PPME
PPME
PPME
Month
Activity 1 2 3 4 5 6 7 8 9 10
A
B
C
D
E
F
G
C
10% work remaining
D
40% work remaining
15
B
30
C
10% work remaining
30
D
40% work remaining
15
E
10
F
20
G
Planned Today
Completed
To be completed
At the end of Month 5
Status of activities
Start Completion
Planned=10
Planned=20
Planned Schedule or Baseline
Month Cost
Planned till
Activity 1 2 3 4 5 6 7 8 9 10 Month-10
A
Planned till
Activity 1 2 3 4 5 6 7 8 9 10 Month-10
3 7 10
A
5 10 15
B
10 5 5 10 30
C
20 5 5 30
D
10 5 15
E
6 3 1 10
F
4 4 12 20
G
130
Month 1 2 3 4 5 6 7 8 9 10
Sum 23 18 17 25 17 5 20 5 0 0
Cumulative 23 41 58 83 100 105 125 130 130 130
Cumulative Cost or PV
150
100
50
0
1 2 3 4 5 6 7 8 9 10
Month 1 2 3 4 5 6 7 8 9 10
Sum 5 6 18 29 17
Cumulative 5 11 29 58 75
Cumulative Cost or AC
80
60
40
20
0
1 2 3 4 5 6 7 8 9 10
PV and AC
140
120
100
80
60
40
PV and AC
140
120
100
80
60
40
20
0
1 2 3 4 5 6 7 8 9 10
Planned till
Activity 1 2 3 4 5 6 7 8 9 10 Month-10
3 7 10
A
5 5
5 10 15
B
10 10 5
10 5 5 10 30
C
12 8 10% work remaining
20 5 5 30
D
1 1 4 4 40% work remaining
10 5 15
E
7 3
6 3 1 10
F
4 4 12 20
G
Actual till
Month-5
Cost
Actual till
Month-5
PV
Cost
Actual till
Month-5
10
25
20
10
10
75
AC
At the end of Month 5
Actual till % work
PV EV AC CV SV Schedule Cost
Month-5 completed
10 10 10 0 0 Same Same
10 100
15 15 25 -10 0 Same Overrun
25 100
15 27 20 7 12 Underrun Underrun
20 90
30 18 10 8 -12 Overrun Underrun
10 60
0 15 10 5 15 Underrun Underrun
10 100
10 0 0 0 -10 Overrun
0
20 0 0 0 -20 Overrun
0
Project 100 85 75 10 -15 Overrun Underrun
PV: Planned Value CV: Cost Variance, CV = EV-AC
EV: Earned Value SV: Schedule Variance, SV = EV-PV
ss than budget) AC: Actual Cost
EAC: Estimated Cost at Completion
EAC = 114.7 =75+(130-85)*75/85