Session2a EMBA-AICNetbooks
Session2a EMBA-AICNetbooks
Assembly Line
A, B C D
0.3 0.4 0.3
minute minute minute
Assembly Line Performance
• Line Balancing
0.2
B
40 hours x 60 minutes / hour 2400
CT = = = 0.4 minute
6,000 units 6000
0.1 A D 0.3
0.1 + 0.2 + 0.3 + 0.4 1.0
N= = = 2.5 workstations
0.4 0.4
C
0.4
Line Balancing
WORK ELEMENT PRECEDENCE TIME (MIN)
A Press out sheet of fruit — 0.1
B Cut into strips A 0.2
C Outline fun shapes A 0.4
D Roll up and package B, C 0.3
0.2
B
40 hours x 60 minutes / hour 2400
CT = = = 0.4 minute
6,000 units 6000
0.1 A D 0.3
0.1 + 0.2 + 0.3 + 0.4 1.0
N= = = 2.5 workstations
0.4 0.4
C 3 workstations
0.4
Line Balancing
WORK ELEMENT PRECEDENCE TIME (MIN)
A Press out sheet of fruit — 0.1
B Cut into strips A 0.2
C Outline fun shapes A 0.4
D Roll up and package B, C 0.3
CT = 0.4
0.2
B N=3
0.1 A D 0.3
C
0.4
Line Balancing
REMAINING REMAINING
WORKSTATION ELEMENT TIME ELEMENTS
CT = 0.4
0.2
B N=3
0.1 A D 0.3
C
0.4
Line Balancing
REMAINING REMAINING
WORKSTATION ELEMENT TIME ELEMENTS
1 A 0.3 B, C
CT = 0.4
0.2
B N=3
0.1 A D 0.3
C
0.4
Line Balancing
REMAINING REMAINING
WORKSTATION ELEMENT TIME ELEMENTS
1 A 0.3 B, C
B 0.1 C, D
CT = 0.4
0.2
B N=3
0.1 A D 0.3
C
0.4
Line Balancing
REMAINING REMAINING
WORKSTATION ELEMENT TIME ELEMENTS
1 A 0.3 B, C
B 0.1 C, D
2 C 0.0 D
CT = 0.4
0.2
B N=3
0.1 A D 0.3
C
0.4
Line Balancing
REMAINING REMAINING
WORKSTATION ELEMENT TIME ELEMENTS
1 A 0.3 B, C
B 0.1 C, D
2 C 0.0 D
3 D 0.1 none
CT = 0.4
0.2
B N=3
0.1 A D 0.3
C
0.4
Line Balancing
REMAINING REMAINING
WORKSTATION Work
ELEMENT Work
TIME Work
ELEMENTS
station 1 station 2 station 3
1 A 0.3 B, C
B A, B C
0.1 D C, D
2 C 0.0 D
0.3 0.4 0.3
3 D minute 0.1
minute
none
minute
CT = 0.4
0.2
B N=3
0.1 A D 0.3
C
0.4
Line Balancing
REMAINING REMAINING
WORKSTATION Work
ELEMENT Work
TIME Work
ELEMENTS
station 1 station 2 station 3
1 A 0.3 B, C
B A, B C
0.1 D C, D
2 C 0.0 D
0.3 0.4 0.3
3 D minute 0.1
minute
none
minute
CT = 0.4
0.2
B N=3
C
0.4
KRISTEN’S COOKIES
Process Flowchart
Date: 9-30-02 Location: Graves Mountain
Analyst: TLR Process: Apple Sauce
Distance
Operation
Transport
Description
Storage
Inspect
(feet)
(min)
Time
Delay
Step
of
process
N
Is order
Place order complete?
Y
Give soup or salad order to chef Prepare soup or
salad order
Gives payment
to waiter Receive payment for meal
Credit
Cash or
Credit?
Cash
Collect change,
leave tip Bring change to customer
Fill in tip
amount Return credit slip to customer
Collect tip
Capacity
Actual output
Utilization =
Design capacity
Processing Time
Requirements &
Capacity Determination
Capacity Planning?
• Size and number of facilities
• Size and number of equipment/
machines
• Size of labor (personnel and shifts)
• Subcontract
• (Scheduling)
• (Impact on Quality)
Example
Item X
Annual demand forecast (units) 2000.00
Standard processing time (hour/unit) 0.40
Item X
Annual demand forecast (units) 2000.00
Standard processing time (hour/unit) 0.40
[Dp]product
M=
N
Item X
Annual demand forecast (units) 2000.00
Standard processing time (hour/unit) 0.40
[2000(0.4)] X
M= (250 days/year)(1 shift/day)(8 hours/shift)
Item X
Annual demand forecast (units) 2000.00
Standard processing time (hour/unit) 0.40
800
M= = 0.4 ≈ 1 machine
2000
Effective Capacity ?
- Impact of Managerial Decisions
Multiple Products
Item X Y
Annual demand forecast (units) 2000.00 6000.00
Standard processing time (hour/unit) 0.40 0.70
Item X Y
Annual demand forecast (units) 2000.00 6000.00
Standard processing time (hour/unit) 0.40 0.70
[2000(0.4)]X + [6000(0.7)]Y
M= (250 days/year)(1 shift/day)(8 hours/shift)
Item X Y
Annual demand forecast (units) 2000.00 6000.00
Standard processing time (hour/unit) 0.40 0.70
5000
M= = 2. 5 ≈ 3 machines
2000
Effective Capacity ?
- Impact of Operational Decisions
Capacity Cushion
Item X Y
Annual demand forecast (units) 2000.00 6000.00
Standard processing time (hour/unit) 0.40 0.70
Non-operating time % (C) = 15
Item X Y
Annual demand forecast (units) 2000.00 6000.00
Standard processing time (hour/unit) 0.40 0.70
Non-operating time % (C) = 15
[2000(0.4)]X + [6000(0.7)]Y
M= (250 days/year)(1 shift/day)(8 hours/shift)(1.0 – 15/100)
Item X Y
Annual demand forecast (units) 2000.00 6000.00
Standard processing time (hour/unit) 0.40 0.70
5000
M= = 2. 94 ≈ 3 machines
1700
Effective Capacity ?
- Impact of Operational Decisions
Lot sizing\Batching
Item X Y
Annual demand forecast (units) 2000.00 6000.00
Standard processing time (hour/unit) 0.40 0.70
Average lot size (units per run) 20.00 30.00
Standard setup time (hours) 1.00 1.20
Item X Y
Annual demand forecast (units) 2000.00 6000.00
Standard processing time (hour/unit) 0.40 0.70
Average lot size (units per run) 20.00 30.00
Standard setup time (hours) 1.00 1.20
5340
M = 1700 = 3. 14 ≈ 4 machines (versus 3 w/o lotsizing
considerations)
Impact of Lean Production
Practices
• Setup time reduction efforts
– GM versus Toyota
Impact of Lean Production
Practices
• Setup time reduction efforts
– GM versus Toyota
Capacity
increment
Time between
increments
Time
Capacity
increment
Time between
increments
Time
Five jobs (in the order that they have arrived) are waiting at the moment to be assigned to the
shopfloor.
How do you recommend to sequence the jobs? Why?
JOB Processing Time(days) Due Date (days from now)
A 2 7
B 8 16
C 4 4
D 10 17
E 5 15
F 12 18
Performance Measures
• Job flow time : actual processing time +
waits
• Job lateness : difference between actual job
completion time and the due date
• Makespan : total time needed to complete a
group of jobs
• Average number of jobs : WIP inventory
Priority Rules
• FCFS – first come first served
• SPT – shortest processing time
• EDD – earliest due date
• CR – critical ratio
FCFS
Job Sequence Processing Time Flow Time Due Date Lateness
A 2 2 7 0
C 4 6 4 2
E 5 11 15 0
B 8 19 16 3
D 10 29 17 12
F 12 41 18 23
Total 41 108 40
EDD
Job Sequence Processing Time Flow Time Due Date Lateness
C 4 4 4 0
A 2 6 7 0
E 5 11 15 0
B 8 19 16 3
D 10 29 17 12
F 12 41 18 23
Total 41 110 38
CR
Jobsequence (t=0) Process time Due date CR
A 2 7 (7-0)/2 = 3.5
B 8 16 (16-0)/8 = 2.0
C 4 4 (4-0)/4 = 1.0 ****
D 10 17 (17-0)/10 = 1.7
E 5 15 (15-0)/5 = 3.0
F 12 18 (18-0)/12 = 1.5
Job seq (t=4) Process time Due date CR
A 2 7 (7-4)/2 = 1.5
B 8 16 (16-4)/8 = 1.5
C [ 1 ]
D 10 17 (17-4)/10 = 1.3
E 5 15 (15-4)/5 = 2.2
F 12 18 (18-4)/12 = 1.17 ****
CR