Power Network Control Report
Power Network Control Report
INTERNAL CORRESPONDENCE
1
tinashe edward chikohora :COPS report
Acknowledgements:
I would like to acknowledge the cooperation that I got during my training period within this
section. I enjoyed the work so much that if wishes were horses, I would have liked to join this
section after my post graduate training. I greatly appreciate the help that I got from all
members of staff with special mention to the following individuals who played a pivotal role
during the two months of training:-
Engineer Peace Machakaire
Engineer Swerdi kalonga
Engineer Moketsi Noku
May the Lord richly bless them for the time they invested in me.
2
tinashe edward chikohora :COPS report
1.0 INTRODUCTION
The Power Network Control section in ZETDC under the Technical Services section is
responsible for the design and maintenance of the control system for the utility’s power
network. A SCADA central system is used to ensure the efficient control of remote plant as
well as the accurate acquisition of information such as measurements and status indications
using RTU( Remote Terminal Units)s . The section is responsible for the assembly and
setting up of RTU ( Remote Terminal Units)s and SCS( Sub-station Control System) The
trainee spent a total of two months in this department.
Supervisory Control and Data Acquisition (SCADA) refers to the combination of telemetry
and data acquisition used to monitor and control plant and equipment. SCADA within the
Power network control department is used to monitor alarm conditions, status conditions and
measurements and control of plant equipment by the use of commands. In short it is needed
for the collection of data and the supervision and control of circuits. In certain applications
SCADA can be used in closed loop systems but in this case it is used for an open loop control
system. The plant and equipment on the process side of SCADA includes substations, lines
and generating stations.
The new type of SCADA currently being used in our system is Network Manager (WS 500)
which is an ABB product. Old SCADA systems which were used before this new SCADA
are SINDAC and SPIDER. SINDAC was replaced by SPIDER, then came Network Manager.
The introduction of Network Manager brought the following changes:
3
tinashe edward chikohora :COPS report
master when they receive requests. This is different from an interrupt mode in which a slave
monitors its inputs. When it detects significant change or exceeds limits, it initiates
communication to the master and transmits data. This means that the MS will ask the
RTU for information, but the RTU will only report changes since the last
polling.
Frequent questions polled include status of apparatus (open/closed etc.)
measurands and indications.
Double indications are used for important objects such as circuit breakers
instead of single indications for the reason of increasing security, (avoiding
single state error) 2 bits have to change so if one changes coz of other reasons
like bad medium, its not validated true.
4
tinashe edward chikohora :COPS report
The components of a SCADA system are as outlined below:
HMI (Human Machine Interface) – Also sometimes referred to as MMI (Man Machine
Interface). It is the apparatus which presents process or plant data to a human operator and
through which the operator controls and monitors the process. In our system there are several
consoles at the control centers dedicated for this function. Displays onscreen the mimic
diagram of the whole plant for easier identification with real system.
Below are the descriptions of components of the supervisory system together with HMI:
Central PC – is the master unit of the SCADA. Is responsible for the collection of
information gathered from the remote stations and accordingly generate necessary action for
any event that is detected. It is composed of system servers which are Application server
(AS), Data Engineering (DE) Server, and Utility Data Warehouse (UDW) which is a
magnetic tape for storage of historical information.
PCU – it sequentially polls the slave stations to gather information, temporarily stores it
before passing it to the Central PC for storage in the UDW. There are two PCUs i.e PCU1
and PCU2. The PCC together with other components make up the Front End (FE)
HMI – runs its program on the Central PCs. The program also creates a separate window for
alarms. Access to the program is permitted only to qualified operators who are allocated
passwords for security purposes.
Bus supervisor – for voltage distribution supervision. Has LEDs which glow red for fault
indication.
Loop reversal or transmission direction switch – two transmission directions are available, A
and B.
The RTU output voltages are +15V, -15V, and +24V dc.
NB: After assembling an RTU, it is tested for proper operation using software known as CTU80. It is
tested for completeness of cycles while not interfaced with the physical world. The trainee
participated in building a DS803 for installation at Harare BSP
Other tasks carried out include measurands checks and rectification at Atlanta, Alaska, Glenview and
Budiriro. An instrument known as a Kompav is used to simulate transducer output and inject current
into RTU for cross checking at NCC.
Connection lists are made use to check correct wiring of status indications and all power system
measurands.