0% found this document useful (0 votes)
128 views2 pages

Contemporary Electronic Systems LTD.: 104 New Road-Belize City, Belize Phone: 223-6786, 223-4912

Contemporary Electronic Systems Ltd. provides an update on works completed at Heritage Bank Mercy Lane. Installation of cameras and wiring is nearly finished, except for the parking lot cameras which will be completed by August 21st. Wiring and devices for the access control system and fire alarm/PA systems are largely complete, pending some additional parts. The fire/burglary, access control, and PA systems are 80% finished with completion expected around mid-August. The surveillance system is 95% complete with parking lot cameras to be installed by August 21st. Percentages billed and amounts due

Uploaded by

Paul Quiros
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
128 views2 pages

Contemporary Electronic Systems LTD.: 104 New Road-Belize City, Belize Phone: 223-6786, 223-4912

Contemporary Electronic Systems Ltd. provides an update on works completed at Heritage Bank Mercy Lane. Installation of cameras and wiring is nearly finished, except for the parking lot cameras which will be completed by August 21st. Wiring and devices for the access control system and fire alarm/PA systems are largely complete, pending some additional parts. The fire/burglary, access control, and PA systems are 80% finished with completion expected around mid-August. The surveillance system is 95% complete with parking lot cameras to be installed by August 21st. Percentages billed and amounts due

Uploaded by

Paul Quiros
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 2

Contemporary Electronic Systems Ltd.

104 New Road-Belize City, Belize


Phone: 223-6786, 223-4912
E-mail: [email protected]

Ms. Samantha Escobar


Senior Project Administrator
Anthony Thurton & Associates Ltd.
Belize City
Belize

10 August 2020

REF: STATUS WORKS DONE AT HERITAGE BANK MERCY LANE

Hi Samantha
Below is a list of works done at Heritage Mercy Lane:

ITEM 2 VIDEO SURVEILLANCE


Installation and wiring of all cameras except for the parking lot have been completed. The wiring and installation
of all cameras (10) for the parking lot will be completed by Friday 21 st August.
PREVIOUS % AMT PRESENT % AMT
COMPLETE RECEIVED COMPLETE DUE
ITEM 2a 50% $8,775.00 100% $8,775.00
b 50% $19,771.50 100% $19,771.50
Items erroneously not in contract for ITEM 2a
(2) 32” TV at $1200.00 each $2400.00
(1) 43” TV at $1500.00 each $1500.00
Additional works
Run cables and install 5 cameras on level one at $100.00 each $500.00

ITEM 3 ACCESS CONTROL SYSTEM


Wiring and device terminations have been completed for all floors. Awaiting 6 more readers from the bank
(Akeem Coye) so as to complete the project. These should be received and completed by Friday 21 st August.
PREVIOUS % AMT PRESENT % AMT
COMPLETE RECEIVED COMPLETE DUE
ITEM 3a 50% $8,071.88 95% $7,668.29
b 50% $20,475.00 100% $20,475.00
c 50% $6,750.00 95% $6,412.50

ITEM 4 WIFI SYSTEM


N/A

ITEM 5 FIRE ALARM & PUBLIC ADDRESS SYSTEM


FIRE Wiring and device terminations have been completed for all floors. System is operational and in service.
PA SYTEM Installation of all speakers and wirings have been completed for all floors. System is operational and in
service
PREVIOUS % AMT PRESENT % AMT
COMPLETE RECEIVED COMPLETE DUE

ITEM 5 a i 50% $38,054.69 95% $36,151.96


ii
iii 95% $4,750.00
b 100% $42,121.25

FIRE/BURGLARY SYSTEM 80% completed


Level one and level two is operational. All wirings and device terminations for remaining floors have been
completed. System will be in complete operation by Friday 14 th August.

ACCESS CONTROL SYSTEM 80%completed


Wiring and device terminations have been completed for all floors. Awaiting 6 more readers from the bank
(Akeem Coye) so as to complete the project. These should be received and completed by Wednesday 19 th August.

PUBLIC ADDRESS SYSTEM 80% completed


Installation of all speakers and wirings have been completed for all floors. Final wiring to control panel will be
completed by Friday 14th August.

SURVEILLANCE SYSTEM 95% completed


Installation and wiring of all cameras except for the parking lot have been completed. The wiring and installation
of all cameras (10) for the parking lot will be completed by 21 st August.

Sincerely

Paul Quiros /for


Mrs. Fairweather
Chief Operating Officer

You might also like