Completion Certificate Letter Request

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 2

Date: 15-07-2020

Ref: JOS-LT-AG-2020-

To: Arabian Gulf Oil Company

Attention: Manager, Engineering and Construction Department

Project: Contract No. ECD513/19 – Flow Lines Project


ELECTROMECHANICAL TIE-IN OF WELLSA NO HH-86,HH-108 AT MESSLA
FIELD,L95 and C-373 AT SARIR FIELD

Subject: Completion certificate Provision

Dear Sir,

With Reference to the mentioned subject project, please note that the construction Work is
completed during this actual worldwide force majeure and after a standby period of almost one
month from 25/04/2020 waiting for the Rig move from the well C-373 and change order from
the well G-315 to the well C-373, and attached is the following reports signed by AGOCO
representative engineer in Messla and Sarir Fields:

1. Hydrostatic test Well HH-86


2. Hydrostatic test Well HH-108
3. Inspection request Electrical work HH-108 and HH-86
4. Coating and wrapping of HH-86
5. Coating and wrapping of HH-108
6. Internal Pipe cleaning record C-373
7. Internal Pipe cleaning record L-95
8. Painting HH-86
9. Painting HH-108
Concerning The hydrostatic test for the wells L-95 done on 04/07/2020 and C-373 done on
07/07/2020 for the second times with a small normal pressure drop caused by environment
temperatures change during the 24 hours hold time test period could be acceptable according
to the Standard ASME B31.4 (attached scan of the chart and the relevant article in ASME B31.4
code).

Accordingly we kindly request to provide the Provisional completion certificate for the Project
and the punch list to be done.

Sincerely yours,

__________________
Hassan Salini
Executive Director

cc : JOS Chairman