Manual Generador 1
Manual Generador 1
TITANTM EC
OCTOBER 2008
iii
TABLE OF CONTENTS
INTRODUCTION
APPENDICIES:
1: DRAWINGS
GENERAL ARRANGEMENT
3: PRODUCT BROCHURES
iv
FOREWORD
Teledyne EC series generators produce hydrogen and oxygen gas through the
electrolysis of water. The end user normally requires high purity hydrogen for an
industrial process, or is compressing hydrogen for storage and/or transport.
Many users also require high purity oxygen, which is available on the EC-C
machines. If the machine is the standard EC model, the reader should disregard
discussion of “C” system components.
The EC generator system is built around the electrochemical cell stack (referred to
as the module), where mechanical, thermal, electrical and chemical actions are
occurring. The EC-750 generator platform (includes EC-500 and EC-600)
contains one module, while the EC-1000 generator contains two modules. The
purification of evolved gases occurs downstream of the module. These processes
involve supporting components that bring various technologies in to an integrated
automatically controlled system. This manual will provide an explanation of each
important machine function by describing the component(s) in terms of their
purpose and specifications, and by discussing how each is controlled and
monitored from a systems standpoint.
Machine operation is also fully covered – from initial preparation and checks
through startup, normal function, and normal or fault condition shutdown. This
manual also includes preventative maintenance procedures and the necessary
information to identify and correct problems. A component listing is provided to
help identify and request information on replacement parts. All process
components are marked with the numbers shown on diagrams and referred to in
the text of this manual.
v
Manual Organization
This manual is divided into sections as follows. The sections are intended to be
essentially independent as regards the activities described. Sections 1 and 2 may
be useful to customers considering an EC generator and/or for planning and early
training. Sections 3 through 6 are normally not available prior to receipt of a
purchase order for an EC:
The generator components are located within one of two structures. The term
"gas cabinet" will be used to describe the steel frame supporting the main EC
components including the electrolysis modules, fluid and gas piping and vessels,
purification and pressure controls and an electrical enclosure which contains the
programmable logic controller (PLC) and other electrical components. FIGURE
1.1 shows the EC "gas cabinet."
The term "power supply" will be used to describe the rectifier, main 3-phase
transformer, auxiliary single phase transformers and rectifier controls, all of which
vi
are enclosed in a single cabinet normally in a different room or location from the
"gas cabinet." FIGURE 1-2 shows the power supply.
The term "feedwater" is used for purified water consumed by the EC in the
electrolysis process.
The diagrams and number references herein pertain to components located in the
gas cabinet. The power supply is manufactured separately and therefore has its
own manufacturer's manual and diagram. Connections between the power supply
and the gas cabinet are shown on the EC electrical diagram, however.
Capital letters A through N (except the letter I) are used to denote the piping
connection points on the EC gas cabinet.
Refer to the P&ID for numbering and the key to symbols used.
Abbreviations
vii
H2 Hydrogen gas
KOH Potassium hydroxide - unless otherwise stated, it refers to a solution of 25%
in water at 20°C.
LPM Liters per minute
MCM Millions of circular mils (refers to metric wire sizes)
NM3 Normal cubic meters
O2 Oxygen gas
P&ID Piping and Instrumentation Diagram
PID Proportion, Integral, Derivative (used in controls)
PLC Programmable Logic Controller
PPM Parts per million
SCF Standard cubic feet
SCFH Standard cubic feet per hour
SCFM Standard cubic feet per minute
SLM Standard liters per minute (gas flow rate)
Abbreviations (Continued)
Units
Units will be stated in standard and metric terms. If a size is given only in standard
form, it indicates an actual specification such as a pipe diameter or thread size.
Swagelok style connections are used in many places to connect small diameter
process tubing. Swagelok is a trademark of the Swagelok Co., Solon, OH, USA.
CPV style connections are used for process pipe and tube connections. CPV is a
trade name of CPV Manufacturing, Inc., Philadelphia, PA., USA.
viii
NOTICE
The manual contains Teledyne Energy Systems Inc. proprietary information which
may not be used for the benefit of others except by express permission.
Distribution and availability of this manual should be restricted to activities
concerned with operation and maintenance of the equipment described herein.
LIMITED WARRANTY
To avoid unnecessary charges and delays in U. S. Customs, any and all returned
components of the Teledyne Energy Systems Inc. equipment should be handled as
follows:
2. Supply Teledyne Energy Systems Inc. with Proforma Invoices and copies of
Bills of Lading indicating the part as "Returned U. S. Goods."
ix
SECTION 1 System Description
Table of Contents:
1-1
FIGURE 1 Gas Cabinet................................................................................................ 1-4
FIGURE 2 Power Supply.............................................................................................1-5
FIGURE 3 Simple Electrochemical Cell ....................................................................... 1-7
FIGURE 4 Electrolysis Module Schematic ................................................................. 1-10
FIGURE 5 Diagram of Electrolyte Loop Components ................................................ 1-12
FIGURE 6 Cooling Water Diagram............................................................................. 1-15
FIGURE 7 Gas Purification ........................................................................................ 1-16
FIGURE 8 Catalyst Portion of Purifier ("C" Model Only)............................................. 1-19
FIGURE 9 Liquid Level Control .................................................................................. 1-20
FIGURE 10 Inert Gas Supply System ........................................................................ 1-22
FIGURE 11 Instrument Air Supply.............................................................................. 1-23
FIGURE 12 System Pressure Control ........................................................................ 1-28
FIGURE 13 Cooling Water Flow Control .................................................................... 1-28
FIGURE 14 Delta Pressure Control -Oxygen Venting................................................ 1-30
FIGURE 15 Delta Pressure Control - Hydrogen Venting ............................................ 1-31
FIGURE 16 PLC Actions ............................................................................................ 1-33
FIGURE 17 Typical Tube Connections ...................................................................... 1-39
1-2
1.1 Configuration
The EC generator system consists of two primary assemblies, the gas cabinet
and the electrical power supply, as well as the electrical cables which
interconnect these units.
FIGURE 1 shows the gas cabinet, a steel frame to which the mechanical fluid
and gas components are mounted. The electrolysis cell stack (referred to as the
module) is supported on base rails at the center of the gas cabinet. The EC-750
generator platform (includes EC-500 and EC-600) contains one module, while
the EC-1000 generator contains two modules. The electrolyte liquid pumping,
cooling, and filtration components are mounted to the gas cabinet base and
connected with 1.5 inch piping.
Components supported on the gas cabinet roof and vertical stanchions are for
gas purification and system controls. These include condensers and liquid traps,
filters, adsorption gas dryers, pressure controls, pneumatic controls, and
feedwater and inert gas supply system components.
The system control touch screen, programmable logic controller (PLC) and
several electrical devices are mounted and pre-wired inside an electrical
enclosure located on the vertical stanchion (back wall) of the gas cabinet.
All components other than the electrolysis module are pre-piped and wired at the
factory. Gas and pure water piping terminations are located at the upper corners
of the gas cabinet at the back wall. The cooling water interface connections are
located at the base corners, below the gas connections. The end-user electrical
interface, a 3-phase AC connection, is inside the power supply enclosure.
Electrical connections required by the end-user such as remote enable or alarm
signals, would be made inside the electrical enclosure located on the gas
cabinet.
1-3
FIGURE 1 Gas Cabinet
1-4
FIGURE 2 Power Supply
Three auxiliary single-phase transformers are also located in the main power
supply enclosure. The rectifier control and isolation boards are mounted in the
side control enclosure. The rectifier instruments and indicating lights are found on
the front of the control enclosure.
1-5
1.1.3 UPS
The auxiliary power and control cables between the gas cabinet and the power
supply are pre-connected on the gas cabinet side. For shipment to the site, the
cables are rolled and stowed in the gas cabinet. The individual cables are
grouped and tied in harnesses according to voltage, so that the end-user can
separate voltages at installation. Figure 2-7 (in Section 2, page 2-21 of this
manual) is a representation of the cable harness configurations providing sizes
and voltages, which can be used for planning cable tray or conduit runs.
The cables that carry the DC current from the rectifier to the electrolysis module
are USA AWG size 4/0 (approximately 1 inch (25 mm) in outside diameter). Six
(6) cables are used on the positive side, and six are used on the negative side of
each module (twelve cables each side for EC 1000 systems). There is also one
(1) 4/0 structural ground cable installed between the gas cabinet structure and
the power supply structure. All of the 4/0 cable is spooled for shipment to the site
with the main EC components.
1-6
Refer to FIGURE 3. The cell halves are divided by a wetted membrane that
permits electrical current flow (via the electrolyte) but prevents the transfer of
evolved gases from one side to the other. When a DC voltage is applied, current
flows through the liquid in contact with the electrodes and the gases evolve.
1-7
At the anode, the reaction is:
To make the process practical, other cell components are required. Adjacent to
each electrode is a metal flow element, which acts as a conductor and provides
volume for liquid and gas flow. A cell must be adequately supported and sealed,
which is accomplished with Polysulfone frames and Teflon gaskets. Means to
introduce liquid to the cell and to carry away evolved gases and waste heat are
provided within the Polysulfone cell frames, which contain cell ports and liquid
and gas manifolds.
The Teledyne electrolysis module is a stack of individual cells through which the
electrical current flows in series, and the liquid electrolyte flows in parallel liquid
paths to each cell. FIGURE 4 shows a schematic of the basic fluid and electric
current paths. Each cell is separated from the next with a bi-polar sheet metal
disc, which isolates the liquid path and provides electrical continuity to the next
cell. The Polysulfone cell frames surround the internal components and are
stacked with interleaved Teflon gaskets to complete the process containment.
The stack components are maintained under a compressive load to assure good
electrical continuity and to achieve the desired sealing. This is accomplished
with 2.5-inch (63.5-mm) thick stainless steel endplates at each end, and 14
insulated steel tie rods.
1-8
The electrical current flow through each module is in series and is the same in all
cells. The current determines the amount of gas produced in each cell, and the
total number of cells determines the module's production rate. EC module
current, regardless of module size is between 100 and 1000 DC amperes,
depending on the user's demand.
The voltage required to flow current through one cell is, depending on operating
conditions, between 1.8 and 2.4 DC volts. Hence, the DC voltage applied to the
endplates of the module is equal to the product of the number of cells and the
individual cell voltage. Refer to section 1.4 for EC module voltage ranges versus
module size.
1-9
FIGURE 4 Electrolysis Module Schematic
1-10
Once the module size is established based on the capacity of the end-user, the
voltage and current ranges are known and the power supply is specified
accordingly.
The electrolysis process also involves the need for several instruments and
controls to properly start, run, monitor, and stop the process. These will be
described in more detail in section 1.3.
1.3.1 Diagrams
There are separate electrolyte pumping loops on the hydrogen and oxygen sides
of the system. Refer to FIGURE 5. Each loop consists of a phase separator
(which serves as a reservoir), a centrifugal pump, a heat exchanger, filter and flow
switch. Downstream of the flow switch, the electrolyte enters the respective side of
the electrolysis module. A mixture of liquid and hydrogen (or oxygen) gas flows
back to the phase separator through the module outlet pipe.
1-11
FIGURE 5 Diagram of Electrolyte Loop Components
G AS TO TRA P
AND
PU RIFICA TION
PHASE
SE PA RA TOR
FLOW
FILTER SW IT C H
HEA T
EXC HANG ER
(SH ELL SIDE)
CENTR IFUG AL
PUMP
All of the electrolyte loop components are supported on the floor of the EC gas
cabinet.
The electrolyte containment materials including vessels, pipe, and fittings are
fabricated from low carbon series 316L stainless steel. Connections are seal
welded accept where access may be required. Access connection fittings are
CPV style O-ring connections. O-ring material is EPT rubber, which is
compatible with the various process fluids.
The pump motor is a 3-phase, 1.0 HP (0.69 KW) motor which operates at the
facility input voltage to the EC's power supply. The motor is a non-sparking
design, totally enclosed fan cooled (TEFC). Motor starters with overload protection
modules are located in the power supply. The motor starters receive a control
voltage signal from the PLC when conditions are acceptable for pump starting.
There are two cooling water systems. Refer to FIGURE 6. The main cooling
water system consists of an inlet strainer (601), a cooling water flow control valve
(609), two heat exchangers (103, 203), and manual valve 603. On "C" model
generators, there is also a gas cooler (428) in the oxygen purification system. The
condenser cooling water system consists of two flat-plate type condensers (301,
401) with manual control valves (605 and 606) and a flat-plate condenser (385)
and manual control valve (611) down stream of the catalyst tank (381). An
additional flat-plate condenser (485) and control valve (610) are used on “C” model
generators.
All wetted process portions of the main cooling system except the strainer body
are constructed of stainless steel. The condenser cooling water lines are
connected in parallel, with stainless steel tubing and Swagelok style fittings. The
KOH heat exchangers are connected in parallel on the water side with 1.0 inch (25
mm) diameter stainless tubing and CPV style fittings.
Refer to section 1.3.2.2 for more information on the KOH heat exchanger. Refer
to section 1.3.4 for discussion of condensers and 1.3.6 for discussion of the gas
cooler.
1-14
FIGURE 6 Cooling Water Diagram
Refer to FIGURE 7. On both standard and "C" system generators, water vapor is
condensed for separation from hydrogen and oxygen, and returned to the
electrolyte system. Gas exiting the phase separator (101 or 201) enters every
other plate of heat exchanger (301, 401), where the temperature is lowered
resulting in condensation of water vapor. The gas exiting the condenser next
enters a trap where moisture is collected and returned by gravity to the phase
separator.
Cooling water flows through the gas condenser in the other plates. Lower cooling
water temperatures improve the condensation process and help to minimize the
moisture load on downstream filters and dryers. A chiller is recommended for high
purity requirements in warmer climates. The operator with manual valves 605 and
606 sets the cooling water flow rates in this part of the system. As an example, if
the cooling water temperature is in the range of 15° to 20° C, the flow through
each condenser would be approximately 1-2 GPM (4-7.5 LPM). Normal variations
in site conditions do not require frequent or significant changes in this flow.
1-15
FIGURE 7 Gas Purification
Coalescing Filters
Again referring to FIGURE 7, from the moisture trap (302), hydrogen flows to a
coalescing filters (380 and then 371) and trap assembly (372, 373 and 374). Each
coalescing filter consists of a stainless steel housing and a layered gas filter
cartridge. As the gas passes from the inside of the cartridge to the outside, vapor
carried by the gas coalesces to form water droplets on the outside of the cartridge.
The droplets then gravity drain to trap 373.
Valve 372, located between the coalescing filter drains and trap 373, is normally
open. Valve 374, which is connected to the gas vent system, is normally closed.
Every 15 minutes, valves 372 and 374 change status for 5 seconds. Valve 372
isolates the process while the pressure in trap 373 causes the small amount of
water in the trap to exit via the vent system.
For a “C” model generator, the configuration is very similar but with each
coalescing filter (480 and then 471) having its own trap assembly (482,483,484
and 472, 473 respectfully). The pressure in traps 483 and 473 causes the small
amount of water in the traps to exit via the oxygen vent system.
1-16
Catalyst Tank and Flat-Plate Condenser
After the first coalescing filter (380) the hydrogen gas flows through a vessel filled
with de-oxo catalyst, which removes any coarse amount of oxygen from the gas
stream. The catalyst in this tank (381) combines H2 and O2 and makes water in
an exothermic reaction. Flat-plate heat exchanger 385 cools the gas and
condenses any water prior to the second coalescing filter (371).
For a “C” model generator, this arrangement is very similar, but the catalyst in the
oxygen side tank must be heated. Thermocouples 486 and 487 measure the
internal temperatures for control and operation.
For the dryers to function effectively, moisture retained by the molecular sieves
must periodically be removed. This is accomplished by taking the dryer out of
service every 6 hours, and completing an automatic regenerating process. Refer
to applicable P&ID as the following details are provided. Part of the regeneration
process involves a continuous slow purge of pure hydrogen from the on-line dryer,
through the off-dryer, and out through valves 313 and 370 to the vent system. This
purge flow crosses through orifice 304. The flow between dryer sets through 304
is constant (it reverses direction every 6 hours).
In the first hour of regeneration, heating elements inside the off-dryer tubes are
energized. This causes the sieves to expand and release trapped water vapor.
Next, the heaters are turned off and a valve (335) connected to the on-line dryer
opens for 60 minutes. This parallel path via orifice 334 increases hydrogen purge
flow and cools the dryers. After 60 minutes, valve 335 closes and, for the
remainder of the off-time, the slow purge continues. After 5.5 hours off-line
(approximately 30 minutes before switching), valve 370 closes, and valve 335
opens again. The increased flow from the on-line dryer is used to pressurize the
off-dryer in preparation for being switched back on-line. When the off-line dryer
pressure, as measured by pressure transmitter (378) is sufficient, the dryers
switch.
Three (3) minutes after a dryer switch, valve 370 is opened, causing the off-line
dryer to depressurize in preparation for the regeneration cycle.
1-17
The above process involves the use of several pneumatic devices that are
controlled by the PLC. Pneumatic control valves are grouped in a modular
assembly with a common air pressure supply and vent port. These are located on
the back wall of the EC. A typical PLC dryer system output sends a 24 VDC signal
to a pneumatic valve. The pneumatic valve directs instrument air pressure to the
operator of a controlled valve, or vents instrument air pressure, to cause a change
in valve position. As can be seen on the P&ID, dryer switching valve 313, vent
valve 370 and bypass valve 335 are all controlled in this manner.
Refer to FIGURE 8. A coalescing filter (471), trap (473) and trap purge valve
arrangement (472, 474) all the same as that of the hydrogen side, are used. The
dryer selection valve (413) is identical to that of the hydrogen side. Oxygen dryer
regeneration occurs on the same cycle, with the same PLC outputs and pneumatic
controls as those described in 1.3.5. For control of the oxygen dryer system
valves (406, 407, 413, 435, 470) a parallel tube is connected to the pneumatic
control outputs for the hydrogen side.
The oxygen dryer vessels are the same as those of the hydrogen side except that
the dryers contain only molecular sieves; there is no layering with a catalyst. In
order to remove trace amounts of hydrogen from the oxygen stream, a heated
catalyst is necessary. The catalyst vessel (412) is aligned with control valves 406
and 407 between dryer tubes 414-A and 414-B or between 415-A and 415-B.
Oxygen enters the first on-line dryer vessel from the coalescing filter (471) for initial
moisture removal. Next, the gas flows through the heated catalyst (412) to cause
recombination of trace hydrogen with oxygen to form water. The hot gas is then
1-18
cooled in heat exchanger 428 and flows to the second on-line dryer vessel for final
moisture removal. Moisture removal is such that a dew point of less than -60 C is
maintained.
The heated catalyst assembly consists of a 3.5-inch (89 mm) diameter vessel with
(4) 750-watt external band heaters. The vessel is mounted in a sheet metal
housing and surrounded with thermal insulation. A thermocouple (418) is installed
in the catalyst and the signal is supplied to the PLC located inside the EC control
enclosure. The controller is set to maintain a temperature of 275 C. The controller
output is an ON/OFF signal to relay 902 supplying power to the four band heaters.
To accomplish the switching of the oxygen flow path through the catalyst, two
additional 4-way valves are used (406 and 407). These valves are physically
identical to valves 313 and 413, and are activated with the same pneumatic air
signal.
Refer to Figure 1-9. To provide high purity water to the system, a displacement
rotary vane pump (701) is used. The pump is a low-volume, high-pressure pump
with a nearly constant flow characteristic. The capacity is 25 GPH (1.6 LPM). The
pump is located on the back wall structure below the electrical enclosure. The
pump motor is a 3-phase, 0.33 HP (0.25 KW) motor which operates at the facility
1-19
input voltage to the EC's power supply. The motor is a non-sparking design, totally
enclosed fan cooled (TEFC). The motor starter and overload module is located in
the power supply.
As the generator consumes water, the liquid level in the phase separators as
1
monitored on transmitter 113, will fall. When it reaches 52% , the PLC will
energize the motor starter and open solenoid valve (702). The pump will operate
until the liquid level reaches 62%. Check valves 703 and 707 are located in the
line leading from the pump to the hydrogen phase separator. These valves, along
with solenoid valve 702, assure that hydrogen gas will not flow in to the feedwater
system. A malfunction resulting in low liquid level (20%) or high liquid level (85%)
will cause the PLC to stop the pump and the electrolysis process.
When the system is not generating gas, feedwater can be added by the operator
at the touch screen.
1
EC500 , EC600 and EC750 generator models fill at 37%, stop at 47% and have a high level
alarm at 70%.
1-20
All process materials except for the pump vane parts are 316 series stainless
steel.
It will be noted that water replenishment occurs only on the hydrogen side of the
system. This is due to the nature of the basic process, which tends to dilute the
electrolyte on the oxygen side (see anode reaction in section 1.2.1), and to
increase electrolyte concentration on the hydrogen side. The addition of water to
the hydrogen side tends to counteract this affect.
The hydrogen generating process cannot be initiated with oxygen (oxygen gas or
air) present in the hydrogen side of the system. This may be the case after the
system has been opened for maintenance or has been down for an extended
period. To purge oxygen from the system, an inert gas is used. Refer to FIGURE
10. The inert gas system consists of supply manifold with relief valve (530),
solenoid valve (504), manual valves (505 and 506), and four check valves (507,
508, 509, and 512).
Inert gas flow into the phase separators (101, 201) is normally added as part of an
automatic prepressurization sequence or can be initiated manually at the touch
screen when the system is in the start-up mode. The inert gas supply cannot be
energized if the EC is generating hydrogen and oxygen. When the supply is
energized, solenoid valve 504 changes position allowing inert gas to flow through
manual valves 505 and 506 to the phase separators. Inert gas pressure is
indicated on gage 503. Check valves 507 and 509 on the hydrogen phase
separator and 508 and 512 on the oxygen phase separator prevent process gases
from entering the inert gas system. When solenoid valve 510 is de-energized, the
inert gas manifold is vented to atmosphere (via third port on the valve).
1-21
FIGURE 10 Inert Gas Supply System
Manual valves 505 and 506 are used to balance the inert gas flow rate to each
side of the system and prevent excessive differential pressure. These valves are
also useful for various maintenance and adjustment procedures.
1-22
FIGURE 11 Instrument Air Supply
Regulator 002 is set at 20 PSIG (1.4 Bar). This is the pneumatic instrument
supply pressure required for I/P transmitters 013, 018 and 019, which control the
cooling water valve and hydrogen and oxygen vent valves.
To assure adequate supply, pressure switch 005 is set to activate if air supply
pressure falls below 70 PSIG (4.8 Bar). This signals the PLC to stop electrolysis
and depressurize the system. Because of the critical function of pneumatic
instruments, loss of instrument air supply also causes valve 010 to energize which
temporarily supplies inert gas to the air system. This will assure that controls are
not disabled while the generator is depressurizing.
On the lower control panel of the generator, the EMERGENCY STOP button must
be pushed out to enable (not to start) electrolysis. This switch is in series with the
signal to supply DC power to the module and will not affect the operation of other
controls or the pumps. The EMERGENCY STOP can be used to stop electrolysis
in the event of a control or touch screen problem. If desired for maintenance or
security purposes, it may be locked.
1-23
If the system pressure at start-up is below 20 PSIG (1.4 Bar) when the operator
wants to start the generator, the PLC will initiate an automatic prepressurization
sequence, supplying inert gas to the system then depressurizing the generator
several times. The system vent valves (320, 420) will close when nitrogen is
added and open when depressurizing. Once the sequence is complete, the inert
gas will turn OFF, and an enable signal will be sent to the power supply control
board. Current will begin to flow through the module and the system pressure will
increase.
The DC module current will be limited by the PLC to a percentage of the ampere
maximum until the system has run a few minutes and the KOH temperature is in
the normal operating range. It will take several minutes for the system to reach
start delivering gas and reach the normal operating pressure. .
If the system is below the pressure set point, higher current (up to 1000 amperes
per module) will be noted until the pressure approaches the set point. If the user is
not demanding gas, the DC current will fall to approximately 100 amperes per
module, once the pressure set point has been reached.
As the KOH temperature rises, the KOH cooling system controls will become active, and
begin to flow cooling water through valve 609. After 1 to 2 hours of operation, the KOH
temperature will stabilize between 60 and 70 C, depending on demand. The
temperature should not exceed 73 C at rated output. A description of the KOH
temperature control system is found in section 1.3.11.2.
The system will function automatically after start-up. The dryer regenerating cycle
will begin and various changes in valve position will be heard periodically (typically
a hissing noise from a pneumatic valve). The traps will purge every 15 minutes.
An increase in module current will be noticed when the 335 and (for a "C" model)
435 valves are open (cool-down and pressurization) as the purge flow represents
a minor increase in demand.
Gas Purity
Upon initial gas generation, there will be a mixture of hydrogen and nitrogen (or
oxygen and nitrogen), within the system, because of the start-up purge. The user
should consider this as regards the purity of delivered gas. It is suggested that a
valve be installed in parallel with the user's delivery valve, which is piped to the
vent system. This will enable a brief purge of impure gas. After approximately 30
minutes of electrolysis, the user may open his delivery valves to receive pure
hydrogen (or oxygen).
For "C" model users requiring very low nitrogen-in-oxygen (less than 0.2 PPM),
several hours of operation may be required to bring nitrogen levels down to this
range. It is noted that the steady-state nitrogen impurity is a function of the gases
entrained in the feed water. Special feed water treatment can significantly reduce
1-24
nitrogen levels in the product gases.
Concerning the time required for typical moisture levels to be reached - a clean
system should deliver pure gas within 30 minutes or so of operation, even after
brief shut-down periods. If the system is new, has not been operated for several
weeks or has been opened for maintenance, it may take one or two days of
operation for the molecular sieves to completely dry out. The amount of time
depends on local ambient conditions and other factors.
If electrical utility power is interrupted (temporary loss and recovery of power), the
UPS will go into battery back-up mode and provide 115 VAC power to the
generator control panel for approximately 100 minutes. In this case, electrolysis
will be unavailable and all pumps will be powerless. All other functions will be
active including the critical differential pressure control system. The system will
alarm and depressurize via the delivery line, down to the set point of valves 309
and 409. From this point the system will slowly depressurize via valves 330 and
430. This could take several hours depending on various other conditions. If
electrical power is not restored the UPS will send a low battery alarm signal to the
PLC when less than 15 minutes of power are remaining. This will initiate a
controlled pressure release before all power is lost. This action prevents any
pressure on the system without differential pressure control.
In a standard EC generator, there are 20 conditions that will result in system shut-
down and alarm:
1-25
Shutdown Set Point EC500
EC1000 EC600
EC750
Low KOH level 20% 20%
High KOH level 85% 70%
Low system pressure 51 PSIG (3.5 Bar)
High system pressure * 170 PSIG (11.7 Bar)
Low KOH flow, hydrogen side
Low KOH flow, oxygen side
High hydrogen-in-oxygen content * 180oC
High oxygen-in-hydrogen content * 180oC
Power supply trouble
Low instrument air pressure 70 PSIG (4.8 Bar)
High KOH temperature, hydrogen side 80oC
High KOH temperature, oxygen side 80oC
High H2 side catalyst tank temperature 250oC
Low feedwater purity 1 micro siemen
Loss of facility power
Hydrogen dryer fill problem 30 minutes
Loss of facility enable signal
High differential pressure, oxygen side * 10 inches water
High differential pressure, hydrogen side* 10 inches water
UPS Fault or Low Battery*
In an oxygen system "C" model, three additional alarms are possible as follows:
1-26
1.3.11 Description of Sub-system Controls
With the system at normal operating temperature (where amperage is not limited),
a response to a change in demand will begin within a few seconds and, depending
on the magnitude of the change, will stabilize within approximately 1 to 4 minutes.
Another purpose of supplying the 4-20 mA system pressure signal to the PLC is to
monitor for high and low pressure conditions. When the pressure is above or
below set points, the generator goes into alarm.
1-27
FIGURE 12 System Pressure Control
3-15
PSIG
4-20 013 I/P
934 PLC
MA TRANSDUCER
The input is the thermocouple signal and the output is a controlled cooling water
flow through the two KOH heat exchangers. Normally, the steady state KOH
temperature at the module outlet will be between 63 and 73oC. It will vary in this
range with the output of the generator. Generator operation at too low a KOH
temperature results in lower efficiency and higher power consumption. Continuous
operation at temperatures higher than 73oC can accelerate corrosion of system
1-28
components. Failure to provide adequate cooling water flow will cause a rise in
KOH temperature and eventually an alarm shutdown. Over-cooling the module
during high current operation can also cause damage to the module since
resistance is increased.
The PLC compares the KOH heat exchanger outlet temperature (from
thermocouple 232) to the controller set point (default factory set point is normally
60oC but adjusted at commissioning). The difference is used as a basis for a 4-20
mA output signal. This output is connected to current-to-pneumatic (I/P)
transducer 013, which converts the signal to a 3-15 PSIG instrument air signal.
The air signal is provided to the diaphragm of the cooling water control valve 609,
which raises or lowers the valve stem and, hence, water flow. The PLC uses
proportional control with integration (PI).
CAUTION: Do Not Turn the UPS OFF while the system is pressurized.
The control transducers 018 and 019 are such that 4 mA input creates an output of
3 PSIG, which corresponds to valve 430 or 330 being 0 percent open. 20 mA
input creates an output of 15 PSIG, which corresponds to valve 430 or 330 being
100 percent open. The range of the delta pressure transmitter is -20 to 20 inches
of H2O, equaling 4-20 mA output to the PLC. The PLC controls are set to
maintain a delta-P between -2 inches (oxygen high) and +2 inches (hydrogen
high). The PLC will shut down the generator if the delta pressure reaches either
1-29
-10 inches or +10 inches.
Refer to FIGURE 14 for a typical hydrogen delivery mode. In this scenario the
oxygen pressure is typically higher than the hydrogen pressure. The oxygen side
vent valve (430) is active. The PLC control is reverse acting, which means that its
output signal to the 430 vent valve rises as its input pressure signal from
transmitter 328 falls. When the delta-P exceeds the set point (-2 inches), the
output signal from the PLC and I/P 018 to vent valve 430 will increase, causing
oxygen to be vented from the system and a corresponding reduction in oxygen
pressure.
Valve 330 functions the same way as valve 430. Referring to FIGURE 15, the
relationship between the PLC, I/P 019 and vent valve is essentially the same,
except that it is set up in the direct acting configuration, which means its output
signal increases as its input signal from 328 rises. If hydrogen pressure exceeds
the oxygen pressure by more than 2 inches of water, the PLC and I/P increase
their output signal to valve 430, thereby venting excess hydrogen. This situation
could occur in a "C" system where oxygen demand is greater than half the
1-30
hydrogen demand. Also, during shutdown the vent rate of oxygen is typically
greater than that of hydrogen. This valve allows the hydrogen vent rate to be
increased in a controlled manner to maintain a low differential pressure.
Instrument air at a pressure of 20 PSIG (1.38 Bar) is essential for correct operation
of the differential pressure control subsystem and must always be provided while
the EC is operating. The air supply is from the instrument air manifold (80 PSIG)
via regulator 002, which reduces pressure to 20 PSIG (1.38 Bar) for these
instruments.
The KOH temperature is monitored on both the hydrogen and oxygen sides of the
system at the module outlet pipes (thermocouples 111 and 211). A bayonet-style
1-31
external pipe thermocouple arrangement is used. Thermocouple 232 is used as
the input for cooling water control and is found on the oxygen side heat exchanger
outlet pipe. It is the same type of thermocouple as 111 and 211.
Thermocouple 382 is banded to the outside of the H2 side catalyst tank and
monitors the surface temperature. If the temperature gets too high, it is an
indication that the concentration of O2 in H2 is too high coming out of the
module.
In "C" model generators, there are three other thermocouples. Two are in the
oxygen side catalyst tank. The catalyst for this tank must be heated to at least 120
degrees C to activate. Thermocouple 486 is the input to the PLC, which controls
the catalyst tank heaters. Because the reaction is also exothermic, thermocouple
487 monitors the internal temperature of the bed for alarm conditions. The third
thermocouple (418) is located inside the catalyst bed between the oxygen dryers.
This type J thermocouple connects to the PLC and functions as both the alarm and
control probe.
Each gas stream is monitored for the presence of the other gas using a special
probe consisting of a type J thermocouple that has been bonded to a small
catalyzed electrode. Oxygen and hydrogen will recombine on the probe surface
and cause a corresponding increase in temperature. After manufacture, the probe
is checked using a 2% hydrogen in air gas mixture. Normally, the temperature will
rise 100 to 150 C, during calibration.
The temperature signal is connected to the PLC temperature input card. If the
temperature exceeds 180 C, the generator will shut down.
Proper flow over the probe is important to its function. For the hydrogen side,
oxygen in the hydrogen stream is measured through the use of a forward pressure
regulator. The regulator (310) is in series with a rotameter (part of 310) and the
gas probe (305). The gas is sampled from a tube upstream of the dryer system,
which necessitates a filter tank (303) to remove moisture and residual KOH. The
sample stream also includes a flame trap in series with the probe.
On the opposite or oxygen side of the system, the same components are used to
detect hydrogen in the oxygen stream. The component numbers are 405 for the
probe, 410 for the regulator and rotameter, and 403 for the trap.
1-32
1.3.14 Programmable Logic Controller (PLC)
A number of automatic controls and monitors have been described that are
performed by the programmable logic controller (PLC). The PLC is a
microprocessor which takes information in various input formats such as voltage,
current or temperature, and energizes or de-energizes outputs according to the
instructions of a user-defined program. The program (referred to as ladder logic)
has comparison, timing, counting, mathematics, and other data manipulation
capabilities that enable decision making and corresponding output action. A
simple diagram of the various input and output types used on the EC generator is
shown in FIGURE 16.
The information stored in the central processing unit (CPU) includes the ladder
logic, working values (information which changes), and read only data which does
not change. The read only data consists of fixed set points used for comparison
by the CPU (typically alarm set points and timing values). The program and read
only data are installed at the factory. The working values change with machine
operation, and may or may not be retained by the CPU when power is turned OFF.
An optional hand-held terminal for interface with the PLC is available, and can be
helpful in troubleshooting. It is also possible to establish personal computer
based communications with the PLC using optional software. Contact Teledyne
for more information.
The PLC is physically configured as a power supply, CPU and a number of input
and output modules. The power supply and CPU are located on the left side of the
back plane. Multiple-channel digital and analog input and output modules and
communication modules are located to the right of the CPU. Several pages of the
electrical wiring diagram are organized according to PLC inputs and outputs. An
understanding of the diagram will help clarify the details of the control system.
1-33
A listing of the input signals is as follows:
1-34
A listing of the output modules is as follows:
Digital Output:
The touch screen is the operator's interface with the EC generator, providing a
means of control as well as status for important machine parameters. The touch
screen is directly interfaced with the PLC and can be considered an input/output
device. Each screen is separately programmed and loaded into the touch screen
memory. During programming, PLC word addresses (where a parameter is
stored) and bit addresses (such as push button status) are placed in a
communication table, which is also loaded into the touch screen memory. This
table enables the direct communication of the touch screen inputs and display
values. The screen also has various optional set-up features, all of which are pre-
set at the factory.
The touch screen can also be used to provide the operator with information such
as programmed set point values and HELP screens that are available if an
automatic shutdown occurs.
1-35
1.3.15 Electrical System
Power Distribution
Refer to sheet 2 of applicable generator system wiring diagram and power supply
wiring diagram. Electrical power for electrolysis and associated sub-systems is
distributed from the power supply enclosure. The only input connection made by
the user is the 3-phase AC power.
This is connected on the primary side of the EC's main transformer (in the power
supply enclosure). Typically, the user will make this connection from a 3-pole
breaker located near the power supply.
From the primary side of the main transformer, 3-phase voltage is provided to the
motor starters for the EC's feedwater pump and 2 KOH pump motors; and single
phase input voltage is fed to the primary of several auxiliary transformers. These
circuits are protected by a circuit breaker located on the front of the power supply
cabinet. One transformer provides 110-120 VAC for the EC's control system
UPS. A second transformer provides 230-240 VAC for heater power in the EC's
dryer system and (for a "C" system) the oxygen side catalyst heater.
The UPS mounted to the power supply cabinet provides the power for the EC
controls and is used to switch control power ON and OFF. This 110-120 AC
voltage is used for the programmable controller (934), instruments,
indicators/alarms, solenoid valves, and other control devices. This voltage is
also the input to a 24 volt DC power supply (966) used for the analog
instruments.
Power is provided to the EC circuits at the gas cabinet via circuit breakers inside
the power supply. These breakers can be used to switch power ON and OFF to
the applicable subsystem.
Breaker 919 provides 220-240 VAC to the hydrogen side dryers (314, 315).
For an optional "C" system, breakers 920 and 935 provide 220-240 VAC to the
oxygen side dryers (414,415) and oxygen catalyst bed heaters (412).
AC to DC Rectifier
The rectifier consists of a 6-pulse (6 SCRs) full wave bridge circuit, and various
control circuit boards. Refer to the power supply manufacturer's wiring diagram
provided in the appendix of this manual. The main control and trigger (CAT) board
1-36
receives current enable and 4-20 mA analog control signals from the EC gas
cabinet. The board also receives inputs from the 3-phase lines and feedback
current and voltage signals from the bridge output terminals. The response of the
controls is such that a DC current of 100 to 1000 amperes (200 to 2000A for EC-
1000) is supplied corresponding to the 4-20 mA input. This is accomplished by
varying the gating of the SCRs. A dampening circuit is in series with the control
signal to prevent module current from increasing too rapidly. DC current and
voltage can be limited by the operator by adjusting potentiometers on the power
supply panel. These functions are useful at start-up and for trouble-shooting.
Total module amperes and volts are displayed with meters on the front of the
power supply enclosure. Indicator lights for AC power ON, DC current ON, phase
loss and over-temperature alarms are also included on the power supply panel.
Inputs to the CAT boards are typically isolated with smaller circuit boards (referred
to as SISO or DISO boards).
The input to the rectifier bridge is from the secondary of the main 3-phase
transformer, which reduces the customer's input voltage to that corresponding to
the EC module size. The AC input is monitored for a loss of phase. The main
transformer and SCRs are monitored for high temperature. The switches of these
alarm devices are connected in series and monitored by the EC's PLC, which
looks for a complete circuit through all of the alarm switches. The power supply
CAT board also has various internal monitoring functions that will disable the
output in a fault condition.
Electrical Wiring
The power supply and the EC gas cabinet are pre-wired, inspected, and tested at
the factory. Refer to the next section for interconnections. Cabling is approved
USA/NEC tray cable placed in covered distribution trays within the gas cabinet, or
inside rigid or liquid-tight conduit. Sealed cable connectors are used at the main
enclosure and the individual components, except at the thermocouples, where
plugs are used.
The AC input wires from the facility, electrolysis module cables, and signal/control
cables typically enter the power supply enclosure through the bottom. Control and
signal wires pass from the main cabinet to the control section on the side of the
cabinet through internal holes or conduit. Inside the power supply control
enclosure, there are several labeled terminal strips where connections to the gas
cabinet are made.
1-37
All of the auxiliary power supply wires and control wires are pre-connected at the
factory on the gas cabinet side. A cable harness approximately 65 ft (20 meters)
long is provided. If the harness does not require trimming, final connections at the
power supply control enclosure are made with pre-installed terminals. The
harness may be trimmed, if necessary.
The DC cable for connection between the rectifier and the electrolysis module is
provided with the generator. Module and ground cable is USA NEC Type W
approved for extra hard service. The length is sufficient to make approximately a
63-ft (19-m) run, based on connecting 6 cables each at the positive and negative
sides of each module, and one cable as a ground between the gas cabinet and
power supply structures. All of the required terminal lugs and connection hardware
are included with the generator.
Inside the EC gas cabinet control enclosure, terminals are provided for a remote
signal connection. If the user desires a remote signal, for example to stop
electrolysis for facility related reasons, wires are installed to remote dry contacts
rated for 24 VDC. One connection each for normally open and normally closed
conditions is available. This function interrupts the DC enable signal only. Gas
generation will stop, and the system will depressurize.
Where possible in the electrolyte and cooling water loops, piping and connections
are seal welded. Where connections must be removed for access, flat-faced
fittings with EPT O-rings are used. A view of the typical fitting is shown in FIGURE
17. The fitting consists of 4 parts including the O-ring. The threaded piece
contains an O-ring groove and external threads. The tail piece contains a flat face
to mate with the O-ring. The nut slides over the tail piece and tightens the flat face
against the threaded piece. This type of connection allows the removal of pipes
and components without the need for threading space (such as with a pipe joint).
For gas tubing and condenser water tubes, Swagelok style compression fittings
are used. These are high quality, leak free fittings that can be opened and closed
repeatedly. Swagelok parts are available worldwide, and most customers can
obtain parts locally, if necessary. FIGURE 17 shows a typical connection.
The joint consists of 4 parts. The fitting with straight threads provides the tube
socket and connection point for the nut. The front and back ferrules combine to
provide proper tube compression during swaging, and the nut tightens the swaged
tube to the fitting. The nut threads are coated with silver to prevent galling. The
installation results in deformation of the tube, which then retains the parts when the
tube is removed. Many fitting sizes and styles are available. The EC incorporates
various fittings that adapt from pipe threads or socket welds to a threaded fitting.
Fittings are available to convert to metric sizes.
1-38
The connections within the EC scope of supply are made at the factory. However,
the user will need to swage a few tubes at the interface points. The user would
also consider the use of similar fittings within the facility. Although this type of
fitting is simple to install and use, a brief training course is recommended to be
sure of proper leak-free connections in the facility. Contact the local representative
for literature or training; or contact Teledyne for more information.
1-39
1.4 EC Generator Specifications
* With degassing equipment for the feed water and reasonable ambient and condensing water temperatures.
1-40
Additional specifications:
Ambient 5 to 50 C
temperature range
The electrical power supply input voltage and frequency are specified by the user
and the power supply is manufactured accordingly. The AC line current will
depend on facility voltage. Power factor is a function of demand. Teledyne can
furnish specific power consumption information when input conditions are known.
1.6.1 Summary
This information pertains to the EC generator. The user is responsible for other
considerations such as civil works, lightning protection, hazard communication,
proper training of personnel, etc. which may impact safety.
Care should be taken to avoid contact with potassium hydroxide (KOH) as it may
be harmful and is an irritant to skin and eyes. If contact does occur, neutralize the
KOH with a 3-5% solution of boric acid, wash with mild soap and rinse with potable
water. Potassium hydroxide is very slippery and minor spills in the walkway
around the generator can be hazardous. Neutralize the spill area with boric acid,
and then clean with water and dry.
Utilize goggles or a face shield when handling KOH. Standard safety glasses may
not protect against splashing. When handling KOH, use gloves that are suitable
for strong caustic applications. An apron is recommended to protect skin and
clothing in case of splashing.
Eye wash bottles or an eye washing station should be installed in the area. This is
a standard chemical safety precaution.
1-42
1.6.3 Flammable Gas
Hydrogen gas when combined with oxygen gas or air can ignite with explosive
violence. Care should be taken to prevent hydrogen gas from mixing with these
gases. Conduct periodic leak checks of facility gas piping connections and valve
packing.
Hydrogen gas production can be initiated only after it is verified that standard
precautions against hydrogen accumulation and ignition have been taken. Refer
to facility related discussion in Section 2 of this manual. Verify that the building
ventilation is functioning and that all heat or spark producing equipment has been
de-energized or removed.
When the system is turned OFF, purge with inert gas to remove hydrogen from the
system. Do not open the hydrogen side of the system for maintenance without
purging hydrogen.
Maintain function of the gas cabinet electrical enclosure purge (door closed,
system ON, and alarm horn set). This assures that any leaked hydrogen cannot
enter the box where it may be exposed to ignition sources.
1.6.4 Oxidizer
Oxygen gas supports rapid combustion. Care should be taken when working with
or venting oxygen gas.
1.6.5 Electrical
There are several operating voltages in the system including the facility 3-phase
power (includes rectifier input and motor voltage), dryer heater voltage (240 VAC),
control voltage (115 VAC) and electrolysis module voltage (up to 280 VDC).
These voltages are lethal and extreme caution is required when operating the
system or performing maintenance. Keep enclosure covers in place. Keep the
control panel door closed at the gas cabinet. Never operate the EC without the
polycarbonate module shields installed. Utilize standard electrical and specific
plant safety procedures.
1-43
When required to perform electrical repair work or adjustments that do not require
power, lock out the main power source at the wall breaker or safety switch, using
plant safety procedures. Double check for the presence of voltage before touching
or working on high voltage circuits.
The hydrogen, oxygen, instrument air and inert gas sub-systems operate at up to
170 PSIG (11.7 BAR), and should be treated with the appropriate precautions for
pressurized gas. Inert gas supply is frequently from high pressure portable
cylinders. Use appropriate safety procedures (provided at site or by industrial gas
supplier) in handling cylinders and regulators. Wear safety glasses when in the
machine area.
Nitrogen and compressed air lines at the EC interface are not automatically
depressurized when the generator is off. Use appropriate precautions if
disconnecting these lines.
Never attempt to tighten a pipe thread fitting while the system is pressurized.
Keep protective shields for the dryer tubes in place. Use caution around the sheet
metal enclosure of the oxygen side catalyst vessel enclosure ("C" model), and
around the gas dryer tubes. Temperatures of these surfaces can exceed 200 C.
On C-Model units, the Oxygen side catalyst tank on the roof of the generator can
also exceed 200 C since it must be heated and has an exothermic reaction.
1-44
SECTION 2 Installation Considerations and Instructions
TABLE OF CONTENTS:
LIST OF FIGURES:
2-1
2.1 Summary
Installation of an EC generator consists of
The user's plumbing will include gas tubing (.50 inch (13 mm) maximum
outside diameter) for instrument air, inert gas supply, hydrogen delivery,
and hydrogen and oxygen vents. Gas tubes are usually best installed on
overhead supports. There will also be 1.0-inch (25.4 mm) diameter cooling
water inlet and outlet pipes.
2.2.1 Tools
Most tools required for work on an EC are standard and include slotted and
Phillips head screw drivers, cutters, pliers, etc. A set of open end wrenches
in standard USA sizes from .25 to 1 inch (in 1/16 inch increments) is
required for small plumbing connections, adjustment screws, brackets, etc.
For intermediate size pipe and tube connections, an adjustable wrench up
to a 1.75-inch (45-mm) opening is suitable. For larger pipe connections in
the KOH pipe loop, a spanner up to 4.38 inches (110 mm) is required.
A set of standard size sockets and a torque wrench up to 120 FT-LB (163
N-M) is required for the filter vessel cover tightening procedure (1-1/4 inch
socket) and the KOH loop ball valve assembly torque procedure (11/16 inch
socket). A torque wrench up to 300 FT-LB (407 N-M) is required for
periodic tightening of electrolysis module tie rod hardware.
2-2
NOTE: Torque procedures are not typically necessary
at installation. The tools are mentioned here so
as to describe mechanical tools for installation
and maintenance purposes.
Equipment supplied with the EC generator includes various special tools for
check valve disassembly and flow meter adjustment. A deep-socket is
supplied for re-torquing of the electrolysis module tie rod hardware.
Tools to cut and strip AWG 4/0 wire will be required for the DC module
cables. A standard voltmeter is required for preliminary checks. A clamp-
on inductive type AC ammeter is recommended so that current can be
checked without disconnecting wires. Refer to section 4 of this manual for
details of other equipment required for calibration or maintenance.
Assuming facility piping and wiring up to the interfaces has been completed
ahead of time and adequate lifting equipment is available, a two or 3 man
team can complete the installation in 1 to 2 days. The time will be longer
depending on the user's choices for the electrical installation, and the
condition of facility plumbing.
2-3
2.3 Installation Considerations
Area classification
Facility inputs and interfaces
Physical access for maintenance
Personnel safety
Ventilation
Floor drains
Ambient rejection of heat from the process and from the rectifier
Noise
Dust control
System Classification
2-4
systems and is not normally present in the environment. Flammable
material is present only in the event of a failure leading to leakage, and such
failures are not simultaneous with activation of exposed ignition sources.
The presence of hazardous material is assumed to be for a relatively short
time.
Refer to Section 1 of this manual for pressure and flow ratings, feedwater
quality, cooling water, instrument air and nitrogen quality, conditions, and
consumption. FIGURE 2-1 contains the sizes and operating conditions of
each interface. If the facility input sources are restricted or physically far
from the EC generator, the facility pipe sizes must be increased
accordingly. The facility supply lines to the EC should be adequately rated
for the application, of compatible materials, and contain the necessary
filtration to meet these requirements. This will insure that impurities such as
oil, minerals, and particles do not enter the system.
Instrument air and nitrogen must be dry and oil free and appropriately
filtered. Feedwater quality must meet the requirements of Section 1.
All fluid and gas interfaces are USA tube sizes (a size refers to the outside
diameter). The user should contact Teledyne in advance of shipment if
assistance is needed in adapting to the EC tube interfaces.
2-5
FIGURE 2-1 System Installation Diagram
2-6
INTERFACE IDENTIFICATIONS
2-7
The AC ampere service to the power supply is determined based on the EC
electrolysis module size and the facility 3 phase input voltage and is shown
in Table 1.4. Contact Teledyne for additional information. Unless otherwise
specified in the purchase order, the user is responsible for AC wiring
(including lugs) from a nearby 3-pole breaker or disconnect to the input
terminals located in the power supply cabinet.
2.3.2 Location
Many users install the EC on a raised cement pad (approx. 100 mm) to
facilitate floor cleaning. The gas cabinet contains a bracket at each of the
base corners, with provision for two anchoring screws. Refer to FIGURE
2-2, for dimensions of a recommended pad and anchor bolt locations.
The room should have at least two doorways and one of these must be
large enough for lifting equipment. It is recommended that the most
commonly used door be placed near the gas cabinet control panel. At least
3 feet (1 meter) of space along the sides of the gas cabinet is required. A
minimum of 6 feet (1.7 meters) is required on the phase separator end of
the gas cabinet for module removal. Approximately 5 feet (1.5 meters) of
clearance in front of the control enclosure is recommended, as this is where
the operator will view the touch screen.
The room and surrounding areas where hydrogen is processed should have
several obvious warning signs against smoking, open flames or sparking
devices in the area.
2-8
FIGURE 2-2 EC Generator with Floor Mounting & Concrete Pad
2-9
2.3.3 Ventilation
The EC is designed with many special features in the electrical system such
that electrical components cannot produce ignition energy under normal
conditions. The processing of a flammable gas (hydrogen) occurs in a
closed system and leakage of hydrogen is the result of an abnormal
situation. These factors are intended to assure safe operating conditions
(as well as controlled shutdown in abnormal situations) whether or not
mechanical ventilation is used. However, Teledyne recommends forced
ventilation of any area where a flammable gas is processed.
If the location, size, and other limiting factors of an existing room or building
are a concern, the user may want to consider connecting an exhaust duct to
a square opening in the roof of the EC gas cabinet. The duct opening
dimensions are 18 X 18 inches (457 X 457 MM). This would provide
additional assurance that any leakage from EC components would be
exhausted. It is emphasized that the use of such a duct is not a mandatory
feature in the EC's design as regards electrical safety. In most situations
with adequate area ventilation, the duct is not required.
Portable devices, plug-in extension cords, etc., should be used only for
maintenance or other temporary functions. Standard electrical devices
should not be permanently installed or operated in the machinery room.
Portable power tools and other motor driven equipment, welding equipment
and the like, should never be operated in the area when hydrogen is being
generated.
Refer to FIGURE 2-1 for a listing of the pipe connections and service. The
EC inert gas, instrument air, hydrogen and oxygen delivery and vent lines
are 0.5 inch (13 mm) or smaller in diameter. Overhead tube runs can be
easily installed at the upper rear corners of the gas cabinet. The oxygen
and feedwater inlet connections are on the same side of the gas cabinet as
the electrical enclosure. The inert gas, instrument air and hydrogen gas
lines are on the opposite side. The cooling water inlet is at the lower
oxygen side corner, below the oxygen gas connections and the cooling
water outlet is opposite, below the hydrogen gas lines.
2-11
The user is advised to install suitable isolation valves as close as possible
to the gas cabinet, for the inert gas, instrument air, feedwater, cooling water
and gas delivery lines. Ball valves are recommended.
Valves and other restrictions should not be placed in any of the gas vent
lines. The use of a cooling water rotameter is advised if the user requires
flow data, but is not essential.
Gas vent lines will carry water vapor. Suitable precautions should be taken
against trapping moisture in gas piping. Install drain valves at system low
points, if necessary. Also, larger diameter pipe and tube may be necessary
if the distance to the vent area is very long, or if the number of fittings
causes excessive back pressure.
2-12
vent assembly. If uncertain, contact Teledyne for more information on this
subject.
2. Remove the four sides of the box and the plastic enclosure. Four
(4) lifting pad-eyes are furnished with the gas cabinet and are found
inside the box.
2-13
2.4.2 Gas and Fluid Pipe Connections
All connections at the top rear corners of the gas cabinet are 316 stainless
steel Swagelok style compression fittings, except brass Swagelok
condenser cooling fitting for the EC-1000. These are high quality, leak free
fittings that can be loosened and re-tightened repeatedly. It is important
that the facility side tube be properly prepared for a leak free connection.
Trim tubes to the proper length and with an even, square end. De-burr the
inside and outside diameter of the tube end. Flush the tube with water and,
if necessary to remove oil, a suitable detergent. Rinse and blow dry the
tube with nitrogen.
A connection nut and the two proper ferrules (front and back ferrules) for
each interface are provided (refer to FIGURE 2-3 below and FIGURE 1-
20, page 1-42).
2. Install the nut, back ferrule, and front ferrule in the proper
orientation over the facility tube.
3. Install the tube fully into the fitting making sure the tube bottoms out
2-14
in the tube socket. Push the nut and ferrules down and tighten the
nut finger tight. Place a mark on the nut for reference.
4. Then using a wrench tighten the nut 1 and 1/4 (1.25) turns from the
finger tight position. This will properly swage the ferrules to the
tube.
At the lower rear corners of the EC, the cooling water pipes are
connected. The EC is furnished with a removable pipe union, which
should be welded directly to the facility cooling water pipe. Size and
service are listed on the chart of FIGURE 2-1.
1. Remove the plywood top and sides from the wood module crate.
NOTE: For EC-1000, two modules are installed with the positive
endplates facing each other in the middle of the gas cabinet. Install
the first module (100B) with the negative endplate nearest the rails
and the second module (100A) with the positive endplate nearest
the rails.
2-15
4. If there is any clearance between the wood floor and the wheels,
install shims under the wheels. Slowly remove the bolts from the
module endplates and transfer the weight to the wheels and floor.
9. Clean the pipe threads and O-ring grooves, if necessary, and apply
fluorolube grease. A small amount of grease is needed on the O-
rings. Using the lubricant on the threads helps to prevent galling.
NOTE: The instructions below are written for EC-1000. Skip to step
19 for single module installation.
10. Carefully push module 100B against rail stops. Chalk module
wheels in place. Position Module 100A approximately 1ft (30cm)
from Module 100A, endplate to endplate.
11. Connect pipe assemblies, items 1 and 2, Fig 2-5-1 (from KOH
filters to flanged tees). Start the CPV fitting nuts at the KOH filters
and place piping in pipe supports.
12. Install tees (items 3 and 4) to flanged ends of items 1 and 2. Insert
gaskets and tighten the flange nuts finger tight.
13. Attach pipes 5, 6, 7 and 8 to the tee flanges, insert gaskets, and
tighten nuts finger tight.
14. Partially thread the CPV fittings on pipes 5, 6, 7, and 8 to the lower
ports on the negative endplates. It may be necessary to pry slightly
against the module wheel nuts, in order to start the four CPV
fittings.
2-16
15. Tighten the CPV fittings on the KOH filter. Torque the nuts on the
flanged connections to approximately 79 ft-lbs (107 N-M). Tighten
the CPV fittings on the module negative endplates.
16. The upper pipes can now be installed. Several of the pipes are
heavy, so use the pipe hangers while installing the pipes to support
and guide the installation. Loosely connect pipes 9 and 10, Figure
2-5-3, to the KOH phase separators. Loosely connect pipes 11 and
12 to top ports on the negative endplate of Module 100B.
17. Install tees (items 13 and 14) to flanged ends of pipes 9, 10, 11 and
12. Insert gaskets and tighten the flange nuts finger tight. Attach
pipes 15 and 16 to the tee flanges, insert gaskets and tighten nuts
finger tight. Connect pipes 15 and 16 to the top ports of the
negative endplate of Module 100A.
18. Once all connections have been started, torque the nuts on the
flanged tees to approximately 79 ft-lbs (107 N-M). Tighten the CPV
fittings on the module negative endplates and phase separators in
small increments.
20. The final step is to install the polycarbonate shield kit on four
sides of the modules. PVC screws are included for attachment to
the end plates. Install the side shields first. Then install the top
and positive end shields using the special nylon screws at the
bottom of the positive end plates.
2-17
FIGURE 2-4 Module Installation
2-18
FIGURE 2-5-1 Top View of Piping Installation
2-19
FIGURE 2-5-3 End View of Piping Installation
2-20
WARNING: FACILITY SUPPLY, AUXILIARY AND
RECTIFIER OUTPUT VOLTAGES ARE
LETHAL. FOLLOW WARNING AND
CAUTIONS REGARDING ELECTRICAL
HAZARDS FOUND IN SECTION 1 OF THIS
MANUAL, AS WELL AS PRESCRIBED
PLANT SAFETY PROCEDURES INVOLVING
WORK ON ELECTRICAL COMPONENTS.
5. The power supply contains several small cooling fans that draw
air up from the bottom and discharge warmer air through the
top. In smaller rooms, consideration should be given to free
airflow toward the bottom of the cabinet, to assure adequate
cooling. As the power supply rejects significant heat, it may be
desirable to duct the warm air from the top of the cabinet to an
outside location. Minimizing of dust in the power supply room
should also be considered.
2-21
FIGURE 2-6 Power Supply with Concrete Pad
All of the interconnecting wire between the EC gas cabinet and the power
supply is furnished with the generator. The cabling between the power
supply and gas cabinet is multi-conductor except module and ground
cables. FIGURE 2-7 shows the cables, sizes and voltages. Control and
instrument wires are pre-connected on the gas cabinet side. The cables
are grouped according to voltage so that they can be separated by the
customer for different conduits or to otherwise comply with local codes. The
control and instrument cable used is USA National Electrical Code (NEC)
type TC tray cable. It is suitable for installation in tray cable systems or in
conduit or a cable pit.
The module cable is AWG 4/0 NEC Type W approved for extra hard
service. For the EC-1000 models two set of module cables are used (6
positive and 6 negative per module). Because of the hard service rating
and heavy insulation, the module cables are not easily pulled through
conduit. Since cable in conduit does not need to be rated Type W, users
planning conduit may wish to consider another type of 4/0 cable. Contact
Teledyne for more information.
2-22
FIGURE 2-7 CABLING FROM EC POWER SUPPLY TO GAS CABINET
2-23
2.5.3 Wiring Steps
Performing the installation in the above sequence minimizes the chance for
a problem or error to cause damage.
Connection terminals and wire number markers can be found on the power
supply end of all control, instrument and motor cables. If the component
separation does not require the entire cable length, the cables may be cut
to a shorter length. In this case, new terminals will need to be crimped to
the wires. Be sure to use the same wire markers.
1. Be sure any facility power to the power supply has been turned
OFF and locked. Push the Emergency Stop button, at the gas
cabinet control panel.
2-24
5. On the rear wall of the EC gas cabinet, there is a vertical cable
tray with entry points at the top and bottom of the EC. Refer to
FIGURE 2-8. This tray gives the user the option of running
cables to the power supply either above the equipment (cable
trays, for example), or below (cable pit or buried conduit).
8. Make the cable run to the power supply and bring the cables in
to the main power supply cabinet through the bottom (toward
the back of the cabinet), making sure the cables do not interfere
with the cabinet cover installation.
9. Use tie wraps to position the cables away from live components,
metal edges or fans.
11. Run the control and signal cables through the conduit passage
to the control section, and connect the cables to the specified
terminals.
12. Run the three motor cables to the motor starters which,
depending on the manufacturer, are located either in the main
cabinet or the control section.
13. Finally, connect the main contactor control cable (for MC1) to
the main contactor located in the main cabinet.
2-25
FIGURE 2-8 ORIENTATION OF POWER SUPPLY CABLES
2-26
FIGURE 2-9 CONTROL CABLE ROUTING
The EC system is supplied with 800 feet (244 meters) of AWG 4/0 cable per
module (EC-1000 has 1600 feet) intended for use as the DC current
conductor, and for a single ground cable. The wire can be cut to 13 lengths
of approximately 19 meters (or shorter): six for the positive side
connections, six for the negative side, and one for the ground cable. The
EC-1000 requires 25 lengths of approximately 19 meters (or less), six each
for the negative side of Module 100A and 100B, six each for the positive
side of Module 100A and 100B, and one for the ground cable. The length of
the positive and negative cables should be determined after considering the
location of cable entrance with respect to the end plates and rectifier. For
example, if all of the cable is brought to the gas cabinet from the end
nearest the positive end plate, the negative cables will need to be longer
than the positive cables. It is very important to trim, mark and position the
positive and negative cables such that they cannot be accidentally reversed
during installation, service or maintenance. This must be done at both the
power supply and electrolysis module ends of the cable.
2-27
WARNING: THE DC RECTIFIER IS AN ISOLATED
OUTPUT AND REVERSAL OF THE POSITIVE
AND NEGATIVE CABLES WILL NOT INHIBIT
OPERATION. SUCH A CONDITION COULD
RESULT IN THE GENERATION OF OXYGEN
ON THE HYDROGEN SIDE AND HYDROGEN
ON THE OXYGEN SIDE, WHICH IS
EXTREMELY HAZARDOUS. TAKE STEPS
DURING FINAL TRIMMING OF CABLES,
INSTALLATION AND MARKING TO BE SURE
CABLES CANNOT BE REVERSED. BE
SURE OPERATORS AND SERVICE
PERSONNEL UNDER-STAND THIS
WARNING.
There are eight triple-barrel lugs furnished with the system, or sixteen for
the EC1000 models. Each lug takes three AWG 4/0 wires and is installed
on the module with two brass screws and copper lock washers. There are
two single-barrel lugs for use with the ground cable, which uses the same
type of fasteners. All of these items are shipped in the installed position on
the module, in the power supply and at the ground plates.
1. Open the front panel of the power supply to gain access to the
DC cable connection points.
2. Remove the triple barrel lugs from the rectifier output bus bars.
Temporarily replace the rear cover panel.
3. Remove the front panel, or open the front door of the power
supply to gain access to the structural ground plate.
5. Remove the single barrel lug from the gas cabinet ground plate
located on the rear wall below the electrical enclosure.
6. Cut and strip the ends of one length of AWG 4/0 cable for the
ground connection between the structures.
7. Mark the ground cable ends with the appropriate color using
2-28
shrink tube of electrical tape. Green (per USA practice) is
suggested to indicate ground.
8. Connect the cable to the lugs and install the lugs on the ground
plates.
9. Temporarily replace the front panel (or close the front door) of
the power supply.
12. Insert three cable ends in to each of the eight triple-barrel lugs
and tighten. If necessary, remove the positive endplate
polycarbonate shield.
13. Connect the lugs to the bottom of the outer surface of each
module endplate.
15. Be sure all connections include lock nuts and are secure.
2-29
2.5.6 Main A/C Power Input and Initial Checks
The main power cables will terminate in the lower or middle section of
the power supply cabinet, near the front. The terminations are lugs on
the line side of the rectifier's main contactor. Because end-user supply
wiring depends on local practices, connection lugs must be furnished by
the end-user. The connection holes on the copper input terminals are
0.68 inches (17.5 mm) diameter.
2. At the power supply cabinet, turn OFF the control system main
circuit breaker. This will isolate the 115 and 240 VAC circuits to
the gas cabinet.
4. Inside the power supply, turn OFF circuit breakers 919 and (for
C system) 920 and 935.
5. There are three motor starters inside for the EC feedwater pump
(MS1), H2 side KOH pump (MS2) and oxygen side KOH pump
(MS3). Below each starter is an overload heater pack with
adjustable set point. These were set at the factory, but should
be checked prior to operation.
11. When facility input voltage has been checked, close (turn ON)
the power supply auxiliary circuit breaker located on the side or
front panel. Check for:
12. Slowly turn the voltage and current potentiometers to the right.
There should be no volts or amps indicated on the panel
meters, under these conditions. Turn the potentiometers back
to the zero position.
13. Make any changes or adjustments with the facility power turned
OFF, and re-check as necessary.
14. Turn OFF and lock out the main input power.
2. With facility power OFF and locked, remove the front panel of
the power supply.
2-31
3. Complete the routing of the module cables and connect the
cable lugs to the correct terminals. Be sure to install lugs such
that conductors are well separated.
5. The positive side (+) is connected to the end of the module with
no pipe connections.
8. Make a final check for correct location and tightness, and install
the power supply enclosure panels or close the door, if
applicable.
Now that power is connected and available at both the power supply
and gas cabinet, the user must take appropriate precautions regarding
safety. Turn OFF breakers for circuits not in use during pre-start
procedures. Keep the voltage and current potentiometers turned down
to zero while the system is not generating gas. Be aware of the various
voltages at points in the gas cabinet - motor circuits, heater circuits, etc.
Keep covers or doors protecting electrical circuits closed. Keep the
module shield assembly in place. Be sure others working around the
machine are aware of electrical hazards.
2-32
SECTION 3 Generator Operation
TABLE OF CONTENTS:
LIST OF FIGURES:
3-1
3.1 Summary
This section will describe start-up procedures, normal machine operation,
normal shutdown, and responding to alarm situations. It is assumed that
installation of the EC and the required facility inputs, and gas vents are
complete. Once the operator has filled the generator with electrolyte and
performed simple pre-start checks, the machine can be operated from the
PLC touch screen.
Proceed to section 3.3 for a normal start-up procedure if the generator has
already been in operation. Otherwise, perform all of the checks starting
with section 3.2.
3-2
INSTALL THE DRYER HEATER SCREENS
TO PROTECT AGAINST HOT SURFACES;
AND INSTALL THE POLYCARBONATE
SHIELD KIT ON THE ELECTROLYSIS
MODULE. NEVER OPERATE THE EC
WITHOUT THE POSITIVE ENDPLATE
SHIELD.
At the power supply, turn the voltage and current potentiometers down to
zero, and turn OFF the circuit breakers for the KOH pumps, Feedwater
Pump and the Dryer Heaters. (See the power supply manual for specific
information). Place the Emergency Stop button on the generator panel in
the STOP position.
Using normal plant safety procedures, establish power to the power supply
at the nearest disconnect or breaker. The power supply power light will
come ON and fans will be heard.
3-3
CAUTION: IN THE NEXT STEP THE CONTROL SYSTEM
WILL BE ENERGIZED. THE "BUZZER
OVERRIDE" BUTTON MAY BE USED TO
TURN OFF THE HORN. DO NOT PUSH THE
RESET OR FEEDWATER ON BUTTONS AT
THIS TIME.
At the power supply cabinet, turn the UPS ON. The alarm horn will sound.
At the touch screen push the ALARM button, and push the BUZZER
OVERRIDE button.
During normal operation, utility power provides energy to the UPS and the
UPS maintains the batteries in a fully charged state. The four green LEDs
indicate an approximate level of load in 25% increments.
CAUTION: Turning off the UPS while in battery mode will result in
loss of output power. Never turn the UPS OFF while the system is
pressurized. A loss of power to the system when pressurized could
result in damage to the equipment.
ON Button
This button controls output power to connected load(s) and has three
functions:
This button controls output power to connected load(s) and has dual
functions:
Manual Bypass - Pressing this button once will cause the load to be
transferred to bypass power.
OFF - Pressing this button twice within 4 seconds will turn power OFF to
the output receptacles and connected loads. Perform all necessary
shutdown procedures on connected loads before pressing this button
twice.
CAUTION
Pressing the Manual Bypass/OFF button once will cause the load to
be transferred to bypass power. Pressing the Standby/Manual
Bypass button a second time within 4 seconds will turn power OFF
to the output receptacles and connected loads. Perform all
necessary shutdown procedures on connected loads before
pressing this button twice.
The UPS provides an alternate path for utility power to the connected load
in the unlikely event of a UPS malfunction. Should the UPS have an
overload, over temperature, or UPS failure condition, the UPS
automatically transfers the connected load to bypass. This also causes
the generator to shutdown and depressurize.
To manually transfer the connected load from the inverter to bypass, press
the Standby button once.
3-5
3.2.2 The "GENERATOR" Touch Screen
Notice the GENERATOR SCREEN. The screen is the main screen and is
shown in FIGURE 3-1 and FIGURE 3-2. It provides a simplified process
flow diagram with indications of all the critical machine parameters such as:
KOH temperature, system pressure, differential pressure, liquid level, safety
temperatures, pump and valve status.
3-6
FIGURE 3-2 Gas Generator Touch Screen - GENERATING
During normal conditions the inert gas purge is fully automatic and a
manual purge is not necessary. Nitrogen can manually be added for a
pressure test or other reasons. The function of inert gas supply should be
checked at this time. Open any facility valves for the inert gas supply.
Push the SYSTEM INFO BUTTON then the MANUAL N2 FILL AND VENT
BUTTON to access the inert gas controls. Turn the nitrogen on and the
system vent valves will close and valve 504 will change position. These
can be heard when the button is pushed. Verify that there is inert gas flow
through valves 506 and 505 into the phase separators. The system
pressure should begin to rise by a few PSIG as indicated on the touch
screen.
3-7
3.2.4 Feed Water Input
At this time, the feedwater pump rotation direction must be checked. Under
the electrical enclosure at the gas cabinet back wall, locate the pump/motor
and the flow direction arrow on the pump case. Open the facility valve(s)
that supply feedwater to the EC interface. At the TEE connection near the
pump suction, loosen (do not remove) the port cap, and allow some
feedwater to drain into a bucket. This will assure the pump is wetted and
will eliminate stagnant water from the supply tube. Tighten the fitting.
Press the FEED WATER button. While looking through the pump/motor
adapter slots, push the PRIME button, and then release it. If the direction of
rotation is incorrect, two of the 3-phase leads must be reversed. This is
normally done at the power supply control enclosure. Change the leads on
the input side of motor starter MS1. Check the rotation again, and proceed.
Whether starting with KOH or by filling with water for a pressure test, the
manual valves in the system should be checked for correct status. The
valves listed in TABLE 3-1 are for maintenance purposes, and are not
changed during normal generator operation. Check to see that these
valves are in the proper OPEN or CLOSED position:
Other manual valves in the system require adjustment during start-up, and
will be discussed in the applicable procedure steps.
3-8
3.2.6 Water Fill and Circulation
On the first few attempts, the pumps will run and will force the liquid into the
electrolysis module. The redistribution of liquid will cause the liquid level to
fall below 20%, which will then cause the KOH pumps to turn OFF on a low-
level alarm. Reset the alarm and turn ON the feedwater pump and add
more water. Repeat the attempts to start the KOH pumps each time the
level reaches approximately 40%. When the liquid level is able to stay
above 20% the KOH pumps will continue to run. The operator should stop
adding feed water once the level is stable and approximately 40%.
The KOH pumps can be operated any time there is liquid in the system,
including during the pressure test.
When the inert gas OFF button is pressed, the gas supply is turned OFF.
Press the DEPRESSURIZE button to open the system vent valves 320, 420
and begin venting gas. If desired, close the vent valves by simply pushing
the inert gas ON button, then immediately pushing the inert gas OFF
button. At this point, the inert gas will be off and the vent valves will be
closed.
Water can be drained from the system using the same procedure as that for
KOH, in section 4.5.2
3-9
3.2.9 Electrolyte Fill and Circulation
The electrolyte fill is very similar to the water fill in section 3.2.6. Fill the
generator with KOH electrolyte in accordance with section 4.5.2. After
draining and filling, the KOH must be allowed to circulate for at least 2 hours
prior to electrolysis. If the system is new or is being started with a
replacement module, or has been drained for more than a few days, then
the KOH should be circulated for 8 hours. It is recommended that the
service be performed such that the KOH circulates overnight, then the
system is ready to operate the next day.
3. Verify the supply of inert gas to the generator interface. Open the
facility supply valve. Check that 505 and 506 valves are open to
permit inert gas flow to the phase separators.
7. Turn ON the UPS at the power supply cabinet. The horn may
sound and touch screen is activated. The GENERATOR screen is
shown on the touch screen.
3-10
10. KOH concentration has been verified within normal range (28-32%
for EC-500, 600, or 750; 28 to 32% for EC-1000).
Check condition of 310 and 410 rotameters. The regulators and needle
valves must be open to permit flow. More precise adjustment is made
with the system at normal operating pressure. If one or the other has
been disturbed since previous operation, open the needle valve 2 or 3
turns.
If the generator has been at ambient pressure for more than a few
minutes, it is recommended to purge any air that may have migrated into
the system. This purge can be performed by pressurizing the system with
inert gas up to 15 psig (1 bar) and then turning the inert gas off and
venting the system. Repeat this procedure once. As inert gas flows into
the system, the operator should carefully monitor the O2-in-H2
temperature. As the inert gas forces air through the system and over the
310 probe, the temperature will rise. If the temperature rises above 90 C,
turn the inert gas OFF and allow the system to de-pressurize. When the
temperature falls, close to ambient, start the nitrogen again.
2. Open the facility condenser cooling water valves at the inlet and
outlet sides. Condenser valves on the generator should already be
preset to a partially open position. If not, flow to each heat
exchanger should be approximately 1 GPM (4 LPM) or two turns
each. Flows will be adjusted again during operation.
3. Push the PRIME button on the FEED WATER screen to turn on the
3-11
feedwater pump for about five to 10 seconds to flow fresh water
over the feedwater probe. This will update the feedwater quality
reading.
6. Push the START GENERATION button. This will clear any alarm
latches and begin the automated start up sequence.
7. The status on the bottom left of the touch screen will now read
PRE-PRESSURIZATION.
8. The system pressurizes and vent valves 320, 420 can be heard
going to a closed position. At a preset pressure 320 and 420 open
and pressure releases. This cycle repeats two times. While inert
gas is flowing, the operator should check for a balanced flow to
each side by observing the differential pressure reading. If the
differential pressure is high on one side (above the set value),
adjust manual valves 505 and 506 with the inert gas flowing.
10. If the gas sensor temperatures are too high, the generator will
automatically depressurize and attempt to pressurize again. If after
15 minutes the system has not been able to start, the generator will
stay shut down.
13. The SYSTEM INFORMATION button will take you to the screen
shown in FIGURE 3-8.
The generator will slowly ramp the current limit over the first few minutes
and operate at the maximum current allowed by the ramp and DC current
potentiometer setting on the power supply panel. When the pressure on
transmitter 325 is within one or 2 PSIG of the set point (normally 120 PSIG
or 8.3 BAR), the generator will automatically adjust production to match
facility demand.
If the pressure is below the set point, the current will rise until the set point
is reached. The current will be limited by the potentiometer setting, which is
now in terms of percentage of the power supply rating. It can take several
minutes for the pressure and current relationship to stabilize based on the
set point and a facility demand. If the demand increases, the system
pressure will fall, the current will begin to rise and, after several more
minutes, the system will stabilize at a higher current. If the demand falls,
the system pressure will increase and the current will drop down and
3-13
stabilize at a lower level.
When the facility is demanding more gas than the rated output, the gas
production will be voltage or current limited by the power supply. When the
system is fully warm and stable, the current limiting potentiometer should be
adjusted to allow full current. With no demand from the facility, the current
will drop to 10% (100A or 200A) of the rated output.
When the KOH temperature is within 1°C or 2 C of the set point, the cooling
water valve will begin to open to allow water flow through the KOH heat
exchanger circuit. The system will stabilize and remain within 1 C of the set
point set by Teledyne. The KOH temperature as indicated on the touch
screen from T/C's 111 and 211 will vary within a range of 60 to 73 C,
depending on system demand. When the generator is operating at full
output, the temperature should not exceed 73 C. If it does, contact
Teledyne Energy Systems for technical support.
3-14
FIGURE 3-3 Cooling System Touch Screen
Hydrogen side: 20 to 30
Oxygen side: 60 to 80
Feel the tube on the gas outlet side of each condenser. It should be at or
near ambient temperature. If the tube is warm or hot to the touch, increase
the water flow in small increments. Wait two or three minutes and check
3-15
again. Another general rule for adjustment is that the inlet and outlet tubes
on the water side of the condensers should be nearly the same. If the outlet
tube is more than a few degrees C above the inlet, increase the flow per the
above steps.
The operator can view all of the dryer related information by pushing the
DRYERS button. Figure 3-4 shows the DRYER STATUS SCREEN.
3-16
FIGURE 3-4 Dryer System Touch Screen
Each change in the dryer cycle can be noticed with a noise associated with
the pneumatic controls that change valve positions.
Feedwater Addition
The PLC monitors the liquid level of the KOH with pressure transducer 113.
The system pumps feed water to the hydrogen phase separator when the
liquid level falls to the factory-set fill set point. The feed water pump will run
until the level rises to full set point. The fill time and frequency will depend
on the system demand. When the pump is started or stopped by the PLC,
the motor starter MS1 may be heard in the electrical room. Near the gas
cabinet, check valves 507 and 509 can be heard when the pump is
stopped. FIGURE 3-5 shows all of the actions, level set points and the
actual level.
3-17
FIGURE 3-5 Status Touch Screen
Other screens that provide useful information during normal operation are
GAS CONTROL, POWER SUPPLY and SYSTEM INFO (FIGURE 3-6, FIGURE
3-7, and FIGURE 3-8.
3-18
FIGURE 3-6 Gas Control Screen
3-19
FIGURE 3-8 System Information Touch Screen
Another useful feature accessed through the SYSTEM INFO screen is the
graphical data logging of important parameters. FIGURE 3-9 shows the DATA
LOGGING screen. From there the operator can choose to view graphs of different
groups of information. FIGURE 3-10 displays an example of a typical screen
showing trends of information.
3-20
FIGURE 3-9 Data Logging Touch Screen
3-21
3.3.6 Stopping the Electrolysis Process
Normal Stop
The operator can push the POWER SUPPLY DISABLE button on any
touch screen, which will interrupt DC current. The operator can also push
the SHUTDOWN/PRESSURE RELEASE button on any screen. This will
interrupt DC current as well as opening the vent valves 320 and 420 to
depressurize the system. In either case, the KOH pumps will continue to
run unless the KOH PUMPS OFF button is pushed. When either button is
pushed, a confirmation screen pops up to make sure you want to stop
generation.
The operator may also use the manual push Emergency Stop switch to stop
electrolysis. This may be used if there is a control or touch screen
malfunction. The result is the same as pushing the POWER SUPPLY
DISABLE button on the touch screen.
If the system is going to be down for more than a few hours, the control
power should be turned OFF at the UPS.
This will cause the vent valves 320, 420 and 370, 470 to close and will
minimize the chance of air being drawn into the system.
3-22
Alarm Condition
3-23
FIGURE 3-11 Alarm Touch Screen
Power Loss
CAUTION: Turning off the UPS while in battery mode will result in
loss of output power. Never turn the UPS OFF while the system is
pressurized. A loss of power to the system when pressurized could
result in damage to the equipment.
3-24
EC Monitoring and Data Collection
The EC generator is designed for automatic operation and response to
changes in user demand. It may be left unattended assuming it has been
properly commissioned and functionally checked. Normal practice is to
check the machine once or twice per 8-hour shift. It is recommended that
the operator record data at this time and the data be kept as an aid to
troubleshooting. A suggested format for data collection is shown in Figure
3-2.
A detailed service history should be kept and should include both routine
maintenance and repairs.
3-25
FIGURE 3-12 EC Generator Data Sheet
3-26
SECTION 4 Maintenance and Calibration Procedures
TABLE OF CONTENTS:
4-1
LIST OF FIGURES:
LIST OF TABLES:
4-2
4.1 General
This section provides information on periodic component checks, regular
maintenance such as filter changes, and procedures for adjustment of controls and
instruments.
Factors other than time affect maintenance. Operating output, cooling water
quality, the number of machine start-ups and other site specific factors can
influence maintenance intervals. Keep detailed records of operating data and
maintenance information in order to adjust the schedule for minimal downtime and
replacement part cost.
4.2.2 Monthly
The following sections include calibration and set-up procedures for these
instruments. Unless you suspect a problem, these procedures should not be
necessary every year. As a general rule, perform calibration recommended every
two to three year for instruments exhibiting normal behavior.
The list below contains instruments with menu-driven set-ups and other types of
adjustments.
4-4
Pressure control system (325) Refer to section 4.5.24
Electrolyte temperature control system (232, 013, 609) Refer to section
4.5.25
Liquid level control system (113) Refer to section 4.5.26
For “C” model only: catalyst vessel temperature control (418) and O2
side catalyst tank temperature control (486) Refer to section 4.5.27
Delta-pressure control system (007, 008, 017, 328, 330, 430) Refer to
section 4.5.28
Feedwater resistivity monitor (705) Refer to section 4.5.29
The instrument air regulator maintenance includes adjustment of the set point and
inspection of the internal filter cartridge.
Each regulator has an outlet pressure gage, which makes it a simple matter to
check the set point. If a faulty gage is suspected, verify the set point by
connecting a second gage to the regulator output plumbing.
3. Perform the adjustment with a slight air flow through the valves. Loosen
the lock nut on the regulator bonnet and turn the adjusting screw
clockwise to raise the set pressure and counter-clockwise to lower the set
pressure. Tighten the lock nut.
4-5
4. To be sure of the adjustment, observe the pressure gages while the
machine is in normal operation.
4-6
KGS) of solid 85% pellets are required, or 31.4 gallons (119 liters) of 45%liquid are
needed.
1. When mixing electrolyte, put the pure water in the mixing container first
and add the concentrated liquid or pellets to the water.
4-7
2. Mix the electrolyte until it is at or near the recommended quantity.
1. The EC instrument air system must be ON. The electric power to the
power supply and controls (UPS) must be ON. This energizes the liquid
level instrument and allows the operation of the electrolyte pumps.
2. If a chemical pump is used, connect the discharge tube to the oxygen side
drain port at valve 220 or to the upper CPV fitting at the phase separator.
3. At the differential pressure transducer 328 open the small manual valves
on the top. This allows gases to be displaced as the liquid is pumped into
the EC.
4. Energize the chemical pump, open valves 210 and 220, and add liquid to
the oxygen plumbing. As the liquid level reaches the phase separator,
liquid begins to flow to the hydrogen side via valve 117. As the hydrogen
phase separator fills, the liquid level instrument 113 indicates the level.
7. Continue adding the liquid until the electrolyte pumps operate with a stable
liquid level of 35-40%.
8. Close valves 210 and 220, and turn OFF the chemical pump.
4-8
9. Disconnect the tubing and install the drain cap.
10. Close the small manual valves on top of pressure transducer 328.
Determine concentration by
In both cases, the temperature of the liquid must be determined. For the specific
gravity method, use Error! Reference source not found.1 to measure the %wt
as a function of temperature and specific gravity. Use the weighing method if the
weighing scale is accurate to within 1 gram.
4-9
TABLE 4-1 Specific Gravity of KOH Solution at Various Temperatures
Wt.% 10oC 20oC 30oC 40oC 50oC 60oC
15 1.142 1.137 1.133 1.123 1.118 1.112
16 1.151 1.147 1.142 1.133 1.128 1.122
17 1.161 1.157 1.152 1.142 1.137 1.131
18 1.171 1.166 1.162 1.152 1.147 1.141
19 1.181 1.176 1.172 1.162 1.156 1.151
20 1.191 1.186 1.181 1.172 1.166 1.160
21 1.201 1.196 1.191 1.181 1.176 1.170
22 1.211 1.206 1.201 1.191 1.186 1.180
23 1.221 1.216 1.211 1.201 1.196 1.190
24 1.231 1.226 1.221 1.211 1.206 1.200
25 1.241 1.236 1.231 1.221 1.216 1.210
26 1.251 1.247 1.242 1.231 1.226 1.220
27 1.262 1.257 1.252 1.241 1.236 1.230
28 1.272 1.267 1.262 1.252 1.246 1.240
29 1.283 1.278 1.272 1.262 1.256 1.250
30 1.293 1.288 1.283 1.272 1.267 1.261
31 1.304 1.299 1.293 1.283 1.277 1.271
32 1.314 1.309 1.304 1.293 1.287 1.281
33 1.325 1.320 1.314 1.304 1.298 1.292
34 1.336 1.331 1.325 1.314 1.308 1.302
35 1.347 1.341 1.336 1.325 1.319 1.313
36 1.358 1.352 1.347 1.341 1.336 1.330
37 1.352 1.363 1.358 1.352 1.347 1.352
38 1.380 1.374 1.369 1.363 1.357 1.351
39 1.391 1.385 1.380 1.374 1.368 1.362
40 1.402 1.396 1.391 1.385 1.379 1.373
2. The electrolyte must be sampled on both sides of the EC, and the results
averaged. Use a stainless steel, polyethylene, or polypropylene container
for the samples.
3. With the system OFF and depressurized, remove the tube fitting caps at
4-10
the electrolyte drain points at valves 110 and 210.
5. Remove and discard a small amount of KOH to be sure that the sample is
not from a stagnant area.
6. Collect the KOH, measure the temperature and then the specific gravity.
8. Repeat this procedure for the opposite side of the generator and average
the results.
The visual appearance of the two KOH samples will differ somewhat. This
is normal due to the difference in electrodes and corrosion characteristics
of the two sides. The normal color for used KOH is clear to a light yellow.
Both sides may exhibit some darkening due to residue from the negative
electrodes (typically a fine suspension in the hydrogen sample giving a
cloudy appearance) or due to the gradual effects on internal metal
surfaces.
9. If the average concentration is outside the normal range, you must correct
it. Usually, adjustment is required because the concentration is low. You
can increase the concentration by removing a calculated amount of KOH
and replacing that amount with a more concentrated solution (typically
45% wt). The following formula gives reasonable results if the volume at
time of measurement was within the normal operating range of the
generator. You must know the concentration of the fresh KOH whether it
is supplied as liquid or mixed using pellets.
or
10. Using a funnel, you can add small quantities of KOH at the top of the
4-11
oxygen side phase separator.
11. If the concentration is too high, dilute the solution according to the data
given in TABLE 4-22.
12. When the concentration has been corrected, clean the KOH from the pipe
connections and replace the caps.
1. The system control power must be ON, so that inert gas can be used. A
container of approximately 70 gallons (265 liters) is required.
2. Drain the system one side at a time or both sides together by connecting
tubes to both sides at the same time.
3. Connect tubing to the drain ports at valves 120 and/or 220 and place the
tubes in a suitable receptacle.
6. Turn ON the inert gas supply and reduce the facility inert gas regulator to
less than15 PSIG (1 Bar).
4-12
The inert gas will immediately begin forcing the electrolyte out of the
system.
7. Turn the inert gas ON and OFF at the touch screen every few minutes to
maintain within 3 to 6 PSIG (0.2 to 0.4 Bar).
8. When liquid is drained, gas bubbles cause the drain tube to move.
9. Close valves 120 and 220 and wait a few minutes. This is done because
there is typically slightly more liquid in the electrolyte filter at the time the
pump suction piping is empty. Within another few minutes of closing 120
or 220, the filter should be empty and gas will again be noted in the tube.
10. Open valves 120 and 220 again until the drain tubes move, then close110,
210, 120, 220.
11. If necessary for heat exchanger service, place a suitable pan or bucket
under the pipe between the heat exchanger and the filter vessel.
12. Remove the cap at the bottom of the pipe and drain liquid from the heat
exchanger.
13. Check the O-ring, clean it, apply Fluorolube® grease, and install the cap.
Module stack load can be reduced over significant operating periods due to
thermal cycling and creep. This can lead to external leakage. Retorque the
module every six months; more often if the generator is subject to repeated
heating and cooling cycles.
2. On the power supply panel, turn the voltage and current limit
potentiometers down to the zero position.
3. Turn OFF the facility power at the input to the DC power supply.
4-13
4. Remove the polycarbonate positive endplate shield.
5. Check and tighten the tie rods in the numerical order stamped on the end
plates. It is necessary to hold one nut (typically the positive end) with a
wrench, while applying measured torque to the negative end. Use the
deep socket supplied with the generator commissioning equipment,
attached to a torque wrench with a range of at least 300 FT-LB (407 N-M).
6. Before applying measured torque, verify that the threads are not galled or
frozen. Turn the nut in both directions to verify free movement with
respect to the tie rod.
7. If the threads are tight, remove the nut, clean the threads, and apply
Fluorolube® lubricant. Loosen the nut of only one rod at a time.
9. If electrolyte has leaked from the module, clean the exterior of the module
and the tie rods with a mild solution of boric acid in water (3-5%). Rinse
with clean water and dry thoroughly using dry air or nitrogen. Use caution
to prevent water from entering the tie-rod holes in the end plates.
1. Refer to FIGURE 4-1. Remove the four screws that secure the
pump/motor bracket to the motor.
4-14
The force of the drive magnet will be felt as the components are
separated.
6. Place the pump on a flat surface with the inlet of the head facing down.
7. Remove the screws that seal the liquid loop against the pump/motor
transition bracket, and separate the pump head from the impeller magnet
housing.
4-15
FIGURE 4-1 Electrolyte Pump
4-16
8. Carefully lift the impeller off the spindle.
9. Inspect the spindle for cracks, wear or a loose fit in the pump head.
The spindle is bonded to the stainless steel fitting which is threaded into
the center of the head. The fitting is a left hand thread.
10. Inspect the impeller center bearing for wear. Replace any worn parts.
11. At the motor, check for a tight fit of the drive magnets and inspect the
magnets for breakage. If the drive magnet assembly requires removal, be
sure to mark the position on the motor shaft.
12. Assembly is the reverse of the above. Wipe the internal parts, fitting
threads, and O-ring grooves clean. Replace the O-ring seals at the pump
impeller housing and the inlet and outlet CPV fittings, using a light coating
of Fluorolube® grease. Hold the motor/drive magnet firmly when sliding
the assembly back over the impeller housing, as the magnetic forces will
be strong.
Facility cooling water flows through one side of the electrolyte heat exchanger,
hence the flat plate’s surfaces are subject to deposits that can interfere with flow
and heat transfer. Because such conditions are strongly dependent on quality of
the facility cooling water, the maintenance interval for this procedure should be
adjusted accordingly. Teledyne recommends installing water filters on the facility
cooling water lines to reduce the amount of fouling and interval for maintenance.
1. Draining the electrolyte from the generator loop and close the facility
cooling water isolation valves.
2. Loosen the CPV fittings at the heat exchanger and remove the heat
exchanger from the gas cabinet. Be cautious of residual KOH in the heat
exchanger.
3. While the heat exchanger is out of the EC, flush water into the outlet
connection (back flush) on the water side of the heat exchanger. Any
debris should be forced out with enough flow.
5. Check the KOH side for any residue and back-flush it with demineralized
water if necessary.
4-17
6. Install the heat exchanger using new O-rings (with Fluorolube grease) at
the CPV fittings.
Regular checking of the flow switches is critical. If the flow switch does not detect
low flow, serious damage to the electrolysis module can result.
This check is performed while the generator is in operation at a low production rate
or when the generator is not producing gas but the pumps are operating and there
is no alarm.
Close the ball valve downstream of the electrolyte pump (108 or 208) and in the
electrolyte loop in which the flow switch is installed. Ensure that the system shuts
down and a flow switch alarm is indicated on the touch screen. Open the valve
and reset the generator and ensure that the pumps are operating for several
seconds before restarting gas generation. Repeat for the other flow switch(s).
Normally the flow switches only need to be checked. However, occasionally the
sensors may need to be adjusted to properly protect the generator. Below is a
procedure for adjusting the Flow Switch Low Flow Set-point.
a. Turn the potentiometer (R26) next to the red light to the left (counter-
clockwise) until the red light goes out. Continue turning R26
approximately 20-30 degrees further.
b. Verify that the flow switch still works by shutting off the KOH pumps
and the red light should come on.
c. Next, with the KOH pumps running, close the manual valve on the
KOH piping and the red light should come on and the alarm should
activate.
d. If the red light does not come on then turn the potentiometer (R26)
clockwise until it comes on. Then test it per the instructions above.
4-18
5. The adjustment of the set point may take a couple of iterations of stopping
and starting the KOH pumps.
6. If the lights on the flow switch do not turn on then check the wiring.
7. If the red light won’t go out at all, then the flow switch is probably bad.
Clean the electrolyte filters every three months or when low flow shut downs occur
due to high filter pressure drop.
Perform this procedure when the electrolyte has been drained from the system. A
torque wrench up to 120 FT-LBS (163 N-M), and a 1-1/4 inch standard socket are
required for reassembly. A new gasket is required for the lid of the filter. Have a
container available to transport the cartridges to the place where they will be
cleaned.
2. Remove the drain cap. Open valve 110 or 210 to drain any remaining
liquid from the filter housing. Close the valve and replace the drain cap.
3. Gradually loosen the filter lid fasteners in small increments. Remove the
fasteners and lid being careful not to damage mating surfaces of the
flange or lid.
4. Loosen the filter cartridge hold-down hardware and remove the six
cartridges. Inspect the Teflon/fiber gaskets. These may be reused unless
damaged or worn. Remove the gaskets and set them aside until after
cleaning.
6. Install the clean filters and two Teflon/fiber gaskets, one each at the top
and bottom. Tighten the hold-down fasteners for the six cartridges.
7. Install a new Teflon gasket and place the lid on the vessel.
4-19
8. Install the screws, lock washers, flat washers and nuts.
10. Filter cartridges may accumulate deposits that cannot be removed. In this
case, replace the cartridges.
1. The filter cartridge is easily accessed by removing the tube fittings of the
trap assembly located below the filter housing. Remove the housing
assembly by hand or, if necessary, with the assistance of a strap wrench.
2. Remove both the nut holding the cartridge in place and the cartridge.
3. Inspect the three seals inside the housing. Two of the same size are for
the filter ends. One is a larger diameter seal for the clamped housing.
5. Install a new cartridge, making sure the o-rings are sitting properly.
Replace the housing and trap assembly. Leak check all components
when the system is pressurized.
NOTE: A gas cooler and dehydro tank are used only in "C" model
generators.
Facility cooling water flows through the condensers and gas cooler; hence, the
inside surfaces are subject to deposits that interfere with flow and heat transfer.
Because such conditions are strongly dependent on quality of the facility cooling
water, the maintenance interval for this procedure should be adjusted accordingly.
4-20
The system must be OFF, depressurized, and purged with nitrogen, since the
hydrogen side will be opened. Remove condenser and inspect the ports. Back
flush through the water connections. If the water ports indicate a lot of fouling,
clean with a diluted nickel scale remover solution. A 5% phosphoric acid or oxalic
acid solution may be used. When back flushing the condenser, do not heat the
acid solution. Flush the condenser with fresh water after cleaning.
Pressure switch 005 signals the PLC to alarm if the facility air supply falls below 70
PSIG (4.8 Bar). The switch can be adjusted with the generator OFF and the
instrument air supply turned OFF.
1. Remove the switch adjustment cover at the top. On the back of the
switch, remove the enclosure cover and expose the electrical contacts.
2. Disconnect one of the two wires from the PLC from the connection
terminal.
3. Set up an ohm meter across the two terminals (normally open and
common). Read the nameplate on the switch to determine which direction
to turn the adjustment screw.
6. Allow the pressure to fall slowly and observe the pressure as the contacts
open. The set point is 70 PSIG (4.8 Bar). Adjust if necessary and check
again.
7. Connect the wire lead, connect the tubes, and replace the cover plates.
Leak check the switch when the air system is again turned ON.
The product hydrogen product gas filters (316, 317) and, for a "C" model, the
oxygen gas filters (416, 417) can be easily replaced on a yearly basis, or when
system pressure drop indicates clogging.
4-21
2. Remove the filter body from the dryer tube pipe fitting.
3. Remove the filter outlet tube fitting from the used filter.
4. Clean the pipe threads on the tube fitting and dryer fitting.
5. Using Teflon pipe thread tape, install the tube fitting in a new filter body,
being sure the flow arrow is properly oriented.
7. Install the remainder of the manifold tubes and tighten all fittings. Leak
check this manifold when the system is under pressure.
There are two gas delivery check valves in a standard EC generator, and 4 on a
"C" model generator. The configuration is shown in FIGURE 4-2. To assure that
internal parts move freely and that small passages do not clog and cause high
pressure drop, disassemble the valve for inspection and cleaning.
1. Remove the valve by loosening the tube fittings in the dryer discharge
manifold and then removing the valve from the manifold (pipe threads).
2. Disassemble the valve using the two special tools provided with the EC
commissioning package, while referring to FIGURE 4-2.
One tool is to hold the internal spring guide and the other is to loosen the
nut.
Seals are provided with the commissioning spares or can be ordered from
the factory.
4. Replace the check valve if there is any damage or binding of parts that
cannot be corrected. Install the valve, tighten all tube fittings and bubble
check the fittings when the system is pressurized.
5. Remove and inspect other check valves located at the feedwater inlet to
the phase separator (703, 707), the nitrogen inlet lines to the hydrogen
and oxygen phase separators (507, 509, 508, 512), and the hydrogen vent
4-22
line (376) once per year for free movement, and signs of leakage or
clogging.
Seals for the nitrogen and water check valves are provided with the
commissioning spares kit or can be ordered from the factory.
4-23
FIGURE 4-2 Check Valves
4-24
4.5.13 Cleaning and Inspecting Gas Orifices
All gas orifices are critical maintenance items due to the very small passages
(especially on the hydrogen side) and the possibility for clogging over a period of
time.
A colored band on the orifice fitting identifies gas service. Yellow is for hydrogen
service, green for oxygen service, and white is for the trap purge line (from 374 or
474) found on either side of the system. Orifices of the same color are not always
identical in size. Use caution to avoid confusing different parts.
4. Before installing new or clean orifices, check the adjacent tubes and
valves for small deposits. Blow the tubes and valve bodies with
compressed inert gas if necessary.
5. After reinstalling the orifice(s), check all tube fittings with bubble solution
while the system is pressurized.
4-25
4.5.14 Cleaning Solenoid Valves
the inert gas supply (504) and the back-up supply to the instrument air
system (010), which are of the same type
the feedwater supply valve (702)
the pneumatic control valve assembly. This assembly consists of
valves 003, 006, 009, 011, 014, and 016.
1. Disassemble valves 504 and 010 according to FIGURE 4-3 and 702
according to FIGURE 4-4.
Internal part repair kits for these valves are available from the factory, as
are replacement solenoids. As the valves are relatively small, it is
generally more practical to replace as a complete assembly.
3. Disconnect tubes and electrical connectors and detach from the bracket.
Removing each individual valve from the base will enable inspection of the
gasket and a partial view of the valve internals through the connection
ports.
4. Verify that the valve parts are clean and move freely, and that the gasket
is in good condition.
5. Install the module, making sure tubes and electrical connectors are placed
on the correct operators.
6. When the air system is turned ON, leak check the operators around the
gaskets.
4-26
FIGURE 4-3 Three-Way Solenoid Valve
4-27
FIGURE 4-4 Two-Way Solenoid Valve
4-28
4.5.15 Replacing Gas Dryer Molecular Sieves
NOTE: The oxygen side dryers 414 and 415 (1 and 2) do not
contain catalyst. When refilling these dryers, skip all
directions associated with catalyst in the following
procedure.
a funnel or other suitable means for loading the molecular sieve and
catalyst into the dryer.
molecular sieve material - 28 pounds (12.7 KG) per vessel. Molecular
sieve material is available through Teledyne Energy Systems under
catalog number 01091 and is supplied in drums containing
approximately 300 pounds (136 KG) of material.
catalyst material - 0.7 pounds (0.32 KG) per hydrogen dryer. Catalyst
material is available through Teledyne Energy Systems under catalog
number 01017.
a scale suitable for accurate measurement of weights up to 2 LBS (1
KG), in .01 LB (5 gram) increments.
each dryer group (hydrogen or oxygen) contains four vessels.
1. With electrical power OFF at the input to the EC power supply, remove the
dryer protective shields and remove the electrical enclosure covers.
3. Mark each lead pair so it will be reconnected to the proper vessel when the
procedure is completed.
5. Remove the two outside vessels first, then the inside pair.
6. Remove the tube caps from the top of the dryer vessel.
7. Turn the dryer upside down and allow the old sieve material to pour into a
suitable container for disposal.
4-29
CAUTION: The sieve may become hot on contact with
moisture or even moist air.
8. Reinvert the vessel and support the dryer in a vertical position, taking care not
to damage the 1/2-inch tube fitting at the bottom of the dryer.
10. Measure out 1.3 ± 0.1 pounds (590 g) of molecular sieve material and pour
into the dryer. Use both ports and attempt to achieve an even fill.
11. For a hydrogen dryer (314 or 315), measure out 0.08 ± 0.01 pounds (36 g) of
catalyst material and pour into the dryer. Use both ports and attempt to
achieve an even fill.
12. Repeat steps 10 and 11 until a total of eight catalyst layers have been added.
13. Fill the remaining cavity with molecular sieve material until the level of fill is 7
± 2 inches (130-230 mm) below the fill port.
14. Reinstall the tube caps and the dryers in the system.
16. Leak check the installation by pressurizing the system with inert gas
(nitrogen) to 50 PSIG (3.5 Bar) and using a soap solution on all dryer fittings.
Recheck the fittings for leakage the next time the system is operated.
The 303 or 403 trap protects the gas sensors from moisture and residual KOH.
The internal sieves can be replaced when the system is OFF and purged to
remove hydrogen. The beads used in the filter tank should be deactivated beads
saturated to ambient moisture conditions. Deactivated beads may be prepared
from dry beads by first wetting the beads with clean water. Use caution because
dry beads become very hot when wetted. Next, spread the beads out on a clean
surface and simply allow them to dry to ambient conditions.
2. Remove one or both end fittings in order to remove the old material.
4-30
4. Fill with approximately 0.2 LBS (90 grams) of new material. Do not overfill, so
that the fittings and screens will go into place.
6. Install the trap in the system and bubble check threaded fittings when the
system is under pressure.
Due to the flow of cooling air through the power supply, dust can accumulate on
the inside surfaces of the power supply and interfere with proper cooling. At this
time, also check the major wire connections for loose fasteners.
1. Remove and lock out facility power following prescribed plant safety
procedures.
3. Use a vacuum cleaner and light brush to remove dirt from internal
components.
6. Open the side control enclosure panel and inspect the terminal
connections from the gas cabinet cables for tightness.
7. Inspect the terminal connections at the three pump motor starters for
tightness.
Regulators 309 and (for a "C" model) 409 protect the EC generator against
overdemand. As system pressure falls below 70-80 PSIG (5 Bar), the regulators
should close.
4-31
The simplest way to verify this is by observing gas flow through a facility flow meter
such as a rotameter or electronic mass flow sensor.
2. Observe the system pressure on the touch screen just as flow is indicated.
3. If necessary, loosen the lock nut and turn the adjusting screw.
5. If facility flow meters are not available, the valve can be removed from the
generator and set using inert gas or instrument air pressure.
Back pressure regulator 340 is located between the hydrogen delivery pipe and
the vent system. It begins to open if the system pressure exceeds 165 PSIG (11.4
Bar). The valve has an adjusting hand-wheel.
1. One method of checking the valve is to remove it from the system and
connect to an inert gas source and pressure gage on the inlet side; and to
a tube leading to a container of water on the outlet side.
2. Apply pressure and observe the point at which the valve opens.
3. Adjust the hand-wheel so that the valve begins opening at 165 PSIG (11.4
Bar).
The adjustment can also be made with the machine in operation. However, this
requires the use of an interface with the PLC to temporarily override the high
pressure shut-down alarm, which occurs at 170 PSIG (11.7 Bar)). Contact
Teledyne Energy Systems for more information.
Perform this test once a year to be sure that instrument air is not leaking into the
system from the trap purge control, dryer bypass, and system vent valves. This
procedure applies to the following valves:
4-32
Depressurize the system and purge it with inert gas before performing this
procedure. The source of inert gas or instrument air must be at 80 PSIG (5.5 Bar).
3. Apply pressure to the operator and look for signs of leakage into the valve
body from the actuator (submerse the body section in water, if necessary).
4. If there is no leakage, install the valve using care to clean pipe threads.
Use Teflon tape, if applicable.
5. If the valve leaks, replace the internal seals or replace the valve as a unit.
6. When the system is again under pressure, bubble check all of the
connections.
An overall leak check is recommended once per year. Use a soap bubble solution
to check portions of the system under pressure.
In some cases, perform the check during portions of the dryer cycle. For example,
the tube between the dryer selection valve (313, 413) and the dryer vent valve
(370, 470) will be under pressure while the off-line dryer is repressurizing. The
same is true for various instrument air lines and associated fittings.
Check the combustible gas monitor probes (305, 405) by flowing a mixture of air
4-33
with a slight concentration of hydrogen gas, and observing the rise in temperature
of the probe. This procedure requires a cylinder of calibration gas, 2% Vol.
hydrogen in air with a suitable pressure regulator, and a source of inert gas, such
as nitrogen.
Perform this test with gas generation OFF, and the system purged with inert gas,
to remove hydrogen. The control power must be ON so that the probe
temperature can be observed at the touch screen.
3. Connect the tube in parallel to both the inert gas and calibration gas
source.
4. Establish a flow of nitrogen through the regulator and adjust the rotameter
valve approximately 90% maximum flow as indicated on the 310 or 410
rotameter.
5. Turn off the nitrogen and establish the same flow of calibration gas
through the sensor.
The temperature should rise and stabilize between 110 and 160 C.
8. When the system is restarted, adjust the 310 and 410 flows as described
in section 3.
The liquid level control loop consists of the 24-VDC (966) power supply, transmitter
113 and the PLC input card. The level signal is 4-20 mA current.
4-34
The liquid level transmitter (113) has zero and span adjustments. The instrument
is calibrated based on "0" being at the point of connection to the instrument, and
the span is 37 inches (940 mm) above 0. A simple calibration tool can be made
using a valve and plastic tube, as shown in FIGURE 4-5. FIGURE 4-6 shows the
use of the tool.
4-35
FIGURE 4-6 Liquid Level Calibration Setup
2. Place a container suitable for KOH under the fittings to be loosened in the
next step.
4-36
3. Remove the caps and open the manual valves at transmitter 113, to drain
liquid from the sensing head.
5. Disconnect the tube between the bottom of the hydrogen phase separator
(101) and the transmitter instrument connection.
7. Fill the tube with water darkened with a dye (food coloring).
8. Open the tool valve to allow the liquid level in the tube to fall to the "O"
mark.
10. If an adjustment is required, remove the nameplate and expose the zero
and span adjustment screws.
11. Adjust the zero until the touch screen indicates 0% liquid level.
13. The touch screen should read 96 or 97% (it will not indicate 100%).
14. If it is low, adjust the span screw until a maximum reading (96 or 97%) is
obtained.
15. Repeat the zero and span checks, as sometimes an adjustment can affect
the opposite end of the scale.
16. Remove the tool and install the tube to the phase separator.
17. Observe these fittings for signs of liquid leakage when the machine is
operational.
4-37
4.5.24 Adjusting Differential Pressure Control System
These steps pertain to the pneumatic differential pressure transmitter 328 and I/P
transmitters 018 and 019. These adjustments are performed at the factory and are
normally not required at the site unless there are problems or parts are replaced.
1. The instrument air system must be ON, regulator 002 must be adjusted to
20 PSIG (1.38 Bar), and there can be no leakage in the instrument
plumbing. Hydrogen must be purged from the system using the inert gas,
because the hydrogen side phase separator will be opened.
5. Verify that the two bleed valves on the 328 transmitter body are tightly
closed.
6. Loosen and remove the CPV nut from the 2 fittings at 328.
7. At the opposite end of each tube (at the respective phase separator),
loosen the CPV nut and swing the tubes out of the way of the transmitter.
9. Fill the manometer to at or near the midpoint zero lines, with water colored
with a few drops of food coloring.
10. With the inert gas supply valve closed and the bleed valve opened 5 or 6
full turns, open the inert gas cylinder valve and adjust the bottle regulator
to no more than 15 PSIG (1 Bar).
4-38
FIGURE 4-7 Differential Pressure System Calibration
2. Carefully open the inert gas supply valve until the reading is within an inch
or two of the desired reading. Then use the bleed valve to "fine tune" the
indication.
5. When a zero adjustment is complete, turn OFF the inert gas supply valve.
6. Move the manometer tube fitting on the manometer from the oxygen side
4-39
to the hydrogen side.
10. Apply various pressures between 0 and 20 inches water on each side in
order to verify correct LCD output
NOTE: If I/P transmitters 018 and 019 produce the correct pressure
signal according to the manometer indication and the vent valves
430 and 330 controllers do not correspond, then contact Teledyne
Energy Systems for more information.
Adjustment procedures for the Badger vent valves are found in the
manufacturer's manual in the appendix. Do not attempt adjustments
or modifications to these valves other than scheduled maintenance.
The readings should correspond. The precise value stored in the PLC can
be observed using the optional PLC hand-held interface terminal, or with a
personal computer and an optional interface card and program. The
address of the delta-p value is D0076, and is expressed on a scale of 0 to
40 inches corresponding to -20 to +20 inches on 007/008. The value will
be "20" with 0 delta pressure.
I/P transmitters 018 and 019, similar to transmitter 013, send an instrument air
output signal based on an input current between 4 and 20 mA.
To measure the pressure, install an accurate 0-20 PSIG or 0-2 BARG pressure
4-40
gauge in the spare outlet port of 017.
The most likely cause of erratic feedwater readings is a faulty probe. A feedwater
probe that is suspected of not indicating correctly should be removed and checked.
Turn off the feedwater supply and open the feedwater drain port to drain the
feedwater plumbing. Remove the probe by unthreading it out of the plastic tee. A
dry probe in air should indicate green on the Feedwater touchscreen. If not, the
probe should be replaced. The probe is easily replaced as a unit, and there is no
calibration or adjustment.
4-41
SECTION 5 Trouble-Shooting and Repairs
TABLE OF CONTENTS:
5-1
5.1 General
This section contains trouble-shooting steps and procedures for the likely
causes of malfunctions or poor machine performance.
Refer to P&ID and electrical diagrams supplied with the generator while
troubleshooting.
5-3
Check for voltage drop across contactor
Check overload device status at motor starter
May require adjustment for facility voltage
May require resetting
Check 115 VAC signal to motor starters
Output light at PLC digital output card coming ON when
RESET is pushed
Check wiring to TB10 and to power supply and MS2 or MS3
Check voltage at drive motor
Faulty drive motor
Check for excessive current
Motor internal mechanical drag
5-5
5.3.6 High Hydrogen-in-Oxygen
5-6
5.3.9 High Differential Pressure
5-7
Thermocouple 418 failure
Check LEDs on UPS; then review the troubleshooting section (pp. 23) in
the UPS manual for information on how to proceed.
The user will install and use gas analysis equipment necessary to assure
the level of purity for his process. This may include monitoring of
moisture, nitrogen content, oxygen in hydrogen, hydrocarbon content, or
other contamination.
5-8
High moisture is the most common result of a system malfunction. Other
possible impurities are
the constituents of air that can enter the system from the facility
water supply (entrained bubbles)
the inert purge gas (usually nitrogen)
oxygen in the hydrogen
hydrogen in the oxygen
Because of the nature of the process and because the required inputs
include only water and nitrogen, it is nearly impossible to detect
hydrocarbon contamination in the product gases.
For electrolysis, one of the most common and effective means of assuring
proper generator function is to monitor gases for the presence of moisture.
When traps, filters, and dryer system components malfunction or are not
maintained the moisture content of product gases increases. Section 4
contains procedures for checking and replacing the various components.
Verify the dryer tube heaters and heater circuits (relays 922, 929, and for
a "C" model, 964 and 965). When in the heating mode, the dryer tubes
should be hot on the surface at both the top and bottom halves. The
current to each dryer heater should be 6.0 to 6.5 amperes, and the current
to each dryer tube should be above 12 amperes. If a heater is defective,
the dryer tube must be replaced.
There are different trim sets for the hydrogen and oxygen sides. These
are listed on the name plate. Remove one valve at a time to avoid
confusion. When the valve is installed, be sure the flow arrow points
toward the vent connection interface.
5-10
5.4.5 Cooling Water System Problems
The controller and transmitter manuals are included in the appendix. The
013 transmitter contains zero and span adjustments that are made to
precisely correlate a 4-20 mA input signal to a 3-15 PSIG (0.21-1.03 Bar)
output signal. Consult the applicable sections of the manufacturer's
manual before performing this adjustment.
The cooling water control valve can be removed for repair of the control
section (top works), stem packing, or the valve and seat assembly. The
manufacturer's manual in the appendix contains detailed procedures and
illustrations. Parts for the stem packing and control section are provided
in the commissioning spare parts with the generator.
There will be normal fluctuation of the DC current once the system has
reached a stable operating condition. Consider the system stable if the
deviations from the pressure set point are within 0.1 to 0.5 PSIG (0.007-
0.03 Bar), and occur over a relatively slow period (once or twice per
minute). Before investigating a possible control problem, the system must
be completely stable. This means the KOH temperature must be stable
for 10 to 15 minutes with the cooling system in control at the set point;
there has been no change in demand for 10 to 15 minutes; and there has
been no change in dryer regenerating status for 10 to 15 minutes. If the
pressure does not become stable, check various system features.
Verify that disturbances are not actual pressure fluctuations, such as from
a problem with differential pressure controls or fluctuations in user
demand.
Check the power supply controls that process the signal from the PLC.
The procedure and check values depend on the type of power supply,
which is identified by its serial number. A qualified technician must
perform this procedure. Contact Teledyne Energy Systems for information
and guidance on verifying power supply controls.
This condition exists when module current is insufficient for the level of
5-11
user demand for hydrogen or oxygen, and the generator is unable to
supply adequate gas flow. It is caused by a loss of product gas to some
other portion of the system or to external leakage.
When the condition exists, check for a high flow of gas at the hydrogen
and oxygen dryer vent exits. When the dryer regenerating system is in the
PURGE or HEATING mode, this flow should be very low: 10 to 30 SLM of
hydrogen (5 to 15 SLM oxygen). When the regenerating system is in the
COOLING mode, this flow increases up to 70 SLM hydrogen (35 SLM
oxygen). When the regenerating cycle is in the FILLING mode, there
should be no flow at this vent.
Excessive flow through the dryer vent system may indicate that valve 313
(standard model) or 313, 406, 407, 413 ("C" model) is not functioning
properly. The result is unintended gas flow to the off-line dryer. Check
the operating cylinder for leakage of instrument air. Check the instrument
air supply via solenoid valve 003 or 014 to the operating cylinders. These
valves should always be in the opposite condition to one another.
Another less likely cause of high flow in the dryer vent line is a faulty
orifice (304, 334) or, for a "C" model (404, 434).
Another cause of excessive flow through the dryer vent system is failure of
valve 335 or 435 (for a "C" model) to close properly at the correct time in
the regenerating cycle. The valve should be open for COOLING and
FILLING, and closed at other times. Remove and leak check the valve. If
necessary, check the controls for the valve, including the PLC output and
solenoid valve 006.
Potential leak points other than the dryer system include valves 374, 474
(for a "C" model), or the system vent valves 320 and 420. These can be
removed and checked. Also, check the controls of these valves: solenoids
011 for the trap vent valves and 009 for the system vent valves.
5-12
5.4.8 O2 Side Catalyst Tank Can’t Be Maintained at Set Point Temperature
Using an inductive ammeter, measure the current at the heater wire lead
at relay 981. Te current should be 4 - 5 amperes. Verify that the relay is
switching and passing current to the heater circuit.
If the supply current to the heaters is low, first check the output voltage at
TB4 in the power supply.
If the current is less than 230 volts, change the taps on the transformer to
increase the voltage to 230 - 240 VAC.
If the current is low with the correct supply voltage, then one or both of the
rod heaters in the catalyst tank is damaged and must be replaced.
Lay the assembly on a table. Remove and replace the heaters, being
careful not to spill any catalyst or damage heater leads. Re install the tank
in the generator. Reconnect the heater and thermocouple connections,
being careful that no wires are near the tank surface, which can reach
temperatures in excess of 300 degrees C.
Using an inductive ammeter, measure the current at the heater wire lead
at relay 902. Te current should be 11 to 13 amperes.
If the supply current to the heaters is low, first check the output voltage at
TB4 in the power supply.
If the current is less than 230 volts, change the lead connections on the
transformer to increase the voltage to 230 - 240 VAC.
5-13
If the current is low with the correct supply voltage, then one or more of
the four band heaters around the catalyst vessel is open and must be
replaced. The problem could also be heater wire inside the catalyst
vessel's sheet metal enclosure.
Flow over the combustible gas probe 305 or 405 is controlled by a forward
pressure regulator needle valve. Verify proper function of the controller by
observing the rotameter at controller 310 or 410. It is normal for the flow
to fluctuate somewhat with operating conditions. The probe functions
properly within a reasonable range of the recommended setting in Section
3. For the hydrogen side, the range is 20 to 30. For the oxygen side, it is
50 to 75.
5-14
5.4.11 Module Cross Leak Test Procedure
Contact Teledyne Energy Systems if you think that this test is necessary.
They will provide procedures and guidance.
There are two basic non-metallic seal materials specified throughout the
EC system. Teflon is a body and stem seal in ball valves and the gasket
in the filter vessels. Teflon is also used as a pipe thread sealant.
Ethylene, propylene, ter-polymer (EPT) is used for O-rings. Both
materials are compatible with all of the process materials. Other types of
seal material may be found, depending on the component, in the gas
delivery systems.
If the 1.0-inch or 1.5 inch KOH ball valve seals are replaced, torque the
5-15
body nuts as follows:
Leaks in the water control valve 609 can be repaired with kits provided
with the generator. These include a body gasket and a stem packing
replacement kit.
5-16
SECTION 6 Spare Parts List
Schematic Reference
# Part Number Part Description
001 ES-HGS143064-013 Filter Regulator (80-100 PSIG and 5- 7
002 ES-HGS143064-005 Filter Regulator (5-30 PSIG and 0.3- 2.0
ES-052450 Replacement Filter for 001, 002
Regulators
003 ES-103469 Pneumatic Solenoid, Double Acting
(Parker)
005 ES-050345 Pressure Switch, Instrument Air Supply
006 ES-103468 Pneumatic Solenoid, Single Acting
(Parker)
009 (See 006)
010 ES-050011 3-Way Solenoid Valve
ES-101425 Rebuild Kit for 50011
ES-052568 Replacement Coil for 50011 Solenoid
Valve
011 (See 006)
013 ES-103870 Current to Pressure (I/P)
014 (See 003)
016 (See 006)
018 (See 013)
019 (See 013)
100 E12100-009 Electrolysis Module, 500 SLM
E12100-019 Electrolysis Module, 600 SLM
E12100-029 Electrolysis Module, 750 SLM
E12100-039 Electrolyte Module, 500 SLM (FOR EC-
1000)
102 ES-E14072-009 KOH Pump, H2 or O2 Side, 3-Phase
Motor
ES-E14072-019 Pump Head
ES-550A1230101- Pump O-Ring Seal
031
ES-551A1400097- Insert Assembly (Spindle)
009
ES-551A1400132- Impeller Magnetic Housing
001
ES-551A1400133- Impeller Assembly
001
ES-103554 Motor, KOH Pump
103 ES-E24018-001 Heat Exchanger, KOH H2 or O2 Side
106 ES-100477 Ball Valve, 1.5 Inch KOH
ES-050733 Seal and Seat Replacement Kit for 106
107 ES-E14102 KOH Filter Vessel Assembly, H2 or O2
Side
ES-050015 Filter Cartridge for 107, 207 (6 per Side)
6-1
Schematic Reference
# Part Number Part Description
ES-050019 Teflon Gasket
108 (See 106)
109 E14177-009 Flow Switch
110 ES-050939 Ball Valve, System Drain/Fill
111 ES-052012 Thermocouple, KOH Temp
ES-052013 Pipe Clamp for 111, 211, 232 T/C
113 ES-HGS143001- Liquid Level Transmitter
007
ES-550A1230101- O-Ring Seal for 113 Transmitter
081
115 ES-050938 ACE Valve
117 ES-050734 Ball Valve, KOH Crossover
ES-050735 Repair Kit for 117 Ball Valve
118 ES-100477 Ball Valve, KOH Crossover
120 ES-050938 Ball Valve, Drain/Fill
202 (See 102)
203 (See 103)
206 (See 106)
207 (See 107)
208 (See 106)
209 (See 109)
210 (See 120)
211 (See 111)
220 (See 120)
232 (See 111)
301 ES-105196 Condenser, H2 side
302 ES-E14003-009 Trap, H2 Side
303 ES-551A1400080- Filter Tank Assembly
009
ES-551B2400007- Filter Tank Refill Kit
009
304 HGS140056-009 Orifice Assembly, .005” Diameter H2
Dryer Bypass
305 Gas Mixture Probe (E14134)
ES-M14174-009 Probe Assembly
ES-104438 Flame Arrest
308 ES-E14308-001 Pressure Gauge, H2 Delivery
309 ES-HGS140058- Back Pressure Regulator, H2 Delivery
001
310 ES-104108 Forward Pressure Regulator
ES-104367 Flow Meter
ES-104333 Pressure Gauge
313 ES-E14202-009 Ball Valve, Air Op., Dryer Switching
ES-105069 Actuating Cylinder, Double Acting
6-2
Schematic Reference
# Part Number Part Description
ES-103071 Ball Valve Body, 4-way
314 See Below Hydrogen Dryer Vessels
314-1 ES-E14081-009 Dryer Vessel w/out Chemicals, H2 Inlet
314-2 ES-E14081-010 Dryer Vessel w/out Chemicals, H2
Outlet
315-1 ES-E14081-010 Dryer Vessel w/out Chemicals, H2 Inlet
315-2 ES-E14081-009 Dryer Vessel w/out Chemicals, H2
Outlet
ES-001017 De-oxo Catalyst for H2 Dryer 1 lb per
vessel
ES-001091 Molecular Seive for h2 Dryer 28 lbs
(12.7 KG) per vessel
316 ES-001377 Product Gas Filter, H2
317 (See 316)
320 ES-050949 Valve, Air Operated, Normally Closed
325 ES-HGS143000- Total Pressure Transmitter
007
same as seal for 113
328 ES-102034 Differential Pressure Transmitter (4-20
mA output)
329 (See 308)
330 ES-HGS143063- Control Valve, H2 side Delta-P
003
ES-050922 Valve Trim Kit G
331 ES-050295 Check Valve, Dryer Delivery
ES-050296 Quad Seal for 331 Check Valve
ES-050297 Adjusting Tool
ES-050298 Nut Driver (Tool)
332 (See 331)
334 ES-HGS140056- Orifice Assembly, .017” Diameter H2
029 Dryer SV Bypass
335 ES-050900 Air Operated Valve, NO, Dryer Bypass
336 ES-HGS140056- Orifice Assy, .040, Shut-down Flow
059
340 ES-103235 Back Pressure Regulator, H2 Vent
370 ES-E14096-009 Valve, 2-way NC Air Operated
ES-050938 Valve Portion of 370 Assy
ES-050936 Actuator, Spring Return
371 ES-104022 Coalescing Filter Housing
ES-104023 Replacement Filter Cartridge
372 ES-050944 Valve, 2-way NO, Air Actuated
ES-050293 Replacement Seal
373 ES-551A1400080- Trap, Coal Filter, H2
039
374 (See 320)
6-3
Schematic Reference
# Part Number Part Description
375 ES-E14028-009 Orifice Assembly, .080” Diameter Filter
Drain
376 ES-050159 Check Valve, H2 Vent System
378 ES-050507 Pressure Transmitter, off-line Dryer
380 (See 371)
381 ES-E14200-009 Catalyst Tank, H2 Side
382 ES-052012 Thermocouple
385 (See 301)
401 (See 301)
402 ES-14003-010 Trap, O2 Side
403 (See 303)
404 ES-HGS140056- Orifice Assy, .005” dia, O2 Dryer
019 Bypass
405 (See 305)
406 (See 313)
407 (See 313)
408 (See 308)
409 (See 309)
410 (See 310)
ES-104366 Flow Meter
412 ES-HGS140070- Catalyst Vessel Assy
009
ES-050542 Replacement Band Heater
ES-052570 Catalyst, 10 lbs (4.5 KG) required per
change
413 (See 313)
414 See Below Dryer Vessel, O2 Side
414-1 ES-E14081-009
414-2 ES-E14081-010
415-1 ES-E14081-009
415-2 ES-E14081-010
416 (See 316)
417 (See 316)
418 ES-001025 Thermocouple, Catalyst Vessel
ES-052010 Quick Disconnect for 418
Thermocouple
ES-052011 Rubber Boot for 418 Thermocouple
Plug
ES-001089 Reducing Fitting for 418 Thermocouple
420 (See 320)
426 (See 308)
427 ES-HGS140056- Orifice, .040", O2 Side Vent
069
428 ES-E14073-009 Gas Cooler, O2 Side Catalyst Outlet
6-4
Schematic Reference
# Part Number Part Description
429 (See 308)
430 ES-HGS1430063- Control Valve, O2 Side Delta-P
005
ES-050923 Valve Trim Kit F
431 (See 331)
432 (See 331)
434 ES-HGS140056- Orifice, .028”, O2 Dryer SV Bypass
039
435 (See 335)
470 (See 370)
471 (See 371)
472 (See 372)
473 (See 373)
474 (See 320)
475 (See 375)
478 (See 378)
480 (See 371)
481 M14078-019 O2 Side Catalyst Tank
ES-002764 Replacement Heater Rod
Catalyst (See 412)
482 (See 372)
483 (See 373)
484 (See 320)
485 (See 385)
486 ES-105271 Thermocouple, Cat Tank Control
487 ES-001025 Thermocouple, Cat Tank Alarm
503 (See 308)
504 (See 010)
505 ES-050943 Manual Valve, N2 Supply
506 (See 505)
507 ES-001507 Check Valve, Nitrogen & Feedwater
ES-001124 Quad Ring
ES-001156 Adjusting Tool
ES-001159 Nut Driver (Tool)
508 (See 507)
509 (See 507)
510 ES-103073 Nitrogen Pressure Tranducer
512 (See 507)
530 ES-050021 Relief Valve, Inert Gas Supply
601 ES-050649 Strainer, Cooling Water Inlet
603 ES-050940 Valve, Manual Cooling Water
608 (See 603)
609 ES-050926 Control Valve, Cooling Water Flow
6-5
Schematic Reference
# Part Number Part Description
610 ES-105045 Manual Globe Valve
611 (See 610)
701 ES-HGS140073- Pump Assembly, Feedwater Supply
009
702 ES-050007 Solenoid Valve, 2-way NC Feedwater
ES-101425 Rebuild Kit for 702 Solenoid Valve
ES-052568 Replacement Coil for 702 Solenoid
Valve
703 (See 507)
705 ES-101124 Conductivity Sensor, Feedwater
System
ES-101552 Conductivity Transmitter
707 (See 507)
Operator Interface Box ES-104521 Programmable Memory
Components
ES-105138 Ethernet Switch
ES-105140 Module CPU, Ethernet
ES-105139 Touch screen
ES-103121 Power supply, 60W
ES-103098 Module, Devicenet
ES-103097 Power Supply, PLC
ES-100067 121 Ohm Resistor
Control Box Components ES-104207 Relay, 25 Amp Solid State
ES-103447 Module, Output, AC
ES-103478 Field Bus Coupler
ES-103476 Supply Module
ES-103480 Temperature Analog Input Card
ES-103102 Remote Output Terminal
ES-103101 Analog Input Terminal
ES-103100 Analog Output Terminal
ES-103096 Remote Input Terminal
972 ES-101552 Conductivity Transmitter
PS1 ES-103121 Power supply, 60W
E-Stop ES-103540 Switch Contacts, 2-button, Electrolysis
Enable
6-6