PMP Math QA
PMP Math QA
Explanation
The most common formula for EAC is AC + bottom-up ETC. Plugging in the numbers from the question,
you get $138 + $62 = $200.
Question: 2
Correct
You are in charge of a software project and you are almost 40%
complete. The project stakeholders want a performance report to
date. You had planned to use Earned Value Management
methodology. You come up with the following numbers: EV = 100
AC = 300 PV = 150 BAC = 600. You and your team have faced
numerous issues till now. However, you choose to ignore the
current work performance and decide to go with what was
originally planned. Based on this information, what would be the
EAC for the project?
800
200
600
1200
Explanation
PMP Math
It is stated that the issues experienced in the project were ignored, so the past performance is not
considered and the planned values are considered. So, the formula: EAC = AC + (BAC - EV) = 300 +
(600 - 100) EAC = 800.
Question: 3
Correct
Neither
Path 2
Path 1
Explanation
The duration of both the paths is 7 weeks. Remember that the path with the longest duration is the critical
path and you can have more than one Critical Path.
Question: 4
Correct
PMP Math
As a part of the Executive Management team, you have a number
of project managers reporting to you. One of the project
managers has reported the data for their project that has got you
worried regarding the health of the project. EV = $ 300000, PV = $
550000, AC = $ 200000. You are worried since, as per your
calculations, the project is behind schedule. However, the Project
Manager disagrees and feels the project is ahead of schedule.
What is the correct interpretation of the data?
Both you and the project manager are correct as interpretation is very subjective
Explanation
SPI = EV / PV = 300000/550000 = less than 1. An SPI less than 1 indicates the project is behind
schedule.
Question: 5
Correct
PMP Math
reports on a monthly basis. At the end of the first month, you
report a CPI greater than 1 and also the SPI greater than 1. What
would this mean?
Explanation
SPI greater than 1 indicates the project is ahead of schedule, while a value less than 1 indicates the
project is behind schedule. CPI value greater than 1 indicates project is under budget, while a value less
than 1 indicates the project is over budget.
Question: 6
Correct
PMP Math
would the Three-point Cost estimate be using Triangular
Distribution?
$112000
$110000
$28000
$113000
Explanation
The question states the use of Three point estimate using triangular distribution. The formula for this
estimation technique is a + b + c /3, where a = Most Likely estimate, b = Estimate based on analysis of
the Best-case scenario, and c = Estimate based on analysis of the Worst-case scenario. So, the Three-
point estimate using Triangular distribution is 108000 + 90000 + 138000 / 3 = 336000/3 = $ 112000.
Question: 7
Correct
An activity has an Early Start (ES) of 5 days and Late Start (LS) of
16 days. What is the activity's float?
11 days
21 days
PMP Math
Question: 9
Correct
You cannot determine if your project is behind or ahead of schedule from the information
given.
Explanation
The project is 5 months long, so you are scheduled to complete 20 percent of the work every month. We
know PV=BAC*planned % complete After two months, the planned value (PV) should be $450,000*40%
= $180,000 We know EV=BAC*actual % complete After two months, you completed 35% of the work, so
the earned value (EV) is $450,000*35%=$157,500 We know SPI=EV/AC=157,000/180,000=.875
Question: 10
Correct
PMP Math
You are the project manager overseeing the development of a
new console video game. It has 10 components, and 5 team
members are working on it. There are 15 stakeholders for this
project, and one of the stakeholders is the previous owner of the
company. One of the components is of major concern because it
is a difficult one to implement. You find out that it will take 10
days to complete the component. You also find out that as of now
the CPI=.81, and the SPI=1.2. What should be your main concern
in this project at this time?
Cost
Schedule
Explanation
Your SPI is more than 1, which indicates that you are ahead of schedule, but your CPI is less than 1,
which suggests that you are over budget. Cost should be the main concern at this time.
Question: 11
Correct
While reviewing the status of your project, you found that for a
PMP Math
given time period, your AC is $390,000 and PV is 380,000. Your
have a budget of $900,000 and so far have completed 40 percent
of the work. What should you report to the management about
your project?
Explanation
EV= BAC* actual % complete So, EV = 900000*40 percent = $360,00 SV = EV-PV So, SV = 360,000 -
$380,000= -$20000 CV= EV ' AC So, CV = $360,000- $390,000 = -$30000 Since both CV and SV are
negative, you are over budget and behind the schedule. We know EV= BAC * actual % complete So, EV
= 900000 * 40 percent = $360,00 SV= EV-PV So, SV = 360,000 - $380,000= -$20000 CV= EV ' AC So,
CV = $360,000- $390,000 = -$30000 Since both CV and SV are negative, you are over budget and
behind the schedule.
Question: 12
Correct
PMP Math
0.9 based on the budget at completion (BAC). Which of the
following is true regarding your project's current situation as
reflected by this TCPI value?
Explanation
The to-complete performance index (TCPI) is a measure of the cost performance that is required to be
achieved with the remaining resources in order to meet a specified management goal, expressed as the
ratio of the cost to finish the outstanding work to the remaining budget. A TCPI value equal to 1.0 means
you are right on budget, and as long as you maintain the present cost performance index (CPI), you
should not exceed the project budget. A TCPI value greater than 1.0 means you need to take a stricter
cost management approach or you will exceed your budget at completion (BAC). A TCPI value less than
1.0 indicates you are within your budget and have done an excellent job of managing project costs.
Question: 13
Correct
PMP Math
To-Complete Performance Index
Variance Analysis
Trend Analysis
Explanation
To-Complete Performance Index (TCPI) is the calculated projection of cost performance that must be
achieved on the remaining work to meet a specified management goal. The formula to calculate TCPI is
Work Remaining (BAC-EV)/Funds Remaining (BAC-AC) or (EAC-AC), where AC is the Actual Cost, EV
is the Earned Value, EAC is Estimate at Completion, and BAC is Budget at Completion.
Question: 14
Correct
The project has been cancelled while it was executed. At that time the project was behind
schedule and on budget.
The project's deliverables have all been finished. The project came in behind schedule but
on budget.
The project's deliverables have all been finished. The project came in ahead of schedule but
on budget.
PMP Math
The project's deliverables have all been finished. The project came in on schedule but over
budget.
Explanation
When the project is completed all of the planned values will have been earned. so there is no variance (
PV=EV ). In the above scenario the project was recently closed out and SPI =0.7, this means that the
project terminated before finished all deliverables. The project has been canceled while it was executed.
At that time the project was behind schedule and on budget.
Question: 15
Correct
Explanation
PV=3/5=0.6 & EV=2.5/5= 0.5 So SV=EV-PV= 0.5-0.6=-0.1 && SPI= EV/PV=0.83
PMP Math
Question: 16
Correct
$41
$300
$450
$409
Explanation
CV=EV-AC. Since these are not given, we need to calculate these. Since EV=SPI*PV,
EV=.9*$500=$450. CPI=EV/AC therefore AC= EV/CPI= $450/1.1 = $409. Now we calculate CV=$450-
$409=$41
Question: 17
Correct
PMP Math
project?
$97,000
$145,000
$94,000
$80,500
Explanation
Estimate at Completion , i.e. EAC = AC + bottom-up ETC, EAC = $22,000 + $75,000 = $97,000.
Question: 18
Correct
$550
$600
PMP Math
$500
$400
Explanation
Using the PERT of 3-point estimate formula expected cost = (O+4xML+P)/6 = (400+4x500+900)/6, we
get $550.
Question: 19
skipped
PMP Math
Explanation
CPI = EV/AC = 100000/150000 = 0.67; SPI = EV/PV = 100000/100000 (5 coaches built as per plan)
Question: 20
Correct
0.625
1.6
1.25
1.667
Explanation
The question is asking about the efficiency that must be maintained to complete the project within the
estimate at
completion (EAC) rather than the original budget at completion (BAC). The formula required
for this calculation is TCPI =
(BAC - EV) / (EAC - AC). The BAC is the initial project budget which is
$20,000. The project's current earned value (EV)
is $15,000, which is calculated by multiplying the actual
percent complete (75% or 0.75) by the BAC ($20,000). The EAC
is the new budget of $25,000, and the
actual cost (AC) is $17,000. Following are the detailed calculations for the correct
answer to this
PMP Math
question:
BAC = $20,000
EV = 0.75 * $20,000 = $15,000
EAC = $25,000
AC = $17,000
Therefore:
TCPI
= (BAC - EV) / (EAC - AC) = ($20,000 - $15,000) / ($25,000 - $17,000) = $5,000 / $8,000 = 0.625
PMP Math