Compress A Schedule Using Duration Types in Primavera P6
Compress A Schedule Using Duration Types in Primavera P6
I’ll ask “What are some actions project controllers can take to get
a project that is behind or falling behind back on track to finish
on time?”
And what’s the #1 answer I get?….it never fails.
It’s always the first answer I get. We are all somehow pre-
programmed to solve that problem by adding more labor or
other Resources to speed things up.
1 – The Setup
In this project, we’re going to focus on just a few activities, those
that have the Operator and Excavator assigned to them in the
Sub-Struct WBS element.
Now I’m free to visit each activity and to double the Budgeted
Units / Time. Here, my team is working 12 hrs/d. So to show that
we have twice as many resources, we double it to 24 hrs/d. The
Budgeted Units / Time field has always confused people who are
unfamiliar with it. I try to explain this as a “productive capability”
value. In a day (12 hour period) we are able to accomplish 24 hrs
of work. So, we should conclude that we have 2 Resources work
12 hrs/d for a total of 24 hrs/d of effort.
The process I’m focusing on here is really the proper use of the
Duration Types field to give you a recalculated Duration value to
shorten work periods. You could easily add some automation to
this process and do it on a bigger scale by using a Global
Change to: