Software Project Management LAB # 09: Course Instructor: Dr. Muhammad Nadeem Majeed Lab Instructor: Engr. Nazia Bibi
Software Project Management LAB # 09: Course Instructor: Dr. Muhammad Nadeem Majeed Lab Instructor: Engr. Nazia Bibi
LAB # 09
The scenario: At Lucerne Publishing, the new book launch plan is now
fully developed. Actual work on the project will soon begin. To allow a
later comparison of actual work and the current schedule with the
original plan, you will first save a baseline.
EXERCISE:
In this exercise, you save the current state of a schedule as a baseline and
then view the baseline task values.
1 On the Project tab, in the Schedule group, click Set Baseline, and then
click Set Baseline.
The Set Baseline dialog box appears.
You’ll set the baseline for the entire plan by using the default settings
of the dialog box .
2 Click OK .
Project saves the baseline, even though there’s no indication in the
Gantt chart view that anything has changed. You will now see some of
the changes caused by saving the baseline.
3 On the Task tab, in the View group click the down arrow below Gantt
chart, and then click Task Sheet.
The Task Sheet view appears. Because this is a tabular view, it does not
include the Gantt chart, so more room is available to see the fields in the
Entry table.
Now you’ll switch to the Variance table in the Task Sheet view. The
Variance table is one of several predefined tables that include baseline
values.
4 On the View tab, in the Data group, click Tables.
In the listed tables, note the check mark next to Entry. This means that
the Entry table is currently displayed in the Task Sheet view. You’ll
switch to another table next.
5 Click Variance.
The Variance table appears. This table includes both the scheduled and
baseline start and finish columns, shown side by side for easy
comparison.
The simplest approach to tracking progress is to report that the actual work is
proceeding exactly as planned. For example, if the first week of a five-week
project has elapsed and all its tasks have started and finished as scheduled,
you can quickly record this in the Update Project dialog box.
When you record progress through a specific date, Project calculates the
actual duration, the remaining duration, actual costs, and other values up to
the date you entered. This approach might be fine even if the actual work and
cost values generated by Project won’t exactly match what happened in the
real world, but are close enough for your schedule tracking purposes. This is
a judgment call that you as a project manager (in consultation with your
project sponsors and other stakeholders) can consider.
The scenario: At Lucerne Publishing, some time has passed since saving
the baseline in the new book launch plan. Work has been completed
through the first week and a half, as planned. You need to account for
the completed work in the plan.
EXERCISE:
In this exercise, you track the plan as scheduled through a specific date,
resulting in Project recording project actuals.
3 Click OK.
Project records the completion percentage for the tasks that were scheduled
to start before March 14. It displays that progress by drawing progress
bars in the Gantt bars for those tasks.
After work begins on a task, you can quickly record its progress as a
percentage. When you enter a completion percentage greater than 0, Project
sets the task’s actual start date to match its scheduled start date. Project then
calculates the actual duration, the remaining duration, actual costs, and other
values based on the percentage you enter.
For example, if you specify that a four-day task is 25 percent complete,
Project calculates that it has had one day of actual duration and three days of
remaining duration.
Here are some ways of entering completion percentages:
Use the 0%, 25%, 50%, 75%, and 100% Complete buttons in the Schedule
group of the Task tab.
Enter any percentage value you want in the Update Tasks dialog box. (To
access this dialog box, on the Task tab, in the Schedule group, click the down
arrow to the right of Mark on Track, and then click Update Tasks).
1 In the Task Name column, select the name of task 5, Design and order
marketing material.
This task has some progress reported against it from the previous
exercise, but it has not yet been set as complete.
2 On the Task tab, in the Schedule group, click 100% Complete .
Project records the actual work for the task as scheduled and extends a
progress bar through the length of the Gantt bar.
Next you’ll record that the completion milestone for the Planning Phase
and the first task of the Internal Launch Phase are complete .
3 In the Task Name column, select the name of task 6, Planning
complete!, and while holding down the Ctrl key, select the name of task
8, Kickoff book launch meeting .
4 On the Task tab, in the Schedule group, click 100% Complete .
Because task 6 is a milestone task with no duration, there is no change
in appearance of its symbol in the chart portion of the Gantt Chart view
as there is for task 8 . You do, however, see the completion check marks
for both tasks in the Indicators column .
Project records the actual work for the task as scheduled and then draws
a progress bar through part of the Gantt bar .
Note that although 50% of the work on task 9 is completed, the progress
bar does not span 50% of the width of the Gantt bar.
This is because Project measures duration in working time but draws the
Gantt bars to extend over nonworking time, which in this case includes
April 22, the nonworking day.
7 In the chart portion (on the right) in the Gantt Chart view, hold the
mouse pointer over the progress bar in task 9’s Gantt bar. When the
mouse pointer changes to a percent symbol and right arrow, a Progress
ScreenTip appears.
When you enter various actual values, Project uses the following rules to
update the plan:
a. When you enter a task’s actual start date, Project moves the
scheduled start date to match the actual start date .
b. when you enter a task’s actual finish date, Project moves the
scheduled finish date to match the actual finish date and sets the task
to 100% complete.
c. When you enter a task’s actual work value, Project recalculates the
task’s remaining work value, if any .
d. when you enter a task’s actual duration, if it is less than the scheduled
duration, Project subtracts the actual duration from the scheduled
duration to determine the remaining duration.
e. When you enter a task’s actual duration, if it is equal to the scheduled
duration, Project sets the task to 100% complete .
f. When you enter a task’s actual duration, if it is longer than the
scheduled duration, Project adjusts the scheduled duration to match
the actual duration and sets the task to 100% complete .
Because your plan is updated with actuals, your plan as scheduled will likely
change . The original plan as saved in a baseline is not altered, however .
The scenario: At Lucerne Publishing, a few more days have passed and
work on the new book launch has progressed. Resources performing the
work have given you actual progress that differs somewhat from the
plan, and you want to record these actuals and observe the effect on the
overall plan.
Exercise:
In this exercise, you record actual work values for some tasks, as well as
actual start dates and durations for other tasks.
1 On the View tab, in the Data group, click Tables and then click
Work.
The Work table appears.
2 If needed, drag the vertical divider bar to the right to expose the last
column in the Work table, %W. Comp (% Work Complete).
3 This table includes both the total scheduled work (labeled Work) and
Actual and Remaining work columns . You’ll refer to the values in
these columns as you update tasks.
In the chart portion of the Gantt Chart view, you can see that task 9 is
partially complete. In the Work table, note the actual work value of 8
hours.This 8 hours is the result of setting the task at 50% complete in the
previous exercise .
The task had 16 hours of work total, so 50% complete equals 8 hours of
actual work completed and 8 hours remaining . You want to record that the
task is now complete but required more actual work than expected .
4 In the Actual field for task 9, Prepare book P&L statement, type or
select 24, and then press Enter .
Project records that 24 hours of work have been completed on task 9 .
Because 24 hours is greater than the originally scheduled 16 hours
(visible in the tasks’ baseline field), Project marks the task as completed
and extends the Gantt bar of the task to indicate its longer duration .
Actual work is rolled up from the
subtask to the summary tasks.
To conclude this exercise, you will enter actual start dates and durations
of other tasks in the Internal Launch Phase .
5 In the Task Name column, click task 10, Plan author’s travel
itinerary.
This task started one working day ahead of schedule (the Tuesday
before its scheduled start date) and took a total of seven days to
complete . You will record this information in the Update Tasks dialog
box .
6 On the Task tab, in the Schedule group, click the down arrow to the
right of the Mark on Track button, and then click Update Tasks .The
Update Tasks dialog box appears .
This dialog box shows both the actual and scheduled values for the
task’s duration, start, and finish, as well as its remaining duration . In
this box, you can update the actual and remaining values .
7 In the Start field in the Actual group on the left side of the dialog box,
type or select 3/20/19 .
To conclude this exercise, you will record that task 11 started on time
but took longer than planned to complete .
10 In the Task Name column, click task 11, Channel Sales prep .
11 On the Task tab, in the Schedule group, click the down arrow to the
right of the Mark on Track button, and then click Update Tasks .
The Update Tasks dialog box appears .
12 In the Actual dur field, type 7d, and then click OK .
Project records the actual duration of the task . Remember that an actual
duration value of “7d” means seven working days, not seven calendar
days.
Because you did not specify an actual start date, Project assumes that the
task started as scheduled. However, the actual duration you entered causes
Project to calculate an actual finish date that is later than the originally
scheduled finish date. Likewise, the actual work value (112 hours) is larger
than the originally scheduled work (80 hours).