Methodology For Wet Mix Macadam
Methodology For Wet Mix Macadam
Methodology For Wet Mix Macadam
HIGHWAY GUIDE
ALWAYS FOR YOU
About Us
Material
o Soil
o Aggregate
o Cement
o Bitumen
o Emulsion
Design Of Mixes
o Concrete Mixes
Construction
o Highway Construction
Contact Us
Privacy Policy
Blog
Wet Mix Macadam consist of laying spreading and compacting of clean, crushed,
well-graded granular materials on a prepared and approved Granular sub-Base. The
material is well mixed with water and rolled to a dense mass. It shall be laid on one
or more layers as per line and level, grade and cross section shown in the drawing or
as directed by the Engineer. The thickness of single compacted Wet Mixed Macadam
(WMM) Base shall not be less than 75 mm. Maximum thickness of single compacted
layer base can be up to 250 mm upon approval of Engineer.
1. Reference
2. Setting Out.
3. Selection of Material.
4. Equipments.
5. Methods of Operation.
6. Quality Control.
7. Work Safety.
8. Environmental Safety.
1.0 Reference
Reference Documents:-
I) Ministry of Road Transport& Highways Specifications
II) Technical Specifications
III) Relevant Drawings.
IV) IS 2720 Codes.
After the layer of GSB Sub-Base has been approved, then line and level are carried
out to fix the Wet Mix Macadam base layer (herein after called WMM Base). Pegs are
fixed at regular intervals on the safe side of the road edge where blade of grader
should not disturb the peg while blending of the Base materials. On each peg’s top
level of Base layer is marked. The chainage boards and working bench mark shall be
set out side the limits of construction areas.
3.1 Aggregate
Coarse aggregate shall be crushed stone or crusher run as per IRC 109 or clause
406.2.1 of MORT&H specification.
The aggregate shall conform to the grading given in table 406.2.1.2 of technical
specification or IRC 109 -2015. Material finer than 425 micron, shall have Plasticity
Index (PI) less than 6. The final gradation approved within these limits shall be well
graded from coarse to fine and shall not vary from low limit on one sieve to high limit
of adjacent sieve or vice versa.
4.0 Equipments
2. Dumper / Tippers.
4. Water Tanker
Proper arrangement shall be made for the lateral confinement of wet mix during
laying. This shall be done by laying materials on adjoining shoulder along with that
of WMM layer. The preparation of mix, spreading of mix and compaction are done
sequentially.
The sequence of operation shall be followed as described in clause: 406.3.3 of
MORT&H.
Wet mix Macadam shall be prepared in an approved WMM mixing plant having
provision for controlled addition of water and forced/positive mixing arrangement.
Optimum moisture for mixing shall be determined in accordance with IS: 2720 (Part
8) after replacing the aggregate fraction retained on 22.4 mm sieve with materials of
passing from 22.4 and retained on 4.75 mm. While adding water, evaporation loss
shall also be taken into account. The mixed material should be uniformly wet and no
segregation shall be permitted.
Immediately after mixing, the aggregate shall be spread uniformly and evenly upon
the approved GSB layer. Materials should neither be dumped in heap nor their
hauling over a partly completed stretch. The first layer will be laid by motor grader
and the second layer mix shall be spread by a WMM paver finisher capable of paving
minimum 4.5m to 9.0m width. The layer may be tested by depth block during
construction. No segregation of materials are allowed. The aggregates should be of
uniform gradation with no pockets of fine materials.
5.4 Compaction
After the mix has been laid on site to the required thickness, grade and camber, then
compaction is carried out with suitable roller to the full depth. For a thickness up to
200mm in a single layer, compaction shall be done with vibratory roller of 80 to 100
KN static weights with plain drum or equivalent capacity roller. Rolling is done from
lower edge towards upper edge longitudinally for the portion having unidirectional
cross fall and super elevation.
Each pass of the roller shall uniformly overlap not less than one third of the track
made in the previous pass. During rolling, grade and cross fall shall be checked and
any high spot or depressions, which become apparent, corrected by adding or
removing fresh materials. The speed of roller shall not exceed 5km/h. Rolling shall
be continued till the density of the layer is achieved 98% of the Maximum Dry
Density.
Rolling should not be done when the WMM layer is soft or yielding or when it causes
a wave like motion. If level difference or irregularities develop during rolling which
exceeds 12 mm when tested with 3 metre straight edge, the surface should be
loosened and premixed materials added or removed as required before rolling again.
In no case the unmixed material be permitted to make up the depressions.
After testing the compaction & level of WMM course the road shall be allowed to dry
for 24 hours. Preferably no vehicular traffic should be allowed on the finished WMM
surface till it has dried and covered with wearing course.
Table 400-12 Physical Requirement of coarse aggregate for Wet Mix Macadam for
Sub-base /Base Courses
2.Vehicles tracks shall be kept moist to prevent flying of dust particles with the
vehicle movement.
1. Wasimsays:
Reply
2.
3. Rupam Mukherjeesays:
Wonderfull Note
Reply
4. Sathasivamsays:
Reply
5. Mukesh Kumarsays:
6. Mukesh Kumarsays:
Reply
7. Meghnad Saha.says:
Nicely explained.
Reply
8.
9. Meghnad Saha.says:
Well explained.
Reply
1. Deepaksays:
Reply
Leave a Reply
Your email address will not be published. Required fields are marked *
COMMENT
NAME *
EMAIL *
WEBSITE
Save my name, email, and website in this browser for the next time I comment.
Post Comment
Post navigation
PREVIOUSPrevious post:Method Statement of Longitudinal Drain
NEXTNext post:CONCRETE KERB CASTING METHOD STATEMENT
RECENT POSTS
Method statement for slurry seal
SOUNDNESS TEST OF CEMENT BY LE – CHATELIER METHOD
Method Statement for Pipe Culvert
Method Statement For Backfilling Behind Abutment & Around Structures.
DETERMINATION OF DRY DENSITY OF SOILS IN PLACE (SAND
REPLACEMENT METHOD)
PROCEDURE FOR QUALITY RECORDS
PROCEDURE OF LAYING DRY LEAN CONCRETE
HIGHWAY ENGINEER INTERVIEW QUESTION AND ANSWER
HOW TO CONVERT 1:2:4 FROM VOLUME TO WEIGHT
RECENT COMMENTS
Pradeep Kumar Singh on COMPRESSIVE STRENGTH TEST OF CEMENT
MORTAR CUBE AS PER IS 4031 PART 6
Deepak on METHODOLOGY FOR WET MIX MACADAM
VINAY BHARADWAJ on COMPRESSIVE STRENGTH TEST OF CEMENT
MORTAR CUBE AS PER IS 4031 PART 6
Abhijeet Katiyar on HIGHWAY ENGINEER INTERVIEW QUESTION AND
ANSWER
Meghnad Saha. on METHODOLOGY FOR WET MIX MACADAM
Meghnad Saha. on METHODOLOGY FOR WET MIX MACADAM
Davalsab on HIGHWAY ENGINEER INTERVIEW QUESTION AND
ANSWER
Subasis Pati on Concrete Mix Design for M25 grade as per IS 10262:2009
Bharat Sukhadia on HIGHWAY ENGINEER INTERVIEW QUESTION AND
ANSWER
ARCHIVES
September 2020
August 2020
July 2020
May 2020
December 2019
November 2019
October 2019
September 2019
August 2019
July 2019
CONTACT US
Email