Method Statement - PILE CAPS PDF
Method Statement - PILE CAPS PDF
REV. :
SHEET :7
EFFECTIVE DATE:
DOCUMENT
STATUS
Revision No Status Note
Page 1 of 7
DOC NO. :
REV. :
SHEET :7
EFFECTIVE DATE:
TABLE OF CONTENT
S/NO DESCRIPTION
Page 2 of 7
DOC NO. :
REV. :
SHEET :7
EFFECTIVE DATE:
Stage 2
1. Excavation
2. Removal of Laitance
3. PCC
4. Reinforcement
5. Fixing Re – Bars
6. Formwork
7. Concreting
8. Backfilling
9. Behavioural Safety
Page 3 of 7
DOC NO. :
REV. :
SHEET :7
EFFECTIVE DATE:
Section 4: Key Personnel / Qualified Persons/Workers List (Attach Training Qualification Certificates):
Name Appointment / Designation / HP Valid CIDB Green Card Registration /
Number Competency Certificates / First Aider Cert:
1
2
3
4
5
Page 4 of 7
DOC NO. :
REV. :
SHEET :7
EFFECTIVE DATE:
2 Handling and Storage - All formwork and rebar should be transported to site by
means of lorry and unloaded appropriately using a mobile
crane. They shall be stored in a proper stockyard
allocated at site
3 Stage 2 - Shoring shall be provided depending upon the stability of the
Excavation soil found in the area. Shoring shall be done with the help of
old steel plates and props. At road locations the pit shall be
excavated to the dimensions providing working space all
around the pile cap, to facilitate fixing of steel & erection of
shuttering as detailed in the drawings. Provision for sump
shall be made at the comer of the pit to pump out
underground water of about 600 mm deep from PCC
bottom. The excavated earth shall be then disposed by
means of lorry dumper.
4 Removal of Laitance After excavation the laitance of the piles shall be removed by using
Pneumatic Jack Hammers seven days after casting of pile or
manually three days after casting of pile. The top of pile after
striping shall project 50 mm into the pile cap and reinforcements of
pile shall be fully anchored in pile cap. The debris of broken
concrete shall be removed from the pit and disposed of to approve
dumping sites. Exposed bars shall be straightened & cleaned
properly.
Page 5 of 7
DOC NO. :
REV. :
SHEET :7
EFFECTIVE DATE:
5 PCC - After levelling the bottom of the bed, sprinkle some water to
keep the soil moist. PCC of Mix G15 or specified in drawing
shall be mixed at the centralized batching plant at the
casting yard and transported to site in transit mixers. The
concrete shall directly pour through chutes from three
locations, shall be spread and levelled manually to the
specified thickness shown in the drawing. PCC edges shall
be projected 100 mm more than that of pile cap as detailed
in the drawing to facilitate the fixing of form work and levels
of PCC shall be jointly checked & verified. The PCC shall be
cured by sprinkling water.
7 Fixing Re – bars - The re-bars shall be manually fixed into its position as
shown in the good for construction drawing. Reinforcement
of pile cap shall be lapped with the reinforcement of pile.
After fixing the pile cap rebar, pier shaft rebar shall be
erected. This rebar shall be supported by erecting a suitable
staging frame across the width of the pile cap. The rebar
cage shall be inspect by Engineer / Site representative. The
rebar, chairs, spacers & laps shall be jointly checked after
completion of cage placing. Sufficient chairs and spacers
shall be provided to keep the cage in its proper position.
Page 6 of 7
DOC NO. :
REV. :
SHEET :7
EFFECTIVE DATE:
11 Rescue Plan / Emergency - To be managed at work site by first aid treatment if minor.
Situation - Report immediately to site representative if complex.
- All workers shall be briefed on the nearest clinic.
- Workers shall understand the emergency procedure and
escape route.
- Assembly point is the workers rest area.
12 Final Inspections - Contactor shall inform consultant on the inspection date and
schedule.
- Consultant shall be informed on the inspection schedule.
- All submission shall be done before inspection take place.
Page 7 of 7