Lecture Notes On Borrowing Costs - 000
Lecture Notes On Borrowing Costs - 000
Definition
Borrowing costs are interest and other costs that an entity incurs in connection with the borrowing of
funds.
Borrowing cost does not include actual or imputed cost of equity capital, including any preferred capital
not classified as a liability pursuant to PAS 32.
Accounting Treatment
Borrowing costs that are directly attributable to the acquisition, construction or production of a qualifying
asset form part of the cost of that asset and, therefore, should be capitalized. Other borrowing costs
are recognized as an expense.
A qualifying asset is an asset that takes a substantial period of time to get ready for its intended use.
That could be property, plant, and equipment and investment property during the construction period,
intangible assets during the development period, or "made-to-order" inventories.
Commencement of capitalization
The commencement date for capitalization is the date when the entity first meets all of the following
conditions:
(a) it incurs expenditures for the asset;
(b) it incurs borrowing costs; and
(c) it undertakes activities that are necessary to prepare the asset for its intended use or sale.
Where construction is completed in stages, which can be used while construction of the other parts
continues, capitalization of attributable borrowing costs should cease when substantially all of the
activities necessary to prepare that part for its intended use or sale are complete.
Disclosure
An entity shall disclose:
(a) the amount of borrowing costs capitalized during the period; and
the capitalization rate used to determine the amount of borrowing costs eligible for capitalization
PROBLEMS
1. On 1 January 2015 The Divine Company took out a 12% P10 million loan to finance the construction
of a building. The key dates are as follows:
1 January 2015 - Loan interest relating to the project starts to be incurred
1 February 2015 - Technical site planning commences
1 March 2015 - Expenditures on the project start to be incurred
1 April 2015 - Construction work commences
1 Nov. 2015 - Substantially all of the activities necessary to prepare the asset for its intended
use are complete
1 Dec. 2015 - Building brought into use
What amount of interest should Divine capitalize for the current year?
2. On 1 January 2015 Imp Company borrowed P6 million at an annual interest rate of 10% to finance the
costs of building an electricity generating plant. Construction commenced on 1 January 2015 and cost
P6 million. Not all the cash borrowed was used immediately, so interest income of P80,000 was
generated by temporarily investing some of the borrowed funds prior to use. The project was completed
on 30 November 2015. What is the carrying amount of the plant at 30 November 2015?
3. Maragondon Company had the following borrowings during 2015. The borrowings were made for
general purposes but the proceeds were used in part to finance the construction of a new building:
Principal Interest
12% bank loan P10,000,000 P1,200,000
15% long-term loan 20,000,000 3,000,000
P30,000,000 P4,200,000
The construction began on January 1, 2015 and was completed on December 31, 2015.
Expenditures on the building were made as follows:
January 1 P8,000,000
June 30 8,000,000
December 31 4,000,000
The capitalizable borrowing cost is
4. During 2015, Grant Industries, Inc. constructed a new manufacturing facility at a cost of
P12,000,000. The weighted average accumulated expenditures for 2015 were calculated to be
P5,400,000. The company had the following debt outstanding at December 31, 2015:
• 10 percent, five-year note to finance construction of the manufacturing facility, dated January
1, 2015, P3,600,000.
• 12 percent, 20-year bonds issued at par on April 30, 2011, P8,400,000.
• 8 percent, six-year note payable, dated March 1, 2014, P1,800,000.
Determine the amount of interest to be capitalized by Grant Industries for 2015.
7. Oceanwide Enterprises, Inc., is involved in building and operating cruise ships. Each ship is identified
as a separate discrete job in the accounting records. At the end of 2014, Oceanwide correctly
reported P5,400,000 as Construction in Progress on the following jobs.
Accumulated Costs
(including 2014
Completion Date interest)
Ship (end of month) December 31, 2014
340 October 31, 2014* P2,300,000
341 June 30, 2015 1,150,000
342 September 30, 2015 1,200,000
343 January 31, 2016 750,000
*Ship 340 was completed and ready for use in October 2014 and will be placed in service May 1,
2015.
Construction costs for 2015, and the dates the expenditures were made, were as follows:
Ship Date Costs
341 April 1 P1,200,000
342 May 1 1,600,000
343 July 1 2,200,000
344 September 1 810,000
345 November 1 360,000
On January 1, 2015, Oceanwide borrowed P2,000,000 specifically for the construction of ship 343.
The loan was for 3 years with interest at 13%.
Capitalized interest on Ship No. 343