6763 TestingLine FC 20160602 Web
6763 TestingLine FC 20160602 Web
Presented at the
GCC Power 2016 Conference & Exhibition
Doha, Qatar
November 8–10, 2016
TESTING LINE DISTANCE RELAYS DURING THEIR LIFE CYCLE
USA
Summary—Different periods in the life cycle of provide guidance for testing them [3] [4]. This paper
protective relays merit different testing considerations. discusses relay testing concepts, using line distance
When a new type of distance relay is under consideration, relay elements as examples.
acceptance (prequalification) tests are performed to
validate manufacturers’ specifications and relay
Manufacturers follow their own design and
functionality. When a substation design requires a certain manufacturing practices to provide products that are
functionality in the protection scheme, functional tests are competitive and that follow industry standards. The
performed to validate the relay against requirements characteristics and specifications are public and
before it is considered for the project. When a relay is published in data sheets or instruction manuals. The
installed in the field, commissioning tests are performed to tests to validate conformance to standards are called
validate the wiring and the interaction of the unit with the
primary equipment and other intelligent electronic devices
type tests, and there is a test certificate or report
in the scheme. When the unit is in service, periodic tests associated with these tests. In some cases, a third-party
may be performed to validate its functionality. In each certificate is obtained to validate conformance to an
period of the relay life cycle, judgment is required in the industry standard. Most manufacturers subject units to
testing of the unit. Careful consideration and background final manufacturing tests. A test report is often included
information should guide the test procedure. This paper with an IED.
uses line distance relay elements as examples to illustrate
specific concepts.
When a particular model of a protective relay is
considered for application by a utility for the first time,
Keywords—Relay life cycle–Relay testing–Distance utility engineers typically require that the IED conform
relay.
to certain standards and they verify its functionality.
Utilities have acceptance criteria published for
I. INTRODUCTION
manufacturers that the model must satisfy [5]. The
Protective relays have a long history in the electric requirements may call for specific types of testing to
power industry. Their design principles, components, qualify the model for application in the power system.
functionality, complexity, size, and other characteristics Proof of compliance to standards may also be
have evolved over decades. However, their main requested. The most important aspect of verification,
functionality—to protect power system elements (lines, however, is for engineers and technicians to familiarize
transformers, and so on)—has not changed over time, themselves with and clearly understand the
and they remain a fundamental component of power functionality of the unit.
systems. Modern protective relays are computers with Acceptance testing has different meanings to
flexible functionality that provide a wealth of different users [3] [4]. Functional tests are often
information to the user [1]. Testing considerations need performed by electric utilities to validate the published
to adjust to account for the large amount of flexibility functionality and specifications of a device and to get a
and information in modern intelligent electronic devices full understanding of its capabilities. Some utilities
(IEDs) [2]. Fortunately, since the early days of additionally evaluate the relay in a real-time digital
numerical protective relays, there has been literature to
* Schweitzer Engineering Laboratories, Inc., 2350 NE Hopkins Court, Pullman, WA 99163 USA • [email protected]
simulation environment by applying the relay to a protective relays used transistor and operational
model of their power system. Once the characteristics amplifier technology [2] [12]. The same operating
and functionality of the device are fully understood, the equations used by electromechanical relays were
model is fully qualified. possible with solid-state technology.
Specific tests may be required by a utility, For example, a classic implementation of a mho
particularly with multifunction relays, to certify the distance element considers two signals, S1 (operating)
functionality for particular applications in the power and S2 (polarizing), that should coincide for at least
system. In a given project, the functionality required of 180 degrees (±90 degrees or 0–180 degrees) [13]. S1 is
a line protection relay can be different from that of the calculated as shown in (1), and S2 is calculated as
same model used in a previous project. shown in (2).
Acceptance testing can also mean testing a group of
S1 = V – Zset I (1)
IEDs upon receipt to ensure that all (or a certain
percentage) of them are operating properly, that the S2 = V (2)
device model is the correct one, and that the units have where:
not been damaged during shipment. V is measured voltage.
Commissioning testing should validate the
I is operating current.
functionality of the relay for a particular application.
Commissioning testing is specific, and there are Zset is relay reach.
guidelines to follow [2] [6] [7]. With modern The angle coincidence can be implemented with an
multifunction protective relays, testing the functionality electromechanical single-phase motor, as shown in
for an application can be much more demanding than in Fig. 1a, or a solid-state circuit with squared signals and
the era of single-function protective relays. As such, the operational amplifiers or transistors, as shown in Fig. 1b
testing should only focus on the specific functionalities [12] [13]. Both implementations provide the same
required from the IED. characteristic result of a mho distance element.
Maintenance testing can be performed to ensure that (a)
an IED is performing correctly after it is in service.
Cylinder
Protective relays are designed for decades of continuous
operation. Modern numerical relays have drastically
reduced periodic maintenance requirements versus
previous technologies [8] [9]. The relays implement S1
self-testing and can report hardware problems so that
users can take action [10]. Self-testing is available for
most IED hardware; most likely, the only hardware not
self-tested is the binary outputs. Some users have
devised means to monitor these automatically as well to
complement the IED self-tests [11]. S2
(b)
II. EVOLUTION OF PROTECTIVE RELAYS
S1
The electric power industry is over a century old, but Timer
0.25
power system components still experience failures that cyc
need to be detected and isolated promptly. Protective 0
Failures
A/D OFFSET FAILURE
wiring of binary and analog inputs. The relay metering Active High-Accuracy Time Synchronization Source: NONE
functionality is also important. If the protective relay is IRIG-B Source Absent
metering properly, it is also executing the protective Relay Programming Environment Errors
No Errors
relaying functions properly.
Validating the protective relaying functionality Relay Disabled
during the acceptance testing period ensures that the Fig. 8. A self-test report from a protective relay with a failure.
already tested and known protective relaying functions
are operating as tested in the laboratory. The situation in Fig. 8 shows the advantage of
Besides protective relaying functions, other checks having intelligence in the relay to determine when there
are needed during commissioning. The wiring of the is a failure in the unit. This allows utilities to reconsider
binary inputs and outputs should be checked carefully maintenance programs for protective relays in the
and validated. Functions or interlocks implemented in following ways:
the programmable logic should be tested as well. • After commissioning, continue to monitor the
Programmable logic in modern relays is very flexible, self-test functionality of protective relays.
and the programmed functionality should be tested. • Over long periods, monitor the metering of
protective relays. If the metering is correct, then
C. Maintenance Testing the protective relay is sound. Metering values
Electromechanical and solid-state relays required can be verified against those of other devices in
injection boxes to test settings and also required manual the system.
setup (e.g., by adjusting screws and taps). By their • Devise an automatic comparison of metered
nature, and depending on the amount of vibration values. This can be done with automation
present in the installation (power plants often have controllers automatically comparing the
significant amounts of vibration), electromechanical metering values of two devices measuring from
and solid-state relays lose their calibration over time. the same location. If the measurements are the
Component degradation can also factor into this same, within a margin, then the protective
problem. Traditionally, therefore, utilities had a relays are sound [16].
periodic (every two years or so) maintenance program There are other approaches that take advantage of
to validate protective relay characteristics and settings the reporting capabilities of numerical relays. For
[2] [3] [4]. example, using time-synchronized measurements
One of the many benefits of numerical relays is that (synchrophasors), users can devise continuous testing
little to no maintenance is required [3]. Reference [8] schemes for the measurements. If a numerical relay is
discusses the maintenance interval for numerical IEDs measuring properly, the protective relaying
with self-testing. The routine tests for numerical relays functionality is working properly.
only include meter checks and binary output checks. If Periodic testing of the relay output contacts to ensure
the relay is measuring properly, and no self-test has that they are operational can also be implemented
failed, there is no reason to test the relay further. Relay automatically. Protective relays may not take action for
self-testing saves routine testing time [8]. very long periods of time; making sure that they are
The A/D conversion in modern numerical relays available when needed is always a concern. Some
does not drift over time, and this subsystem is clever schemes take advantage of programmable logic
monitored by the self-test mechanism of the relay. to test binary outputs, as described in [11].
Fig. 8 shows a report from a line distance relay with
a failure. The A/D conversion system has failed because
IV. CONCLUSION the particular application. The main objectives are to
Modern protective relays have made the operation of validate the main protective functions for selectivity
power systems more reliable and efficient. and operating time for internal faults, to validate
Multifunction IEDs have several capabilities, and most security for external faults, and to fine-tune the setting
of the protective relaying functionality is programmed parameters.
in instructions that run continously in hardware. Having B. Laboratory Acceptance Tests
many capabilities in one device requires users to learn
The utility engineers and manufacturer’s technical
and verify what is published in the data sheet and
representative use the finalized configuration file
instruction manual. This should be done in the
approved after the real-time simulator testing to review
laboratory, not the substation. Acceptance testing
in detail the characteristics of the unit. The utility
verifies that units meet the requirements for particular verifies the relay element pickup characteristics and
functions and protective relaying principles.
validates the operating times. At this time, the full
Modern protective relays are computers. Testing a
characteristics of the distance elements, for example,
single unit and making sure the protective relaying are plotted and verified.
characteristiccs are correct implies that the tests are
valid for all units with similar characteristics. The C. Commissioning Tests
computer program running internally is the same and Commissioning tests focus on the integration of the
does not change over time. device into the overall scheme for protection and
One of the most stressful activities in a project is the control in the substation. A few test points are selected
commissioning stage. Commissioning testing can be to validate functionality. No detailed plots of
made simpler and more efficient by focusing on testing characteristics are programmed in the test protocol. The
key points in the characteristics of the relay. wiring and programmed logic functions are verified
Commissioning testing should spot check certain points together with any communications of parameters to the
of the key functions. Most of the detailed functionality control center.
should have been tested in the laboratory during
acceptance testing. D. Maintenance Tests
Maintenance testing should take advantage of the No routine maintenance tests are programmed for
self-test functionality of protective relays. The only numerical relays. The utility fully relies on the internal
routine testing required for numerical relays is meter self-tests of the devices.
checks and binary output checks. The sequence of
events (SOE) report and oscillography can be used to VI. REFERENCES
properly evaluate the operation of protective relays and [1] R. D. Kirby and R. A. Schwartz, “Microprocessor-Based
determine if any maintenance testing is needed. Protective Relays Deliver More Information and Superior
Reliability With Lower Maintenance Costs,” proceedings of the
42nd Annual Industrial and Commercial Power Systems
V. APPENDIX Technical Conference, Detroit, MI, April 2006.
An electric utility in the United Arab Emirates the [2] I. Stevens, “Testing Philosophy,” PAC World Magazine, Winter
2009. Available: https://www.pacw.org.
authors have worked with defines the testing throughout
[3] J. J. Kumm, M. S. Weber, E. O. Schweitzer, III, and D. Hou,
the life of their protective relays as follows. “Philosophies for Testing Protective Relays,” proceedings of the
A. Prequalification Tests 47th Annual Conference for Protective Relay Engineers,
College Station, TX, March 1994.
The manufacturer receives all of the necessary [4] C. Werstiuk, “Testing Requirements for Microprocessor
application details and proposes a relay model with Relays,” Valence Electrical Training Services, 2010.
specific options (hardware and software) to meet the [5] Pacific Gas and Electric, “PG&E Interconnection Handbooks:
application needs. Appendix R – Protective Relay Requirements and Approvals,”
February 2015. Available: https://www.pge.com/.
The relay manufacturer visits the utility and provides
[6] K. Zimmerman, “Commissioning of Protective Relay Systems,”
a presentation about the relay features. The presentation proceedings of the 61st Annual Conference for Protective Relay
includes an exchange of ideas and discussion about how Engineers, College Station, TX, April 2008.
to apply the device to the application. [7] WECC, “Installation and Maintenance for Protective Relay
The manufacturer’s technical representative and a Systems,” July 2009. Available: https://www.wecc.biz.
utility engineer jointly develop a wiring template and [8] J. J. Kumm, M. S. Weber, D. Hou, and E. O. Schweitzer, III,
the relay configuration file for the application. The “Predicting the Optimum Routine Test Interval for Protective
Relays,” IEEE Transactions on Power Delivery, Vol. 10,
manufacturer sends a sample relay for the utility Issue 2, April 1995, pp. 659-665.
engineers to test and become familiar with. [9] K. Zimmerman, “SEL Recommendations on Periodic
Upon agreement between the manufacturer and the Maintenance Testing of Protective Relays,” March 2014.
utility, the sample relay is tested (with the agreed upon Available: https://selinc.com.
configuration file) in a real-time power system
simulator to validate the performance requirements for
[10] J. J. Kumm, E. O. Schweitzer, III, and D. Hou, “Assessing the
Effectiveness of Self-Tests and Other Monitoring Means in
Protective Relays,” proceedings of the 48th Annual Conference
for Protective Relay Engineers, College Station, TX, April 1995.
[11] S. Imai, T. Ohmori, H. Kitajima, H. Okamura, and F. Calero,
“Integration of Standard IEDs in TEPCO’s 66 kV Protection
Scheme Philosophy,” proceedings of the 36th Annual Western
Protective Relay Conference, Spokane, WA, October 2009.
[12] W. A. Elmore, Protective Relaying Theory and Applications.
ABB, 1994.
[13] F. Calero, “Distance Elements: Linking Theory With Testing,”
proceedings of the 62nd Annual Conference for Protective
Relay Engineers, College Station, TX, March 2009.
[14] E. O. Schweitzer, III, and Jeff Roberts, “Distance Relay Element
Design,” proceedings of the 19th Annual Western Protective
Relay Conference, Spokane, WA, October 1992.
[15] Z. Zhou, X. Shen, D. Hou and S. Chen, “Analog Simulator Tests
Qualify Distance Relay Designs to Today’s Stringent Protection
Requirements,” proceedings of the 32nd Annual Western
Protective Relay Conference, Spokane, WA, October 2005.
[16] D. Stewart, R. Jenkins, and D. Dolezilek, “Case Study in
Improving Protection System Reliability With Automatic NERC
PRC-005 Inspection, Testing, Reporting, and Auditing,”
proceedings of the 66th Annual Conference for Protective Relay
Engineers, College Station, TX, April 2013.
VII. BIOGRAPHIES
Fernando Calero is a principal engineer in the Schweitzer
Engineering Laboratories, Inc. (SEL) international organization. His
responsibilities include application support for SEL products, training
and technical support for SEL customers, and internal training and
mentoring of SEL engineers. He started his professional career with
the ABB relay division in Coral Springs, Florida, where he
participated in product development and technical support for
protective relays. He also worked for Florida Power & Light in the
energy management system group and for the Siemens energy
automation group. Since 2000, he has worked for SEL as an
application engineer. He holds five patents and has written technical
papers on protective relaying, remedial action schemes, and other
protection and control applications.