ITEM - II MASONRY WORKS

A. DETERMINING THE NUMBER OF CONCRETE HOLLOW BLOCKS USED


B. DETERMINING THE NUMBER OF CEMENT & VOLUME OF SAND FOR MORTAR & PLASTERING
Enter Wall Height H (M) 2.60 M
Enter Wall Length L (M) 460.00 M
Enter Area of Window AW (SQ.M.) - SQ.M
Enter Area of Door AD (SQ.M) - SQ.M.
Breakage Allowance % 5.00 %

TOTAL WALL AREA: 1,196.00 SQ.M.


TOTAL NUMBER OF CHB: 15,698.00 PCS

MORTAR USING 4" CHB


# OF CEMENT BAGS 628.00 BAGS
VOL. OF SCREENED SAND CU.M. 52.40 CU.M.
MORTAR USING 6" CHB
# OF CEMENT BAGS 1,212.00 BAGS
VOL. OF SCREENED SAND CU.M. 101.00 CU.M.

PLASTER : 16mm thk Mix: 1:2


One face ofthe wall only
# OF CEMENT BAGS 345.00 BAGS
VOL. OF FINE SAND CU.M. 19.20 CU.M.
PLASTER : 16mm thk Mix: 1:2
Two faces of the wall
# OF CEMENT BAGS 689.00 BAGS
VOL. OF FINE SAND CU.M. 38.30 CU.M.

RIPRAPING WORKS L
W1 Enter Height H (M) 1.00 M
Enter Width 1 W1 (M) 0.40 M
Enter Width 2 W2 (M) 0.40 M
Enter Length L (M) 460.00 M

Using: Stones ranging from 15 to 25 kgs with atleast


H 50% of stones weighing more than 20 kgs, &
Class A Mixture

TOTAL SIDE AREA: 0.40 SQ.M.


TOTAL VOLUME: 184.00 CU.M.
VOL. OF BOULDERS CU.M. 184.00 CU.M.
# OF CEMENT BAGS 474.00 BAGS
VOL. OF SAND CU.M. 26.40 CU.M.
W2

BASED ON MAX FAJARDO - SIMPLIFIED CONSTRUCTION ESTIMATE HANDBOOK

You might also like