Microsoft Project 2013 137 Days 17 Nov '20 07 Apr '21: Please Change It Into Auto-Scheduled
Microsoft Project 2013 137 Days 17 Nov '20 07 Apr '21: Please Change It Into Auto-Scheduled
Successors 18 Oct '20 15 Nov '20 13 Dec '20 10 Jan '21 07 Feb '21 07 Mar '21 04 Apr '21
Mode T S W S T M F T S W S T M F T S W
0 microsoft project 2013 137 days 17 Nov '20 07 Apr '21
1 general 137 days 17 Nov '20 07 Apr '21
2 milestones 137 days 17 Nov '20 07 Apr '21
3 project start 0 days 17 Nov '20 17 Nov '20 6,12 17-11
4 project finish 0 days 07 Apr '21 07 Apr '21 31,61,89,119 07-04
5 preliminaries 25 days 17 Nov '20 12 Dec '20
6 site clearing 3 days 17 Nov '20 20 Nov '20 3 7
7 site survey 1 day 21 Nov '20 21 Nov '20 6 8,22,34,64,92
8 site fencing 8 days 22 Nov '20 29 Nov '20 7 9
9 site office 7 days 30 Nov '20 06 Dec '20 8 10
10 temp water and electricity 6 days 07 Dec '20 12 Dec '20 9 23,36,66,94
11 design 38 days 17 Nov '20 26 Dec '20
12 archi Please change it into 7 days 17 Nov '20 24 Nov '20 3 13
13 structure auto-scheduled 6 days 25 Nov '20 30 Nov '20 12 14,17,18
14 m and e 5 days 01 Dec '20 05 Dec '20 13 15
15 submission 20 days 06 Dec '20 26 Dec '20 14 22,34,64,92
16 procurement 6 days 17 Nov '20 23 Nov '20
17 procurement of rebers 5 days 01 Dec '20 05 Dec '20 13 38,68,96
18 procurement of concrete 2 days 01 Dec '20 02 Dec '20 13 40,70,98
19 construction 55 days 27 Dec '20 21 Feb '21
20 septic tank 16 days 27 Dec '20 13 Jan '21
21 sub-structure 8 days 27 Dec '20 03 Jan '21
22 hardcore laying 4 days 27 Dec '20 30 Dec '20 7,15 23
23 lean concrete 2 days 31 Dec '20 01 Jan '21 22,10 24
24 cement concrete 2 days 02 Jan '21 03 Jan '21 23 26
25 super structure 8 days 05 Jan '21 13 Jan '21
26 oil tank 1 day 05 Jan '21 05 Jan '21 24 27
27 tank cordle brick wall 2 days 06 Jan '21 07 Jan '21 26 28
28 brick chamfer 1 day 08 Jan '21 08 Jan '21 27 29
29 sand filling 1 day 09 Jan '21 09 Jan '21 28 30
30 rcc cover slab 2 days 10 Jan '21 11 Jan '21 29 31
31 finishing work 1 day 13 Jan '21 13 Jan '21 30 4
32 convenience store and toilet 55 days 27 Dec '20 21 Feb '21
33 sub structure 44 days 27 Dec '20 10 Feb '21
34 excavation 2 days 27 Dec '20 28 Dec '20 7,15 35
35 hardcore 4 days 29 Dec '20 01 Jan '21 34 36
36 lean concrete 3 days 02 Jan '21 05 Jan '21 35,10 38
37 footing 10 days 06 Jan '21 16 Jan '21
38 footing rebars 5 days 06 Jan '21 10 Jan '21 36,17 39
39 footing formworks 3 days 11 Jan '21 14 Jan '21 38 40
40 footing casting 2 days 15 Jan '21 16 Jan '21 39,18 42
41 short column 8 days 17 Jan '21 24 Jan '21
Task Project Summary Manual Task Start-only Deadline
Project: microsoft project 2013 Split Inactive Task Duration-only Finish-only Progress
Date: 20 Nov '20 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress
Page 1
ID Task Task Name Duration Start Finish Predecessors Successors 18 Oct '20 15 Nov '20 13 Dec '20 10 Jan '21 07 Feb '21 07 Mar '21 04 Apr '21
Mode T S W S T M F T S W S T M F T S W
42 sc rebars 4 days 17 Jan '21 20 Jan '21 40 43
43 sc formworks 3 days 21 Jan '21 23 Jan '21 42 44
44 sc casting 1 day 24 Jan '21 24 Jan '21 43 46
45 retaining wall 5 days 25 Jan '21 29 Jan '21
46 brick laying 5 days 25 Jan '21 29 Jan '21 44 48
47 ground beam 10 days 30 Jan '21 08 Feb '21
48 gb rebars 5 days 30 Jan '21 03 Feb '21 46 49
49 gb formworks 3 days 04 Feb '21 06 Feb '21 48 50
50 gb casting 2 days 07 Feb '21 08 Feb '21 49 51
51 earth filling 2 days 09 Feb '21 10 Feb '21 50 54
52 super structure 6 days 11 Feb '21 16 Feb '21
53 ground floor 6 days 11 Feb '21 16 Feb '21
54 gf formworks 3 days 11 Feb '21 13 Feb '21 51 55
55 gf casting 1 day 14 Feb '21 14 Feb '21 54 57
56 Roof 2 days 15 Feb '21 16 Feb '21
57 roof truss 1 day 15 Feb '21 15 Feb '21 55 58
58 roofing sheet 1 day 16 Feb '21 16 Feb '21 57 59
59 architectural works 2 days 17 Feb '21 18 Feb '21 58 60
60 m and e 2 days 19 Feb '21 20 Feb '21 59 61
61 testing and commissioning 1 day 21 Feb '21 21 Feb '21 60 4
62 gas station 42 days 27 Dec '20 08 Feb '21
63 sub structure 42 days 27 Dec '20 08 Feb '21
64 excavation 2 days 27 Dec '20 28 Dec '20 7,15 65
65 hardcore laying 4 days 29 Dec '20 01 Jan '21 64 66
66 lean concrete 3 days 02 Jan '21 05 Jan '21 65,10 68
67 footing 10 days 06 Jan '21 16 Jan '21
68 footing rebars 5 days 06 Jan '21 10 Jan '21 66,17 69,82
69 footing formworks 3 days 11 Jan '21 14 Jan '21 68 70
70 footing casting 2 days 15 Jan '21 16 Jan '21 69,18 72
71 short column 8 days 17 Jan '21 24 Jan '21
72 sc rebars 4 days 17 Jan '21 20 Jan '21 70 73
73 sc formworks 3 days 21 Jan '21 23 Jan '21 72 74
74 sc casting 1 day 24 Jan '21 24 Jan '21 73 76
75 retaining wall 7 days 25 Jan '21 31 Jan '21
76 brick laying 5 days 25 Jan '21 29 Jan '21 74 77
77 earth filling 2 days 30 Jan '21 31 Jan '21 76 79
78 ground floor 8 days 01 Feb '21 08 Feb '21
79 gf formworks 5 days 01 Feb '21 05 Feb '21 77 80
80 gf casting 3 days 06 Feb '21 08 Feb '21 79
81 steel structure 5 days 11 Jan '21 16 Jan '21
82 footing 1 day 11 Jan '21 11 Jan '21 68 83
83 column 1 day 13 Jan '21 13 Jan '21 82 84
Task Project Summary Manual Task Start-only Deadline
Project: microsoft project 2013 Split Inactive Task Duration-only Finish-only Progress
Date: 20 Nov '20 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress
Page 2
ID Task Task Name Duration Start Finish Predecessors Successors 18 Oct '20 15 Nov '20 13 Dec '20 10 Jan '21 07 Feb '21 07 Mar '21 04 Apr '21
Mode T S W S T M F T S W S T M F T S W
84 beam 1 day 14 Jan '21 14 Jan '21 83 85
85 roof trust 1 day 15 Jan '21 15 Jan '21 84 86
86 roofing sheet 1 day 16 Jan '21 16 Jan '21 85 87
87 decoration with composite board 3 days 17 Jan '21 19 Jan '21 86 88
88 m and e 2 days 20 Jan '21 21 Jan '21 87 89
89 testing and commissioning 1 day 22 Jan '21 22 Jan '21 88 4
90 office building and staff lounge 54 days 27 Dec '20 20 Feb '21
91 sub structure 54 days 27 Dec '20 20 Feb '21
92 excavation 2 days 27 Dec '20 28 Dec '20 7,15 93
93 hard core laying 4 days 29 Dec '20 01 Jan '21 92 94
94 lean concrete 3 days 02 Jan '21 05 Jan '21 93,10 96
95 footing 10 days 06 Jan '21 16 Jan '21
96 footing rebars 5 days 06 Jan '21 10 Jan '21 94,17 97
97 footing formworks 3 days 11 Jan '21 14 Jan '21 96 98
98 footing casting 2 days 15 Jan '21 16 Jan '21 97,18 100
99 short column 8 days 17 Jan '21 24 Jan '21
100 sc rebars 4 days 17 Jan '21 20 Jan '21 98 101
101 sc formworks 3 days 21 Jan '21 23 Jan '21 100 102
102 sc casting 1 day 24 Jan '21 24 Jan '21 101 104
103 retaining wall 5 days 25 Jan '21 29 Jan '21
104 bricks laying 5 days 25 Jan '21 29 Jan '21 102 106
105 ground beam 12 days 30 Jan '21 10 Feb '21
106 gb rebars 5 days 30 Jan '21 03 Feb '21 104 107
107 gb formworks 3 days 04 Feb '21 06 Feb '21 106 108
108 gb casting 2 days 07 Feb '21 08 Feb '21 107 109
109 earth filling 2 days 09 Feb '21 10 Feb '21 108 112
110 super structure 10 days 11 Feb '21 20 Feb '21
111 ground floor 5 days 11 Feb '21 15 Feb '21
112 gf formworks 3 days 11 Feb '21 13 Feb '21 109 113
113 gf casting 2 days 14 Feb '21 15 Feb '21 112 115
114 roof 2 days 16 Feb '21 17 Feb '21
115 roof trust 1 day 16 Feb '21 16 Feb '21 113 116
116 roofing sheet 1 day 17 Feb '21 17 Feb '21 115 117
117 architectural works 1 day 18 Feb '21 18 Feb '21 116 118
118 m and e 1 day 19 Feb '21 19 Feb '21 117 119
119 testing and commissioning 1 day 20 Feb '21 20 Feb '21 118 4
Project: microsoft project 2013 Split Inactive Task Duration-only Finish-only Progress
Date: 20 Nov '20 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress
Page 3