Lean Constuction Question Bank
Lean Constuction Question Bank
a) Over production
b) Taxes
c) Transportation
Q3. What type of waste is Creating extra reports that no one needs ?
a) Defect
b) Inventory
c) Over Production
b) Security, performance
c) OEM metrics
Q5. At which Lean maturity level you can expect Well Defined Process to Follow Lean Principles ?
a) Level 01
b) Level 02
c) Level 03
c) Inventory / Days
a) Provide perfect value to the customer through a perfect value creation process that has zero waste
Explanations:Correct Answer A. Lean philosophy is to provide perfect value to the customer through a perfect value
creation process that has zero waste. While cost reduction is not the main focus on Lean, this approach helps in cost
reduction as well.
a) Ford
b) Toyota
c) Lean Association
Explanations:Correct Answer B. The definition of waste due to wrong use of Metrics is: Any Metrics that is
incorrectly measured, incorrectly used, misinterpreted or mis-used is another type of waste called "wrong use of
metrics"
a) Continuous Improvement
b) Prevent Defects
Explanations:Correct Answer C. Japanese 5s methodology was created and used for organizing, cleaning, developing,
and sustaining a productive work environment
Q13. Which of the 5S technique requires you to separate necessary and unnecessary items at the workplace?
a) Seiri (Sort)
b) Seiton (Stabalize)
c) Non-Value Add
Explanations:Correct Answer A. Seiri (Sort), is the first step in making things cleaned up, sorted, and organized. It
starts out by sorting the necessary and the unnecessary items and remove the unnecessary items from the workplace
Q14. While implementing 5S, red color tags are used to mark items for what reason?
Explanations:Correct Answer C. The 5S methodology starts by sorting the necessary and the unnecessary. All the
items that are not used frequently and those that are unnessary are marked by red tags so that it can be visually
identified and removed.
Explanations:Correct Answer C. Once the first three S of the 5Ss have been implemented, the next pillar is to
standardize the best practices in the work area. Seiketsu called as Standardize in English, is the method to maintain
the first three pillars. It creates a consistent approach with which tasks and procedures are done.
Q17. What part of 5S promotes that all work stations for a particular job should be identical?
a) Seiketsu (Standardize)
b) Seiso (Shine)
c) Seiri (Sort)
Explanations:Correct Answer A. Seiketsu (Standardize) is the right answer. All work stations for a particular job
should be identical. All employees doing the same job should be able to work in any station with the same tools that
are in the same location in every station.
a) Ishikawa Diagram
b) Six Sigma
Explanations:Correct Answer A. There are normally a series of root causes stemming from one problem, and they can
be visualized in cause and effect manner using Cause-and-Effect diagram. This was developed by Ishikawa and also
called as Ishikawa diagram.
Q19. Which is the tool or technique used for rapid improvement for discrete process issues?
a) Kanban
b) Kaizen Blitz
c) Kaizen
Explanations:Correct Answer B. The correct answer is Kaizen Blitz (or as it is also called, kaikaku in Japanese). It is a
rapid improvement workshop designed to produce results/approaches to discrete process issues within a few days.
b) Throughput time
Explanations:Correct Answer C. Lean production uses takt time as the rate at which a completed product needs to be
finished in order to meet customer demand.
Q21. What is the name of the process, tool or technique which help in automatic detection of process malfunction and
product defect and prevents it from moving forward in the production process?
a) Kanban
b) Jidoka (Autonomation)
c) Poka Yoke
Explanations:Correct Answer B. Jidoka is a Japanese term used for autonomation means "intelligent automation" or
"humanized automation." In practice, it means that an automated process is sufficiently "aware" of itself so that it will
detect when the desired quality is produced, detect process malfunctions, detect product defects, stop itself and alert
the operator. A future goal of autonomation is selfcorrection.
a) Kaizen
b) Six Sigma
c) Kanban
Explanations:Correct Answer A. The word kaizen means "continuous improvement." It is a system of continuous
improvement in quality, technology, processes, company culture, productivity, safety, and leadership. It comes from
the Japanese words ("kai") which means "change" or "to correct" and ("zen") which means "good."
a) Ishikawa
b) Kaizen
c) Deming
Explanations:Correct Answer C. PDCA was made popular by Dr W. Edwards Deming, who is considered by many to
be the father of modern quality control.
Q24. The "5 Whys" technique is used for what purpose?
a) Continuous Improvement
Explanations:Correct Answer C. Five (5) Whys, is a form of root cause analysis in which the user asks "why" to a
problem and finds an answer five successive times. There are normally a series of root causes stemming from one
problem.
Explanations:Correct Answer A. SMED is the term used to represent the Single-Minute Exchange of Die or setup
time that can be counted in a single digit of minutes. SMED is often used interchangeably with quick changeover.
Q26. For many people, changing a single tire can easily take 15 minutes. But, for a NASCAR pit crew, changing four
tires takes less than 15 seconds. This represent good use of what tool?
b) Kanban
c) Six Sigma
Explanations:Correct Answer A. The successful implementation of SMED and quick changeover is the key to a
competitive advantage for any Process
Explanations:Correct Answer C. The five steps in 5S are Sort, Set-in-Order, Shine, Standardize & Sustain.
Explanations:Correct Answer B. PDCA stands for Plan Do Check Act is the correct.
a) Call Center
b) Supermarkets
c) Toyota Manufacturing
Explanations:Correct Answer B. Taiichi Ohno was inspired by the American supermarket's working and applied to
auto industry. The technique is called Kanban that means Signboard
a) Lean Manufacturing
b) Six Sigma
c) Re-Engineering
Explanations:Correct Answer A. Lean manufacturing represents a fundamental paradigm shift from traditional batch
and queue mass production to production systems based on product aligned single-piece flow, pull production.
a) Year 1971
b) Year 2000
c) Year 1996
Explanations:Correct Answer C. The Boeing Company began implementing Lean manufacturing throughout its
Commercial Airplanes division in February 1996.
Q32. In healthcare service industry "excess amount of blood drawn" is what type of waste?
a) OverProduction
b) Defect
c) Inventory
a) OverProduction
b) Motion
c) Under-utilization
Explanations:Correct Answer C. When people are doing some work that could be done by lower skill people, it would
fall into this type of waste. An example would be a nurse transporting patients to x-ray room; this could very well be
done by ward-boy or assistants.
a) Waiting
b) Over production
c) Under-utilization
Explanations:Correct Answer A. Patients waiting for doctor to be seen is waiting type of waste. If the doctor is
waiting for patients then it would be underutilization.
Q35. What type of waste is "insufficient quantity or overdose of medicine is given to the patient"?
a) Over Production
b) Defect
c) Under-utilization
Explanations:Correct Answer B. The severity of this waste can be fatal if the work is not done right the first time. If
an incorrect medicine, insufficient quantity or overdose of medicine is given to the patient, it will be an critical defect
type of waste - which might lead to fatal injury/death or retreatment, etc.
Q36. What type of waste is "Purchasing and storing office supply, sales literature, etc."?
a) Over Production
b) Inventory
c) Motion
Explanations:Correct Answer B. Any access purchase and storage of office supply, sales literature, Reports, etc.
would constitute inventory type of waste.
Q37. What type of waste is "Excessive or unnecessary emails and document get forwarded multiple times"?
a) Over Production
b) Inventory
c) Extra Motion
Explanations:Correct Answer C. The Waste type is "Extra Motion". If excessive or unnecessary emails and document
get forwarded multiple times sometimes with large attachments due to multiple distribution groups, it constitutes
waste of type motion.
Q38. What is an appropriate Lean metric to capture effective utilization of manufacturing operation in a factory?
b) Efficiency
c) Six Sigma
Explanations:Correct Answer A. Overall equipment effectiveness (OEE) is a hierarchy of metrics which evaluates and
indicates how effectively a manufacturing operation is utilized.
Q39. How can one provide assessment of financial, behavioral, and core process performances on an on-going basis
to track continuous improvement efforts of the company?
Q40. What metrics capture availability, performance, and quality components of a manufacturing unit?
a) Quality of Service
Explanations:Correct Answer B. Overall Equipment Effectiveness (OEE) breaks the performance of a manufacturing
unit into three separate but measurable components: availability, performance, and quality.