.
(vii) Contract Demand.
a) The contract demand means the maximum kW/kVA for the supply of
which the Licensee undertakes to provide facilities from time to time.
b) In case the consumer exceeds his Contract Demand in
any month by more than 5%, a surcharge of 25% will be
levied on the Sale of Power (SOP)/monthly minimum charges (Industrial,
Factory Lighting and Colony Lighting).
c) If in any case the maximum demand is being measured in kW, the same
shall be converted in kVA by the use of actual power factor.
(viii) Power Factor
The monthly average power factor of the plant and apparatus installed by the
151
consumer shall not be less than 90% lagging. The monthly average power factor
shall mean the ratio expressed, as percentage of total kWh to total KVAH
supplied during the month. The ratio shall be rounded upto two figures. In case
the 3rd figure is 5 or more than 5, then the figure at the second decimal place
shall be increased by one. In case the monthly average power factor falls below
90% lagging, the consumer shall have to pay a surcharge of 1% of SOP charges
for every 1% decrease in the power factor upto 80% and 2% of SOP charges for
every 1% decrease in power Factor below 80%. Rebate of 0.5% on SOP will be
allowed for every 1% increase in Power factor above 90%.
The rebate/ surcharge on account of power factor being higher/ lower than
the 90% is also applicable where the consumer is billed on MMC basis. In
such case, the rebate/ surcharge shall be allowed/ levied on actual SOP
charges and shall be deducted/ added to the monthly minimum charges in
case a consumer is billed on MMC basis.
(ix) Peak Load Exemption Charge (PLEC).
The H.T. industrial consumers where metering is though Electronic Tri-vector
Meters, using electricity by availing permitted special dispensation or exemption
during peak load hours notified by the Licensee from time to time shall be billed
at extra charge of Rs. 2/- per kWh over and above the normal tariff on the
consumption recorded by the Electronic Tri-vector Meter during this period. If the
consumption of a consumer during peak load hours in a month exceeds the
prescribed limit, the consumption during peak load hours shall be charged @ Rs.
4/- per kWh extra over and above the normal tariff. The permissible load
equivalent to percentage of contract demand during peak load hours shall be
converted into units by the following formula.
Permissible Contract demand allowed in kVA x
consumption = during Average standard power factor x
the month No. of peak load hours x 30
Note: Average standard power factor shall be taken as 0.90
All HT industrial consumers with Electronic Tri-vector Meters, who have not
sought/ granted special dispensation, can avail 10% of Contract demand during
peak load hours and the consumption recorded during such peak load hours
152
shall be subject to additional charge and regulated as mentioned above.
(x) Payment.
In the event of the monthly bill not being paid in full within the time specified in
the bill, a surcharge of 2% shall be levied on the unpaid amount of the bill for
each 30 days’ successive period or part thereof until the amount is paid in full.
(xi) Single Point Delivery.
The above tariff is based on the supply being given through a single delivery and
metering point and at a single voltage. Supply at other points or at other voltage
shall be separately metered and billed.
********
153
NOTE:
The twelve months period for determining the Annual minimum charges
(AMC) shall be taken as 1st November to 31st October. The recoveries
shall however be regulated on monthly basis after reviewing half yearly in
May and November to be finally adjusted annually.
c) Private Irrigation Tube well (Flat Rate un-metered Supply):
(Upto 20 kW or 26 Flat Rate Rs.35/- BHP/Month.
BHP)
NOTES {for (b) and (c) above}.
i) The existing flat rate tube well consumers on rural feeders shall have
the option to be governed under metered supply rate. Prospective
tubewell consumers will be given only metered supply. The tube well
consumers given supply from urban feeders shall be given metered
supply only.
ii) The consumption for bona-fide lighting of the pump or machine house
upto 2 light points with a total candle power of 80 watts shall be
allowed free of cost per tube well connection for private Irrigation tube
well at ‘c’ above and for metered tube- wells at ‘b’ it will be included in
the metered consumption.
iii) The consumption of energy made through plug points shall be charged
at the rate of Rs. 5/- per plug point per month for private Irrigation Tube
wells at ‘c’ above and for metered Tube wells at ‘b’, it will be included
in the metered consumption.
iv) A.P. consumers running industries other than threshers and chaff
cutters on their tubewell connections irrespective of the quantum of
connected load shall be given metered supply and charged under
relevant industrial tariff. They shall however, be subjected to minimum
charges as provided in the relevant industrial tariff.
v) The facility of temporary disconnection is available to metered agriculture
pumping supply consumers in single crop belt on following conditions:-
(a) This facility shall be available to the metered Agricultural Pumping
154
supply consumers in single crop belt comprising Gurgaon,
Faridabad, Bhiwani, Rewari and Narnaul districts.
(b) The facility shall not be available to such metered AP consumers
who fall within Command Area of Canal Irrigation System, in above
districts.
(c) No light load shall be provided while resorting to physical
disconnection, which shall be by way of removal of jumpers of
service line cable from terminal pole of LT line or Distribution Sub-
Station as the case may be. Any such consumers opting for TDCO,
if desirous of having lighting load, shall apply for a separate
domestic connection, which shall be granted under a separate
seniority for DS consumers.
(d) The facility of TDCO shall be available between May and October
on receipt of request during April.
(e) As levy of MMC is stopped one month after TDCO, the existing
MMC for Metered AP connections which is adjustable over a yearly
cycle shall accordingly get reduced to 7/12th of existing MMC i.e.
Rs.200/- per BHP/Annum.
(iv) Fuel Surcharge Adjustment(FSA)
As per applicable charges calculated in accordance with the Haryana Electricity
Regulatory Commission (Tariff) Regulations, 1999 as amended from time to time.
(v) Capacitor Surcharge.
a) All the consumers are required to install shunt capacitors of adequate
rating and of ISI mark manufactured by the standard firms approved by
the Licensee. No new connection shall be released without installation
of such shunt capacitors. Rating of LT shunt capacitors required to be
installed on various sizes of motors shall be as under:
Sr. Rating of KVAR rating of LT capacitors for
No. motors various R.P.M. of the Motors.
(BHP)
750 1000 RPM 1500
RPM RPM
1. 3 1 1 1
155
2 5 3 2 2
3. 7.5 4 3 2
4. 10 5 4 3
5. 15 7 5 4
6. 20 9 7 5
7. 25 10 9 7
8. 30 12.5 10. 7.5
9. 40 15 12.5 10
10. 50 20 15 12.5
11. 60 22.5 17.5 15
12. 75 25 20 17.5
13. 90 30 25 20
14 100 35 25 22.5
********
156
ii) Railways, other than traction.
iii) Central P.W.D.
iv) Institutions.
v) Hospitals.
vi) Colonies including departmental colonies, multi-storey buildings etc.
vii) Schools/ Colleges/Educational Institutions.
viii) Other similar Establishments.
NOTE:
a) Only one connection will be given at one contiguous area of
reticulation.
b) The word hospital shall include dispensaries clinics, nursing
homes, and maternity homes.
c) Further distribution of power for resale shall be subject to the
relevant provisions of Haryana Electricity Reform Act 1997.
(ii) Character of Service.
A.C.50 cycles, 3 phase 400 volts
A.C. 50 cycles 3 phase 11 KV or higher voltage
The loads above 70 kW are to be released on 11 KV or higher voltage
depending on feasibility. Existing consumers having load above 70KW and
given supply on LT shall be served with a notice for the change of
character of service within a period of 6 months failing which their supply
shall liable to be disconnected.
(iii) Tariff.
For Low Tension voltage 419 paise per kwh
For 11 KV supply 409 paise per kwh
For 33 KV supply 397 paise per kwh
For 66 or 132 KV supply 385 paise per kwh
For 220 KV supply 377 paise per kwh
(iv) Fuel Surcharge Adjustment (FSA)
As per applicable charges calculated in accordance with the Haryana Electricity
Regulatory Commission (Tariff) Regulations 1999 as amended from time to time.
(v) Monthly Minimum Charges (MMC)
Monthly Minimum Charges (excluding service charges) shall be Rs. 200/- per kW
157
or part thereof per month for supply on LT.
Monthly minimum charges(excluding service charges) shall be Rs.200/- per kVA
or part thereof per month for supply on H.T. where C.L. is more than 70 kW.
(vi) Payment.
In the event of the monthly bill not being paid in full within the time specified in
the bill, a surcharge of 2% shall be levied on unpaid amount of the bill for each
30 days’ successive period or part thereof until the amount is paid in full.
(vii) Single Point Delivery.
The above tariff is based on the supply being given through single delivery and
metering point and at a single voltage. Supply at other points or at other voltages
shall be separately metered and billed.
********
158
Regulatory Commission (Tariff) Regulations, 1999 as amended from time to time.
(v) Monthly Minimum Charges (MMC)
Monthly minimum charges (excluding service charges) shall be Rs. 150/- per kW
per month.
(vi) Line Maintenance and Lamp Renewal Charges.
Lamp renewal charges (labour only) will be charged @ `Rs. 16 per month w.e.f.
1.4.2001 with a provision of 10% increase every year compounded annually
where municipal committee or corporation wishes to use the services of the
Nigam for this purpose. In case they wishes to withdraw this work from the utility
then they would be allowed to use the services of the contractors notified /
certified by the Chief Electrical Inspector to carry out this job on the poles of the
Nigam. The material for this job is required to be supplied by the concerned
municipal committee/ corporation to the Nigam in advance.
(vii) Payment
In the event of the monthly bill not being paid in full within the time specified in
the bill, surcharge of 2% shall be levied on the unpaid amount of the bill for each
30 days successive period or part thereof until the amount is paid in full.
********
159
Regulatory Commission (Tariff) Regulations 1999 as amended from time to time.
(v) Demand Assessment
The demand for any month shall be defined as the highest average load
measured in Kilovolt amperes during any 30 consecutive minute’s period of the
month.
The billable demand shall be the actual maximum demand or 65% of the
contract demand or 100 kVA whichever is higher.
The contract demand means the maximum kW/kVA for the supply of which the
Licensee undertakes to provide facilities from time to time.
(vi) Contract Demand.
In case the consumer exceeds his contract demand in any month, the excess
demand shall be charged @ Rs. 120 per kVA or part thereof per month. In case
consumer exceeds his contract demand in any month due to shifting of load by
the consumer in case of failure of supply at any other point under the jurisdiction
of Licensee and for reasons attributable to the Licensee, the excess contract
demand shall be determined on the basis of supply at such points taken together.
(vii) Power factor
The monthly average power factor of the plant and apparatus owned by the
consumer shall not be less than 90% lagging. The monthly average power factor
shall mean the ratio expressed as percentage of total kWh to total KVAH
supplied during the month. The ratio shall be rounded upto two figures. In case
the third figure is 5 or more than 5, then the figure at second decimal place shall
be increased by one. In case the monthly average power factor falls below 90%
lagging, the consumer shall have to pay a surcharge of 1% of SOP charges for
every 1% decrease in the power factor up to 80% and 2% of SOP charges for
every 1% decrease in Power Factor below 80%. Rebate of 0.5% on SOP will be
allowed for every 1% increase in Power factor above 90%.
The rebate/surcharge on account of power factor being higher/ lower than the
90% is also applicable where the consumer is billed on MMC basis. In such case,
the rebate / surcharge shall be allowed/ levied on actual SOP charges and shall
be deducted/ added to the monthly minimum charges in case a consumer is
160
billed on MMC basis.
(viii) Payment.
In the event of the monthly bill not being paid in full within the time specified in
the bill, a surcharge of 2% shall be levied on the unpaid amount of the bill for
each 30 days successive period or part thereof until the amount is paid in full.
(ix) Single point delivery.
The above tariff is based on the supply being given through a single delivery and
metering point and at a single voltage. Supply at other points or at other voltages
shall be separately metered and billed.
********
161
kW or part thereof of the connected load.
(vii) Capacitor Surcharge.
a) All the consumers are required to install shunt capacitors of adequate
rating and of ISI mark manufactured by the standard firms approved by
the Licensee. No new connection shall be released without installation of
such shunt capacitors. Rating of LT shunt capacitors required to be
installed on various sizes of motors shall be as under :-
Sr. Rating of KVAR rating of LT capacitors for
No. motors various R.P.M. of the Motors.
(BHP) .
750 1000 RPM 1500 RPM
RPM
1. 3 1 1 1
2 5 3 2 2
3. 7.5 4 3 2
4. 10 5 4 3
5. 15 7 5 4
6. 20 9 7 5
7. 25 10 9 7
8. 30 12.5 10. 7.5
9. 40 15 12.5 10
10. 50 20 15 12.5
11. 60 22.5 17.5 15
12. 75 25 20 17.5
13. 90 30 25 20
14 100 35 25 22.5
b) In case of existing consumers where the shunt capacitors have not been
installed or where these are found missing or in-operative or damaged,
one month registered notice shall be served on such consumers to
provide the desired quantity of healthy shunt capacitors and in case of
non-compliance, a surcharge of 10% of SOP amount shall be levied and it
shall continue to be levied till the prescribed capacity of shunt capacitors
are installed by the consumers. The intimation of installation of shunt
capacitors shall be required to be given by the consumer through the
submission of Test Report, which would be duly verified and accepted by
the SDO concerned.
(viii) Excess connected load Surcharge.
162
If the connected load of a consumer exceeds the sanctioned load, the excess
load shall be treated as unauthorized load, wherever use of unauthorized load is
detected by the Licensee, the excess load shall be charged at the rate of Rs. 70/-
per kW per month for the preceding six months and onwards till complete papers
alongwith Advance Consumption deposit are submitted for regularizing such
extension in connected load. In addition, MMC for the preceding six months and
onwards shall be applied to the original sanctioned load plus the excess load till
complete papers along with Advance Consumption Deposit are submitted for
regularizing such extension in connected load.
Where the MDI meters have been installed, the charges shall be levied from the
month in which the excess load is recorded and shall be continued to be charged
till the excess connected load is got regularized or the intimation regarding
removal through test report is submitted.
Where category is changed i.e. load is found above 70 kW
If there is a change of category from LT to HT due to unauthorized extension in
load recorded by the Maximum demand indicator or as per physical checking of
the inspecting officer, the consumer shall be charged HT tariff for that month with
LT Surcharge @ 25% along with penalty for unauthorized load @ Rs. 70/- per
kW. The MMC shall also be worked out on the extended load. In future, the
consumer shall be treated as a HT industrial Consumer having supply on LT with
provisional contract demand as 70 kW and shall be charged/ billed accordingly till
he shifts to HT or submits written intimation (through test report) of having
disconnected such unauthorized extended load. A notice to this effect shall also
be issued to the consumer by the concerned SDO immediately after the load is
found exceeded beyond 70 kW.
(ix) Payment.
In the event of the monthly bill not being paid in full within the time specified in
the bill, a surcharge of 2% shall be levied on the unpaid amount of the bill for
each 30 days successive period or part thereof until the amount is paid in full.
(x) Single point Delivery.
The above tariff is based on the supply being given through a single delivery and
163
metering point and at a single voltage. Supply at other points or at other voltages
shall be separately metered and billed.
********
164
b) Temporary Non Domestic Supply.
The monthly minimum charges (excluding service charges) shall be Rs.
220/- per kW or part thereof for each period of 30 days or less.
165
been given.
ii) If a consumer provides the material for the service equipment and meter
box (the Licensee installing the same), the consumer shall be responsible
for payment to the Licensee all above service and departmental charges
at rate of 50% on the cost of labour for erection and dismantlement. In
such a case the consumer shall be charged no Service Charges but only
four times the relevant general charges (e.g. meter service charges) as
referred to in special condition (i),
iii) Before any expenditure is incurred in giving temporary supply, cash
deposit should be taken in advance from the applicant to cover the
following:
a) If the material is to be provided and installed by the Licensee
Service Charges, General Service Charges (meter service
Charges, etc.) and Energy Charges, calculated according to
Special Condition No. (i)
b) If the material is provided by the consumer and the service installed
by the Licensee.
Erection and dismantlement charges, General charges (e.g. meter
service charges etc.) and Energy charges, calculated according to
special condition No. (ii) including departmental charges.
********
166
L.T and H.T. Industrial Consumer. 10
Bulk Supply 10
Street Lighting Supply 10
Temporary Supply As per relevant schedule of E.D
applicable on permanent supply.
NOTE:
1. Electricity Duty @ Re. 1/- per unit will be charged for illumination purposes i.e.
ornamental lighting used for display or decoration.
2. Municipal tax shall be levied on the consumption of electricity within the limits of
municipality in the State of Haryana @ five paise per unit.
********
INSTRUCTION NO. 5.13
167
2(b) Meter Inspection & Testing
Charges.
(If the correctness of a meter
belonging to the Licensee is
challenged by the consumer)
i) Single phase Rs. 25/- per meter.
ii) 3-phase whole current Rs. 50/- per meter.
i.e. without C.T
iii) L.T. meter with CTs. Rs. 250/- per
meter.
iv) H.T & E.H.T. metering Rs. 500/- per
equipment. meter.
168
i) Domestic consumer Rs. 50/-
ii) Non-Domestic consumer Rs. 100/-
iii) A.P. consumer Rs. 60/-
iv) L.T. Industrial consumer Rs. 250/-
(upto 20KW)
v) L.T. Industrial consumer Rs 500/-
(above 20KW)
vi) H.T. Industrial consumer. Rs.1000/-
vii) Bulk Supply & Street Rs. 500/-
Lighting consumer
5. Testing Consumer’s
installation.
i) For first test of new Nil.
installation or of any
extension to an existing
installation if the installation is
found to be not defective and
wiring contractor or his
representative is present at
the test.
ii) For first or subsequent test of
a new installation or an
extension to an existing
installation if the installation is
found to be defective or the
wiring contractor or his
representative fails to be
present.
(a) Single phase Rs.50/-
(Payable in
advance for each
subsequent visit
for the purpose of
testing the
installation.)
b) Three phase. Rs. 100/-
(Payable in
advance for each
subsequent visit
for the purpose of
testing the
installation.)
6. Meter Reading Cards
(New/Replacement).
169
i) Provision of meter reading Rs. 5/-
cards including PVC jacket
(for DS & NDS consumers).
170
v) LT Conventional Trivector Rs. 25000/-
meter with CTs/PT
vi) HT Conventional Trivector Rs. 35000/-
meter with CTs/PT
vii) HT electronic meter with Rs. 40000/-
CTs/PT
********
171
2. Line Service Charges (per At a flat rate of 4% of
month) the cost of service line
(excluding the cost of
30 metres) and
equipment (other than
meter(s)) except in the
case of industrial/Bulk
supply/NDS
connections who have
paid service connection
charges.
3. Service connection charges (For N.D.S
Industrial and bulk supply consumers
in lieu of monthly line service charges.
i) Single phase NDS Rs. 350/- per kW.
ii) Three phase NDS Rs. 750/- per kW.
iii) LT Industrial supply & Bulk supply Rs. 500/- per kW
upto 70KW
iv) H.T. Industrial supply & Bulk supply Rs. 750/- per kVA of
above 70KW Contract Demand
172
In case of Independent feeder, the cost of controlling OCB &
terminal equipments at sub station end for taking out the
independent feeder shall also be recoverable in addition to the
Service Connection Charges worked out as above.
NOTE:
While recovering the above service connection charges
the benefit of first 100 ft. length of this service is not to be
allowed.
4. Extension in Load.
i) Extension in load by single Rs.350/- per kW
phase (for extension part
in NDS only)
ii) Extension in load by three Rs.750/- per kW
phase in NDS (for extension part
only)
iii) Extension in load bringing the Rs.500/- per kW
total load Upto 70 kW (Both for (for extension part
Bulk and L.T. Industrial Supply) only)
iv) Extension in load bringing the Rs.750/- per kW
total load Above 70 kW. (Both (for extension part
for Bulk and H.T. Industrial only)
supply
NOTE :
Where there is a change of category from L.T. (upto 70
kW) to HT (above 70 kW), the charges would be levied on
the additional kVA demand, calculated as under (as an
example):
Existing sanctioned load 40 kW
Applied Load 150 kW with Contract 140 kVA
demand of 140-(40/0.90)=95.55
Additional Demand kVA
NOTES :
i) The line service charges on the original load, if already
being levied, shall continue.
ii) While assessing the connected load for working out this
charge both general and industrial loads shall be taken into
account.
iii) Load exceeding 70 kW shall be catered on 11 KV and
above. The above limit shall be applicable both for new and
extension cases after taking into account the existing load.
173
iv) An increase in the connected load without increase in
Contract Demand shall not call for payment of service
connection charges. However, consumers seeking
extension in Contract Demand within the sanctioned
connected load shall be required to pay service connection
charges on kVA basis on the incremental contract demand.
174
NOTES:
i) Upto 70 kW: The Advance Consumption deposit
may be accepted in two equal installments, first installment
along with the application and the 2nd installment at the time
of compliance demand notice.
ii) Above 70 kW: The Advance Consumption Deposit
may be recovered in two installments. First installment
being 1/3rd(but not less than the first installment for 70 kW)
and (remaining) or 2/3rd at the time of compliance of
demand notice.
6. Capacitor Service Charges For A.P. For
(per month) Consumers Industrial
Capacitor Size Consumers
a) Capacitors upto 2 KVAR Rs. 2/- Rs. 4/-
b) Capacitors of 3 KVAR Rs. 7/- Rs. 14/-
c) Capacitors of 4 KVAR Rs. 9/- Rs. 18/-
d) Capacitors of 5 KVAR Rs. 12/- Rs. 24/-
e) Capacitors of 7 KVAR Rs. 20/- Rs. 40/-
GENERAL NOTES:
i) Wherever in the above schedule, a rate is
expressed as a rate per month or as a monthly
rate, it means a proportionate charge if the period
of charge is less than one month.
ii) In case where disconnection and connection takes
place in the same month, a full month’s charge
shall be recovered.
iii) In case a consumer elects to pay the cost of the
service line, the amount payable by him shall be
the estimated cost of service line (excluding the
cost of 30 meters) and equipment and of installing
the same.
iv) In case of temporary general and industrial supply,
if the service line and meter are provided and
installed by the Licensee, the consumer shall be
charged four times the relevant charges provided
above for each period of 30 days or less.
Concession of first 30 meters of free service line is
not to be allowed.
********
175
submit their written requests giving therein specific reasons for the same to SDO (OP)
concerned at least one month in advance of the date from which the disconnection is
being sought. Such requests for a maximum period of six months shall be examined
and decided by concerned Executive Engineer in case of LT industrial consumer and by
SE (OP) in the case of HT industrial consumer keeping in view the merits of each case.
The request for temporary disconnection beyond a period of six months shall be
referred by respective SEs to concerned Chief Engineer (OP) for decision. CE (OP)
may allow temporary disconnection for a maximum continuous period of 12 months on
the merit of each case. While considering such requests for temporary disconnections,
the following guidelines are to be kept in view :-
i) The consumer is not a defaulter of Nigam’s dues, whether disputed or
undisputed.
ii) The consumers seeking temporary disconnection under “Force Majeure Clause”
are not required to submit their requests one month in advance as stipulated
under above paragraph.
iii) The force Majeure Conditions for the purpose of this clause will include only the
following :-
(a) Acts of God e.g. floods, Tempests, Earthquakes. Lightning.
(b) Act of Civil and Military Authorities e.g. Wars, Mutiny, and Civil
commotion/disturbances, Riots.
(c) Fires, Strikes, Lockouts.
NOTE: The disputes between partners, shortage of funds and raw materials
etc. will not be considered as Force Majeure reasons under this clause.
iv) The disconnections sought under Force Majeure reasons must be supported by
documentary evidence issued by concerned Civil Authorities.
v) Temporary Disconnection Order (T.D.C.O.) under Force Majeure reasons can be
allowed even beyond a continuous period of 12 months by CE (OP) concerned.
The CE (OP) will however, submit periodical report after every six months
relating to temporary disconnections allowed by him to the G.M./Commercial of
the Nigam.
vi The requests for further-extension of temporary disconnection who have been
176
allowed TDCO for a period upto 12 months shall be considered only after a
minimum period of six months from the date upto which the last disconnection
was allowed. For example in case a consumer seeks temporary disconnection
for 12 months and the same is approved from 01.01.2005 to 31.12.2005 and if
he applies for further extension the same will not be allowed before 1st July,
2006. During the intervening period i.e. for the period 1st January 2006 to 30th
June 2006, he will be billed on normal tariff, as if there were no temporary
disconnection.
vii) Industries, which are allowed temporary disconnection, will pay minimum
charges for one month following the month in which temporary disconnection has
been allowed and no MMC will be levied thereafter. Since (MMC will be charged
for the first month of the TDCO, the consumer will be entitled for consuming
electricity equivalent to the MMC.)
viii) Separate NDS connection
a) The existing or new LT/HT industrial consumers can seek a separate
single phase NDS connection upto a load 5 kW on the same premises
having regular industrial connection for the purpose of meeting the
requirement of lighting etc. for offices, security, elevators, pumps etc. The
consumer through this connection shall not perform any industrial activity
even during temporary disconnection period of their regular industrial
connection.
b) This connection would be treated as a separate and distinct NDS
connection altogether from the regular industrial connection and will be
considered as a new connection.
c) This connection will be available to the consumer even during the
temporary disconnections of industrial connections.
d) The wiring and the connected load for this NDS connection will be
physically & distinctly separated from the wiring of the regular industrial
connection at all times & shall be connected to only lighting loads.
e) The shifting of load from this NDS connection to the regular industrial
connection will be treated as un-authorised use of electricity and will be
177
treated as per applicable instruction /policy of the Nigam.
f) The Location of the metering arrangement for this NDS connection will be
separate from the metering arrangement of their industrial connection and
will not be tapped from the existing LT/HT Industrial connection.
With the provision of a separate connection in the NDS category for
factory lighting purposes the facility to consume upto 5% of the monthly
average consumption of preceding 6 months for factory lighting is not
available to the consumer. And while effecting the TDCO of the LT/HT
industrial consumer the same shall be effected by disconnecting/ removing
of all 3 phases.
ix) In few cases, Nigam is not in a position to release separate NDS connection as
above due to non-availability of LT lines within a radius of 300 meters. In such
cases during the period of temporary disconnection beyond one month, the
consumption of industry for repair work and factory lighting, if any, upto 5% of the
monthly average consumption of preceding six months (or less, if 6 month
consumption is not available) will be charged at 200% of the normal tariff. In
case of excess consumption than the said limit of 5%, the temporary
disconnection facility shall be considered to have been withdrawn from that
month and the consumer shall be billed on normal tariff as if there were no
temporary disconnection.
vi) The word’ month’ can be taken as the billing month or the calendar month or
a period of 30 days. In this regard, it is clarified that since the billing to a
consumer is done on the basis of consumption during his billing cycle which is
also called as “ Billing Month”, it would be desirable to grant the benefit of
temporary disconnection to the consumer from the start of the billing month only.
********
Levy of surcharge:
The surcharge is leviable on all types of dues raised through energy bills
including energy charges recoverable under the schedule of tariff and the amount
178
recoverable under the schedule of general and miscellaneous charges (excepting the
amount of Electricity Duty and M. Tax) in case the payment is not made within the due
date.
********
179
********
180
the SE (OP) does not agree
with the same, he will proceed
to act as revisory authority and
commence proceedings &
pronounce his order, which shall
be final.
SE Upto Rs.1,00,000/-
i. The appeal for cases upto
Rs.1,00,000/- will be made
direct to him.
ii. He will hear the appeal and
decide. If the decision is
partially or fully against the
Nigam then the case will be
referred to concerned CE (OP).
He will then give his consent to
the implementation of the order
of the SE (OP), in case he
agrees with the same. In case,
the CE(OP) does not agree with
the same, he will proceed to act
as revisory authority and
commence proceedings and
pronounce his order which shall
be final.
CE Beyond Rs.1,00,000/-
(i) The appeal for cases beyond
Rs.1,00,000/- will be made
direct to him.
(ii) He will hear the appeal and
decide. If the decision is
partially or fully against the
Nigam then the case will be
referred to Director(OP). He will
then give his consent to the
implementation of the order of
the CE (OP). in case he agrees
with the same. In case, the
Director (OP) does not agree
with the same, he will proceed
to act as revisory authority and
commence proceedings and
pronounce his order, which shall
be final.
6. Amount got SDO/O Rs. 2500/- with concurrence of IA.
charged by P
IA/Chief Auditor
181
or other audit
parties.
XEN/O Upto Rs.50,000/-.
P i. The appeal will be made by the
consumer to the appellate
authority.
ii. If the decision of the
appellate authority is partially or
fully against the Nigam, then the
concurrence of Chief Auditor will
be sought for refund. In case the
Chief Auditor does not agree with
the order, the matter will be
referred to SE (OP) whose
decision shall be final.
SE/OP Upto Rs.1,00,000/-.
i. The appeal will be made by the
consumer to the appellate
authority.
ii. If the decision of the appellate
authority is partially or fully
against the Nigam, then the
concurrence of Chief Auditor will
be sought for refund. In case the
Chief Auditor does not agree with
the order, the matter will be
referred to CE (OP) whose
decision shall be final.
CE Beyond Rs.1,00,000/-.
i. The appeal will be made by
the consumer to the appellate
authority.
ii. If the decision of the appellate
authority is partially or fully
against the Nigam, then the
concurrence of Chief Auditor will
be sought for refund. In case the
Chief Auditor does not agree with
the order, the matter will be
referred to Director (OP) whose
decision shall be final.
2. Any party aggrieved by the orders of original Appellate Authority viz. Xen/SE/CE
concerned, may within one month of such order, file revision to the next higher authority
whose decision shall be final and binding upon the parties. The next higher authority to
182
the Appellate Authority concerned may also any time Suo-Motto call for the records of a
case decided by such Appellate Authority and review the matter. It shall be binding on
the appellate authority to decide the case within 30 days and the next higher authority
should also dispose off the application within 30 days.
3. The amount becoming refundable to the consumer, if any, as per decision of
appellate authority/arbitrator/court of law shall be in general, adjusted by way of
adjustment in future bills. However, in case the amount to be refunded is substantial
and consumer wants the refund in cash, the same shall be refunded to the consumer in
lump sum subject to the condition that the lump sum refund shall be allowed after
retaining an amount equal to 6 months average energy bill of the consumer, based on
the average consumption during 12 months prior to the date of decision by authority.
The balance amount will be refunded in lump sum through cheque by the concerned
XEN (OP) Division.
Provided that if the connection of the consumer has been disconnected the total
amount shall be refunded in one go.
4. In case total amount refundable to the consumer is found in excess of
Rs.50,000/- the refund shall only be allowed after getting the refund pre-audited from
the local audit party. The cases in which the amount of refund exceeds Rs.5 lacs the
refund case duly checked by the local audit party shall be sent to the Chief Auditor,
DHBVNL, Hisar for pre-audit.
********
********
183
The Right to Information Act, 2005
(See Rule 3)
I.D.No.______________
To
2. Address:
3. Particulars of Information
4. I state that the information sought does not fall within the restrictions
contained in Section 8 of the Act and to the best of my knowledge it
pertains to your office.
184
Place:
Tel.No.(Office)_____
(Residence)________
Note: (I) Reasonable assistance can be provided by the PIO in filling up the
Form-A.
(ii) Please ensure that the Form-A is complete in all respect and there is no
ambiguity in providing the details of information required.
(See Rule 3)
I.D.No.______________
185
To
2. Address:
3. Particulars of Information
4. I state that the information sought does not fall within the restrictions
contained in Section 8 of the Act and to the best of my knowledge it
pertains to your office.
Place:
Tel.No.(Office)_____
(Residence)________
186
Note: (I) Reasonable assistance can be provided by the PIO in filling up the
Form-A.
(ii) Please ensure that the Form-A is complete in all respect and there is no
ambiguity in providing the details of information required.
187