1 Skin wall construction 3,483,338.25 Rejected Structural Rejected
3 Floor height change for lift machine room 770,190.39 Rejected Architectural Rejected
4 Steel bracket preparation for frameless windows 847,416.00 Rejected Architectural Rejected
14 8.00 Ramp area donut finishing work ( Level 3 to 9) 5,247,675.00 466,984.00 466,984.00 Architectural Architectural requirement Variation Order Form 2 issued - do -.
15 9.00 Supply and installation of PFR (Mockup) 42,983.36 42,983.36 42,983.36 MEP Variation Order Form 2 issued - do -.
Supply and installation of wall mounted type fan exhaust air flow
17 11.00
90m3/hr
360,540.00 360,540.00 360,540.00 MEP MEP Drawings & Spec changes Variation Order Form 2 issued - do -.
5. Omission of driver's toilet at level 4 (563,504.90) (674,459.86) 262,004.67 936,464.53 Variation Order Form 2 issued - do -.
7. Supply and laying of 50 mm dia uPVC type 600 vent pipes instead of
40 mm dia uPVC type 600 vent pipes - Instruction given by Haritha 728,506.00 728,506.00 4,304,472.00 3,575,966.00
Consultants
19 13.00 13.00 Omission of driver's toilet at level 5 & 7 (1,679,464.38) (1,749,502.92) 28,980.72 1,778,483.64 Architectural MEP Drawings & Spec changes Variation Order Form 2 issued - do -.
Change of river sand to manufacture sand in concrete works- 60 % M Consultant's proposal for cost
21 8.00 15.00 (3,503,816.55) (3,687,289.25) - 3,687,289.25 Structural Variation Order Form 2 issued - do -.
Sand reduction
24 12.00 18.00 Change of Apartments from 25th-36th floors 28,471,889.49 13,761,379.49 202,793,026.35 189,031,646.86 Employer New requirement by Client Variation Order Form 2 issued - do -.
25 19 R Supply & Installation of traffic sign lights 925,419.38 925,419.38 925,419.38 Employer Part of TIA Variation Order Form 2 issued - do -.
27 21.00 Panel board changes to rapid car charging 185,677.92 167,582.10 167,582.10 Employer New requirement by Client Variation Order Form 2 issued - do -.
28 16.00 22 R Adding dishwasher to Unit 1 & 7 1,387,664.38 1,387,664.38 1,387,664.38 Employer New requirement by Client Variation Order Form 2 issued - do -.
Change of river sand to manufacture sand in concrete works- 75 % M Consultant's proposal for cost
29 23.00 Sand & 25% River sand (1,694,733.69) (6,041,690.21) 6,041,690.21 Structural reduction Variation Order Form 2 issued - do -.
30 24.00 Ceiling changes in Level 10 (695,716.06) (695,716.06) 4,237,493.30 4,933,209.36 Architectural Design change Variation Order Form 2 issued - do -.
31 25.00 CEB room AC variation 780,963.80 777,814.99 777,814.99 P.Sum CEB requirement Variation Order Form 2 issued - do -.
32 26.00 Ramp area 300 mm thick block wall change to G25 concrete guard wall 652,414.59 652,414.59 652,414.59 Architectural Safety concern Variation Order Form 2 issued - do -.
35 29.00 Construction of LSSP side drain 644,728.34 352,433.24 352,433.24 MEP Site requirement Variation Order Form 2 issued - do -.
36 30.00 Location change of diesel tank 6,697,311.89 6,503,860.23 7,059,958.40 556,098.17 MEP Site requirement Variation Order Form 2 issued - do -.
39 33.00 Re-conduiting socket outlets in unit 01 pantry area 218,745.60 100,277.30 100,277.30 - MEP Variation Order Form 2 issued - do -.
42 36.00 Addition & Omission of guard wall 498,876.02 486,132.02 8,345,712.62 7,859,580.60 Architectural Fire safety concern Variation Order Form 2 issued - do -.
43 37.00 Insurance cost for terrorism cover 110,450.83 110,450.83 110,450.83 - Employer New item Variation Order Form 2 issued - do -.
45 39.00 Toilet partition work 99,844.81 99,844.81 1,399,922.51 1,300,077.70 Architectural Design change Variation Order Form 2 issued - do -.
46 40R Garbage chute timber door change to aluminium 236,239.92 (120,936.22) 2,909,675.78 3,030,612.00 Architectural Design change Variation Order Form 2 issued - do -.
Ironmongery changing work unit 6 pantry area D15 sliding door ( Duty
49 43.00
paid)
405,469.58 405,469.58 405,469.58 - Architectural Design change Variation Order Form 2 issued - do -.
50 44.00 Apartment area unit 02 & 03 ceiling changing work 964,477.83 210,086.18 210,086.18 Architectural Design change Variation Order Form 2 issued - do -.
51 45.00 Additional steel fire doors for refuge area 653,734.67 653,734.67 1,639,978.67 986,244.00 Architectural Safety concern Variation Order Form 2 issued - do -.
52 46.00 Garbage chute void covering work 734,590.65 720,578.65 720,578.65 - Site Requirement Site Requirement Variation Order Form 2 issued - do -.
53 47.00 Balancing tank ( Addition & Omission ) 635,229.89 635,229.89 1,108,067.69 472,837.80 Structural Design change Variation Order Form 2 issued - do -.
54 48.00 Rain water harvesting tank 1,708,508.08 1,708,508.08 2,073,314.06 364,805.98 Structural Design change Variation Order Form 2 issued - do -.
New safety
55 49.00 Safety handrail at level 10 gym area 290,804.80 290,571.06 290,571.06 - Safety concern Variation Order Form 2 issued - do -.
requirement
57 51.00 Existing boundary wall survey work 99,200.00 99,200.00 99,200.00 Employer Site requirement Variation Order Form 2 issued - do -.
58 52.00 S/S hand rail vertical member strengthening using solid flat bar 11,389,448.66 7,763,208.99 7,763,208.99 Structural/Architect Safety concern Variation Order Form 2 issued - do -.
ural
60 54.00 Common area bathroom ledge wall work 20,576.46 20,576.46 20,576.46 Architectural Design change Variation Order Form 2 issued - do -.
61 55.00 D 02 door ironmongery changing work 1,258,704.16 1,167,346.60 1,167,346.60 Architectural Design change Variation Order Form 2 issued - do -.
66 60.00 Water sump smooth rendering 239,279.13 239,279.13 590,538.78 351,259.65 Architectural Variation Order Form 2 issued - do -.
cost management services (pvt) ltd Page - 5
Cost Report -05 15th December 2017
68 62.00 Level 10 garden area changes 6,229,308.61 1,726,305.74 5,141,977.74 3,415,672.00 Architectural Design change Variation Order Form 2 issued - do -.
69 63.00 Level 48 S/S handrail changing work 1,856,144.01 1,532,192.40 4,795,466.40 3,263,274.00 Architectural Safety concern Variation Order Form 2 issued - do -.
New safety
70 64.00 Proposed Lifeline system 2,198,086.72 2,183,756.04 2,183,756.04 - requirement Safety concern Variation Order Form 2 will be issued
71 65.00 Level 32 unit 6 pantry variation 142,537.04 142,537.04 142,537.04 - Employer Customization Variation Order Form 2 will be issued
72 66.00 Variation 82
Unit 2&3 balcony GI riser area painting work 142,042.97 87,869.80 87,869.80 -
Additional door stopper for shower cubical 120,706.56 120,706.56 120,706.56 -
Level 03 wash room area additional waterproofing work 9,922.64 9,922.64 9,922.64 -
Level 46 additional beam & related work 68,947.20 67,827.20 67,827.20 - Design changes done by NCD Variation Order Form 2 will be issued
Architectural & and PWA as per site
Level 2 truck parking area concrete curbs & related works 684,638.15 681,638.15 681,638.15 - Structural requirements identified during
Level 48 additional wall & related works 93,940.89 93,940.89 93,940.89 - the construction.
Level 03 additional beam detail (above W52 window) 78,867.46 77,267.46 77,267.46 -
Level 03 to Level 04 new column ( size 250 x 400 ) 71,114.37 69,514.37 69,514.37 -
Additional requirement
74 68.00 Aluminium U chanel fixing work for W51a (Level 37 to 46) 166,970.00 154,744.00 154,744.00 - Architectural Variation Order Form 2 will be issued
identified during construction
Additional requirement
75 69.00 Level 37- 46, unit 7 powder room new geyser point 323,831.88 319,831.88 319,831.88 MEP Variation Order Form 2 will be issued
identified during construction
77 71.00 Concrete pit for diesel tank in level 1, level 3 & level 26 642,507.13 63,497.96 93,384.38 29,886.42 RFI issue Variation Order Form 2 will be issued
Additional requirement
79 73.00 Additional water line for irrigation tank with BMS provision 480,052.26 471,952.26 471,952.26 - MEP Variation Order Form 2 will be issued
identified during construction
80 74.00 Level 48 SS safety bars for SC 02 & SC 03 98,394.00 91,252.50 91,252.50 - Architectural Safety concern Variation Order Form 2 will be issued
Additional requirement
82 76.00 Level 26 pump room additional skirting preparation 72,572.95 72,572.95 Architectural Variation Order Form 2 will be issued
identified during construction
Additional requirement
86 80.00 Cooker hood socket outlet changing work in L 11 to 20 936,402.23 815,985.20 815,985.20 Variation Order Form 2 will be issued
identified during construction
Additional requirement
88 82.00 Level 03 additional water proofing ceiling preparation 152,583.40 29,013.10 152,583.40 123,570.30 identified during construction Variation Order Form 2 will be issued
Level 2 reception table location change, L 2-3 ELV provision location Additional requirement due to
90 84.00 530,401.28 513,174.55 513,174.55 Variation Order Form 2 will be issued
change & L 48 additional bulk head site condition
92 86.00 Ramp area new GI handrail 660,646.91 660,646.91 660,646.91 Architectural concern Variation Order Form 2 will be issued
96 90.00 Tile finish for walls in wet garbage cold room at level 2 588,658.17 560,916.45 560,916.45 New requirement Variation Order Form 2 will be issued
97 91.00 Fire test drain line 482,814.62 408,942.35 408,942.35 - New requirement Cost to be revised
98 92.00 Level 1-26 day tank interconnection work 100,804.93 98,358.04 98,358.04 New requirement Variation Order Form 2 will be issued
101 Supply & installation of Logos & signage work 15,187,371.20 8,085,062.00 14,085,062.00 6,000,000.00 P.Sum
102 94.00 Level 11 aluminium window height changing & related work 3,011,587.29 2,634,101.58 Architectural
103 95.00 Level 47 ALS 3 height changing work 90,683.87 90,683.87 Structural
Level 47 booster pump room,pool pump room & L48 store room
105 97.00 waterproofing work 216,835.63 133,288.92
107 99.00 Level 48 SS handrail design calculation charges 125,000.00 76,609.62 Structural
108 100.00 Level 2 plantrough area new cylinder installation 486,324.93 486,324.93 Architectural
cost management services (pvt) ltd Page - 7
Cost Report -05 15th December 2017
109 101.00 Level 2 additional ceiling, lintol and riser preparation 341,416.08 301,195.47 Architectural
110 102.00 Kitchen sink removing & refixing of bottle trap & waste pipe 448,507.00 448,507.00
112 104.00 Ground floor interlocking pavings and other related works 1,012,969.46 840,679.00 To be discussed with PWA
114 107.00 L-48 additional drain 72,518.50 68,983.14 Sent to Haritha Consultants
115 108.00 Level 48 cladding flashing to internal walls 592,000.00 549,056.00 Architectural
118 Level 02 reflective pond side filling and additional wall 209,422.46 Structural To be discussed with PWA
119 Level 3 management room ceiling height changes and new bulk head 51,503.90 Architectural To be discussed with PWA
120 Level 10 gym area ceiling height changing work 193,061.86 To be discussed with PWA
121 L 48 pool area new finwall & granite finish on pool top 643,319.47 To be discussed with PWA
123 Car park area guard wall top side preparation work 832,451.29 Returned to Sanken to discuss with PWA
124 Level 48 & roof level additional expantion joint preparation work 1,067,699.03 Sent to NCD
8,251,401.59 - - 52,000,000.00