Modelo para RBM
Modelo para RBM
Abstract: The progress of technology has caused operating of many processes and resulted
in more complexity of the process industries and the safe operations of their operation are at
least as important as their design. In addition, the cost of maintenance is a considerable part
of the total life cycle in industries and researches proved that some critical components are
responsible for the most of the downtime at workplaces. Therefore, an improvement in the
maintenance practices which focused on risk based approach for critical components
improves reliability and safety; at the same time can reduces maintenance costs. Thus, we
aim to prepare a domestic risk management model for based on Risk Based Maintenance
(RBM) using FAHP technique. The initial steps involve literature review followed by
subsequent interviews with experienced practitioners to identify their failures. All of the
RBM criteria have been localized by expert team and risk number could be calculated
according to these factors. However, there are several tools to analysis the risks of them, but
the classic approach always comes with uncertainty. Thus, FAHP model will be introduced as
an applicable approach for modeling of the risk management to overcome this limitation.
Overall, by applying this technique, it will be anticipated that the safety of system will be
improved, the environmental impacts and maintenance costs would be reduced, and the spare
parts will be allocated where necessary. Finally, this technique results in prioritization of the
process’s safety measures according to their risk levels.
Keywords: Risk, Fuzzy, Safety, Process, Hazards
Introduction
The progress of technology has caused operating of many processes and resulted in more
complexity of chemical process industries, so that one of the main challenges for these
companies are to manage existing assets in the complex infrastructure(1, 2). However, beside
of valuable application of these industries, there are potential risks associated with their
chemical processes (Figure 1).
Received Aug 15, 2015 * Published Oct 2, 2015 * www.ijset.net
1266 Saeed Nazari, Noreddin Ghanbari, Najmeh Karami, Masoom Nazari and Sajad Mousavi
Accidents like in Bhopal and Basle led to the development of a regulatory regime to control
the risks in these industries (3). Thus, the safe operations of these systems are at least as
important as their design(4)so that designers and operators have to find appropriate solutions
to ensure safety of operations as well as being economically viable.
3%
31%
36%
30%
academic professor, turbine operators, maintenance engineer, and plant and process
engineering, to form proposed approach.
This approach was performed in Turbine Unit within Petrochemical Company as a case study
in order to demonstrate its usefulness, characteristics and for efficient maintenance
scheduling. However, through three rounds of Delphi process experts helped to filter all the
information to come up with a series of the most important strategic actions to the RBM of
assets. Also, HAZOP1and FMEA2 studies conducted by the Delphi team for identifying
failures and calculate final risk using literature review and finally proposed a model (1, 18-
22)(Figure 2).
Financial Loss (FL)
Production loss (PL)
Frequency (F) System Performance Loss (SPL)
Risk Score Maintenance Cost (MC)
Health (H)
Total Consequences (CT)
HSE Safety (S)
Property Damage (PD) Environment (E)
1
Hazard and Operation
2
Failure Mode and Effect Analysis
1268 Saeed Nazari, Noreddin Ghanbari, Najmeh Karami, Masoom Nazari and Sajad Mousavi
The engineering and expert knowledge base used to establish the set of rules by the collection
of IF-THEN statements (e.g. Rule 1 if (frequency is very low) and (consequence is very low)
then the risk is very low). Then, the fuzzy risk (Rf) value calculated using the failure
consequences and frequency as input and risk number as an output. Finally, the RBM
calculated by summing up the individual FR out of the total number of failures (N) within the
subsystem as follows:
∑*+, *
!"(subsyetem) =
-
Conclusion
The proposed model applied in the Turbine and Generator Unit of the Petrochemical
Company as a case study. Totally, 7 subsystems and 32 P&IDs have been assessed. Results
of proposed risk models for maintenance program showed that oil system is the most
important component for the maintenance. However, 39 recommendations suggested to
mitigate failures in selected asset.
Furthermore, the expert team believed that using Fuzzy Logic and AHP’s pair comparison
weighting, would improve the performance of the system. Reduction in HSE consequences,
cut in maintenance cost, decrease in property damage, and an allocation of spare parts where
necessary were the main reasons.
Discussion
Overall, this model contribute to the prioritization of recommended maintenance practices,
according to their risk levels and using this technique positively effects the scheduling of
these activities. Of course, the robustness, sensitivity analysis, and safety integrity level (SIL)
studies for further researches are recommended by the authors in order to find the application
of this approach in other industries.
Acknowledgement
Authors really appreciate the endless collaboration of engineers, managers, and other
practitioners in the Petrochemical Company. Also, many thanks to academic staff from
Tarbiat Modares and Ardabil Universities who contribute positively to this paper.
References
[1] Sa'idi E, Anvaripour B, Jaderi F, Nabhani N. Fuzzy risk modeling of process operations
in the oil and gas refineries. Journal of Loss Prevention in the Process Industries. 2014
7//;30(0):63-73.
Risk Based Maintenance (RBM) Modeling of Petrochemical Industry …. 1269
[2] Hu J, Zhang L. Risk based opportunistic maintenance model for complex mechanical
systems. Expert Systems with Applications. 2014 5//;41(6):3105-15.
[3] Mitchison N, Porter S. Guidelines on a major accident prevention policy and safety
management system, as required by Council Directive 96/82/EC (SEVESO II): European
Commission; 1998.
[4] Arunraj NS, Maiti J. Risk-based maintenance—Techniques and applications. Journal of
Hazardous Materials. 2007 4/11/;142(3):653-61.
[5] Daniel A. Crow1 JFL. Chemical process safety: fundamentals with applications. 2 ed:
Prentice Hall; 2002.
[6] Dalzell G. Is Operating Cost a Direct Measure of Inherent Safety? Process Safety and
Environmental Protection. 2003 11//;81(6):414-7.
[7] Hale AR, Heming BHJ, Smit K, Rodenburg FGT, van Leeuwen ND. Evaluating safety in
the management of maintenance activities in the chemical process industry. Safety Science.
1998 2//;28(1):21-44.
[8] Hu H, Cheng G, Li Y, Tang Y. Risk-based maintenance strategy and its applications in a
petrochemical reforming reaction system. Journal of Loss Prevention in the Process
Industries. 2009 7//;22(4):392-7.
[9] Qingfeng W, Wenbin L, Xin Z, Jianfeng Y, Qingbin Y. Development and application of
equipment maintenance and safety integrity management system. Journal of Loss Prevention
in the Process Industries. 2011 7//;24(4):321-32.
[10]. Vassiliadis CG, Pistikopoulos EN. Process design and maintenance optimization
under uncertainty. Computers & Chemical Engineering. 1999 6/1/;23, Supplement(0):S555-
S8.
[11] Arunraj NS, Maiti J. Risk-based maintenance policy selection using AHP and goal
programming. Safety Science. 2010 2//;48(2):238-47.
[12] Nielsen JJ, Sørensen JD. On risk-based operation and maintenance of offshore wind
turbine components. Reliability Engineering & System Safety. 2011 1//;96(1):218-29.
[13] Krishnasamy L, Khan F, Haddara M. Development of a risk-based maintenance (RBM)
strategy for a power-generating plant. Journal of Loss Prevention in the Process Industries.
2005;18(2):69-81.
[14] Arunraj N, Maiti J. Risk-based maintenance—techniques and applications. Journal of
Hazardous Materials. 2007;142(3):653-61.
1270 Saeed Nazari, Noreddin Ghanbari, Najmeh Karami, Masoom Nazari and Sajad Mousavi
[15] Guimarẽes ACF, Ebecken NFF. FuzzyFTA: a fuzzy fault tree system for uncertainty
analysis. Annals of Nuclear Energy. 1999 4//;26(6):523-32.
[16] Erol İ, Sencer S, Özmen A, Searcy C. Fuzzy MCDM framework for locating a nuclear
power plant in Turkey. Energy Policy. 2014 4//;67(0):186-97.
[17] Markowski AS, Mannan MS, Bigoszewska A. Fuzzy logic for process safety analysis.
Journal of Loss Prevention in the Process Industries. 2009 11//;22(6):695-702.
[18] Mingda W, Guoming C, Jianmin F, Weijun L. Safety Analysis Approach of MFM-
HAZOP and Its Application in the Dehydration System of Oilfield United Station. Procedia
Engineering. 2012;43:437-42.
[19] Wang Y, Cheng G, Hu H, Wu W. Development of a risk-based maintenance strategy
using FMEA for a continuous catalytic reforming plant. Journal of Loss Prevention in the
Process Industries. 2012 11//;25(6):958-65.
[20] Bertolini M, Bevilacqua M. A combined goal programming—AHP approach to
maintenance selection problem. Reliability Engineering & System Safety. 2006
7//;91(7):839-48.
[21] Petrović DV, Tanasijević M, Milić V, Lilić N, Stojadinović S, Svrkota I. Risk
assessment model of mining equipment failure based on fuzzy logic. Expert Systems with
Applications. 2014 12/15/;41(18):8157-64.
[22] Bertolini M, Bevilacqua M, Ciarapica FE, Giacchetta G. Development of Risk-Based
Inspection and Maintenance procedures for an oil refinery. Journal of Loss Prevention in the
Process Industries. 2009 3//;22(2):244-53.
[23] Chen T, Jin Y, Qiu X, Chen X. A hybrid fuzzy evaluation method for safety
assessment of food-waste feed based on entropy and the analytic hierarchy process methods.
Expert Systems with Applications. 2014;41(16):7328-37.
[24] An M, Chen Y, Baker CJ. A fuzzy reasoning and fuzzy-analytical hierarchy process
based approach to the process of railway risk information: A railway risk management
system. Information Sciences. 2011;181(18):3946-66.
[25] Badri A, Nadeau S, Gbodossou A. Proposal of a risk-factor-based analytical approach
for integrating occupational health and safety into project risk evaluation. Accident; analysis
and prevention. 2012 Sep;48:223-34. PubMed PMID: 22664685.