Cswdo Drop in Office
Cswdo Drop in Office
City of Dipolog
CITY PLANNING AND DEVELOPMENT OFFICE
PROGRAM OF WORKS
TOTAL 100.00
DETAILED ESTIMATE OF PROPOSED WORK
Item
Work Descriptions Unit Unit Cost Quantity Total
No.
I Filling Works cu.m. 104.53 75 7,839.60
II Form Works bd.ft 49.12 400 19,647.20
III Concrete & Masonry Works lot 494,280.00 1 494,280.00
IV Carpentry & Glass Works lot 163,838.20 1 163,838.20
V Roofing Works lot 141,726.00 1 141,726.00
VI Steel Works lot 190,323.00 1 190,323.00
VII Painting Works gals 83,602.80 1 83,602.80
VIII Plumbing Works lot 123,973.80 1 123,973.80
IX Electrical Works lot 37,276.30 1 37,276.30
MARIA CHAREL M. CABANTUG Engr. MA. TERESITA R. TUBUNGBANUA Engr. ALBERT S. ALIMPULOS
Casual Employee Project Devt. Officer - II City Development Coordinator
APPROVED:
Copy furnished:
1. City Mayor's Office
2. City Budget Office
3. City Treasurer's Office Hon. EVELYN T. UY
4. City Accountant Office City Mayor
5. City Engineering Office
charm2015
Project : Construction of CSWD Drop In Center
Location : Barangay Sta. Isabel, Dipolog City
Subject : Cost Estimates and Bill of Materials
charm2015
Project : Construction of CSWD Drop In Center
Location : Barangay Sta. Isabel, Dipolog City
Subject : Cost Estimates and Bill of Materials
charm2015
.3m x .3m Unglazed Floor Tiles 130 pcs. 35.00 4,550.00
.3m x .3m Glazed Wall Tiles (1.8 m from floor) 650 pcs. 35.00 22,750.00
Portland Cement 5 bags 285.00 1,425.00
4"ф Cutting diamond 2 pcs. 380.00 760.00
8' Tile Trim 4 pcs. 85.00 340.00
Tile Grout 35 kgs 60.00 2,100.00
Tile Adhesive 25 bags 325.00 8,125.00
h. Concrete Stairs with railings
Portland Cement 20 bags 285.00 5,700.00
Riversand 3 cu.m. Supplied by City Gov't
Coarse Aggregates 2 cu.m. Supplied by City Gov't
4" CHB 320 pcs. 12.00 3,840.00
10mmØ x 6m Def. Bars 6 pcs. 155.00 930.00
2"Ø G.I. Pipe Sched. 40 4 pcs. 1,300.00 5,200.00
1"Ø G.I. Pipe Sched. 40 4 pcs. 520.00 2,080.00
charm2015
Project : Construction of CSWD Drop In Center
Location : Barangay Sta. Isabel, Dipolog City
Subject : Cost Estimates and Bill of Materials
MARIA CHAREL M. CABANTUG Engr. MA. TERESITA R. TUBUNGBANUA Engr. ALBERT S. ALIMPULOS
Casual Employee Project Devt. Officer - II City Development Coordinator
charm2015
Project : Construction of CSWD Drop In Center
Location : Barangay Sta. Isabel, Dipolog City
Subject : Cost Estimates and Bill of Materials
charm2015
Project : Construction of CSWD Drop In Center
Location : Barangay Sta. Isabel, Dipolog City
Subject : Cost Estimates and Bill of Materials
charm2015
.3m x .3m Unglazed Floor Tiles 130 pcs. 35.00 4,550.00
.3m x .3m Glazed Wall Tiles (1.8 m from floor) 650 pcs. 35.00 22,750.00
Portland Cement 5 bags 285.00 1,425.00
4"ф Cutting diamond 2 pcs. 380.00 760.00
8' Tile Trim 4 pcs. 85.00 340.00
Tile Grout 35 kgs 60.00 2,100.00
Tile Adhesive 25 bags 325.00 8,125.00
h. Concrete Stairs with railings
Portland Cement 20 bags 285.00 5,700.00
Riversand 3 cu.m. 700.00 2,100.00
Coarse Aggregates 2 cu.m. 750.00 1,500.00
4" CHB 320 pcs. 12.00 3,840.00
10mmØ x 6m Def. Bars 6 pcs. 155.00 930.00
2"Ø G.I. Pipe Sched. 40 4 pcs. 1,300.00 5,200.00
1"Ø G.I. Pipe Sched. 40 4 pcs. 520.00 2,080.00
charm2015
Project : Construction of CSWD Drop In Center
Location : Barangay Sta. Isabel, Dipolog City
Subject : Cost Estimates and Bill of Materials
MARIA CHAREL M. CABANTUG Engr. MA. TERESITA R. TUBUNGBANUA Engr. ALBERT S. ALIMPULOS
Casual Employee Project Devt. Officer - II City Development Coordinator
charm2015
Republic of the Philippines
City of Dipolog
CITY PLANNING AND DEVELOPMENT OFFICE
PROGRAM OF WORKS
TOTAL 100.00
DETAILED ESTIMATE OF PROPOSED WORK
Item
Work Descriptions Unit Unit Cost Quantity Total
No.
I Filling Works cu.m. 104.53 75 7,839.60
II Form Works bd.ft 49.12 400 19,647.20
III Concrete & Masonry Works lot 494,280.00 1 494,280.00
IV Carpentry & Glass Works lot 163,838.20 1 163,838.20
V Roofing Works lot 141,726.00 1 141,726.00
VI Steel Works lot 190,323.00 1 190,323.00
VII Painting Works gals 83,602.80 1 83,602.80
VIII Plumbing Works lot 123,973.80 1 123,973.80
IX Electrical Works lot 37,276.30 1 37,276.30
MARIA CHAREL M. CABANTUG Engr. MA. TERESITA R. TUBUNGBANUA Engr. ALBERT S. ALIMPULOS
Casual Employee Project Devt. Officer - II City Development Coordinator
APPROVED:
Copy furnished:
1. City Mayor's Office
2. City Budget Office
3. City Treasurer's Office Hon. EVELYN T. UY
4. City Accountant Office City Mayor
5. City Engineering Office
charm2015
Project : Construction of CSWD Drop In Center
Location : Barangay Sta. Isabel, Dipolog City
Subject : Cost Estimates and Bill of Materials
charm2015
Project : Construction of CSWD Drop In Center
Location : Barangay Sta. Isabel, Dipolog City
Subject : Cost Estimates and Bill of Materials
charm2015
.6m x .6m Granite Floor Tiles 230 pcs. 250.00 57,500.00
.3m x .3m Unglazed Floor Tiles 130 pcs. 35.00 4,550.00
.3m x .3m Glazed Wall Tiles (1.8 m from floor) 650 pcs. 35.00 22,750.00
Portland Cement 15 bags 285.00 4,275.00
4"ф Cutting diamond 4 pcs. 380.00 1,520.00
8' Tile Trim 4 pcs. 85.00 340.00
Tile Grout 80 kgs 60.00 4,800.00
Tile Adhesive 60 bags 325.00 19,500.00
h. Concrete Stairs with railings
Portland Cement 20 bags 285.00 5,700.00
Riversand 3 cu.m. 700.00 2,100.00
Coarse Aggregates 2 cu.m. 750.00 1,500.00
4" CHB 320 pcs. 12.00 3,840.00
10mmØ x 6m Def. Bars 6 pcs. 155.00 930.00
.3m x .3m Ceramic Floor Tiles 100 pcs. 35.00 3,500.00
Tile Adhesive 4 bags 325.00 1,300.00
Tile Grout 4 kgs 60.00 240.00
1 1/2" Brass stair Nosing (6m) 2 pcs. 4,290.00 8,580.00
1 1/2" stair Nosing (8ft) PVC 3 pcs. 580.00 1,740.00
2"Ø Stainless Steel Pipe Sched. 40 2 pcs. 3,100.00 6,200.00
1"Ø Stainless Steel Pipe Sched. 40 2 pcs. 1,545.00 3,090.00
Stainless Welding Rod 2 kls 680.00 1,360.00
2"Ø G.I. Pipe Sched. 40 2 pcs. 1,300.00 2,600.00
1"Ø G.I. Pipe Sched. 40 2 pcs. 520.00 1,040.00
charm2015
1/4" Marine Plywood 52 pcs 495.00 25,740.00
170 pcs - 2" x 2" x 12' Mahogany 680 bd.ft 32.00 21,760.00
Solignum 4 gals 1,080.00 4,320.00
1" finishing Nails 5 kls 65.00 325.00
2 1/2" CWN 10 kls 58.00 580.00
3" CWN 5 kls 55.00 275.00
4" CWN 5 kls 55.00 275.00
4" Paint Brush 2 pcs 100.00 200.00
b. Doors
(D1) 1.70m x 2.1m Double Leaf Swing Door, Analok Frame
1 units 20,200.00 20,200.00
with 1/4" Bronze Glass (w/ Installation)
(D2) .80m x 2.10m Solid Panel Door with Jamb 4 units 8,500.00 34,000.00
(D3) 2.10m x .70m PVC Door w/ complete accessories 3 units 2,500.00 7,500.00
c. Windows
(W1) 1/4" thk x 4" x 26" Bronze jalousie glass 270 pcs 49.00 13,230.00
Aluminum Frame single control 20 pair 250.00 5,000.00
(W2) 1/4" thk x 4" x 26" Bronze jalousie glass 8 pcs 49.00 392.00
Aluminum Frame single control (4 Blade) 2 pair 80.00 160.00
(W3) 2.83m x 2.4m Fixed Curtain Window, Analok Frame
1 unit 16,050.00 16,050.00
with 1/4" Bronze Glass (w/ Installation)
B. Manpower P 46,485.00
Eng'g Asst. 1 man 25 days CEO Personnel
Skilled Worker 3 men 25 days 309.90 23,242.50
Laborer 3 men 25 days 309.90 23,242.50
ITEM NO. IV - TOTAL ESTIMATED COST P 196,492.00
charm2015
Item No. VII - Painting Works
Description Qty Unit Unit Price Amount
A. Materials P 69,240.00
Interior wall
Skim coat 22 gals 650.00 14,300.00
Latex Flat white 24 gals 550.00 13,200.00
Sand paper no. 60 20 pcs 20.00 400.00
Sand paper no. 100 20 pcs 20.00 400.00
Exterior walI
Skim coat 16 gals 650.00 10,400.00
Latex Flat white 16 gals 550.00 8,800.00
Sand paper no. 60 20 pcs 20.00 400.00
Sand paper no. 100 20 pcs 20.00 400.00
Ceiling
Enamel wall flat white 6 gals 600.00 3,600.00
Quick Dry Enamel ( White ) 8 gals 650.00 5,200.00
Patching compound powder 20 kls 60.00 1,200.00
Glazing Putty 5 gals 650.00 3,250.00
Epoxy pioneer a & b 3 liter 510.00 1,530.00
Fiber tape 1" 5 rolls 130.00 650.00
Sand paper no. 60 10 pcs 20.00 200.00
Sand paper no. 100 10 pcs 20.00 200.00
Paint Thinner 4 gals 300.00 1,200.00
1 liter T/C (Water Based)(Any desired Color) 20 cans 125.00 2,500.00
8" Paint Roller Includes Handle & Basin 6 pcs 150.00 900.00
4" Paint Brush 2 pcs 100.00 200.00
2" Paint Brush 2 pcs 30.00 60.00
1" Masking Tape 10 rolls 25.00 250.00
B. Manpower P 26,031.60
Eng'g Asst. 1 man 14 days CEO Personnel
Painter 3 men 14 days 309.90 13,015.80
Laborer 3 men 14 days 309.90 13,015.80
ITEM NO. VII - TOTAL ESTIMATED COST P 95,271.60
charm2015
Project : Construction of CSWD Drop In Center
Location : Barangay Sta. Isabel, Dipolog City
Subject : Cost Estimates and Bill of Materials
MARIA CHAREL M. CABANTUG Engr. MA. TERESITA R. TUBUNGBANUA Engr. ALBERT S. ALIMPULOS
Casual Employee Project Devt. Officer - II City Development Coordinator
charm2015
Project : Construction of CSWD Drop In Center
Location : Barangay Sta. Isabel, Dipolog City
Subject : Cost Estimates and Bill of Materials
charm2015
Project : Construction of CSWD Drop In Center
Location : Barangay Sta. Isabel, Dipolog City
Subject : Cost Estimates and Bill of Materials
charm2015
.6m x .6m Granite Floor Tiles 230 pcs. 250.00 57,500.00
.3m x .3m Unglazed Floor Tiles 130 pcs. 35.00 4,550.00
.3m x .3m Glazed Wall Tiles (1.8 m from floor) 650 pcs. 35.00 22,750.00
Portland Cement 15 bags 285.00 4,275.00
4"ф Cutting diamond 4 pcs. 380.00 1,520.00
8' Tile Trim 4 pcs. 85.00 340.00
Tile Grout 90 kgs 60.00 5,400.00
Tile Adhesive 70 bags 325.00 22,750.00
h. Concrete Stairs with railings
Portland Cement 20 bags 285.00 5,700.00
Riversand 3 cu.m. 700.00 2,100.00
Coarse Aggregates 2 cu.m. 750.00 1,500.00
4" CHB 320 pcs. 12.00 3,840.00
10mmØ x 6m Def. Bars 6 pcs. 155.00 930.00
.3m x .3m Ceramic Floor Tiles 100 pcs. 35.00 3,500.00
Tile Adhesive 4 bags 325.00 1,300.00
Tile Grout 4 kgs 60.00 240.00
1 1/2" Brass stair Nosing (6m) 2 pcs. 4,290.00 8,580.00
1 1/2" stair Nosing (8ft) PVC 3 pcs. 580.00 1,740.00
2"Ø Stainless Steel Pipe Sched. 40 2 pcs. 3,100.00 6,200.00
1"Ø Stainless Steel Pipe Sched. 40 2 pcs. 1,545.00 3,090.00
Stainless Welding Rod 2 kls 680.00 1,360.00
2"Ø G.I. Pipe Sched. 40 2 pcs. 1,300.00 2,600.00
1"Ø G.I. Pipe Sched. 40 2 pcs. 520.00 1,040.00
charm2015
1/4" Marine Plywood 52 pcs 495.00 25,740.00
170 pcs - 2" x 2" x 12' Mahogany 680 bd.ft 32.00 21,760.00
Solignum 4 gals 1,080.00 4,320.00
1" finishing Nails 5 kls 65.00 325.00
2 1/2" CWN 10 kls 58.00 580.00
3" CWN 5 kls 55.00 275.00
4" CWN 5 kls 55.00 275.00
4" Paint Brush 2 pcs 100.00 200.00
b. Doors
(D1) 1.70m x 2.1m Double Leaf Swing Door, Analok Frame
1 units 20,200.00 20,200.00
with 1/4" Bronze Glass (w/ Installation)
(D2) .80m x 2.10m Solid Panel Door with Jamb 4 units 8,500.00 34,000.00
(D3) 2.10m x .70m PVC Door w/ complete accessories 3 units 2,500.00 7,500.00
c. Windows
(W1) 1/4" thk x 4" x 26" Bronze jalousie glass 270 pcs 49.00 13,230.00
Aluminum Frame single control 20 pair 250.00 5,000.00
(W2) 1/4" thk x 4" x 26" Bronze jalousie glass 8 pcs 49.00 392.00
Aluminum Frame single control (4 Blade) 2 pair 80.00 160.00
(W3) 2.83m x 2.4m Fixed Curtain Window, Analok Frame
1 unit 16,050.00 16,050.00
with 1/4" Bronze Glass (w/ Installation)
B. Manpower P 46,485.00
Eng'g Asst. 1 man 25 days CEO Personnel
Skilled Worker 3 men 25 days 309.90 23,242.50
Laborer 3 men 25 days 309.90 23,242.50
ITEM NO. IV - TOTAL ESTIMATED COST P 196,492.00
charm2015
Item No. VII - Painting Works
Description Qty Unit Unit Price Amount
A. Materials P 58,075.00
Interior wall
Skim coat 15 gals 650.00 9,750.00
Latex Flat white 22 gals 550.00 12,100.00
Patching compound powder 20 kls 60.00 1,200.00
Sand paper no. 60 20 pcs 20.00 400.00
Sand paper no. 100 20 pcs 20.00 400.00
Exterior walI
Skim coat 10 gals 650.00 6,500.00
Latex Flat white 14 gals 550.00 7,700.00
Patching compound powder 16 kls 60.00 960.00
Sand paper no. 60 20 pcs 20.00 400.00
Sand paper no. 100 20 pcs 20.00 400.00
Ceiling
Enamel wall flat white 6 gals 600.00 3,600.00
Quick Dry Enamel ( White ) 8 gals 650.00 5,200.00
Glazing Putty 4 gals 650.00 2,600.00
Epoxy pioneer a & b 3 liter 510.00 1,530.00
Fiber tape 1" 5 rolls 130.00 650.00
Sand paper no. 60 5 pcs 20.00 100.00
Sand paper no. 100 5 pcs 20.00 100.00
Paint Thinner 4 gals 300.00 1,200.00
1 liter T/C (Water Based)(Any desired Color) 15 cans 125.00 1,875.00
8" Paint Roller Includes Handle & Basin 6 pcs 150.00 900.00
4" Paint Brush 2 pcs 100.00 200.00
2" Paint Brush 2 pcs 30.00 60.00
1" Masking Tape 10 rolls 25.00 250.00
B. Manpower P 23,242.50
Eng'g Asst. 1 man 15 days CEO Personnel
Painter 2 men 15 days 309.90 9,297.00
Laborer 3 men 15 days 309.90 13,945.50
ITEM NO. VII - TOTAL ESTIMATED COST P 81,317.50
charm2015
Project : Construction of CSWD Drop In Center
Location : Barangay Sta. Isabel, Dipolog City
Subject : Cost Estimates and Bill of Materials
MARIA CHAREL M. CABANTUG Engr. MA. TERESITA R. TUBUNGBANUA Engr. ALBERT S. ALIMPULOS
Casual Employee Project Devt. Officer - II City Development Coordinator
charm2015
Project : Construction of CSWD Drop In Center
Location : Barangay Sta. Isabel, Dipolog City
Subject : Cost Estimates and Bill of Materials
charm2015
Project : Construction of CSWD Drop In Center
Location : Barangay Sta. Isabel, Dipolog City
Subject : Cost Estimates and Bill of Materials
charm2015
.3m x .3m Unglazed Floor Tiles 130 pcs. 35.00 4,550.00
.3m x .3m Glazed Wall Tiles (1.8 m from floor) 650 pcs. 35.00 22,750.00
Portland Cement 5 bags 285.00 1,425.00
4"ф Cutting diamond 2 pcs. 380.00 760.00
8' Tile Trim 4 pcs. 85.00 340.00
Tile Grout 35 kgs 60.00 2,100.00
Tile Adhesive 25 bags 325.00 8,125.00
h. Concrete Stairs with railings
Portland Cement 20 bags 285.00 5,700.00
Riversand 3 cu.m. Supplied by City Gov't
Coarse Aggregates 2 cu.m. Supplied by City Gov't
4" CHB 320 pcs. 12.00 3,840.00
10mmØ x 6m Def. Bars 6 pcs. 155.00 930.00
2"Ø G.I. Pipe Sched. 40 4 pcs. 1,300.00 5,200.00
1"Ø G.I. Pipe Sched. 40 4 pcs. 520.00 2,080.00
1 1/2"X 8ft Stair Nosing PVC (Entrance only) 4 pcs. 580.00 2,320.00
charm2015
Item No. VII - Painting Works
Description Qty Unit Unit Price Amount
A. Materials P 61,290.00
Interior wall
Skim coat 18 bags 650.00 11,700.00
Latex Flat white 20 gals 550.00 11,000.00
Sand paper no. 60 20 pcs 20.00 400.00
Sand paper no. 100 20 pcs 20.00 400.00
Exterior walI
Skim coat 12 bags 650.00 7,800.00
Latex Flat white 15 gals 550.00 8,250.00
Sand paper no. 60 20 pcs 20.00 400.00
Sand paper no. 100 20 pcs 20.00 400.00
Ceiling
Enamel wall flat white 6 gals 600.00 3,600.00
Quick Dry Enamel ( White ) 8 gals 650.00 5,200.00
Patching compound powder 20 kls 60.00 1,200.00
Glazing Putty 5 gals 650.00 3,250.00
Epoxy pioneer a & b 3 liter 510.00 1,530.00
Fiber tape 1" 5 rolls 130.00 650.00
Sand paper no. 60 10 pcs 20.00 200.00
Sand paper no. 100 10 pcs 20.00 200.00
Paint Thinner 4 gals 300.00 1,200.00
1 liter T/C (Water Based)(Any desired Color) 20 cans 125.00 2,500.00
8" Paint Roller Includes Handle & Basin 6 pcs 150.00 900.00
4" Paint Brush 2 pcs 100.00 200.00
2" Paint Brush 2 pcs 30.00 60.00
1" Masking Tape 10 rolls 25.00 250.00
B. Manpower P 22,312.80
Eng'g Asst. 1 man 12 days CEO Personnel
Painter 3 men 12 days 309.90 11,156.40
Laborer 3 men 12 days 309.90 11,156.40
ITEM NO. VII - TOTAL ESTIMATED COST P 83,602.80
charm2015
Project : Construction of CSWD Drop In Center
Location : Barangay Sta. Isabel, Dipolog City
Subject : Cost Estimates and Bill of Materials
MARIA CHAREL M. CABANTUG Engr. MA. TERESITA R. TUBUNGBANUA Engr. ALBERT S. ALIMPULOS
Casual Employee Project Devt. Officer - II City Development Coordinator
charm2015
Republic of the Philippines
City of Dipolog
CITY PLANNING AND DEVELOPMENT OFFICE
PROGRAM OF WORKS
TOTAL 100.00
DETAILED ESTIMATE OF PROPOSED WORK
Item
Work Descriptions Unit Unit Cost Quantity Total
No.
I Filling Works cu.m. 104.53 75 7,839.60
II Form Works bd.ft 49.12 400 19,647.20
III Concrete & Masonry Works lot 494,280.00 1 494,280.00
IV Carpentry & Glass Works lot 163,838.20 1 163,838.20
V Roofing Works lot 141,726.00 1 141,726.00
VI Steel Works lot 190,323.00 1 190,323.00
VII Painting Works gals 83,602.80 1 83,602.80
VIII Plumbing Works lot 123,973.80 1 123,973.80
IX Electrical Works lot 37,276.30 1 37,276.30
MARIA CHAREL M. CABANTUG Engr. MA. TERESITA R. TUBUNGBANUA Engr. ALBERT S. ALIMPULOS
Casual Employee Project Devt. Officer - II City Development Coordinator
APPROVED:
Copy furnished:
1. City Mayor's Office
2. City Budget Office
3. City Treasurer's Office Hon. EVELYN T. UY
4. City Accountant Office City Mayor
5. City Engineering Office
charm2015
c. Pipes and Fittings (Sanitary Line)
4"Ø Neltex PVC Pipe (s-1000) pcs
3"Ø Neltex PVC Pipe (s-1000) pcs
2"Ø Neltex PVC Pipe (s-1000) pcs
4"Ø x 90⁰ PVC Elbow pcs
3"Ø x 90⁰ PVC Elbow pcs
2"Ø x 90⁰ PVC Elbow pcs
4"Ø x 45⁰ PVC Elbow pcs
2"Ø x 45⁰ PVC Elbow pcs
3"Ø PVC Tee pcs
2"Ø x 2"Ø PVC Tee pcs
3"Ø PVC P-Trap pcs
4"Ø PVC P-Trap pcs
4"Ø PVC Clean out pcs
4"Ø x 2" PVC Wye pcs
3"Ø x 4"Ø PVC Wye pcs
4"Ø x 4"Ø PVC Wye pcs
PVC Solvent Cement 400cc Neltex can
d. Pipes and Fittings (Water Line)
1 1/2"Ø x 10' PVC Blue Pipe (s-1000) pcs
1"Ø x 10' PVC Pipe Blue (s-1000) pcs
1/2"Ø x 10' PVC Pipe Blue (s-1000) pcs
1/2"Ø x 1"Ø PVC Tee Reducer (s-1000) pcs
1 1/2"Ø x 1"Ø PVC Tee Reducer (s-1000) pcs
1/2"Ø x 1/2"Ø PVC Tee (s-1000) pcs
1/2"Ø x 90° PVC Plain Elbow pcs
1/2"Ø x 90° PVC Threaded Elbow pcs
1/2" Teflon Tape pcs
Brass Gatevalve 1"Ø pcs
Brass Gatevalve 1 1/2"Ø pcs
fuz2010
PURCHASE REQUEST
DIPOLOG CITY
#NAME?
#NAME?
TOTAL #NAME?
Purpose: Completion of 36 stalls at Bus Terminal Parking Shed
at Miputak, Dipolog City
Signature
#NAME?
#NAME?
TOTAL #NAME?
Purpose: Completion of 36 stalls at Bus Terminal Parking Shed
at Miputak, Dipolog City
Signature
Printed Name NEDILLA D. MAGDAYAO SANCEN D. CARORO EVELYN T. UY
Designation City Engineer City Treasurer City Mayor
Annex A
Republic of the Philippines
CITY GOVERNMENT OF DIPOLOG
Dipolog City
Payee
Office
Address Dipolog City
Responsibility Account
Center Particulars F.F.R. Code Amount
Charge to:
2009-20% Development Fund
Small Infrastructure Project
Total P
A. Certified B. Certified
Charges to appropriation/Allotment necessary, lawful
and my direct supervision Existence of available appropriation
Supporting documents valid, proper and legal
Signature Signature
Date Date
SUPPLEMENTAL PROCUREMENT PLAN
CALENDAR YEAR 2009
LGU Form No. 01 APPENDIX "A"
Name of Local Government Unit: DIPOLOG CITY
Program Control No: Page 1 of 2 pages
ALBERT S. ALIMPULOS
OIC- City Dev't. Coordinator EVELYN T. UY
Requesting Official City Mayor
SUPPLEMENTAL PROCUREMENT PLAN
CALENDAR YEAR 2009
LGU Form No. 01 APPENDIX "A"
Name of Local Government Unit: DIPOLOG CITY
Program Control No: Page 2 of 2 pages
ALBERT S. ALIMPULOS
OIC- City Dev't. Coordinator EVELYN T. UY
Requesting Official City Mayor
Pe pipe 1/2 sdr-50 50 mts
Pvc blue pipe 1/2 15 pcs
Pvc blue tee 1/2 10 pcs
Pvc blue elbow 1/2 35 pcs
Pvc blue plug 1/2 16 pcs
Pvc male adator plug 1/2 16 pcs
Brass gate valve 1/2 10 pcs
Faucet plastic 10 pcs
Pvc elbow 2"x90 sch. 1000 15 pcs
Pvc wye 2"x2" sch. 1000 15 pcs
Pvc pipe 2"x 3m s-1000 5 pcs
Pvc P-trap 2" 6 pcs
water Closet 5 set
Lavatory 5 set
Floor Drain 9 set
Dome type stainless strainer 4" 4 set
Lavatory foucet 5 set
Pvc Pipe 4"x3m sch. 1000 32 pcs
Pvc Wye 4"x4" sch. 1000 30 pcs
Pvc Elbow 4"x 90 sch. 1000 20 pcs
Pvc Elbow 4"x45m sch. 1000 10 pcs
Pvc Wye 4"x2" sch. 1000 9 pcs
Pvc Tee 2"x2"m sch. 1000 20 pcs
Pvc elbow 2"x90 sch. 1000 30 pcs
Pvc elbow 2"x45 sch. 1000 9 pcs
Pvc P-trap 4"x4" sch. 1000 9 pcs
Pvc pipe 2"x6m sch. 1000 3 pcs
Pvc Clean Out 4" sch. 1000 15 pcs
Neltex 400cc 6 can