The Foundations of PM-merged PDF
The Foundations of PM-merged PDF
Leadership academy
project management program
The Foundations of PM(PM6111)
chapter1: PM principles
» The process of defining the business need, analysing the situation, making recommendations, and defining
evaluation criteria is applicable to any organization’s projects. A business case may include but is not limited to
documenting the following:
» Business needs:
» Determination of what is prompting the need for action;
» Situational statement documenting the business problem or opportunity to be addressed including the
value
» Identification of stakeholders affected; and
» Identification of the scope.
» Analysis of the situation:
» Identification of organizational strategies, goals, and objectives;
» Identification of root cause(s) of the problem or main contributors of an opportunity;
» Gap analysis of capabilities needed for the project versus existing capabilities of the organization;
» Identification of known risks;
» Identification of critical success factors;
3/21/2020 Fentaw Leykun (PhD) PM63114
4
» Identification of decision criteria by which the various courses of action may be assessed
Cont’d
» Identification of a set of options to be considered for addressing the business problem or opportunity.
» Options are alternative courses of action that may be taken by the organization.
» Options may also be described as business scenarios. For example, a business case could present
the following three options:
» Do nothing. This is also referred to as the “business as usual” option. Selection of this option results
in the project not being authorized.
» Do the minimum work possible to address the problem or opportunity. The minimum may be
established by identifying the set of documented criteria that are key in addressing the problem or
opportunity
» Do more than the minimum work possible to address the problem or opportunity. This option meets
the minimum set of criteria and some or all of the other documented criteria. There may be more
than one of these options documented in the business case.
6
Cont’d
» Recommendation:
» A statement of the recommended option to pursue in the project;
» Items to include in the statement may include but are not limited to:
» Analysis results for the potential option;
» Constraints, assumptions, risks, and dependencies for the potential options;
and
» Success measures (see Section 1.2.6.4).
» An implementation approach that may include but is not limited to:
» Milestones,
» Dependencies, and
» Roles and responsibilities.
7
Cont’d
»Evaluation:
» Statement describing the plan for measuring benefits the project will
deliver. This should include any on-going operational aspects of the
recommended option beyond initial implementation.
» The business case document provides the basis to measure success
and progress throughout the project life cycle by comparing the results
with the objectives and the identified success criteria.
8
Project business documents: project benefit
plan
9
Cont’d
» The benefits management plan describes key elements of the benefits and may include but is not
limited to documenting the following:
» Target benefits (e.g., the expected tangible and intangible value to be gained by the
implementation of the project; financial value is expressed as net present value);
» Strategic alignment (e.g., how well the project benefits align to the business strategies of the
organization);
» Timeframe for realizing benefits (e.g., benefits by phase, short-term, long-term, and on-
going);
» Benefits owner (e.g., the accountable person to monitor, record, and report realized benefits
throughout the timeframe established in the plan);
» Metrics (e.g., the measures to be used to show benefits realized, direct measures, and
indirect measures);
» Assumptions (e.g., factors expected to be in place or to be in evidence); and
» Risks (e.g., risks for realization of benefits). 10
Cont’d
» Developing the benefits management plan makes use of the data and information documented in the
business case and needs assessment.
» For example, the cost-benefit analyses recorded in the documents illustrate the estimate of
costs compared to the value of the benefits realized by the project.
» The benefits management plan and the project management plan include a description of how the business
value resulting from the project becomes part of the organization’s on-going operations, including the
metrics to be used.
» The metrics provide verification of the business value and validation of the project’s success.
Development and maintenance of the project benefits management plan is an iterative activity.
» This document complements the business case, project charter, and project management plan.
» The project manager works with the sponsor to ensure that the project charter, project management plan,
and the benefits management plan remain in alignment throughout the life cycle of the project.
11
Project Management
Framework PMBOK 5th edition
Key Concepts
&
Organization
Influences
The specific form, function, and structure of a PMO are dependent upon the
needs of the organization that it supports.
Organizational Strategy &
Project / Operations Management
1. Staff members are grouped by specialty, 1. Its organizational units called departments.
Production, marketing ,,,,,,. 2. Department directly to the project manager or provide
support services to the various projects
2. Specialties may be further subdivided into
3. Project managers have a great deal of independence and
functional units mechanical, electrical, authority
engineering,,,,. 4. Team members are often co-located.
3. Each department in a functional organization 5. Most of the organization’s resources are involved in
will do its project work independently of other project work
departments.
Influences
Organizational Structures
Does not provide the PM
1. Have full-time project with the full authority over
managers with the project & project funding.
The role of a project manager is
considerable authority
more of a Coordinator
2. Have full-time project
or Expediter.
administrative staff.
EEF refer to conditions, not under the control of the project team, that influence,
constrain, or direct the project.
EEF may enhance or constrain project management options, and may have a
positive or negative influence on the outcome (Risk Management).
The project team includes the project manager and the group of individuals who act together in
performing the work of the project to achieve its objectives.
Project teams include roles such as
– Project management staff. ( Perform project management activities )
– Project staff (Creating the project deliverables)
– Supporting experts
– User or Customer Representatives.(Accept project‘s deliverables or products)
– Sellers.(Vendors, Suppliers or contractors)
– Business partners. (external companies Provide specialized expertise or fill a specified role )
– Business partner members.(Members of business partners’ organizations)
Composition of Project Teams. The composition of project teams varies based on factors such as
organizational culture, scope, and location.
– Examples of basic project team compositions
Dedicated. In a dedicated team, all or a majority of the project team members are assigned to work full-
time on the project.
Part-Time.
Project Life Cycle
Product, Projects & Phases
Project
Lifecycle
Project Life Cycle
Characteristics
Project Life Cycle
Characteristics
The life cycle provides the basic framework for managing the project,
regardless of the specific work involved
Project life cycles can range from Predictive (plan-driven) approaches to
adaptive (change-driven) approaches.
A project life cycle is the series of phases that a project passes through
from its initiation to its closure.
Project Life Cycle
Predictive
Project Life Cycle
Iterative and incremental
Project Life Cycle
Adaptive
Project Life Cycle
Phase-to-Phase Relationships
Phase
• A project phase is a collection of logically related activities in the project that
aimed to complete one or more deliverables.
• A project may be divided into any number of phases.
• The phase is closed with transfer(hand-off) the Work Product (deliverables of
phase) and approved it.
• The end of phase is called a stage gate, milestone, phase review, phase gate or
kill point.
Project Management Process
Groups
Project Management Process
Groups
The links among the processes in the
Project Management Process Groups are
often iterative in nature. For example, the
Planning Process Group provides the Executing Process
Group with a documented project management plan early
in the project and then updates the project management
plan if changes occur as the project progresses.
Project Information
Work performance
reports.
The physical or electronic
representation of work
performance information
Project Management
Processes PMBOK 5th edition
Initiating
Process Group
The key purposes of this Process Group is define a new project or a new phase of
an existing project by obtaining authorization to start the project or phase through
the following steps,
1. Select a project to be initiated (Outside Project Boundaries).
2. The initial scope is defined and initial financial resources are committed.
3. Internal and external stakeholders who will interact and influence the overall. outcome
of the project are identified.
6. When the project charter is approved, the project becomes officially authorized.
BCR < 1 means the revenues (benefits) are less than the
costs.
n = Number of Periods
Payback Period,
– Length of time it takes to recoup funds invested in the project.
– This method compares the initial investment to the cash inflows expected over
the life of the product, service or results
– Obviously with all other things being equal, shorter payback periods are
generally better for an organization.
Project Selection Methods
Comparative Approach
Opportunity Cost,
– The cost of selecting a project over another project. i.e. the lost
opportunity cost.
– Example
– Project A – NPV : $100,000
– Project B – NPV : $250,000
– Opportunity Cost of selecting Project B is $ 100,000
Project Selection Methods
Comparative Approach
(Example),
– Make one value in each column that shows the most
desirable value , given the information provided:
Project Selection Methods
Mathematical Approach
It provides a way to calculate the value of the projects
– Linear programming
For internal projects, the project initiator or sponsor provides SOW based on business needs,
product, or service requirements. For external projects, the SOW be received from the customer as
part of a bid document, (e.g., a request for proposal, request for information, or request for bid) or
as part of a contract.
Develop Project Charter: Inputs
2. Business Case
It used for decision making by managers or executives above the project level to
determine whether or not the project is worth the required investment.
The project manager is responsible for ensuring that the project effectively and
efficiently meets the goals of the organization and those requirements of a broad
set of stakeholders, as defined in the business case.
Periodic review of the business case by the sponsoring organization confirm that
the project is still aligned with the business case.
3. Agreements are used to define initial intentions for a project.
Agreements may take the form of contracts, memorandums of understanding
(MOUs), service level agreements (SLA), letter of agreements, letters of intent,
verbal agreements, email, or other written agreements.
4. Enterprise Environmental Factors (EEF).
5. Organizational Process Assets (OPA).
Develop Project Charter:
Tools & Techniques (T&T)
1. Expert Judgment, To assess the inputs used to develop the
project charter
2. Facilitation Techniques, Like Brainstorming, conflict resolution,
problem solving, and meeting management to used by facilitators to
help teams and individuals accomplish project activities.
General Notes:
1. A project manager is identified and assigned as early in the project as is
feasible, preferably while the project charter is being developed and always
prior to the start of planning.
2. The two techniques above have broad application within project
management processes.
Develop Project Charter: Outputs
Project Charter
It is the document issued by the project initiator or sponsor.
It formally authorizes the existence of a project.
It provides the project manager with the authority to apply
organizational resources to project activities.
Notes,
A project charter establish internal agreements within an
organization to assure proper delivery under the contract.
A project charter is not considered to be a contract, because there
is no consideration or money promised or exchanged in its
creation.
Develop Project Charter: Outputs
Project Charter documents the following project’s information ,
– Project purpose or justification(business needs),
– Measurable project objectives and related success criteria,
– High-level requirements,
– Assumptions and constraints,
– High-level project description and boundaries,
– High-level risks,
– Summary milestone schedule,
– Summary budget,
– Stakeholder list,
– Project approval requirements
(i.e., what constitutes project success, who decides the project is successful, and who signs off
on the project),
– Assigned project manager, responsibility, and authority level,
– Name and authority of the sponsor or other person(s) authorizing the project charter.
Initiating Process Group
& Stakeholder Management Knowledge Area
Project stakeholders are individuals, groups, or organizations who may affect,
be affected by, or perceive themselves to be affected by a decision, activity, or
outcome of a project.
Project Stakeholder Management includes the processes required to
1. Identify the people, groups, or organizations that could impact or be impacted by the
project,
2. Analyze stakeholder expectations and their impact on the project,
3. Develop appropriate management strategies for effectively engaging stakeholders in
project decisions and execution.
Initiating Process Group
Identify Stakeholders
Current situation
Project charter have been developed, the project aurhorized and the
project manager identfied.
Every project will have stakeholders who are impacted by or can impact
the project in a positive or negative way. While some stakeholders may
have a limited ability to influence the project, others may have
significant influence on the project and its expected outcomes.
The ability of the project manager to correctly identify and manage
these stakeholders in an appropriate manner can mean the difference
between success and failure.
General Notes:
1. Stakeholder satisfaction should be managed as a key project objective.
Identify Stakeholders
1. Stakeholder Register,
The stakeholder register should be consulted and updated on a regular basis, as
stakeholders may change—or new ones identified—throughout the life cycle of the project.
Project Management
Processes PMBOK 5th edition
Planning
Process Group
The objective of this Process Group is to describe the strategy and tactics as well as
the course of action or path to successfully complete the project or phase.
It set up the total scope of the effort, define and refine the objectives, and develop
the course of action required to attain those objectives.
Its outputs (The project management plan and project documents ) will explore all
aspects of the scope, time, cost, quality, communications, human resources,
risks, procurements, and stakeholder engagement.
Planning and documentation are an iterative and ongoing activities due to more
information or characteristics are gathered and understood(progressive
elaboration), also a significant changes occurring throughout the project life cycle
trigger a need to revisit one or more of the planning processes and possibly some
of the initiating processes.
When the Planning Process Group is well managed, it is much easier to get
stakeholder buy-in and engagement.
Planning Process Group
& Knowledge Areas
Develop Project Management Plan:
Data Flow Diagram
It’s the process of defining, preparing, and coordinating all subsidiary plans and
integrating them into a comprehensive project management plan.
2. Project Charter
It provides the high-level project description and product
characteristics from the project statement of work.
Expert Judgment
Knowledgeable and Experienced parties.
Meetings
Attendees at these meetings may include the project manager, the
project sponsor, selected project team members, selected
stakeholders, anyone with responsibility for any of the scope
management processes, and others as needed.
Plan Scope Management: Output
The Requirements
1. Or (stakeholder’s needs and expectations) must be quantifiable and documented
in enough detail to be measured once project execution begins
2. The requirements is foundation of the WBS.
3. Cost, schedule, quality planning, and sometimes procurement are all based
upon these requirements.
4. Can be grouped into classifications
1. Business requirements ( The Needs of the organization)
2. Stakeholder requirements (stakeholder’s needs and expectations)
3. Solution requirements (features, functions and characteristics of the product, service)
4. Transition requirements, describe temporary capabilities such as data conversion & training
needs
Collect Requirements Process
Data Flow Diagarm
Collect Requirements Process:
Inputs
4. Project Charter
Include The high-level description of the product, service, or result of the
project
5. Stakeholder Register
Collect Requirements Process:
Tools and Techniques (T&T)
Interviewing
Focus groups and facilitated workshops
Using group creativity and decision-making
techniques
Questionnaires and surveys
Observation
Prototyping
Benchmarking, or generating ideas by comparing specific
project practices or product characteristics to those of other projects or products
inside or outside the performing organization, can also be used to collect
requirements
Collect Requirements Process:
Tools and Techniques (T&T)
1. Interviews
Interviewing experienced project participants,stakeholders,
and subject
matter experts (one on one conversation) can aid in
identifying and determining the features and functions of the
desired project deliverables.
2. Focus groups
Bring together prequalified stakeholders and subject matter
experts to
learn about their expectations and attitudes about a
proposed product, service, or result. Usually conducted by
a trained moderator
Collect Requirements Process:
Tools and Techniques (T&T)
3. Facilitated Workshops
1. Project charter
2. Scope Management Plan
3. Requirements Document
4. Organizational Process Assets
– Procedures & Templates
– Historical Data
– Lessons learned from old Projects
Define Scope Process:
Tools and Techniques (T&T)
1. Expert Judgment
To analyze the information needed to develop the project scope
statement
2. Context Diagrams
Product analysis includes techniques such as product breakdown,
systems analysis, requirements analysis, systems engineering,
value engineering, and value analysis
3. Alternatives Generation
Identify different approaches to execute and perform the work of the
project using brainstorming, lateral thinking, analysis of
alternatives, etc
4. Facilitated Workshops
Define Scope Process: Outputs
1. Scope Statement
describes project’s deliverables and the
work required to create those deliverables.
It includes
Product scope description
Deliverables’ Acceptance Criteria
Project Deliverables
Project Exclusion
Project Assumptions and Constraints
Define Scope Process: Outputs
Define Scope Process: Outputs
Requirements Document
1. Decomposition
– Decomposition of the total work into work packages generally
involves the following activities:
Identifying and analyzing the deliverables and related work.
Structuring and organizing the WBS.
Decomposing the upper WBS levels into lower level detailed
components.
Developing and assigning identification codes to the WBS
components.
Verifying that the degree of decomposition of the work is
necessary and sufficient.
2. Expert Judgment
Create WBS Process: Outputs
1. Scope Baseline
– Project Scope Statement
– WBS
– WBS Dictionary
Planning
Process Group
Project Time Management includes the processes required to manage the timely
completion of the project and their associated tools and techniques. All this
information is documented in the schedule management plan.
The schedule management plan identifies a scheduling method, tool and sets the
format and establishes criteria for developing and controlling the project schedule.
Plan Schedule Management
Data Flow Diagram
2. Project Charter,
Defines the Summary Milestone Schedule
& project approval requirements
that will influence the management of
the project schedule.
1. Expert Judgment
Expert judgment can be obtained through individual consultations (one-on-one
meetings, interviews, etc.) or through a panel format (focus groups, surveys,
etc.).
2. Analytical Techniques
The Plan Schedule Management process may involve choosing strategic options
to estimate and schedule the project such as: scheduling methodology, tools and
techniques, estimating approaches, formats, and project management software.
So you use Analytical Techniques to take the decision.
3. Meetings
Project teams may hold planning meetings to develop the schedule management
plan. Participants at these meetings may include the project manager, the project
sponsor, selected project team members, selected stakeholders, anyone with
responsibility for schedule planning or execution, and others as needed.
Plan Schedule Management:
Outputs
1. Decomposition
Dividing and subdividing the project scope and project deliverables into smaller, more
manageable parts.
Each work package within the WBS is decomposed into the activities required to
produce the work package deliverables.
Involving team members in the decomposition can lead to better and more accurate
results.
The activity list, WBS, and WBS dictionary can be developed either sequentially or
concurrently, with the WBS and WBS dictionary as the basis for development of the
final activity list
2. Expert Judgment
Project team members or other experts, who are experienced and skilled in developing
detailed project scope statements, the WBS, and project schedules, can provide
expertise in defining activities.
Define Activities Process:
Outputs
1. Activity Attributes extend the description of the activity by identifying the multiple
components associated with each activity.
1. Milestone List,
1. A milestone is a significant point or event in a project.
2. Milestones are similar to regular schedule activities, with the same structure and attributes,
but they have zero duration because milestones represent a moment in time .
Sequence Activities Process:
Data Flow Diagram
- Mandatory dependencies can be external or internal dependencies, also discretionary dependencies can be
external or internal.
- Since discretionary dependencies are more arbitrary, they should be fully documented so the reasons for their
placement can be maintained and available during future revisions. When fast tracking techniques are employed,
these discretionary dependencies should be reviewed and considered for modification or removal
Sequence Activities Process:
Tools & Techniques (T&T)
3) Leads and Lags
A lead is the amount of time whereby a successor
activity can be advanced with respect to a
predecessor activity.
Ex, on a project to construct a new office building, the landscaping
(Task A)could be scheduled to start two weeks prior to the
scheduled punch list (Task B) completion. This would be shown
as a finish-to-start with a two-week lead . Lead is often
represented as a negative value for lag in scheduling software.
2. Project Documents Updates, include, but are not limited to Activity lists, Activity
attributes, Milestone list and Risk register.
Estimate Activity Resources:
Data Flow Diagram
1. Schedule Management Plan, It identifies the level of accuracy and the units of measure for the
resources to be estimated..
2. Activity List, It identifies the activities which will need resources.
3. Activity Attributes, It provide the primary data input for use in estimating those resources required
for each activity
4. Resource Calendars, It specify when and how long identified project resources (such as
human resources, equipment, and material) will be available during the project. This information may be
at the activity or project level and includes resource attributes.
5. Risk Register, It includes a risks those may impact resource selection & availability.
6. Activity Cost Estimates, The cost of resources may impact resource selection.
7. Enterprise Environmental Factors (EEF), resource location, availability & skills
8. Organizational Process Assets (OPA), Policies and procedures regarding staffing,
rental and purchase of supplies & equipment.
Estimate Activity Resources:
Tools & Techniques (T&T)
1. Bottom-Up Estimating, is a method of estimating project duration or cost by
aggregating the estimates of the lower-level components of the WBS.As following ,
1. When an activity cannot be estimated with a reasonable degree of confidence, the work
within the activity is decomposed into more detail.
2. The resource needs are estimated then aggregated into a total quantity for each of the
activity’s resources.
3. If there are dependencies between the activities that can affect the application and use of
resources, this pattern of resource usage is reflected and documented in the estimated
requirements of the activity
1. Project Scope Statement, The assumptions and constraints from the project scope statement
are considered when estimating the activity durations.
2. Risk Register, It includes a risks those may impact resource availability.
3. Schedule Management Plan,
4. Activity List, It identifies the activities which will need resources.
5. Activity Attributes, It provide the primary data input for use in estimating those resources
required for each activity.
6. Activity Resource Requirements,
7. Resource Breakdown Structure,
8. Resource Calendars, it influence the duration of schedule activities due to the availability of
specific resources, type of resources, and resources with specific attributes.
9. Enterprise Environmental Factors (EEF).
10. Organizational Process Assets (OPA).
Estimate Activity Durations:
Tools & Techniques (T&T)
1. Analogous Estimating, is a technique for estimating the duration or cost of
an activity or a project using historical data from a similar activity or project.
1. It uses parameters from a previous, similar project, such as duration, budget, size,
weight, and complexity, as the basis for estimating the same parameter or measure for
a future project.
2. It relies on the actual duration of previous similar projects.
3. It is uses when there is a limited amount of detailed information about the project.
4. It is less costly and less time consuming than other techniques, but it is also less
accurate.
5. It applied to a total project or to segments of a project and used in conjunction with
other estimating methods (It is a gross value estimating approach).
6. It is most reliable when the previous activities are similar in fact and not just in
appearance, the project team members preparing the estimates have the needed
expertise and take in consideration the differences in complexity of the projects.
Estimate Activity Durations:
Tools & Techniques (T&T)
2. Parametric Estimating, is an estimating technique in which an algorithm is
used to calculate cost or duration based on historical data and project parameters.
Note: As more precise information about the project becomes available, the contingency reserve may
be used, reduced, or eliminated.
Estimate Activity Durations:
Tools & Techniques (T&T)
4. Reserve Analysis, Estimates may also be produced for the amount of
management reserve of time for the project.
Management reserves,
- Not included in the schedule baseline, but it is part of the overall project duration
requirements.
- Depending on contract terms, use of management reserves may require a change to the
schedule baseline.
Estimate Activity Durations:
Tools & Techniques (T&T)
5. Group Decision-Making Techniques, Is a Team-based approaches, such as
brainstorming, the Delphi or nominal group techniques
1. It is useful for engaging team members to improve estimate accuracy and commitment to
the emerging estimates. By involving a structured group of people who are close to the
technical execution of work in the estimation process, additional information is gained and
more accurate estimates obtained.
When people are involved in the estimation process, their commitment towards
meeting the resulting estimates increases
6. Scheduling Tool, Automated scheduling tools contain the schedule model and expedite
the scheduling process by generating start and finish dates based on the inputs of activities,
network diagrams, resources and activity durations using schedule network analysis.
Develop Schedule:
Tools & Techniques (T&T)
7. Leads and Lags, Applied during network analysis to develop a viable schedule by adjusting the start time
of the successor activities. (Please refer to - Sequence Activities Process T&T)
Leads are used in limited circumstances to advance a successor activity with respect to the predecessor activity.
Lags are used in limited circumstances where processes require a set period of time to elapse between the
predecessors and successors without work or resource impact.
8. Schedule Compression techniques are used to shorten the schedule duration without
reducing the project scope, in order to meet schedule constraints, imposed dates, or other schedule objectives.
Schedule compression techniques include, but are not limited to:
3. Crashing. A technique used to shorten the schedule duration for the least incremental cost by adding
resources. Examples of crashing include approving overtime, bringing in additional resources, or
paying to expedite delivery to activities on the critical path. Crashing works only for activities on the
critical path where additional resources will shorten the activity’s duration. Crashing does not always
produce a viable alternative and may result in increased risk and/or cost.
4. Fast tracking. A schedule compression technique in which activities or phases normally done in
sequence are performed in parallel for at least a portion of their duration. An example is constructing
the foundation for a building before completing all of the architectural drawings. Fast tracking may
result in rework and increased risk. Fast tracking only works if activities can be overlapped to shorten
the project duration.
Develop Schedule:
Outputs
1. Schedule Baseline, An approved version of schedule, changed only through formal change
control, used as a basis for comparison to actual results, one of the project management plan.
2. Project Schedule, is an output of a schedule model that presents linked activities with planned
dates, durations, milestones, and resources.
1. Bar charts or Gantt charts
2. Milestone charts, identify the scheduled start or completion of major deliverables.
3. Project schedule network diagrams. These diagrams are commonly presented in the activity-on-node
diagram format
3. Schedule Data, is the collection of information for describing and controlling the schedule. It includes at least
the schedule milestones, schedule activities, activity attributes, and documentation of all identified assumptions and
constraints. Ex, Resource requirements by time period, Scheduling of contingency reserves or Alternative
schedules,
4. Project Calendars, identifies working days and shifts that are available for scheduled activities.
5. Project Management Plan Updates,
6. Project Documents Updates, Like, Activity resource requirements, Activity attributes, Calendars or
Risk register.
Develop Schedule:
Outputs
Planning Process Group
& Cost Management Knowledge Areas
- Project Cost Management includes the processes involved in planning, estimating, budgeting,
financing, funding, managing and controlling costs so that the project can be completed within the
approved budget.
- The ability to influence the cost is greatest at the early stages of the project.
- Different stakeholders will measure project costs in different ways and at different times. So
Project Cost Management should consider the stakeholder requirements for managing costs.
Plan Cost Management
Data Flow Diagram
Plan Cost Management:
Inputs
2. Project Charter, provides the summary budget from which the detailed project costs are
developed. Also defines the project approval requirements that will influence the management of the
project costs.
3. Meetings, Project teams may hold planning meetings to develop the cost management
plan. Attendees at these meetings may include the project manager, the project sponsor,
selected project team members, selected stakeholders, anyone with responsibility for project
costs, and others as needed.
Plan Cost Management:
Outputs
– Level of precision. The degree to which activity cost estimates will be rounded up or down (e.g.,
US$100.49 to US$100, or US$995.59 to US$1,000), based on the scope of the activities and
magnitude of the project.
– Reporting formats.
– Process descriptions.
Estimate Cost:
Data Flow Diagram Developing an approximation of
the monetary resources needed to
complete project activities based
on the information known at a
given point in time.
1. Cost Management Plan, It includes the method used and the level of accuracy required to estimate
activity cost.
2. Human Resource Management Plan, provides project staffing attributes, personnel rates, and
related rewards/recognition,
3. Scope Baseline,
1. Project scope statement, we can determine direct project costs and indirect costs through Product description,
acceptance criteria, key deliverables, project boundaries, assumptions, and constraints. One of the most common
constraints for many projects is a limited project budget. Examples of other constraints are required delivery dates,
available skilled resources, and organizational policies.
2. Work breakdown structure, ( The project deliverables )
3. WBS dictionary
4. Project Schedule
5. Risk Register, To consider cost of Risk Management activities and response costs.
6. Enterprise Environmental Factors (EEF)
7. Organizational Process Assets (OPA)
Estimate Cost:
Tools & Techniques (T&T)
1. Expert Judgment, uses historical information, to provide duration estimate information
or recommended maximum activity durations from prior similar projects. Also determine whether
to combine methods of estimating and how to reconcile differences between them
2. Analogous Estimating,
Estimate Cost:
Tools & Techniques (T&T)
3. Parametric Estimating,
Uses a statistical relationship between relevant historical data and other variables (e.g., square footage
in construction) to calculate a cost estimate for project work.
- It can produce higher levels of accuracy depending upon the sophistication and underlying data
built into the model.
- It applied to a total project or to segments of a project and used in conjunction with other
estimating methods (It is a gross value estimating approach).
Estimate Cost:
Tools & Techniques (T&T)
4. Bottom-Up Estimating, is a method of estimating a component of work.
Estimate Cost:
Tools & Techniques (T&T)
5. Three-Point Estimating
Estimate Cost:
Tools & Techniques (T&T)
6. Reserve Analysis,
Contingency reserve is the cost or time reserve that is used to manage identified risks or
“known-unknown” (known=identified, unknown=risks). Contingency reserve is not a random
reserve, it is an estimated reserve based on various risk management techniques, such as expected
monetary value and the decision tree method.
This reserve is controlled by the project manager. The project manager has full authority to use it
whenever any identified risk occurs. He can also delegate this authority to the risk owner who will
use this reserve at the time of risks occurring. The project manager can be updated on later stages.
Management reserves is the cost or time reserve that is used to manage the unidentified risks
or “unknown-unknown” (unknown=unidentified, unknown=risks). Management reserve is not an
estimated reserve; it is a random figure, which is defined according to the organization’s policy.
Management reserve is not controlled by the project manager; it is managed by someone outside
the project team, usually someone from management. Whenever any unidentified risk occurs, the
project manager has to get approval from management to use the management reserve.
Management reserve is used in emergencies. It is basically used to avoid a situation where you
need some urgent money and the organization says that they don’t have additional money
available for your project.
Estimate Cost:
Tools & Techniques (T&T)
1. Activity Cost Estimates, are quantitative assessments of the probable costs required to
complete project work.
2. Basis of Estimates, "how the cost estimate was derived." Documentation of, how it was
developed, all assumptions made, any known constraints, confidence level of the final estimate.
2. Reserve Analysis, Establish both the contingency reserves and the management reserves.
3. Expert Judgment ,
5. Funding Limit Reconciliation, The expenditure of funds should be reconciled with any
funding limits on the commitment of funds for the project.
Determine Budget:
Outputs
Planning
Process Group
The basic approach to project quality management as described in this section is intended to be
compatible with International Organization for Standardization (ISO) quality standards.
Planning Process Group
& Project Quality Management
Failure to meet the quality requirements can have serious, negative consequences for
any or all of the project’s stakeholders.
Ex. Meeting customer requirements by overworking the project team may result in decreased profits and
increased project risks, employee attrition, errors, or rework.
Meeting project schedule objectives by rushing planned quality inspections may result in undetected
errors, decreased profits, and increased post-implementation risks
Planning Process Group
& Project Quality Management
2. Stakeholder Register
3. Risk Register
4. Requirements Documentation
5. Enterprise Environmental Factors (EEF).
6. Organizational Process Assets (OPA).
Plan Quality Management:
Tools & Techniques (T&T)
1. Cost-Benefit Analysis, Compares the cost of the quality step to the expected
benefit (Less Rework, Higher Productivity, Lower Costs, Increased Stakeholder
Satisfaction, & Increased Profitability).
2.
Plan Quality Management:
Tools & Techniques (T&T)
1. Cause-and-effect diagrams
2. Flowcharts
3. Check-Sheets
4. Pareto diagrams
5. Histograms
6. Control charts
7. Scatter diagrams
The seven basic quality tools are used within the context of the PDCA Cycle to
solve quality-related problems.
Plan Quality Management - T&T
3 - Seven Basic Quality Tools - 7QC Tools
1. Cause-and-effect diagram - Fishbone or Ishikawa diagrams -
Check-Sheets are used to organize facts in a manner that will facilitate the effective collection of useful data about a potential
quality problem.
Check-Sheets are especially useful for gathering attributes data while performing inspections to identify defects.
Ex. Data about the frequencies or consequences of defects collected in check-sheets are often displayed using Pareto diagrams.
Plan Quality Management - T&T
3 - Seven Basic Quality Tools - 7QC Tools
4. Pareto Diagram - A special form of vertical bar chart used to identify the vital few
sources that are responsible for causing most of a problem’s effects.
Unlike the control chart, the histogram does not consider the influence of time
on the variation that exists within a distribution.
Plan Quality Management - T&T
3 - Seven Basic Quality Tools - 7QC Tools
6. Control Chart - A graphic display of process data over time and against established
control limits, which has a centerline that assists in detecting a trend of plotted values toward
either control limit.
- Control Limits. The area composed of three standard deviations on either side of the centerline or
mean of a normal distribution of data plotted, which reflects the expected variation in the data.
- Specification Limits. The area, on either side of the centerline, or mean, of data plotted that meets
the customer’s requirements for a product or service. This area may be greater than or less than the area
defined by the control limits.
Plan Quality Management - T&T
3 - Seven Basic Quality Tools - 7QC Tools
7. Scatter Diagram - Correlation Chart - displays the data set as a collection of points in
Cartesian coordinates; each of them is determined by the values of two variables
Scatter Diagrams are used for identifying potential linear and nonlinear relationships between variables and how a change in one
variable affects another.
Scatter Diagrams are used to depict the relationships of price and quality rating, and to show the absence or presence of correlation
between two variables and its degree. The correlation can be positive, negative, or null, its type can be easy defined with only a glance on
the position of points on the Scatter Chart.
Plan Quality Management:
Tools & Techniques (T&T)
7. Meetings - Project teams may hold planning meetings to develop the quality management plan.
Attendees at these meetings may include the project manager; the project sponsor; selected project
team members; selected stakeholders; anyone with responsibility for Project Quality Management
activities namely Plan Quality Management, Perform Quality Assurance, or Control Quality; and
others as needed.
Plan Quality Management:
Tools & Techniques (T&T)
8. Additional Quality Planning Tools
Brainstorming- is a group creativity
technique by which efforts are made to
Nominal group technique- This Force field analysis- These are find a conclusion for a specific problem by
technique is used to allow ideas to be gathering a list of ideas spontaneously
diagrams of the forces for and against
brainstormed in small groups and then contributed by its members. For more
reviewed by a larger group change. information refer to Identify Risks: Tools and
( Involving problem identification, solution . Techniques / Information Gathering Techniques
generation, and decision making.)
Quality management and control tools- Affinity diagrams, Process decision program charts (PDPC),
Interrelationship digraphs, Tree diagrams, Prioritization matrices, Activity network diagrams and Matrix diagrams, for more
information please refer to Perform Quality Assurance: Tools and Techniques)
Plan Quality Management:
Outputs
1. Quality Management Plan - Describes how the organization’s quality policies will
be implemented to meet the quality requirements set for the project.
The quality management plan should be reviewed early in the project to ensure that decisions are based
on accurate information & reductions in costs and in the frequency of schedule overruns that were caused
by rework.
2. Process Improvement Plan - Details the steps for analyzing project management
and product development processes to identify activities that enhance their value through taking in
consideration the following,
- Process boundaries. Describe the purpose of the process, the start and end of the process, its inputs and outputs,
the process owner, and the stakeholders of the process.
- Process configuration. Provides a graphic depiction of processes, with interfaces identified, used to facilitate
analysis.
- Process metrics. Along with control limits, allows analysis of process efficiency.
- Targets for improved performance. Guide the process improvement activities.
4. Quality Metrics - Specifically describes a project or product attribute and how the control
quality process will measure it.
- A measurement is an actual value.
- The tolerance defines the allowable variations to the metric. For example, if the quality objective
is to stay within the approved budget by ± 10%, the specific quality metric is used to measure the
cost of every deliverable and determine the percent variance from the approved budget for that
deliverable.
Quality metrics are used in the perform quality assurance and control quality processes which include,
on-time performance, cost control, defect frequency, failure rate, availability, reliability, and test coverage….
5. Quality Checklists - Checklist is a structured tool used to verify that a set of required steps
has been performed – Quality checklists should incorporate the acceptance criteria included in the
scope baseline.
Many organizations have standardized checklists also they available from professional associations or
commercial service providers.
Planning Process Group
& Project Human Resource Management
As a result of the interactions between Project Human Resource Management processes & the processes in other
Knowledge Areas the additional planning may be required throughout the project. For example:
– After initial team members create a work breakdown structure, additional team members may need to be added to
the team.
– As additional team members are added to the team, their experience levels, or lack thereof, could decrease or
increase project risk, creating the need for additional risk planning.
– When activity durations are estimated, budgeted, scoped, or planned prior to identifying all project team members
and their competency levels, the activity durations may change.
Managing and leading the project team includes, but is not limited to:
1. Influencing the project team. Factors that may impact the project team like team environment, geographical locations
of team members, communications among stakeholders, internal and external politics, cultural issues,…….
2. Professional and ethical behavior.
Planning Process Group
& Project Human Resource Management
Project Human Resource Management includes the processes that organize, manage, &
lead the project team.
The project team - A comprised of the people with assigned roles and responsibilities for completing
the project.
The project management team - A subset of the project team which responsible for the project
management and leadership activities such as initiating, planning, executing, monitoring, controlling, and
closing the various project phases. This group can also be referred to as the core, executive, or leadership
team.
The project sponsor - A person who works with the project management team, typically assisting
with matters such as project funding, clarifying scope, monitoring progress, and influencing stakeholders in
both the requesting and performing organization for the project benefit.
The project’s staff - Project team members - May have varied skill sets, may be assigned full or
part-time, and may be added or removed from the team as the project progresses.
Although specific roles and responsibilities for the project team members are assigned, Participation
of team members during planning adds their expertise to the process and strengthens their
commitment to the project.
Plan Human Resource Management
Data Flow Diagram
The process of identifying and
documenting Project roles,
responsibilities, required skills,
reporting relationships, and creating a
staffing management plan.
5. Meetings.
Plan Human Resource Management:
Outputs
1. Human Resource Management Plan - Provides guidance on how project human
resources should be defined, staffed, managed, and eventually released. includes, but is not limited to,
i. Roles and responsibilities,
- Role - A defined function to be performed by a project team member, such as testing, filing, inspecting,
or coding. Role clarity concerning authority, responsibilities, and boundaries should also be documented.
- Authority - The right to apply project resources, expend funds, make decisions, or give approvals,,,,
.Team members operate best when their individual levels of authority match their individual
responsibilities.
- Responsibility - The assigned duties and work that a project team member is expected to perform in
order to complete the project’s activities.
- Competency - The skill and capacity required to complete assigned activities within the project
constraints. If project team members do not possess required competencies, performance can be
jeopardized. When such mismatches are identified, proactive responses such as training, hiring, schedule
changes, or scope changes are initiated.
2. Resource calendars - Calendars that identify the working days and shifts on which each specific resource is
available.
3. Staff release plan - Determining the method and timing of releasing team members benefits both the project
and team members.
4. Recognition and rewards - Clear criteria for rewards, promote and reinforce desired behaviors.
5. Training needs - To obtain required competencies & certifications.
6. Compliance - Strategies for complying with human resource policies.
7. Safety - Policies and procedures that protect team members.
Planning Process Group
& Plan Communications Management
Includes the processes that are required to ensure timely and appropriate planning, collection,
creation, distribution, storage, retrieval, management, control, monitoring, and the ultimate
disposition of project information.
Effective communication creates a bridge between diverse stakeholders who may have different
cultural and organizational backgrounds, different levels of expertise, and different perspectives and
interests, which impact or have an influence upon the project execution or outcome.
Project managers spend most of their time communicating with team members and other project
stakeholders, whether they are internal (at all organizational levels) or external to the organization.
Planning Process Group
& Plan Communications Management
The process of developing an
appropriate approach and plan
for project communications based
on stakeholder’s information
needs and requirements, and
available organizational assets.
Effective communication means that the information is provided in the right format, at the right
time, to the right audience, and with the right impact.
Efficient communication means providing only the information that is needed.
Plan Communication Management :
Inputs
2. Communication Technology,
The methods used to transfer information among project stakeholders may vary significantly.
Factors that can affect the choice of communication technology include,
Urgency of the need for information.
Availability of technology.
Ease of Use .
Project environment .
Sensitivity and confidentiality of the information .
Plan Communication Management :
Tools & Techniques (T&T)
3.Communication Models,
Used to facilitate communications and the exchange of information . It vary
from project to project and also within different stages of the same project
Encode - Thoughts or ideas are translated (encoded) into language by the sender.
Decode - The message is translated by the receiver back into meaningful thoughts
or ideas.
5. Meetings - To determine the most appropriate way to update and communicate project
information
– Most project meetings are more formal with a prearranged time, place, and agenda. Typical meetings begin with
a defined list of issues to be discussed, which are circulated in advance with minutes and other information
documented specifically for the meeting. This information is then disseminated to other appropriate stakeholders
on an as-needed basis.
Plan Communication Management:
Outputs
Includes the processes necessary to purchase or acquire products, services, or results needed from
outside the project team. The organization can be either the buyer or seller of the products, services,
or results of a project.
Include the contract management and change control processes required to develop and administer
contracts or purchase orders issued by authorized project team members.
Include controlling any contract issued by an outside organization (the buyer) that is acquiring
deliverables from the project in the performing organization (the seller), and administering
contractual obligations placed on the project team by the contract.
Planning Process Group
& Project Procurement Management
In this contest we assume that the buyer of an item for the project is assigned to the project team and the seller is
organizationally external to the project team & a formal contractual relationship will be developed and exists
between the buyer and the seller.
Project Procurement Management is discussed within the perspective of the buyer-seller relationship.
Planning Process Group
& Project Procurement Management
This process,
• Determines whether to acquire
outside support, and if so, what
to acquire, how to acquire it,
how much is needed, and when
to acquire it.
• Evaluating potential sellers
• Evaluating the risks involved
with each make-or-buy analysis
• Reviewing the type of contract
planned to be used with respect
to avoiding or mitigating risks.
2. Expert Judgment,
- To assess the inputs to and outputs from this process.
- To develop or modify the criteria that will be used to evaluate seller proposals.
3. Market Research,
- To examination of industry and specific vendor capabilities.
4. Meetings, Research alone may not provide specific information to formulate a procurement strategy. By
collaborating / meeting with potential bidders, the organization purchasing the material or service may benefit
while the supplier can influence a mutually beneficial approach or product.
Plan Procurement Management:
Outputs
4. Procurement documents -
Used to solicit proposals from prospective sellers and facilitate easy evaluation of the responses. It include
a description of the desired form of the response, and should be consistent with the value of, and risks
associated with, the planned procurement.
- Types of procurement documents include,
RFI - Request For Information, IFB - Invitation For Bid, RFP - Request For Proposal ,
RFQ -Request For Quotation ,
Tender Notice, Invitation For Negotiation, and Invitation for seller’s initial response.
- Terms such as Bid, Tender, or Quotation are generally used when the seller selection decision
will be based on price, while a term such as Proposal is generally used when other
considerations, such as technical capability or technical approach are paramount.
5. Change Requests - A decision that involves procuring goods, services, or resources
typically requires a change request. Other decisions during procurement planning can also create the
need for additional change requests.
6. Project Documents Updates - Requirements documentation, Requirements traceability
matrix, and Risk register.
Plan Procurement Management:
Outputs
7. Source Selection Criteria - Such Criteria are developed and used to rate or score seller
proposals, and can be objective or subjective. It is often included as a part of the procurement
documents.
Some possible source selection criteria are,
Planning Process Group
& Plan Stakeholder Management
Identifies how the project will
affect stakeholders, which then
allows the project manager to
develop various ways to effectively
engage stakeholders in the project,
to manage their expectations, and
to ultimately achieving the project
objectives.
Stakeholder management
Is about creation and maintenance
of relationships between the
project team and stakeholders,
with the aim to satisfy their
respective needs and requirements
within project boundaries.
2. Stakeholder Register- Provides the information needed to plan appropriate ways to engage
project stakeholders.
2. Meetings,
To define the required engagement levels of all stakeholder.
3. Analytical Techniques,
Identify gaps between the current and desired stakeholder engagement levels. Then actions and
communications required to close these gaps can be identified by the project team using expert
judgment.
Plan Stakeholder Management :
Outputs
Planning
Process Group
Project Risk could exist at the moment a project is initiated. Moving forward on a
project without a proactive focus on risk management is likely to lead to more
problems arising from unmanaged threats.
Project Risk Management
Knowledge Area
Risk Management's General Concepts -
- Project risk is an uncertain event or condition that, if it occurs, has a positive or negative
effect on one or more project objectives such as scope, schedule, cost, & quality.
- A risk may have one or more causes and, if it occurs, it may have one or more impacts.
A cause may be a given or potential requirement, assumption, constraint, or condition
that creates the possibility of negative or positive outcomes.
- Overall project risk is more than the sum of the individual risks within a project, since
it includes all sources of project uncertainty. It represents the exposure of stakeholders
to the implications of variations in project outcome, both positive and negative.
- The objectives of project risk management are to increase the likelihood and impact
of positive events, and decrease the likelihood and impact of negative events in the
project.
Project Risk Management
Knowledge Area
Risk Management's General Concepts -
The Project risk has its origins in the uncertainty present in all projects,
- Known risks are those that have been identified and analyzed, making it possible to
plan responses for those risks.
- Risks & Contingency Reserve – Known Risks that cannot be managed proactively,
should be assigned a contingency reserve. [Known – Unknowns]
- Risks & Management Reserve - Unknown Risks cannot be managed proactively and
therefore may be assigned a management reserve. [Unknown – Unknowns]
The risk attitudes of both the organization & the stakeholders may be influenced by a number of factors,
which are broadly classified into three themes:
1. Risk Appetite - The degree of uncertainty an entity is willing to take on in anticipation of a
reward.
2. Risk Tolerance - The degree, amount, or volume of risk that an organization or individual will
withstand / hold out.
3. Risk Threshold - Which refers to measures along the level of uncertainty or the level of impact
at which a stakeholder may have a specific interest. Below that risk threshold, the organization
will accept the risk. Above that risk threshold, the organization will not tolerate the risk.
4. Risk Exposure is usually calculated by multiplying the probability of an incident occurring by its
impact or potential losses
The project may be accepted if the risks are within tolerances and are in balance with the rewards
that may be gained by taking the risks.
Plan Risk Management
Data Flow Diagram
2. Project Charter - Provide various inputs such as high-level risks, high-level project
descriptions, and high-level requirements.
3. Stakeholder Register - Contains all details related to the project’s stakeholders, provides
an overview of their roles.
4. Enterprise Environmental Factors - Include, but are not limited to, risk attitudes,
thresholds, and tolerances that describe the degree of risk that an organization will withstand.
1. Analytical Techniques - To understand and define the overall risk management context of the project.
– Risk management context is a combination of stakeholder risk attitudes and the strategic risk exposure of a
given project based on the overall project context. Ex. A stakeholder risk profile analysis may be performed
to grade and qualify the project stakeholder risk appetite and tolerance. Other techniques, such as the use of
strategic risk scoring sheets, are used to provide a high-level assessment of the risk exposure of the project
based on the overall project context.
– Depending on these assessments, the project team can allocate appropriate resources and focus on the risk
management activities.
2. Expert Judgment - To ensure a comprehensive establishment of the risk management plan. Ex.
Senior management, Project stakeholders, Subject matter experts (SMEs).
3. Meetings - Project teams hold planning meetings to develop the risk management plan.
– High-level plans for conducting the risk management activities are defined in these meetings.
– Risk management cost elements and schedule activities should be developed for inclusion in the project budget and
schedule, respectively.
– Risk contingency reserve application approaches may be established or reviewed.
– Risk management responsibilities should be assigned.
– General organizational templates for risk categories and definitions of terms such as levels of risk, probability by type
of risk, impact by type of objectives, and the probability and impact matrix will be tailored to the specific project.
– The outputs of these activities are summarized in the risk management plan.
Plan Risk Management
Outputs
1. Risk Management Plan - Describes how risk management activities will be structured
and performed. Includes,
– Methodology - Defines the approaches, tools, and data sources that will be used to perform
risk management on the project.
– Budgeting - Estimates funds needed, based on assigned resources, for inclusion in the cost
baseline and establishes protocols for application of contingency and management reserves.
– Timing - Defines when and how often the risk management processes will be performed
throughout the project life cycle, establishes protocols for application of schedule contingency
reserves, and establishes risk management activities for inclusion in the project schedule.
– Definitions of risk probability and impact - The quality and credibility of the risk
analysis requires that different levels of risk probability and impact be defined that are
specific to the project context.
– Probability and impact matrix - A probability and impact matrix is a grid for mapping
the probability of each risk occurrence and its impact on project objectives if that risk occurs.
– Reporting formats - Describes the content and format of the risk register as well as any
other risk reports required.
– Tracking - Tracking documents how risk activities will be recorded for the benefit of the
current project and how risk management processes will be audited.
Plan Risk Management
Outputs
Identify Risks
Data Flow Diagram
The process of
determining which risks
may affect the project
and documenting their
characteristics.
It provides the
knowledge and ability
for the project team to
anticipate the Risk's
events through
documentation.
Identify Risks
General Notes
- The process should involve the project team so they can develop and
maintain a sense of ownership and responsibility for the risks and associated
risk response actions.
- The risk statements format should be consistent to ensure that each risk is
understood clearly and unambiguously in order to support effective analysis
and response development.
Identify Risks
Inputs
1. Project Management Plan,
2. Risk Management Plan,
3. Cost Management Plan,
4. Schedule Management Plan,
5. Quality Management Plan,
6. Human Resource Management Plan,
7. Scope Baseline - Project assumptions are found in the project scope statement. The WBS is
a critical input to identifying risks as it facilitates an understanding of the potential risks at both the
micro and macro levels. Risks can be identified and subsequently tracked at summary, control
account, and/or work package levels.
8. Activity Cost Estimates - They provide a quantitative assessment of the likely cost to
complete scheduled activities and ideally are expressed as a range, with the width of the range
indicating the degree(s) of risk.
Identify Risks
Inputs
9. Activity Duration Estimates - Identifying risks related to the time allowances for the
activities or project as a whole.
10. Stakeholder Register - To ensure that key stakeholders, especially the stakeholder,
sponsor, and customer are interviewed or otherwise participate during the Identify Risks process.
11. Project Documents - Project charter, Project schedule, Schedule network diagrams, Issue
log, Quality checklist...
12. Procurement Documents - The complexity and the level of detail of the procurement
documents should be consistent with the value of, and risks associated with, planned procurement.
1. Risk Data Quality Assessment - Is a technique to evaluate the degree to which the
data about risks is useful for risk management.
2. Risk Categorization - Risks to the project can be categorized by,
1. Sources of risk (e.g., Using the RBS),
2. The area of the project affected (e.g., Using the WBS), or
3. Risks can also be Categorized by Common Root Causes.
4. Other useful categories (e.g., Project Phase) to determine the areas of the project most exposed to the effects
of uncertainty.
This technique helps determine work packages, activities, project phases or even roles in the project, which can lead
to the development of effective risk responses.
4. Expert Judgment.
Perform Qualitative Risk Analysis
Outputs
The Opportunities are expressed as positive values, while those of Threats are expressed as negative values.
EMV for a project is calculated by multiplying the value of each possible outcome by its probability of occurrence and adding the products together.
Perform Quantitative Risk Analysis
Tools & Techniques (T&T)
2. Quantitative Risk Analysis and Modeling Techniques -
III. Modeling and simulation - Uses a model that translates the specified detailed uncertainties of
the project into their potential impact on project objectives. Simulations are typically performed
using The Monte Carlo technique.
Perform Quantitative Risk Analysis
Tools & Techniques (T&T)
4. Expert Judgment - The ideally using experts with relevant, recent experience is required
to identify potential cost and schedule impacts, to evaluate probability, and to define inputs such as
probability distributions into the tools.
- Expert judgment also comes into play in the interpretation of the data and identify the
weaknesses of the tools as well as their strengths.
Perform Quantitative Risk Analysis
Outputs
1. Project Documents Updates - Are updated with,
I. Probabilistic analysis of the project
Estimates are made of potential project schedule and cost outcomes listing the possible
completion dates and costs with their associated confidence levels.
This output, often expressed as a cumulative frequency distribution, is used with
stakeholder risk tolerances to permit quantification of the cost and time contingency
reserves.
Such contingency reserves are needed to bring the risk of overrunning stated project
objectives to a level acceptable to the organization.
II. Probability of achieving cost and time objectives. Ex. The likelihood of achieving
the cost estimate of US$41 million is about 12%.
III. Prioritized list of quantified risks - This list includes those risks that pose the greatest
threat or present the greatest opportunity to the project.
Perform Quantitative Risk Analysis
Outputs
1. Project Documents Updates - Are updated with,
IV. Trends in quantitative risk analysis results -
- As the analysis is repeated, a trend may become apparent that leads to conclusions
affecting risk responses.
- Organizational historical information on project schedule, cost, quality, and performance
should reflect new insights gained through the Perform Quantitative Risk Analysis
process. Such history may take the form of a quantitative risk analysis report. This report
may be separate from, or linked to, the risk register.
Plan Risk Responses
Data Flow Diagram
The process of developing options and
actions to enhance opportunities & to
reduce threats to project objectives.
2. Enhance- The project team acts to increase the probability and/or the positive impacts of an
opportunity. Identifying and maximizing key drivers of these positive-impact risks may increase
the probability of their occurrence.
Examples of enhancing opportunities include adding more resources to an activity to finish early.
3. Share- The project team acts to allocating some or all of the ownership of the opportunity to a
third party who is best able to capture the opportunity for the benefit of the project.
Examples of sharing actions include forming risk-sharing partnerships, teams, special-purpose companies, or joint
ventures, which can be established with the express purpose of taking advantage of the opportunity so that all parties
gain from their actions.
3. Expert Judgment -
Plan Risk Responses
Tools & Techniques (T&T)
Specific actions are developed to implement the strategy, including primary and backup
strategies, as necessary.
Identify & Assign one person (an owner for risk response) to take responsibility for each
agreed-to and funded risk response.
A fallback plan can be developed for implementation if the selected strategy turns out not to
be fully effective or if an accepted risk occurs.
Secondary risks should also be reviewed. Secondary risks are risks that arise as a direct result
of implementing a risk response.
Plan Risk Responses
Tools & Techniques (T&T)
Executing
Process Group
This Process Group involves Coordinating People & Resources, Managing Stakeholder Expectations, as
well as Integrating & Performing the Project’s Activities accordance with the project management plan.
The results may require Planning Updates & Re-Baselining.
A large portion of the Project’s Budget will be expended in performing the processes of this Process Group.
Direct and Manage Project work:
Data Flow Diagram
- During project execution, The Work Performance Data is collected and appropriately actioned and
communicated. It includes information about the completion status of deliverables and other relevant details
about project performance. Which used as an input to the Monitoring and Controlling Process Group.
- All Project Changes & the Implementation of Approved Changes & its impacts
Require to be reviewed for taking the proper actions,
• Corrective action - An intentional activity that realigns the performance of the project work with the project
management plan.
• Preventive action - An intentional activity that ensures the future performance of the project work is aligned with
the project management plan.
• Defect repair - An intentional activity to modify a nonconforming product or product component.
• Updates - Changes to formally controlled project documents, plans, etc.,.
Direct and Manage Project work:
General Note:
1. Expert Judgment,
Used to assess the inputs needed to direct and manage execution of the project management plan.
3. Meetings,
– Meetings tend to be one of three types - Information exchange; Brainstorming, option evaluation, or design;
Decision making –
– Meetings should be prepared with a well-defined agenda, purpose, objective, and time frame and should be
appropriately documented with meeting minutes and action items.
– Meeting Minutes should be stored as defined in the project management plan.
– Meetings are most effective when all participants can be face-to-face in the same location.
– Virtual Meetings generally require additional preparation and organization to achieve the same effectiveness of a
face-to-face meeting.
Direct and Manage Project work:
Outputs
1. Deliverables,
3. Change Requests,
Include Corrective action, Preventive action, Defect repair & Updates.
II. Building a confidence that A Future Output or an Unfinished Output - Work in Progress - will be
completed in a manner that meets the specified requirements and expectations.
III. Providing an umbrella for Continuous Process Improvement for improving the quality of all
processes to Reduces Waste & Eliminates Activities that do Not Add Value which increase levels of
Efficiency & Effectiveness.
The Prevention & Inspection aspects of quality assurance should have a demonstrable influence on the
Project Management.
Quality Assurance work will fall under the Conformance Work Category in the Cost Of Quality framework.
Perform Quality Assurance:
Inputs
Quality audits may be Scheduled or Random, and may be conducted by Internal or External auditors.
3. Process Analysis – Follows the steps outlined in the process improvement plan to
identify needed improvements. It includes root cause analysis—a specific technique used to
identify a problem, discover the underlying causes that lead to it, and develop preventive actions.
Perform Quality Assurance:
Outputs
Consists of
Outlining & Guiding the
Team Selection &
Responsibility Assignment
to obtain a successful
team.
Acquire Project Team:
General Note:
The following factors should be Considered during the process of Acquiring The Project
Team & Planned for in The Planning Stages of the Project:
1. The Project Manager or Project Management Team should Effectively Negotiate & Influence
Others who are in a position To Provide the Required Human Resources for the project.
2. Failure to Acquire the Necessary Human Resources for the project may affect Project Schedules,
Budgets, Customer Satisfaction, Quality, & Risks. The project manager or project management team
will be required to reflect the impact of any unavailability of required human resources in the project
schedule , , , , , , & the other project management plans.
3. Insufficient Human Resources or Capabilities Decrease the Probability of Success and, in a worst
case scenario, Could Result in Project Cancellation.
4. If the Human Resources are Not Available due to constraints, such as economic factors or previous
assignments to other projects, the project manager or project team may be required to assign
alternative resources, perhaps with lower competencies, Provided there is No Violation of legal,
regulatory, mandatory, or other specific criteria.
Acquire Project Team:
Inputs
3. Organizational Process Assets - That influence the Acquire Project Team process.
Acquire Project Team:
Tools & Techniques (T&T)
2. Negotiation
Negotiate the Project Staff Assignments with Functional managers, Other project management
teams within the performing organization, External organizations, vendors, suppliers, contractors.
3. Acquisition When the performing organization is unable to provide the staff needed to
complete a project, the required services may be Acquired From Outside Sources.
Acquire Project Team:
Tools & Techniques (T&T)
4. Virtual Teams - A Groups of people with a shared goal who fulfill their roles with little or
no time spent meeting face to face.
5. Multi-Criteria Decision Analysis - A valuable tool that we can apply to many
complex decisions. It is most applicable to solving problems that are characterized as a choice
among alternatives.
– Examples of selection criteria that can be used to score team members:
Availability, Cost , Experience, , Knowledge, Skills.
Ability - The Team Member has the competencies needed by the project. -.
Attitude - The ability to work with others as a cohesive team -.
International factors - Consider team member location, time zone & communication capabilities.
Acquire Project Team:
Outputs
It results in
Improve Teamwork, Enhance
People Skills & Competencies,
Motivate Employees, Reduce
Staff Turnover Rates, &
Improve Overall Project
Performance.
Develop Project Team:
General Note:
1. Project Manager -
– Should Acquire Skills To Identify, Build, Maintain, Motivate, Lead, & Inspire Project Teams To
Achieve High Team Performance & Meet the Project’s Objectives.
– Should Continually Motivate Their Team By Providing Challenges & Opportunities, Providing
Timely Feedback & Support as needed, plus Recognizing & Rewarding Good Performance.
– Should Request Management Support and/or Influence the Appropriate Stakeholders To
Acquire the Resources needed to Develop Effective Project Teams.
– Responsible for Create an Environment that Facilitates Teamwork & Developing an Effective
Project Teams.
– Should Capitalize on Cultural Differences Creating a Dynamic, Cohesive, & Collaborative
Team Culture To Improve Individual & Team productivity, Team Spirit, & Cooperation Plus
Allow Cross Training & Mentoring Between Team Members to Share Knowledge & Expertise.
2. Project Communication -
High team performance can be achieved by using open and effective communication, creating
team building opportunities, developing trust among team members, managing conflicts in a
constructive manner, and encouraging collaborative problem solving and decision making.
Develop Project Team:
Inputs
2. Project Staff Assignments - Identify the people who are on the team / List of project
team members.
3. Resource Calendars - Identify times when the project team members can participate in
team development activities.
Develop Project Team:
Tools & Techniques (T&T)
4. Team-Building Activities
5. Colocation -Tight Matrix- Involves placing many or all of the most active project
team members in the same physical location to enhance their ability to perform as a team.
While colocation is considered a good strategy, the use of virtual teams can bring benefits such as the use of more skilled
resources, reduced costs, less travel, and relocation expenses and the proximity of team members to suppliers, customers, or
other key stakeholders.
Develop Project Team:
Tools & Techniques (T&T)
7. Personnel Assessment Tools - Give the project manager and the project team an
insight into areas of strength and weakness.
– Tools such as attitudinal surveys, specific assessments, structured interviews, ability tests, and
focus groups.
– These tools help project managers assess the team preferences, aspirations, behavior and attitude.
Develop Project Team:
Outputs
1. Observation and Conversation - Used to stay in touch with the work & attitudes of
project team members.
The project management team monitors progress toward project deliverables, accomplishments that are a
source of pride for team members, and interpersonal issues.
2. Project Performance Appraisals
– Objectives for conducting performance appraisals during the course of a project can include
clarification of roles and responsibilities, constructive feedback to team members, discovery of
unknown or unresolved issues, development of individual training plans, & the establishment of
specific goals for future time periods.
– The need for formal or informal project performance appraisals depends on the length of
the project, complexity of the project, organizational policy, labor contract requirements, and the
amount and quality of regular communication.
Manage Project Team:
Tools & Techniques (T&T)
3. Conflict Management.
Manage Project Team:
Tools & Techniques (T&T)
4. Interpersonal Skills.
The ability of Stakeholders to Influence the project is typically highest during the initial
stages and gets progressively lower as the project progresses.
- Managing Stakeholder Engagement helps to increase the probability of project success by ensuring
that stakeholders clearly understand the project goals, objectives, benefits, and risks. Which enables
stakeholder to be active supporters of the project and to help guide activities and project decisions.
- By Anticipating People’s Reactions to the project, proactive actions can be taken to win support or
minimize negative impacts and Decreases the risk of the project failing to meet its goals and
objectives.
- The project manager is responsible for Managing Stakeholder Engagement which involves
activities such as,
1. Engaging Stakeholders at appropriate project stages to obtain or confirm their continued commitment to the
success of the project,
2. Managing Stakeholder Expectations through negotiation and communication, Ensuring Project Goals are
Achieved,
3. Addressing Potential Concerns that have not yet become issues & Anticipating Future Problems that may be
raised by stakeholders,
4. Clarifying and Resolving Issues that have been identified.
Manage Stakeholder Engagement:
Inputs
3. Change Log - Used to document changes that occur during a project. These changes - & their
impact on the project in terms of time, cost, and risk - are communicated to the appropriate
stakeholders.
1. Issue Log - This log is updated as new issues are identified and current issues are resolved.
2. Change Requests - Managing stakeholder engagement may result in a change request
to the product or the project, corrective or preventive actions to the project itself or to the
interaction with the impacted stakeholders.
3. Project Management Plan Updates
Ex. Some communications may no longer be necessary, an ineffective communication method may
be replaced by another method, or a new communication requirement may be identified.
Ex. It may be determined that a stakeholder has additional informational needs.
4. Project Documents Updates
Ex. The stakeholder register.
5. Organizational Process Assets Updates -
Ex. Stakeholder notifications, Project reports, Project presentations, Project records, Feedback from
stakeholders, Lessons learned documentation.
Conduct Procurements:
Data Flow Diagram
It provides alignment of
internal and external
stakeholder expectations
through established
agreements.
Conduct Procurements:
General Note:
The effort of the buyer & seller in this process is to Collectively Prepare a
Procurement Statement of Work that will satisfy the requirements of the project.
The parties will then negotiate a final contract for award.
2. On major procurement items, the overall process of requesting responses from sellers
and evaluating those responses can be repeated.
4. A more detailed evaluation can then be conducted based on a more specific and
comprehensive requirements document requested from the sellers on the short list.
Conduct Procurements:
Inputs
4. Seller proposals - Prepared in response to a procurement document package. They form the
basic information that will be used by an evaluation body to select one or more successful bidders (sellers).
5. Project Documents - Ex. The risk-related contract decisions included within the risk register.
6. Make-or-Buy Decisions.
7. Procurement Statement of Work - It is a critical component of the procurement
process and can be modified as needed through this process until a final agreement is in place
(Specifications, Quantity desired, Quality levels…..). It Provides suppliers with a clearly stated set of
goals, requirements, and outcomes from which they can provide a quantifiable response.
8. Organizational Process Assets.
Conduct Procurements:
Tools & Techniques (T&T)
The Tools and Techniques described here may be used alone or in combination with select sellers.
1. Bidder Conferences - Contractor Conferences, Vendor Conferences, & Pre-Bid Conferences -
They are meetings between the buyer and all prospective sellers, Prior to submittal of a Bid or
Proposal, To Ensure That all prospective sellers have a clear and common understanding of the
procurement requirements, & that no bidders receive preferential treatment.
To be fair, buyers should take great care to ensure that all prospective sellers hear every question
from any individual prospective seller and every answer from the buyer. Responses to questions can
be incorporated into the procurement documents as amendments.
2. Proposal Evaluation Techniques - A formal evaluation review process will be
defined by the buyer’s procurement policies.
3. Independent Estimates - The procuring organization may elect to either prepare its
own independent estimate, or have an estimate of costs prepared by an outside professional
estimator, To Serve As a Benchmark on proposed responses.
Significant differences in cost estimates can be an indication that the procurement statement of
work was deficient, ambiguous, and/or that the prospective sellers either misunderstood or failed to
respond fully to the procurement statement of work.
Conduct Procurements:
Tools & Techniques (T&T)
4. Expert Judgment - The evaluation of proposals may be accomplished by a multi-
discipline review team with expertise in each of the areas covered by the procurement documents
and proposed contract. Such as contracting, legal, finance, accounting, engineering, design, research,
development, sales, and manufacturing.
5. Advertising - Placing advertisements for procurement to expand the lists of potential sellers
or because the government jurisdictions require public advertising.
6. Analytical Techniques - Help organizations identify the readiness of a vendor to
provide the desired end state, determine the cost expected to support budgeting, and avoid cost
overruns due to changes.
Ex. By Examining Past Performance Information, teams may Identify Areas that may have more
risk & that need to be monitored closely to ensure success of the project.
7. Procurement Negotiations - Help in Clarify the structure, Requirements, & other
terms of the purchases so that mutual agreement can be reached prior to signing the contract. The
Project Manager & other Project Management Team may not be the lead negotiator on procurements. They may
be present during negotiations to provide assistance & clarification.
For Complex Procurement Items, contract negotiation can be an independent process with inputs (e.g., issues or an open
items listing) and outputs (e.g., documented decisions) of its own. For Simple Procurement Items, the terms and
conditions of the contract can be previously set and nonnegotiable, and only need to be accepted by the seller.
Conduct Procurements:
Outputs
1. Selected Sellers - Those who have been judged to be in a competitive range based upon
the outcome of the proposal or bid evaluation, & who have negotiated a draft contract that will
become the actual contract when an award is made.
Final approval of all complex, high-value, high-risk procurements will generally require organizational
senior management approval prior to award.
2. Agreements - A Procurement Agreement includes terms and conditions, and may
incorporate other items that the buyer specifies regarding what the seller is to perform or provide.
Include, Statement of work or deliverables, Schedule baseline, Performance reporting, Period of
performance, Roles and responsibilities, Seller’s place of performance, Pricing, Payment terms, Place of
delivery, Inspection and acceptance criteria, Warranty, Product support, Limitation of liability, Fees and
retainer, Penalties, Incentives, Insurance and performance bonds, Subordinate subcontractor approvals,
Change request handling, & Termination clause and alternative dispute resolution (ADR) mechanisms.
The project management team is responsible for making sure that all agreements meet the
specific needs of the project while adhering to organizational procurement policies.
The ADR method can be decided in advance as a part of the procurement award.
Conduct Procurements:
Outputs
3. Resource Calendars - The quantity and availability of contracted resources and those
dates on which each specific resource or resource group can be active or idle are documented.
4. Change Requests.
5. Project Management Plan Updates - Any impacted baseline plans.
6. Project Documents Updates - Requirements documentation, Requirements
traceability documentation, Risk register, Stakeholder register
Project Management
Processes PMBOK 5th Edition
It allows stakeholders to
understand the Current State
of the Project, the Steps Taken,
& Budget, Schedule, & Scope
Forecasts.
Monitor & Control Project Work:
General Note:
Monitoring includes,
Collecting, Measuring, & Distributing Performance Information.
Assessing Measurements & trends to effect Process Improvements.
Control includes,
Determining Corrective or Preventive Actions or Re-planning.
Following up on Action Plans to determine whether the actions taken resolved the performance issue.
2. Schedule Forecasts - Derived from a schedule progress against a schedule baseline and computed time
estimate to complete (ETC). The forecast may be used to determine if the project is still within defined tolerance
ranges and identify any necessary change requests.
5. Work Performance Information is the work performance data collected from various
controlling processes then analyze it in context integrated based on relationships across areas for providing a
sound foundation for project decisions.
Data in itself cannot be used in the decision-making process as it has only Out-Of-Context Meaning.
Work performance information is circulated through Communication Processes.
A Change Control Board (CCB) is a formally chartered group Responsible For Reviewing, Evaluating,
Approving, Delaying, or Rejecting Changes to the Project, & For Recording & Communicating such
Decisions.
Approved Change Requests can require new or revised cost estimates, activity sequences, schedule
dates, resource requirements, and analysis of risk response alternatives.
Customer or Sponsor approval may be required for certain change requests after CCB approval, unless
they are part of the CCB.
As part of Change & Configuration Management Processes the Changes are documented and updated
within the project management plan.
Perform Integrated Change Control:
& Configuration Control
Configuration Control is focused on the specification of both the Deliverables & the Processes.
Change Control is focused on identifying, documenting, and approving or rejecting changes to the
project documents, deliverables, or baselines.
Following is some of the Configuration Management Activities included in the Perform Integrated
Change Control process:
- Configuration Identification - Identification & Selection of a Configuration item to provide the basis for which
The Product Configuration is Defined & Verified, Products & Documents are Labeled, Changes are managed, and
Accountability is Maintained.
- Configuration Status Accounting - Information is Recorded & Reported as to when appropriate data about the
configuration item should be provided. This information includes a Listing of Approved Configuration Identification,
Status of Proposed Changes to the Configuration, and the Implementation Status of Approved Changes.
- Configuration Verification & Audit - To make sure that the functional requirements defined in the
configuration documentation have been met, by ensure the composition of a project’s configuration items is correct &
that corresponding changes are registered, assessed, approved, tracked, & correctly implemented.
Perform Integrated Change Control:
Inputs
1. Project Management Plan - All Project Plans & Baselines.
Changes are documented and updated within the project management plan as part of the change &
configuration management processes.
Ex. Change management plan, which provides the direction for managing the change control process and documents the
formal change control board (CCB) . It’s an output of Develop Project Management Plan as part of Subsidiary plans.
2. Work Performance Reports - Work performance reports of particular interest to the Perform
Integrated Change Control process include Resource Availability, Schedule & Cost Data, Earned Value
Management (EVM) reports……
3. Change Requests - All of the Monitoring and Controlling processes and many of the Executing
processes produce change requests as an output.
The Corrective & Preventive Actions do not normally affect the project baselines—only the performance against
the baselines.
Cost of Implementing Changes in the project goes up as the project gets further along. Therefore, it is best to
prevent changes if possible, and if not possible, to make those changes as soon as possible in the project. If you
cannot avoid making a change, then you need to go through the process of analyzing what the impact on the project
will be.
1. Change Control Tools - Tools are used to manage the change requests & the resulting
decisions In order To Facilitate Configuration & Change Management.
Tool selection should be based on the needs of the project stakeholders including organizational and environmental
considerations and/or constraints.
Additional Considerations should be made for communication to assist the CCB members in their duties as well as
distribute the decisions to the appropriate stakeholders.
Perform Integrated Change Control:
Outputs
1. Approved Change Requests - are processed according to the Change Control
System by the project manager, CCB, or by an assigned team member.
Approved change requests will be implemented through the Direct & Manage Project Work process.
The disposition of all change requests, approved or not, will be updated in the change log as part of updates to the
project documents.
3. Project Management Plan Updates- Any subsidiary plans & Baselines that are
subject to the formal change control process.
Changes to baselines should only show the changes from the current time forward. Past performance may not be
changed. This protects the integrity of the baselines and the historical data of past performance.
A Deliverable is any Unique & Verifiable Product, Result, or Capability that results in a Validated
Deliverable Required by the Project.
The Validate Scope process differs from the Control Quality process in that,
Validate Scope is primarily concerned with Formal Acceptance of the Deliverables.
Quality Control is primarily concerned with Correctness of the Deliverables & Meeting the
Quality Requirements Specified For the Deliverables.
Control Quality is generally performed before Validate Scope, although the two processes may be
performed in parallel.
The relation between Validate Scope process & Control Quality process,
The verified deliverables obtained from the Control Quality process
are reviewed with the customer or sponsor to ensure that they are completed satisfactorily
&
have Received Formal Acceptance of the Deliverables - Validated Scope - by the customer or sponsor.
Validate Scope:
Inputs
1. Project Management Plan -
The scope management plan specifies how formal acceptance of the completed project deliverables will
be obtained.
The scope baseline includes the approved version of a scope statement, work breakdown structure (WBS),
and its associated WBS dictionary, that can be changed only through formal change control procedures and
is used as a basis for comparison Validate Scope.
2. Requirements Documentation - Lists all types of requirements for the project and
product, along with their acceptance criteria.
3. Requirements Traceability Matrix - Link requirements to their origin and tracks them
throughout the project life cycle.
4. Verified Deliverables - The project deliverables that are Completed & Checked for Correctness
through the Control Quality process.
2. Change Requests - The completed Deliverables that have not been formally accepted
are documented, along with the reasons for non-acceptance of those deliverables. Those
deliverables may require a change request for defect repair.
3. Work Performance Information - Includes information, such as which
deliverables have started, their progress, which deliverables have finished, or which have been
accepted.
4. Project Documents Updates - Ex. Any documents that define the product or report
status on product completion.
Control Scope:
Data Flow Diagram
Scope Creep is the Uncontrolled Expansion
To Product or Project Scope
Without Adjustments
To Time, Cost, & Resources is Referred.
2. Requirements Documentation -
Well-documented requirements make it easier to detect any deviation in the scope agreed for the
project or product.
Requirements should be Unambiguous [ Measurable & Testable ], Traceable, Complete, Consistent,
& Acceptable to key stakeholders.
4. Work Performance Data - Include, the number of change requests received, the number
of requests accepted or the number of deliverables completed.
Project performance measurements are used to Assess the Magnitude of Variation from
the Original Scope Baseline.
Control Scope:
Outputs
1. Work Performance Information - This information provides a foundation for
making scope decisions. Includes,
Correlated & Contextualized information on How the Project Scope is performing Compared To the
Scope Baseline. The Categories of the Changes Received, The Identified Scope Variances & Their
Causes, How They Impact Schedule or Cost, & The Forecast of the Future Scope Performance.
2. Change Requests - Analysis of scope performance can result in a change request to the
Scope Baseline or other Components of the Project Management plan.
3. Quality Checklists - A structured Lists that help to Verify That The Project’s Work & its Deliverables
Fulfill a Set of Requirements.
4. Work Performance Data - Ex. Planned vs. Actual Technical, Schedule, & Cost performance.
5. Approved Change Requests - To verify that the Approved Changes are implemented on time.
6. Deliverables -
7. Project Documents - Ex. Agreements, Quality Audit Reports & Change Logs supported with
corrective action plans, Process documentation.
8. Organizational Process Assets - Ex. Organization’s Quality Standards & Policies, Standard
work guidelines, Issue & defect reporting procedures and communication policies…….
Control Quality:
Tools & Techniques (T&T)
1. Seven Basic Quality Tools - Please refer to Planning Process Group – [ Plan Quality Management ]
Control Quality:
Tools & Techniques (T&T)
2. Statistical Sampling - Samples are Selected & Tested as defined in the quality management plan.
Please refer to Planning Process Group – [ Plan Quality Management ]
3. Verified Deliverables - are the results of performing the Control Quality process.
Verified Deliverables Are an Input To Validate Scope For Formalized Acceptance.
5. Change Requests -
6. Project Management Plan Updates -
7. Project Documents Updates - Ex. Quality standards, Agreements, Quality audit reports.
8. Organizational Process Assets Updates - Ex. Completed checklists & Lessons
learned documentation.
Project Management
Processes PMBOK 5th Edition
The Key Principle, The Schedule should be Controlled Proactively by The Project Manager by
Influencing Changes Before they Affect The Project.
Control Schedule:
Inputs
1. Project Management Plan -
The Schedule Management Plan describes how the schedule will be managed and controlled
The Schedule Baseline to compare with Actual Results & determine if a Change, Corrective or
Preventive action is necessary.
2. Project Schedule - The most recent version with notations to indicate Updates, Completed
Activities, & Started Activities.
3. Work Performance Data - Information about Project Progress such as which
activities have started, their progress (e.g., actual duration, remaining duration, and physical percent
complete), & which activities have finished.
4. Project Calendars - Schedule model may require more than one project calendar to allow
for different work periods for some activities to calculate the schedule forecasts.
5. Organizational Process Assets - Existing formal and informal schedule control-
related policies, procedures, and guidelines; Schedule control tools; Monitoring and reporting
methods to be used……
Control Schedule:
Tools & Techniques (T&T)
1. Performance Reviews - Measure, compare, and analyze schedule performance.
I. Trend Analysis - Please refer to Planning Process Group Part two - [ Control Project Work ].
II. Critical Path Method & Critical Chain Method - Please refer to Planning Process Group Part two - [ Develop
Schedule Process ].
3. Resource Optimization Techniques - Please refer to Planning Process Group Part two - [ Develop
Schedule Process ].
4. Modeling Techniques - Please refer to Planning Process Group Part two - [Develop Schedule Process ].
5. Leads and Lags - Please refer to Planning Process Group Part two - [ Sequence Activities Process ].
6. Schedule Compression - Please refer to Planning Process Group Part two - [Develop Schedule Process ].
7. Scheduling Tool - Please refer to Planning Process Group Part two - [ Develop Schedule Process ].
Control Schedule:
Outputs
1. Work Performance Information - The Calculated SV & SPI for WBS
components, in Particular the Work packages & Control accounts, are documented &
communicated to stakeholders.
2. Schedule Forecasts - Estimates or Predictions of Conditions & Events in The Project’s
Future Based On Information & Knowledge Available At the Time Of the Forecast.
– Forecasts are Updated & Reissued Based On Provided Work Performance Information During Project
Execution.
3. Change Requests - Schedule Variance Analysis may result in Change Requests to the
Schedule Baseline, Scope Baseline, and/or other components of the project management plan.
3. Work Performance Data - Which activities started & their progress, which deliverables
have finished and Costs that have been authorized & incurred…….
EVM Develops & Monitors Three Key Dimensions for each Work Package & Control Account:
Control Costs:
Tools & Techniques (T&T)
Monitor The Variances From The Approved Baseline,
1. Earned Value Management (EVM)
Control Costs:
Tools & Techniques (T&T)
Monitor The Variances From The Approved Baseline,
1. Earned Value Management (EVM)
Control Costs:
Tools & Techniques (T&T)
Monitor The Variances From The Approved Baseline,
1. Earned Value Management (EVM)
SPI can used in conjunction with CPI to Forecast The Final Project Completion Estimates.
The Performance on The Critical Path Needs To Be Analyzed to determine whether the project will
Finish Ahead Of or Behind its Planned Finish Date.
Control Costs:
Tools & Techniques (T&T)
2. Forecasting
Control Costs:
Tools & Techniques (T&T)
3. To-Complete Performance Index (TCPI) -
Measure of the Cost Performance that is Required To Be Achieved With The Remaining Resources.
It Expressed As The Ratio Of The Cost to finish the outstanding work to the Remaining Budget (A Specified Management Goal).
If The Cumulative CPI falls below the Baseline All the Project’s future work will need to be performed immediately in
the range of the TCPI (BAC) to stay within the Authorized BAC.
If BAC is no Longer Viable, The Project Manager should consider The Forecasted EAC.
Once approved, the EAC may replace the BAC in the TCPI calculation.
Control Costs:
Tools & Techniques (T&T)
4. Performance Reviews - Compare Cost Performance Over Time, Schedule Activities or
Work Packages Over-Running & Under-Running The Budget, and Estimated Funds Needed To
Complete Work In Progress.
II. Trend Analysis - Examines Project Performance over time to determine if performance is
improving or not. Graphical Analysis Techniques are valuable for understanding performance to date.
III. Earned value performance - Compares the Performance Measurement Baseline to Actual
Schedule & Cost Performance. If EVM is not being used, then the analysis of The Cost Baseline
against Actual Costs for the Work Performed is used for Cost Performance comparisons.
Control Costs:
Tools & Techniques (T&T)
5. Project Management Software - Often used to Monitor the Three EVM
Dimensions (PV, EV, AC), To Display graphical trends, & Forecast a range of possible final
project results.
6. Reserve Analysis -
Monitor the Status of Contingency & Management Reserves to determine if these reserves are
still needed or if additional reserves need to be requested.
As Work On The Project Progresses, These reserves may be used as planned to cover the cost of
risk mitigation events or other contingencies. Or, if the probable risk events do not occur, the
unused contingency reserves may be removed from the project budget to free up resources for other
projects or operations.
Control Costs:
Outputs
1. Work Performance Information - The Calculated CV, SV, CPI, SPI, TCPI, &
VAC values for WBS components, Work Packages & Control Accounts, are Documented &
Communicated to Stakeholders.
2. Cost Forecasts - A Calculated EAC value or A Bottom-Up EAC value is Documented &
Communicated to Stakeholders.
3. Change Requests - Analysis of project performance may result in a change request to the
Cost Baseline or other components of the project management plan.
It Ensures an Optimal
Information Flow Among All
Communication Participants,
At Any Moment in Time
Throughout The Entire project
Life Cycle.
Control Communications:
Inputs
1. Project Management Plan - Describes how Communications control will be performed
within the project.
Ex. Stakeholder communication requirements, Reason for the distribution of the information, Timeframe and
frequency for the distribution of required information, Individual or group responsible for communication of the
information, and Individual or group receiving the information.
3. Issue Log
4. Work Performance Data - Planned vs. Actual Technical Performance, Schedule
Performance, and Cost Performance.
5. Organizational Process Assets - Report templates, Specific communication
technologies available, Allowed communication media, Security requirements, Policies/standards
and procedures that define communications.
Control Communications:
Tools & Techniques (T&T)
1. Information Management Systems - Provides a set of standard tools for the project
manager to capture, store, and distribute information to stakeholders about the project’s costs, schedule progress,
and performance.
2. Expert Judgment
3. Meetings
Control Communications:
Outputs
1. Work Performance Information - Is the, Performance Data Collected from
various controlling processes, Analyzed in context, Integrated based on relationships across
areas & Circulated through communication processes.
2. Change Requests.
Control Procurements has a Financial Management Component That involves, monitoring payments
To the seller.
When Making Payments the suppliers have to insure that, Payment Terms defined within the contract are
met & Seller compensation is linked to Seller Progress, as defined in the contract. Also, there is a close
relationship of Payments Made to the Work Accomplished.
Control Procurements Capture the Necessary Details For Managing Any Early Terminations Of The
Contracted Work in Accordance With the Termination Clause of The Agreement. ( for Cause,
Convenience, or Default ). These Details are used in The close procurements process to terminate the
agreement.
Control Procurements:
Inputs
1. Project Management Plan - Explain how the procurement processes will be managed
from developing procurement documentation through contract closure.
4. Approved Change Requests - Modifications to the terms & conditions of the contract,
statement of work, pricing, descriptions of the products, services, or results…..
– All Procurement-Related Changes are formally documented in writing & approved before being
implemented through the Control Procurements process.
3. Inspections & Audits - Conducted during execution of the project to verify compliance
in the Seller’s work processes or deliverables. It’s Specified in the procurement contract
– It’s required by the buyer & supported by the seller.
2. Issue Log -
Updated with New Identified Issues & Current Resolved Issues.
4. Project Documents -
Project Schedule, Stakeholder Register, Issue Log, Change Log, & Project Communications.
Control Stakeholder Engagement:
Tools & Techniques (T&T)
Stakeholder Engagement Activities are included in the Stakeholder Management Plan & are
Executed During the Life Cycle of the Project.
Stakeholder engagement should be Continuously Controlled.
3. Meetings - Status Review Meetings are used to exchange and analyze information about
Stakeholder Engagement.
Control Stakeholder Engagement:
Outputs
1. Work Performance Information - This information is communicated to the
appropriate stakeholders to provides status and progress information on the project at the level of
detail required by the various stakeholders.
Data Per Se aren’t used in the Decision-Making Process, because the meaning may be misinterpreted.
Information, however, is Correlated, Contextualized & Provides a Sound Foundation For Project Decisions.
2. Change Requests.
3. Project Management Plan Updates.
4. Project Documents Updates - Stakeholder register, Issue log…..
5. Organizational Process Assets Updates - Stakeholder notifications, Project reports,
Project presentations, Project records, Feedback from stakeholders, Lessons learned documentation.
Control Risks
Data Flow Diagram
The process of Implementing
risk Response plans, Tracking
identified risks, Monitoring
Residual risks, Identifying
new risks, & Evaluating risk
process effectiveness
throughout the project.
3. Variance and Trend Analysis - For the purposes of controlling risks, trends in the
project’s execution should be reviewed using performance information. [ Earned value analysis and
other methods of project variance and trend analysis may be used. Deviation from the baseline plan
may indicate the potential impact of threats or opportunities ]
4. Reserve Analysis - Reserve analysis compares the amount of the contingency reserves
remaining to the amount of risk remaining at any time in the project in order to determine if the
remaining reserve is adequate.
Control Risks
Tools & Techniques (T&T)
5. Technical Performance Measurement -
– Technical performance measurement compares technical accomplishments during project
execution to the schedule of technical achievement.
– It requires the definition of objective, quantifiable measures of technical performance, which
can be used to compare actual results against targets.
6. Meetings -
– Project risk management should be an agenda item at periodic status meetings .
5. Organizational Process Assets Updates - Include the probability and impact matrix
and risk register, Risk breakdown structure, and Lessons learned from the project risk management activities.