Cable Trench Works Calc - 2
Cable Trench Works Calc - 2
Cable Trench Works Calc - 2
Qty
1
c Civil works approx/KM Rs.10,000
Lumpsum
6 Laying of cable up to ground level from 33kv feeder outgoing isolator
Laying of 33 KV ,3 core, 400sqmm in DWC HDPE pipes
1.5 hour per meter including laying of warning tapes
cable cover tiles, clamping and connection 1500
50
over heads and Supervision @ .05 hr per meter
Consumables approx Rs.8,000
Lumpsum
1
c Civil works approx/KM Rs.10,000
IV Laying and testing from RMU outgoing to HT service metering cubical point
1 Laying of 3 core, 185sqmm, 11 kv cable in open trench
cable cover tiles, supply and laying of bricks every 3 meters
a Per Kilometer=0.2 hrX1000 200
b over heads and Supervision @ .05 hr per meter 50
c Bricks Approx cost Rs.15,000 1
2 Laying of 3 core, 185sqmm 11 kv in DWC HDPE pipes
0.2 hour per meter including laying of warning tapes
cable cover tiles
a Per Kilometer=1.0X1000 1000
b over heads and Supervision @ .05 hr per meter 50
1
c Civil works approx/KM Rs.10,000
V RCC Cable trench
1 Supply and erection of cable trench of size 1M Wx 1.2M D x 1M L Rmtr
Excavation
2.1 Excavation of all soils by Machine except haard rock and morrum Cu.m
2.2 Excavation of all soils by Manpower except haard rock and morrum Cu.m
1 person per day=5 running meter
2 persons per day= 5 cubic meter
one digging, one banking & clearing soil
20 manhours per day for 5 cum 4
4 hours per cum
cum
Excavation in soft rock , BT roads and Maccadam surfaces,PCC and hard
murrum 4
2.3 Cu.m
Excavation by using manpower hard morrum and soft rock
6
3.3 Cu.m
In hard rock excavation shall be done by chiseling and by pneumatic drilling
20
4.3 Cu.m
In concrete roads excavation shall be done by chiseling and by pneumatic
drilling 12
Cu.m
Filling with clean sand in excavated trench in layers
2
3 Cu.m
Back filling the cable trench and restoring up to thre ground level with
1
3 avilable earth Cu.m
50 400.00 20,000.00
5 1,000.00 5,000.00
1 15,000.00 15,000.00
1 10,000.00 10,000.00
75,000.00 129,567.00 54,567.00
5 1,000.00 5,000.00
8,000.00
30 400.00 12,000.00
5 1,000.00 5,000.00
1 15,000.00 15,000.00
20 400.00 8,000.00
5 1,000.00 5,000.00
1 15,000.00 15,000.00
1 10,000.00 10,000.00
55,000.00 97,750.00 42,750.00
20 400.00 8,000.00
5 1,000.00 5,000.00
1 15,000.00 15,000.00
1 10,000.00 10,000.00
10 4,000.00 40,000.00
160,000.00
30 4,800,000.00
Billing per month Billing per month
Comments for 10 KM for 5 KM
83,020.00 41,510.00
1,500,000.00 750,000.00
3,070,000.00 1,535,000.00
2,300,000.00 1,150,000.00
Not required every day, should be
subcontract on target basis.
30,156,990.00 15,078,495.00