LM Power Engineering Corporation Vs Capitol Industrial Construction Group PDF
LM Power Engineering Corporation Vs Capitol Industrial Construction Group PDF
LM Power Engineering Corporation Vs Capitol Industrial Construction Group PDF
CAPITOL INDUSTRIAL
CONSTRUCTION GROUPS, INC., respondent.
DECISION
PANGANIBAN, J.:
Alternative dispute resolution methods or ADRs -- like arbitration, mediation, negotiation and conciliation --
are encouraged by the Supreme Court. By enabling parties to resolve their disputes amicably, they provide
solutions that are less time-consuming, less tedious, less confrontational, and more productive of goodwill
and lasting relationships.[1]
The Case
Before us is a Petition for Review on Certiorari[2] under Rule 45 of the Rules of Court, seeking to set aside
the January 28, 2000 Decision of the Court of Appeals[3] (CA) in CA-GR CV No. 54232. The dispositive
portion of the Decision reads as follows:
"WHEREFORE, the judgment appealed from is REVERSED and SET ASIDE. The parties are ORDERED to
present their dispute to arbitration in accordance with their Sub-contract Agreement. The surety bond posted
by [respondent] is [d]ischarged."[4]
The Facts
On February 22, 1983, Petitioner LM Power Engineering Corporation and Respondent Capitol Industrial
Construction Groups Inc. entered into a "Subcontract Agreement" involving electrical work at the Third Port of
Zamboanga.[5]
On April 25, 1985, respondent took over some of the work contracted to petitioner.[6] Allegedly, the latter had
failed to finish it because of its inability to procure materials.[7]
Upon completing its task under the Contract, petitioner billed respondent in the amount of P6,711,813.90.[8]
Contesting the accuracy of the amount of advances and billable accomplishments listed by the former, the
latter refused to pay. Respondent also took refuge in the termination clause of the Agreement.[9] That clause
allowed it to set off the cost of the work that petitioner had failed to undertake -- due to termination or
take-over -- against the amount it owed the latter.
Because of the dispute, petitioner filed with the Regional Trial Court (RTC) of Makati (Branch 141) a
Complaint[10] for the collection of the amount representing the alleged balance due it under the Subcontract.
Instead of submitting an Answer, respondent filed a Motion to Dismiss,[11] alleging that the Complaint was
premature, because there was no prior recourse to arbitration.
In its Order[12] dated September 15, 1987, the RTC denied the Motion on the ground that the dispute did not
involve the interpretation or the implementation of the Agreement and was, therefore, not covered by the
arbitral clause.[13]
After trial on the merits, the RTC[14] ruled that the take-over of some work items by respondent was not
equivalent to a termination, but a mere modification, of the Subcontract. The latter was ordered to give full
payment for the work completed by petitioner.
The Issues
In its Memorandum, petitioner raises the following issues for the Court's consideration:
"A
Whether or not there exist[s] a controversy/dispute between petitioner and respondent regarding the
interpretation and implementation of the Sub-Contract Agreement dated February 22, 1983 that requires prior
recourse to voluntary arbitration;
"B
In the affirmative, whether or not the requirements provided in Article III [1] of CIAC Arbitration Rules
regarding request for arbitration ha[ve] been complied with[.]"[17]
First Issue:
Petitioner claims that there is no conflict regarding the interpretation or the implementation of the Agreement.
Thus, without having to resort to prior arbitration, it is entitled to collect the value of the services it rendered
through an ordinary action for the collection of a sum of money from respondent. On the other hand, the latter
contends that there is a need for prior arbitration as provided in the Agreement. This is because there are
some disparities between the parties' positions regarding the extent of the work done, the amount of
advances and billable accomplishments, and the set off of expenses incurred by respondent in its take-over of
petitioner's work.
We side with respondent. Essentially, the dispute arose from the parties' ncongruent positions on whether
certain provisions of their Agreement could be applied to the facts. The instant case involves technical
discrepancies that are better left to an arbitral body that has expertise in those areas. In any event, the
inclusion of an arbitration clause in a contract does not ipso facto divest the courts of jurisdiction to pass upon
the findings of arbitral bodies, because the awards are still judicially reviewable under certain conditions.[18]
In the case before us, the Subcontract has the following arbitral clause:
"6. The Parties hereto agree that any dispute or conflict as regards to interpretation and implementation of
this Agreement which cannot be settled between [respondent] and [petitioner] amicably shall be settled by
means of arbitration x x x."[19]
Clearly, the resolution of the dispute between the parties herein requires a referral to the provisions of their
Agreement. Within the scope of the arbitration clause are discrepancies as to the amount of advances and
| Page 2 of 7
billable accomplishments, the application of the provision on termination, and the consequent set-off of
expenses.
A review of the factual allegations of the parties reveals that they differ on the following questions: (1) Did a
take-over/termination occur? (2) May the expenses incurred by respondent in the take-over be set off against
the amounts it owed petitioner? (3) How much were the advances and billable accomplishments?
The resolution of the foregoing issues lies in the interpretation of the provisions of the Agreement. According
to respondent, the take-over was caused by petitioner's delay in completing the work. Such delay was in
violation of the provision in the Agreement as to time schedule:
"[Petitioner] shall adhere strictly to the schedule related to the WORK and complete the WORK within the
period set forth in Annex C hereof. NO time extension shall be granted by [respondent] to [petitioner] unless a
corresponding time extension is granted by [the Ministry of Public Works and Highways] to the
CONSORTIUM."[20]
Because of the delay, respondent alleges that it took over some of the work contracted to petitioner, pursuant
to the following provision in the Agreement:
"[Respondent] has the right to terminate and/or take over this Agreement for any of the following causes:
xxxxxxxxx
'6. If despite previous warnings by [respondent], [petitioner] does not execute the WORK in accordance with
this Agreement, or persistently or flagrantly neglects to carry out [its] obligations under this Agreement."[21]
Supposedly, as a result of the "take-over," respondent incurred expenses in excess of the contracted price. It
sought to set off those expenses against the amount claimed by petitioner for the work the latter
accomplished, pursuant to the following provision:
"If the total direct and indirect cost of completing the remaining part of the WORK exceed the sum which
would have been payable to [petitioner] had it completed the WORK, the amount of such excess [may be]
claimed by [respondent] from either of the following:
'1. Any amount due [petitioner] from [respondent] at the time of the termination of this Agreement."[22]
The issue as to the correct amount of petitioner's advances and billable accomplishments involves an
evaluation of the manner in which the parties completed the work, the extent to which they did it, and the
expenses each of them incurred in connection therewith. Arbitrators also need to look into the computation of
foreign and local costs of materials, foreign and local advances, retention fees and letters of credit, and taxes
and duties as set forth in the Agreement. These data can be gathered from a review of the Agreement,
pertinent portions of which are reproduced hereunder:
xxxxxxxxx
"All progress payments to be made by [respondent] to [petitioner] shall be subject to a retention sum of ten
percent (10%) of the value of the approved quantities. Any claims by [respondent] on [petitioner] may be
| Page 3 of 7
deducted by [respondent] from the progress payments and/or retained amount. Any excess from the retained
amount after deducting [respondent's] claims shall be released by [respondent] to [petitioner] after the
issuance of [the Ministry of Public Works and Highways] of the Certificate of Completion and final acceptance
of the WORK by [the Ministry of Public Works and Highways].
xxxxxxxxx
"[Respondent shall open the letters of credit for the importation of equipment and materials listed in Annex E
hereof after the drawings, brochures, and other technical data of each items in the list have been formally
approved by [the Ministry of Public Works and Highways]. However, petitioner will still be fully responsible for
all imported materials and equipment.
"All expenses incurred by [respondent], both in foreign and local currencies in connection with the opening of
the letters of credit shall be deducted from the Contract Prices.
xxxxxxxxx
xxxxxxxxx
"2. All customs duties, import duties, contractor's taxes, income taxes, and other taxes that may be required
by any government agencies in connection with this Agreement shall be for the sole account of
[petitioner]."[23]
Being an inexpensive, speedy and amicable method of settling disputes,[24] arbitration -- along with
mediation, conciliation and negotiation -- is encouraged by the Supreme Court. Aside from unclogging judicial
dockets, arbitration also hastens the resolution of disputes, especially of the commercial kind.[25] It is thus
regarded as the "wave of the future" in international civil and commercial disputes.[26] Brushing aside a
contractual agreement calling for arbitration between the parties would be a step backward.[27]
Consistent with the above-mentioned policy of encouraging alternative dispute resolution methods, courts
should liberally construe arbitration clauses. Provided such clause is susceptible of an interpretation that
covers the asserted dispute, an order to arbitrate should be granted.[28] Any doubt should be resolved in
favor of arbitration.[29]
Second Issue:
According to petitioner, assuming arguendo that the dispute is arbitrable, the failure to file a formal request for
arbitration with the Construction Industry Arbitration Commission (CIAC) precluded the latter from acquiring
jurisdiction over the question. To bolster its position, petitioner even cites our ruling in Tesco Services
Incorporated v. Vera.[30] We are not persuaded.
Section 1 of Article II of the old Rules of Procedure Governing Construction Arbitration indeed required the
submission of a request for arbitration, as follows:
"SECTION. 1. Submission to Arbitration -- Any party to a construction contract wishing to have recourse to
arbitration by the Construction Industry Arbitration Commission (CIAC) shall submit its Request for Arbitration
in sufficient copies to the Secretariat of the CIAC; PROVIDED, that in the case of government construction
| Page 4 of 7
contracts, all administrative remedies available to the parties must have been exhausted within 90 days from
the time the dispute arose."
Tesco was promulgated by this Court, using the foregoing provision as reference.
On the other hand, Section 1 of Article III of the new Rules of Procedure Governing Construction Arbitration
has dispensed with this requirement and recourse to the CIAC may now be availed of whenever a contract
"contains a clause for the submission of a future controversy to arbitration," in this wise:
The foregoing amendments in the Rules were formalized by CIAC Resolution Nos. 2-91 and 3-93.[31]
The difference in the two provisions was clearly explained in China Chang Jiang Energy Corporation
(Philippines) v. Rosal Infrastructure Builders et al.[32] (an extended unsigned Resolution) and reiterated in
National Irrigation Administration v. Court of Appeals,[33] from which we quote thus:
"Under the present Rules of Procedure, for a particular construction contract to fall within the jurisdiction of
CIAC, it is merely required that the parties agree to submit the same to voluntary arbitration Unlike in the
original version of Section 1, as applied in the Tesco case, the law as it now stands does not provide that the
parties should agree to submit disputes arising from their agreement specifically to the CIAC for the latter to
acquire jurisdiction over the same. Rather, it is plain and clear that as long as the parties agree to submit to
voluntary arbitration, regardless of what forum they may choose, their agreement will fall within the jurisdiction
of the CIAC, such that, even if they specifically choose another forum, the parties will not be precluded from
electing to submit their dispute before the CIAC because this right has been vested upon each party by law,
i.e., E.O. No. 1008."[34]
Clearly, there is no more need to file a request with the CIAC in order to vest it with jurisdiction to decide a
construction dispute.
The arbitral clause in the Agreement is a commitment on the part of the parties to submit to arbitration the
disputes covered therein. Because that clause is binding, they are expected to abide by it in good faith.[35]
And because it covers the dispute between the parties in the present case, either of them may compel the
other to arbitrate.[36]
Since petitioner has already filed a Complaint with the RTC without prior recourse to arbitration, the proper
procedure to enable the CIAC to decide on the dispute is to request the stay or suspension of such action, as
provided under RA 876 [the Arbitration Law].[37]
WHEREFORE, the Petition is DENIED and the assailed Decision AFFIRMED. Costs against petitioner.
SO ORDERED.
| Page 5 of 7
[3] Seventh Division. Written by Justice Portia Aliño-Hormachuelos and concurred in by Justices Corona
Ibay-Somera (Division chairman) and Wenceslao I. Agnir Jr. (member).
[5] See Pay Item Nos. 7.01 to 7.26 of the Bill of Quantities; Records, pp. 16-25.
[6] See Letters dated March 15, 1985 and April 25, 1985, pp. 63-64.
[16] This case was deemed submitted for decision on October 25, 2001, upon this Court's receipt of
respondent's Memorandum signed by Atty. Henry S. Rojas. Petitioner's Memorandum, filed on October 10,
2001, was signed by Atty. Eleazar G. Ferry.
[24] Del Monte Corporation-USA v. Court of Appeals, 351 SCRA 373, February 7, 2001; Eastboard
Navigation, Ltd. v. Juan Ysmael and Co., Inc., 102 Phil. 1, September 10, 1957.
[25] Home Bankers Savings and Trust Company v. Court of Appeals, 318 SCRA 558, November 19, 1999.
[26] Heirs of Augusto L. Salas Jr. v. Laperal Realty Corporation, 320 SCRA 610, December 13, 1999; BF
Corporation v. Court of Appeals, 288 SCRA 267, March 27, 1998.
| Page 6 of 7
[27] Ibid.
[28] Seaboard Coastline Railroad Co. v. National Rail Passenger Corporation, 554 F2d 657 (US Court of
Appeals, 5th Circuit), June 22, 1977.
[29] Moses H. Cone Hospital v. Mercury Construction Co., 460 US 1, February 23, 1983; Metro Industrial
Painting Corp. v. Terminal Construction Co., 287 F2d 382 (US Court of Appeals, 2nd Circuit), February 16,
1961.
[31] These were promulgated by the CIAC on June 21, 1991 and August 25, 1993, respectively.
[35] Toyota Motor Philippines Corporation v. Court of Appeals, 216 SCRA 236, December 7, 1992.
[37] "SEC. 7. Stay of Civil Action. If any suit or proceeding be brought upon an issue arising out of an
agreement providing for the arbitration thereof, the court in which such suit or proceeding is pending, upon
being satisfied that the issue involved in such suit or proceeding is referable to arbitration, shall stay the
action or proceeding until an arbitration has been had in accordance with the terms of the agreement:
Provided, That the applicant for the stay is not in default in proceeding with such arbitration."
| Page 7 of 7