Gabčíkovo-Nagymaros Project (Hungary v. Slovakia) PDF
Gabčíkovo-Nagymaros Project (Hungary v. Slovakia) PDF
Gabčíkovo-Nagymaros Project (Hungary v. Slovakia) PDF
REPORTS O F JUDGMENTS,
ADVISORY OPINIONS AND ORDERS
CASE CONCERNING
THE GABCIKOVO-NAGYMAROS PROJECT
(HUNGARYISLOVAKIA)
Sales number
ISSN 0074-4441
ISBN 92-1-070757-5
No de vente: 692
25 SEPTEMBER 1997
JUDGMENT
GABC~KOVO-NACYMAROS PROJECT
(HUNGARYISLOVAKIA)
PROJET GABCIKOVO-NAGYMAROS
(HONGRIEISLOVAQUIE)
INTERNATIONAL COURT O F JUSTICE
CASE CONCERNING
THE GABC~KOVO-NAGYMAROSPROJECT
(HUNGARYISLOVAKIA)
ting the parties, by mutual consent, to take account of those norms - Repudia-
tion of the Treaty - Reciprocal non-compliance - Integrity of the rule pacta
sunt servanda - Treaty remaining in force until terminated by mutual consent.
JUDGMENT
composed as above,
after deliberation,
delivers the following Judgment ;
1. By a letter dated 2 July 1993, filed in the Registry of the Court on the
same day, the Ambassador of the Republic of Hungary (hereinafter called
"Hungary") to the Netherlands and the Chargé d'affaires ad interim of the Slo-
vak Republic (hereinafter called "Slovakia") to the Netherlands jointly notified
to the Court a Special Agreement in English that had been signed at Brussels
o n 7 April 1993 and had entered into force on 28 June 1993, on the date of the
exchange of instruments of ratification.
2. The text of the Special Agreement reads as follows:
GABcIKOVO-NAGYMAROS PROJECT (JUDGMENT)
( c ) what are the legal effects of the notification, on 19 May 1992, of the
termination of the Treaty by the Republic of Hungary.
(2) The Court is also requested to determine the legal consequences,
including the rights and obligations for the Parties, arising from its Judg-
ment on the questions in paragraph 1 of this Article.
Article 3
(1) Al1 questions of procedure and evidence shall be regulated in accord-
ance with the provisions of the Statute and the Rules of Court.
(2) However. the Parties request the Court to order that the written
proceedings should consist of:
(LI)a Memorial presented by each of the Parties not later than ten
months after the date of notification of this Special Agreement to the
Registrar of the International Court of Justice;
( h i a Counter-Memorial presented by each of the Parties not later than
seven months after the date o n which each has received the certified
copy of the Memorial of the other Party;
( c i a Reply presented by each of the Parties within such time-limits as the
Court may order.
(d) The Court may request additional written pleadings by the Parties if
it so determines.
(3) The above-mentioned parts of the written proceedings and their
annexes presented to the Registrar will not be transmitted to the other
Party until the Registrar has received the corresponding part of the pro-
ceedings from the said Party.
Article 4
(1) The Parties agree that, pending the final Judgment of the Court,
they will establish and implement a temporary water management régime
for the Danube.
(2) They further agree that, in the period before such a régime is estab-
lished or implemented, if either Party believes its rights are endangered by
the conduct of the other, it may request immediate consultation and ref-
erence, if necessary, to experts, including the Commission of the European
Communities, with a view to protecting those rights; and that protection
shall not be sought through a request to the Court under Article 41 of the
Statute.
to visit the locality to which the case relates and there to exercise its functions
with regard to the obtaining of evidence, in accordance with Article 66 of the
Rules of Court. For his part, the Agent of Hungary indicated, by a letter dated
28 June 1995, that, if the Court should decide that a visit of that kind would be
useful, his Government would be pleased to co-operate in organizing it. By a
letter dated 14 November 1995, the Agents of the Parties jointly notified to the
Court the text of a Protocol of Agreement, concluded in Budapest and New
York the same day, with a view to proposing to the Court the arrangements
that might be made for such a visit in situ; and, by a letter dated 3 February
1997, they jointly notified to it the text of Agreed Minutes drawn up in Buda-
pest and New York the same day, which supplemented the Protocol of Agree-
ment of 14 November 1995. By an Order dated 5 February 1997, the Court
decided t o accept the invitation to exercise its functions with regard to the
obtaining of evidence at a place to which the case relates and, to that end, to
adopt the arrangements proposed by the Parties. The Court visited the area
from 1 to 4 April 1997; it visited a number of locations along the Danube and
took note of the technical explanations given by the representatives who had
been designated for the purpose by the Parties.
I l . The Court held a first round of ten public hearings from 3 to 7 March
and from 24 to 27 March 1997, and a second round of four public hearings on
10, 1 1, 14 and 15 April 1997, after having made the visit in situ referred to in
the previous paragraph. During those hearings, the Court heard the oral argu-
ments and replies of:
For Hungary: H . E . Mr. Szénasi,
Professor Valki,
Professor Kiss,
Professor Vida,
Professor Carbiener,
Professor Crawford,
Professor Nagy,
Dr. Kern,
Professor Wheater,
Ms Gorove.
Professor Dupuy,
Professor Sands.
For Slovakia: H.E. Dr. Tomka,
Dr. Mikulka,
Mr. Wordsworth,
Professor McCaffrey,
Professor Mucha,
Professor Pellet,
Mr. Refsgaard,
Sir Arthur Watts.
12. The Parties replied orally and in writing to various questions put by
Members of the Court. Referring to the provisions of Article 72 of the Rules of
Court, each of the Parties submitted to the Court its comments upon the replies
given by the other Party to some of those questions.
15 GABC~KOVO-NAGYMAROSPROJECT (JUDGMENT)
13. In the course of the written proceedings, the following submissions were
presented by the Parties:
On hekaif of Hungary,
in the Memorial, the Counter-Memorial and the Reply (mutatis mutandis iden-
ticai texts) :
"On the basis of the evidence and legal argument presented in the
Memorial, Counter-Memorial and this Reply, the Republic of Hungary
On behaif of Slovakia,
in the Memorial, the Counter-Memorial and the Reply (mutatis mutandis iden-
tical texts) :
"On the basis of the evidence and legal arguments presented in the Slo-
vak Memorial, Counter-Memorial and in this Reply, and reserving the
right to supplement or amend its claims in the light of further written
pleadings, the Slovak Republic
Requests fhe Court to udjudge and declare:
1. That the Treaty between Czechoslovakia and Hungary of 16 September
1977 concerning the construction and operation of the Gabtikovol
Nagymaros System of Locks, and related instruments, and to which the
Slovak Republic is the acknowledged successor, is a treaty in force and
has been so from the date of its conclusion; and that the notification of
termination by the Republic of Hungary on 19 May 1992 was without
legal effect.
2. That the Republic of Hungary was not entitled to suspend and subse-
quently abandon the works on the Nagymaros Project and on that part
of the Gabtikovo Project for which the 1977 Treaty attributed respon-
sibility to the Republic of Hungary.
3. That the act of proceeding with and putting into operation Variant C,
the 'provisional solution', was lawful.
4. That the Republic of Hungary must therefore cease forthwith al1 con-
duct which impedes the full and bona fide implementation of the 1977
Treaty and must take al1 necessary steps to fulfil its own obligations
under the Treaty without further delay in order to restore compliance
with the Treaty.
5. That, in consequence of its breaches of the 1977 Treaty, the Republic of
Hungary is liable to pay, and the Slovak Republic is entitled to receive,
full compensation for the loss and damage caused to the Slovak Repub-
lic by those breaches, plus interest and loss of profits, in the amounts
to be determined by the Court in a subsequent phase of the proceedings
in this case."
14. In the oral proceedings. the following submissions were presented by the
Parties
On behaif of Huagury,
at the hearing of 1 1 April 1997:
The submissions read at the hearing were mutatis mutandis identical to those
presented by Hungary during the written proceedings.
On behalf of' Slovakia,
at the hearing of 15 April 1997 :
"On the basis of the evidence and legal arguments presented in its writ-
ten and oral pleadings, the Slovak Republic,
Requests the Court to adjudge and declare:
1. That the Treaty, as defined in the first paragraph of the Preamble to the
Compromis between the Parties, dated 7 April 1993, concerning the
construction and operation of the GabtikovolNagymaros System of
Locks and related instruments, concluded between Hungary and
Czechoslovakia and with regard to which the Slovak Republic is the
successor State, has never ceased to be in force and so remains, and
that the notification of 19 May 1992 of purported termination of the
Treaty by the Republic of Hungary was without legal effect;
2. That the Republic of Hungary was not entitled to suspend and subse-
quently abandon the works on the Nagymaros Project and on that part
of the Gabeikovo Project for which the 1977 Treaty attributes respon-
sibility to the Republic of Hungary;
3. That the Czech and Slovak Federal Republic was entitled, in Novem-
ber 1991, to proceed with the 'provisional solution' and to put this sys-
tem into operation from October 1992; and that the Slovak Republic
was, and remains, entitled to continue the operation of this system;
4. That the Republic of Hungary shall therefore cease forthwith al1 con-
duct which impedes the bona fide implementation of the 1977 Treaty
and shall take al1 necessary steps to fulfil its own obligations under the
Treaty without further delay in order to restore compliance with the
Treaty, subject to any amendments which may be agreed between the
Parties ;
5. That the Republic of Hungary shall give appropriate guarantees that it
will not impede the performance of the Treaty, and the continued
operation of the system;
6. That, in consequence of its breaches of the 1977 Treaty, the Republic of
Hungary shall, in addition to immediately resuming performance of its
Treaty obligations, pay to the Slovak Republic full compensation for
the loss and damage, including loss of profits, caused by those breaches
together with interest thereon;
7. That the Parties shall immediately begin negotiations with a view, in
particular, to adopting a new timetable and appropriate measures for
the implementation of the Treaty by both Parties, and to fixing the
amount of compensation due by the Republic of Hungary to the Slo-
vak Republic; and that. if the Parties are unable to reach an agreement
within six months, either one of them may request the Court to render
an additional Judgment to determine the modalities for executing its
Judgment."
17. The Danube has always played a vital part in the commercial and
economic development of its riparian States, and has underlined and
reinforced their interdependence, making international CO-operation
essential. Improvements to the navigation channel have enabled the Dan-
ube, now linked by canal to the Main and thence to the Rhine, to become
an important navigational artery connecting the North Sea to the Black
Sea. In the stretch of river to which the case relates, flood protection
measures have been constructed over the centuries, farming and forestry
practised, and, more recently, there has been an increase in population
and industrial activity in the area. The cumulative effects on the river and
on the environment of various human activities over the years have not
al1 been favourable, particularly for the water régime.
20 GABCIKOVO-NAGYMAROS
PROJECT (JUDGMENT)
Those delegates had, inter alia, "to ensure that construction of the Sys-
tem of Locks is . . . carried out in accordance with the approved joint
contractual plan and the project work schedule". When the works were
brought into operation, they were moreover "To establish the operating
Bratislava
Slovakia
Komarom
Szentendre
Island
SKETCH-MAP NO.2
Hungary
The Original Project
N.B.: This sketch-map has
been prepared for illustrative
purposes only
Sketch-mapnot to scale II
and operational procedures of the System of Locks and ensure compli-
ance therewith."
Article 4, paragraph 4, stipulated that:
"Operations relating to the joint investment [should] be organized
by the Contracting Parties in such a way that the power generation
plants [would] be put into service during the period 1986-1990."
Article 5 provided that the cost of the joint investment would be borne
by the contracting parties in equal measure. It specified the work to be
carried out by each one of them. Article 8 further stipulated that the
Dunakiliti dam, the bypass canal and the two series of locks at Gab-
Cikovo and Nagymaros would be "jointly owned" by the contracting
parties "in equal measure". Ownership of the other works was to be
vested in the State on whose territory they were constructed.
The parties were likewise to participate in equal measure in the use of
the system put in place, and more particularly in the use of the base-load
and peak-load power generated at ,the hydroelectric power plants
(Art. 9).
According to Article 10, the works were to be managed by the State on
whose territory they were located, "in accordance with the jointly-agreed
operating and operational procedures", while Article 12 stipulated that
the operation, maintenance (repair) and reconstruction costs of jointly
- owned works of the System of Locks were also to be borne jointly by the
contracting parties in equal measure.
20. Thus, the Project was to have taken the form of an integrated joint
project with the two contracting parties on an equal footing in respect of
the financing, construction and operation of the works. Its single and
indivisible nature was to have been realized through the Joint Contrac-
tua1 Plan which complemented the Treaty. In particular, Hungary would
have had control of the sluices at Dunakiliti and the works at Nagy-
maros, whereas Czechoslovakia would have had control of the works at
GabCikovo.
21. The schedule of work had for its part been fixed in an Agreement
on mutual assistance signed by the two parties on 16 September 1977, at
25 GABCIKOVO-NAGYMAROS
PROJECT (JUDGMENT)
the same time as the Treaty itself. The Agreement moreover made some
adjustments to the allocation of the works between the parties as laid
down by the Treaty.
Work on the Project started in 1978. On Hungary's initiative, the two
parties first agreed, by two Protocols signed on 10 October 1983 (one
amending Article 4, paragraph 4, of the 1977 Treaty and the other the
Agreement on mutual assistance), to slow the work down and to post-
pone putting into operation the power plants, and then, by a Protocol
signed on 6 February 1989 (which amended the Agreement on mutual
assistance), to accelerate the Project.
22. As a result of intense criticism which the Project had generated in
Hungary, the Hungarian Government decided on 13 May 1989 to sus-
pend the works at Nagymaros pending the completion of various studies
which the competent authorities were to finish before 31 July 1989. On
21 July 1989, the Hungarian Government extended the suspension of the
works at Nagymaros until 31 October 1989, and, in addition, suspended
the works at Dunakiliti until the same date. Lastly, on 27 October 1989,
Hungary decided to abandon the works at Nagymaros and to maintain
the status quo at Dunakiliti.
23. During this period, negotiations were being held between the
parties. Czechoslovakia also started investigating alternative solutions.
One of them, subsequently known as "Variant CM,entailed a unilateral
diversion of the Danube by Czechoslovakia on its territory some 10 kilo-
metres upstream of Dunakiliti (see sketch-map Nol 3, p. 26 below). In its
final stage, Variant C included the construction at Cunovo of an overflow
dam and a levee linking that dam to the south bank of the bypass canal.
The corresponding reservoir was to have a smaller surface area and pro-
vide approximately 30 per cent less storage than the reservoir initially
contemplated. Provision was made for ancillary works, namely: an intake
structure to supply the Mosoni Danube; a weir to enable, inter dia,
floodwater to be directed along the old bed of the Danube: an auxiliary
shiplock; and two hydroelectric power plants (one capable of an aniiual
production of 4 GWh on the Mosoni Danube, and the other with a pro-
duction of 174 GWh on the old bed of the Danube). The supply of water
to the side-arms of the Danube on the Czechoslovak bank was to be
secured by means of two intake structures in the bypass canal a t
DobrohoSt' and GabEikovo. A solution was to be found for the Hungar-
ian bank. Moreover, the question of the deepening of the bed of the Dan-
ube a t the confluence of the bypass canal and the old bed of the river
remained outstanding.
on 19 April 1995. That Agreement raised the discharge of water into the
Mosoni Danube to 43 m3/s. It provided for an annual average of 400 m3/s
in the old bed (not including flood waters). Lastly, it provided for the con-
struction by Hungary of a partially underwater weir near to Dunakiliti
with a view to improving the water supply to the side-arms of the Danube
on the Hungarian side. It was specified that this temporary agreement
would come to an end 14 days after the Judgment of the Court.
Lastly the Court notes that the Parties, in setting out the replies which
should in their view be given to the questions put in the Special Agree- ,
ment, concentrated their reasoning on the 1977 Treaty; and that they
would appear to have extended their arguments to "related instruments"
in considering them as accessories to a whole treaty system, whose fate
was in principle linked to that of the main part, the 1977 Treaty. The
Court takes note of the positions of the Parties and considers that it does
not need to go into this matter further at this juncture.
29 GABCIKOVO-NAGYMAROS
PROJECT (JUDGMENT)
30. As the Court has already indicated (see paragraph 18 above), Ar-
ticle 1, paragraph 4, of the 1977 Treaty stipulated in general terms that
the "technical specifications" concerning the System of Locks would be
included in the "ioint contractual dan". The schedule of work had for its
part been fixed in an Agreement on mutual assistance signed by the two
parties on 16 September 1977 (see paragraph 21 above). In accordance
with the provisions of Article 1, paragraph 1, of that Agreement, the
whole of the works of the barrage
. + svstem
, were to have been comoleted in
1991. As indicated in paragraph 2 of that same article, a summary con-
struction schedule was appended to the Agreement, and provision was
made for a more detailed schedule to be worked out in the Joint Con-
tractual Plan. The Agreement of 16 September 1977 was twice amended
further. By a Protocol signed on 10 October 1983, the parties agreed first
to postpone the works and the putting into operation of the power plants
for four more years; then, by a Protocol signed on 6 February 1989, the
parties decided, conversely, to bring them forward by 15 months, the
whole system having to be operational in 1994. A new summary con-
struction schedule was appended to each of those Protocols; those sched-
ules were in turn t o be implemented by means of new detailed schedules,
included in the Joint Contractual Plan.
31. In spring 1989, the work on the GabCikovo sector was well
advanced: the Dunakiliti dam was 90 per cent complete, the Gabëikovo
dam was 85 per cent complete, and the bypass canal was between 60 per
cent complete (downstream of Gabcikovo) and 95 per cent complete
(upstream of GabCikovo) and the dykes of the Dunakiliti-HruSov reser-
voir were between 70 and 98 per cent complete, depending on the loca-
tion. This was not the case in the Nagymaros sector where, although
dykes had been built, the only structure relating to the dam itself was the
coffer-dam which was to facilitate its construction.
32. In the wake of the profound political and economic changes which
occurred at this time in central Europe, the Gabcikovo-Nagymaros
Project was the object, in Czechoslovakia and more particularly in Hun-
gary, of increasing apprehension, both within a section of public opinion
and in some scientific circles. The uncertainties not only about the eco-
nomic viability of the Project, but also, and more so, as to the guarantees
it offered for preservation of the environment, engendered a climate of
growing concern and opposition with regard to the Project.
33. It was against this background that, on 13 May 1989, the Govern-
ment of Hungary adopted a resolution to suspend works at Nagymaros,
and ordered
. . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Having studied the expected impacts of the construction in accord-
ance with the original plan, the Committee [ad hoc] of the Academy
[set up for this purpose] came to the conclusion that we do not have
adequate knowledge of the consequences of environmental risks.
In its opinion, the risk of constructing the Barrage System in
accordance with the original plan cannot be considered acceptable.
Of course, it cannot be stated either that the adverse impacts will
33 GABCIKOVO-NAGYMAROS PROJECT (JUDGMENT)
39. The two Parties to this case concur in recognizing that the 1977
Treaty, the above-mentioned Agreement on mutual assistance of 1977
and the Protocol of 1989 were validly concluded and were duly in force
when the facts recounted above took place.
Further, they do not dispute the fact that, however flexible they may
have been, these texts did not envisage the possibility of the signatories
unilaterally suspending or abandoning the work provided for therein, or
even carrying it out according to a new schedule not approved by the two
partners.
40. Throughout the proceedings, Hungary contended that, although it
did suspend or abandon certain works, on the contrary, it never sus-
pended the application of the 1977 Treaty itself. To justify its conduct, it
relied essentially on a "state of ecological necessity".
42. Hungary moreover contended from the outset that its conduct in
the present case should not be evaluated only in relation to the law of
treaties. It also observed that, in accordance with the provisions of
Article 4, the Vienna Convention of 23 May 1969 on the Law of Treaties
could not be applied to the 1977 Treaty, which was concluded before that
Convention entered into force as between the parties. Hungary has
indeed acknowledged, with reference to the jurisprudence of the Court,
that in many respects the Convention reflects the existing customary law.
Hungary nonetheless stressed the need to adopt a cautious attitude, while
37 GABCIKOVO-NACYMAROS PROJECT (JUDGMENT)
suggesting that the Court should consider, in each case, the conformity of
the prescriptions of the Convention with customary international law.
43. Slovakia, for its part, denied that the basis for suspending o r aban-
doning the performance of a treaty obligation can be found outside the
law of treaties. It acknowledged that the 1969 Vienna Convention could
not be applied as such to the 1977 Treaty, but at the same time stressed
that a number of its provisions are a reflection of pre-existing rules of
customary international law and specified that this is, in particular, the
case with the provisions of Part V relating to invalidity, termination and
suspension of the operation of treaties. Slovakia has moreover observed
that, after the Vienna Convention had entered into force for both parties,
Hungary affirmed its accession to the substantive obligations laid down
by the 1977 Treaty when it signed the Protocol of 6 February 1989 that
cut short the schedule of work: and this led it to conclude that the Vienna
Convention was applicable to'the "contractual legal régime" constituted
by the network of interrelated agreements of which the Protocol of 1989
was a part.
44. In the course of the proceedings, Slovakia argued at length that the
state of necessity upon which Hungary relied did not constitute a reason
for the suspension of a treaty obligation recognized by the law of treaties.
At the same time, it cast doubt upon whether "ecological necessity" or
"ecological risk" could, in relation to the law of State responsibility, con-
stitute a circumstance precluding the wrongfulness of a n act.
In any event, Slovakia denied that there had been any kind of "eco-
logical state of necessity" in this case either in 1989 o r subsequently. It
invoked the authority of various scientific studies when it claimed that
Hungary had given an exaggeratedly pessimistic description of the situa-
tion. Slovakia did not, of course, deny that ecological problems could
have arisen. However, it asserted that they could to a large extent have
been remedied. It accordingly stressed that no agreement had been
reached with respect to the modalities of operation of the GabCikovo
power plant in peak mode, and claimed that the apprehensions of Hun-
gary related only to operating conditions of a n extreme kind. In the same
way, it contended that the original Project had undergone various modi-
fications since 1977 and that it would have been possible to modify it
even further, for example with respect to the discharge of water reserved
for the old bed of the Danube, o r the supply of water to the side-arms by
means of underwater weirs.
45. Slovakia moreover denied that it in any way breached the 1977
Treaty - particularly its Articles 15 and 19 - and maintained, inter dia,
that according to the terms of Article 3, paragraph 2, of the Agreement
of 6 May 1976 relating to the Joint Contractual Plan, research into the
impact of the Project on the environment was not the exclusive respon-
sibility of Czechoslovakia but of either one of the parties, depending on
the location of the works.
Lastly, in its turn, it reproached Hungary with having adopted its uni-
lateral measures of suspension and abandonment of the works in viola-
tion of the provisions of Article 27 of the 1977 Treaty (see paragraph 18
above), which it submits required prior recourse to the machinery for dis-
pute settlement provided for in that Article.
46. The Court has n o need to dwell upon the question of the applica-
bility in the present case of the Vienna Convention of 1969 on the Law of
Treaties. It needs only to be mindful of the fact that it has several times
had occasion to hold that some of the rules laid down in that Convention
might be considered as a codification of existing customary law. The
Court takes the view that in many respects this applies to the provisions
of the Vienna Convention concerning the termination and the suspension
of the operation of treaties, set forth in Articles 60 to 62 (see Legal Con-
seyuences for States o f t h e Continued Presence of South Afiicu in Namibia
(South West Ajrica) not1vithstunding Security Council Resolution 276
(1970), Advisory Opinion, I.C.J. Reports. 1971, p. 47, and Fisheries
Jurisdiction (United Kingdom v. Iceland), Jurisdiction of the Court,
Judgment, I.C.J. Reports 1973, p. 1 8 ; see also Interpretation qf the
Agreement of 25 Murch 1951 hetitjeen the W H O and Egypt, Advisory
Opinion, 1.C.J. Reports 1980, pp. 95-96).
Neither has the Court lost sight of the fact that the Vienna Convention
is in any event applicable to the Protocol of 6 February 1989 whereby
Hungary and Czechoslovakia agreed to accelerate completion of the
works relating to the GabEikovo-Nagymaros Project.
47. Nor does the Court need to dwell upon the question of the rela-
tionship between the law of treaties and the law of State responsibility, to
which the Parties devoted lengthy arguments, as those two branches of
international law obviously have a scope that is distinct. A determination
of whether a convention is o r is not in force, and whether it has or has
not been properly suspended o r denounced, is to be made pursuant to the
law of treaties. O n the other hand, a n evaluation of the extent to which
the suspension o r denunciation of a convention, seen as incompatible
with the law of treaties, involves the responsibility of the State which pro-
ceeded to it, is to be made under the law of state responsibility.
49. The Court will now consider the question of whether there was, in
1989, a state of necessity which would have permitted Hungary, without
incurring international responsibility, to suspend and abandon works
that it was committed to perform in accordance with the 1977 Treaty and
related instruments.
50. In the present case, the Parties are in agreement in considering that
the existence of a state of necessity must be evaluated in the light of the
criteria laid down by the International Law Commission in Article 33 of
the Draft Articles on the International Responsibility of States that it
adopted on first reading. That provision is worded as follows:
"Article 33. Stufe of' Necrssify
1. A state of necessity may not be invoked by a State as a ground
for precluding the wrongfulness of an act of that State not in con-
formity with an international obligation of the State unless:
( a ) the act was the only means of safeguarding an essential interest
of the State against a grave and imminent peril; and
40 GABCIKOVO-NAGYMAROS PROJECT (JUDGMENT)
( 6 ) the act did not seriously impair an essential interest of the State
towards which the obligation existed.
2. In any case, a state of necessity may not be invoked by a State
as a ground for precluding wrongfulness:
( a ) if the international obligation with which the act of the State is
not in conformity arises out of a peremptory norm of general
international law; or
( b ) if the international obligation with which the act of the State is
not in conformity is laid down by a treaty which, explicitly or
implicitly, excludes the possibility of invoking the state of neces-
sity with respect to that obligation; or
(c) if the State in question has contributed to the occurrence of the
state of necessity." (Yearbook of the International Laiv Com-
mission, 1980, Vol. II, Part 2, p. 34.)
In its Commentary, the Commission defined the "state of necessity" as
being
"the situation of a State whose sole means of safeguarding an essen-
tial interest threatened by a grave and imminent peril is to adopt
conduct not in conformity with what is required of it by an interna-
tional obligation to another State" (ibid., para. 1).
have been the "only means" of safeguarding that interest; that act must
not have "seriously impair[ed] an essential interest" of the State towards
which the obligation existed; and the State which is the author of that act
must not have "contributed to the occurrence of the state of necessity".
Those conditions reflect customary international law.
The Court will now endeavour to ascertain whether those conditions
had been met a t the time of the suspension and abandonment, by Hun-
gary, of the works that it was to carry out in accordance with the 1977
Treaty.
53. The Court has no difficulty in acknowledging that the concerns
expressed by Hungary for its natural environment in the region affected
by the Gabtikovo-Nagymaros Project related to an "essential interest" of
that State, within the meaning given to that expression in Article 33 of
the Draft of the International Law Commission.
The Court recalls that it has recently had occasion to stress, in the fol-
lowing terms, the great significance that it attaches to respect for the envi-
ronment, not only for States but also for the whole of mankind:
56. The Court now comes to the GabEikovo sector. It will recall that
Hungary's concerns in this sector related on the one hand to the quality
of the surface water in the Dunakiliti reservoir, with its effects on the
quality of the groundwater in the region, and on the other hand, more
generally, to the level, movement and quality of both the surface water
and the groundwater in the whole of the Szigetkoz, with their effects on
the Sauna and flora in the alluvial plain of the Danube (see paragraph 40
above).
Whether in relation to the Dunakiliti site or to the whole of the
Szigetkoz, the Court finds here again, that the peril claimed by Hungary
was to be considered in the long term, and, more importantly, remained
uncertain. As Hungary itself acknowledges, the damage that it appre-
44 GABC~KOVO-NAGYMAROS PROJECT (JUDGMENT)
also, have resorted to other means in order to respond to the dangers that
it apprehended. In particular, within the framework of the original
Project, Hungary seemed to be in a position to control at least partially
the distribution of the water between the bypass canal, the old bed of the
Danube and the side-arms. It should not be overlooked that the Dunakiliti
dam was located in Hungarian territory and that Hungary could con-
struct the works needed to regulate flows along the old bed of the Dan-
ube and the side-arms. Moreover, it should be borne in mind that
Article 14 of the 1977 Treaty provided for the possibility that each of the
parties might withdraw quantities of water exceeding those specified in
the Joint Contractual Plan, while making it clear that, in such an event,
"the share of electric power of the Contracting Party benefiting from the
excess withdrawal shall be correspondingly reduced".
57. The Court concludes from the foregoing that, with respect to both
Nagymaros and GabCikovo, the perils invoked by Hungary, without pre-
judging their possible gravity, were not sufficiently established in 1989,
nor were they "imminent"; and that Hungary had available to it at that
time means of responding to these perceived perils other than the suspen-
sion and abandonment of works with which it had been entrusted. What
is more, negotiations were under way which might have led to a review of
the Project and the extension of some of its time-limits, without there
being need to abandon it. The Court infers from this that the respect by
Hungary, in 1989, of its obligations under the terms of the 1977 Treaty
would not have resulted in a situation "characterized so aptly by the
maxim summum jus summa injuria" ( Yearbook of the International Law
Commission, 1980, Vol. II, Part 2, p. 49, para. 31).
Moreover, the Court notes that Hungary decided to conclude the 1977
Treaty, a Treaty which - whatever the political circumstances prevailing
at the time of its conclusion - was treated by Hungary as valid and in
force until the date declared for its termination in May 1992. As can be
seen from the material before the Court, a great many studies of a scien-
tific and technical nature had been conducted a t an earlier time, both by
Hungary and by Czechoslovakia. Hungary was, then, presumably aware
of the situation as then known, when it assumed its obligations under the
Treaty. Hungary contended before the Court that those studies had been
inadequate and that the state of knowledge at that time was not such as
to make possible a complete evaluation of the ecological implications of
the GabCikovo-Nagymaros Project. It is nonetheless the case that
although the principal object of the 1977 Treaty was the construction of
a System of Locks for the production of electricity, improvement of navi-
gation on the Danube and protection against flooding, the need to ensure
the protection of the environment had not escaped the parties, as can be
seen from Articles 15, 19 and 20 of the Treaty.
What is more, the Court cannot fail to note the positions taken by
Hungary after the entry into force of the 1977 Treaty. In 1983, Hungary
asked that the works under the Treaty should go forward more slowly,
46 GABC~KOVO-NAGYMAROS PROJECT (JUDGMENT)
for reasons that were essentially economic but also, subsidiarily, related
to ecological concerns. In 1989, when, according to Hungary itself, the
state of scientific knowledge had undergone a significant development, it
asked for the works to be speeded up, and then decided, three months
later, to suspend them and subsequently to abandon them. The Court is
not however unaware that profound changes were taking place in Hun-
gary in 1989, and that, during that transitory phase, it might have been
more than usually difficult to co-ordinate the different points of view pre-
vailing from time to time.
The Court infers from al1 these elements that, in the present case, even
if it had been established that there was. in 1989, a state of necessity
linked to the performance of the 1977 Treaty, Hungary would not have
been permitted to rely upon that state of necessity in order to justify its
failure to comply with its treaty obligations, as it had helped, by act or
omission to bring it about.
58. It follows that the Court has no need to consider whether Hun-
gary, by proceeding as it did in 1989, "seriously impair[ed] an essential
interest" of Czechoslovakia, within the meaning of the aforementioned
Article 33 of the Draft of the International Law Commission - a finding
which does not in any way prejudge the damage Czechoslovakia claims
to have suffered on account of the position taken by Hungary.
Nor does the Court need to examine the argument put forward by
Hungary, according to which certain breaches of Articles 15 and 19 of
the 1977 Treaty, committed by Czechoslovakia even before 1989, con-
tributed to the purported state of necessity; and neither does it have to
reach a decision on the argument advanced by Slovakia, according to
which Hungary breached the provisions of Article 27 of the Treaty,
in 1989, by taking unilateral measures without having previously
had recourse to the machinery of dispute settlement for which that
Article provides.
59. In the light of the conclusions reached above, the Court, in reply to
the question put to it in Article 2, paragraph 1 ( a ) , of the Special Agree-
ment (see paragraph 27 above), finds that Hungary was not entitled to
suspend and subsequently abandon, in 1989, the works on the Nagy-
maros Project and on the part of the GabEikovo Project for which the
1977 Treaty and related instruments attributed responsibility to it.
61. The Court will recall that, as soon as Hungary suspended the
works a t Nagymaros on 13 May 1989 and extended that suspension to
certain works to be carried out a t Dunakiliti, Czechoslovakia informed
Hungary that it would feel compelled to take unilateral measures if Hun-
gary were to persist in its refusa1 to resume the works. This was inter alia
expressed as follows in Czechoslovakia's Note Verbale of 30 October
1989 to which reference is made in paragraph 37 above:
GabEikovo power plant into service and indicated that the available data
enabled the effects of four possible scenarios to be assessed, each of them
requiring the co-operation of the two Governments. At the same time, it
proposed the setting up of a tripartite committee of experts (Hungary,
Czechoslovakia, European Communities) which would help in the search
for technical solutions to the problems arising from the entry into opera-
tion of the GabCikovo sector. Hungary, for its part, took the view that :
72. Before dealing with the arguments advanced by the Parties, the
Court wishes to make clear that it is aware of the serious problems with
which Czechoslovakia was confronted as a result of Hungary's decision
to relinquish most of the construction of the System of Locks for which
it was responsible by virtue of the 1977 Treaty. Vast investments had
been made, the construction at GabEikovo was al1 but finished, the
bypass canal was completed, and Hungary itself, in 1991, had duly ful-
filled its obligations under the Treaty in this respect in completing work
on the tailrace canal. It emerges from the report, dated 31 October 1992,
of the tripartite fact-finding mission the Court has referred to in para-
graph 24 of the present Judgment, that not using the system would have
53 GABCIKOVO-NAGYMAROS PROJECT (JUDGMENT)
led to considerable financial losses, and that it could have given rise to
serious problems for the environment.
73. Czechoslovakia repeatedly denounced Hungary's suspension and
abandonment of works as a fundamental breach of the 1977 Treaty and
consequently could have invoked this breach as a ground for terminating
the Treaty; but this would not have brought the Project any nearer to
completion. It therefore chose to insist on the implementation of the
Treaty by Hungary, and on many occasions called upon the latter to
resume performance of its obligations under the Treaty.
When Hungary steadfastly refused to d o so although it had expressed
-
80. Slovakia also maintained that it was acting under a duty to miti-
gate damages when it carried out Variant C. It stated that "It is a general
principle of international law that a party injured by the non-perform-
ance of another contract party must seek to mitigate the damage he has
sustained."
It would follow from such a principle that an injured State which has
failed to take the necessary measures to limit the damage sustained would
not be entitled to claim compensation for that damage which could have
been avoided. While this principle might thus provide a basis for the cal-
culation of damages, it could not, on the other hand, justify an otherwise
wrongful act.
81. Since the Court has found that the putting into operation of Vari-
ant C constituted an internationally wrongful act, the duty to mitigate
damage invoked by Slovakia does not need to be examined further.
87. The Court thus considers that the diversion of the Danube carried
out by Czechoslovakia was not a lawful countermeasure because it was
not proportionate. It is therefore not required to pass upon one other
condition for the lawfulness of a countermeasure, namely that its purpose
must be to induce the wrongdoing State to comply with its obliga-
57 G A B ~ ~ K O V O - N A G Y M A R OPROJECT
S (JUDGMENT)
tions under international law, and that the measure must therefore be
reversible.
88. In the light of the conclusions reached above, the Court, in reply to
the question put to it in Article 2, paragraph 1 ( h ) , of the Special Agree-
ment (see paragraph 60), finds that Czechoslovakia was entitled to pro-
ceed, in November 1991, to Variant C in so far as it then confined itself
to undertaking works which did not predetermine the final decision to be
taken by it. O n the other hand, Czechoslovakia was not entitled to put
that Variant into operation from October 1992.
basis of what it saw as the scientific facts; and argued that even if such a
state of necessity had existed, this would not give rise to a right to ter-
minate the Treaty under the Vienna Convention of 1969 on the Law of
Treaties.
94. Hungary's second argument relied on the terms of Article 61 of the
Vienna Convention, which is worded as follows:
"Article 6 1
Supervening Impossibility of' Pe~forrnunce
1. A party may invoke the impossibility of performing a treaty as
a ground for terminating o r withdrawing from it if the impossibility
results from the permanent disappearance o r destruction of an object
indispensable for the execution of the treaty. If the impossibility is
temporary, it may be invoked only as a ground for suspending the
operation of the treaty.
2. Impossibility of performance may not be invoked by a party as
a ground for terminating, withdrawing from or suspending the opera-
tion of a treaty if the impossibility is the result of a breach by that
party either of an obligation under the treaty o r of any other inter-
national obligation owed to any other party to the treaty."
Hungary declared that it could not be "obliged to fulfil a practically
impossible task, namely to construct a barrage system on its own terri-
tory that would cause irreparable environmental damage". It concluded
that
"By May 1992 the essential object of the Treaty - a n economic
joint investment which was consistent with environmental protection
and which was operated by the two parties jointly - had perma-
nently disappeared, and the Treaty had thus become impossible to
perform."
In Hungary's view, the "object indispensable for the execution of the
treaty", whose disappearance o r destruction was required by Article 61 of
the Vienna Convention, did not have to be a physical object, but could
also include, in the words of the International Law Commission, "a legal
situation which was the raison d'être of the rights and obligations".
Slovakia claimed that Article 61 was the only basis for invoking impos-
sibility of performance as a ground for termination, that paragraph 1 of
that Article clearly contemplated physical "disappearance or destruction"
of the object in question, and that, in any event, paragraph 2 precluded
the invocation of impossibility "if the impossibility is the result of a
breach by that party . . . of an obligation under the treaty".
Slovakia, for its part, contended that the changes identified by Hun-
gary had not altered the nature of the obligations under the Treaty from
those originally undertaken, so that no entitlement to terminate it arose
from them.
96. Hungary further argued that termination of the Treaty was justi-
fied by Czechoslovakia's material breaches of the Treaty, and in this
regard it invoked Article 60 of the Vienna Convention on the Law of
Treaties, which provides:
PROJECT
GABC~KOVO-NAGYMAROS (JUDGMENT)
"Article 60
Terminution or Suspension of the Operution o f u Treaty
us u Consequence of Its Breach
1. A material breach of a bilateral treaty by one of the parties
entitles the other to invoke the breach as a ground for terminating
the treaty or suspending its operation in whole or in part.
(c) any party other than the defaulting State to invoke the breach
as a ground for suspending the operation of the treaty in whole
o r in part with respect to itself if the treaty is of such a charac-
ter that a material breach of its provisions by one party radi-
cally changes the position of every party with respect to the
further performance of its obligations under the treaty.
3. A niaterial breach of a treaty, for the purposes of this article,
consists in:
( a ) a repudiation of the treaty not sanctioned by the present Con-
vention; o r
( 6 ) the violation of a provision essential to the accomplishment of
the object or purpose of the treaty.
4. The foregoing paragraphs are without prejudice to any provi-
sion in the treaty applicable in the event of a breach.
5. Paragraphs 1 to 3 d o not apply to provisions relating to the
protection of the human person contained in treaties of a humani-
tarian character, in particular to provisions prohibiting any form of
reprisals against perçons protected by such treaties."
and joint operation. Consequently, the parties not having agreed other-
wise, the Treaty could be terminated only on the limited grounds enu-
merated in the Vienna Convention.
101. The Court will now turn to the first ground advanced by Hun-
gary, that of the state of necessity. In this respect, the Court will merely
observe that, even if a state of necessity is found to exist, it is not a
ground for the termination of a treaty. It may only be invoked to exon-
erate from its responsibility a State which has failed to implement a
treaty. Even if found justified, it does not terminate a Treaty; the Treaty
may be ineffective as long as the condition of necessity continues to exist ;
it may in fact be dormant, but - unless the parties by mutual agreement
terminate the Treaty - it continues to exist. As soon as the state of
necessity ceases to exist, the duty to comply with treaty obligations
revives.
had permanently disappeared and that the Treaty had thus become
impossible to perform. It is not necessary for the Court to determine
whether the term "object" in Article 61 can also be understood to
embrace a legal régime as in any event, even if that were the case, it
would have to conclude that in this instance that régime had not defini-
tively ceased t o exist. The 1977 Treaty - and in particular its Articles 15,
19 and 20 - actually made available to the parties the necessary means
to proceed at any time, by negotiation, to the required readjustments
between economic imperatives and ecological imperatives. The Court
would add that, if the joint exploitation of the investment was no longer
possible, this was originally because Hungary did not carry out most of
the works for which it was responsible under the 1977 Treaty; Article 61,
paragraph 2, of the Vienna Convention expressly provides that impossi-
bility of performance may not be invoked for the termination of a treaty
by a party to that treaty when it results from that party's own breach of
an obligation flowing from that treaty.
The Court recalls that, in the Fislzrries Jurisdiction case, it stated that
105. The Court will now examine Hungary's argument that it was
entitled to terminate the 1977 Treaty on the ground that Czechoslovakia
had violated its Articles 15, 19 and 20 (as well as a number of other con-
ventions and rules of general international law); and that the planning,
construction and putting into operatinn of Variant C also amounted to a
material breach of the 1977 Treatv.
106. As to that part of Hungary's argument which was based on other
treaties and general rules of international law, the Court is of the view
that it is only a material breach of the treaty itself, by a State party to
that treaty, which entitles the other party to rely on it as a ground for
terminating the treaty. The violation of other treaty rules or of rules of
general international law may justify the taking of certain measures,
including countermeasures, by the injured State, but it does not consti-
tute a ground for termination under the law of treaties.
The Court has not found sufficient evidence t o conclude that Czechoslo-
vakia had consistently refused to consult with Hungary about the desir-
ability or necessity of measures for the preservation of the environment.
The record rather shows that, while both parties indicated, in principle, a
willingness to undertake further studies, in practice Czechoslovakia
refused to countenance a suspension of the works at Dunakiliti and,
later, on Variant C, while Hungary required suspension as a prior condi-
tion of environmental investigation because it claimed continuation of
the work would prejudice the outcome of negotiations. In this regard it
cannot be left out of consideration that Hungary itself, by suspending the
works at Nagymaros and Dunakiliti, contributed to the creation of a
situation which was not conducive to the conduct of fruitful negotiations.
Hungary further submitted that the 1977 Treaty did not create "obli-
gations and rights . . . relating to the régime of a boundary" within the
meaning of Article I I of that Convention, and noted that the existing
course of the boundary was unaffected by the Treaty. It also denied that
the Treaty was a "localized" treaty, o r that it created rights "considered
as attaching to [the] territory" within the meaning of Article 12 of the
1978 Convention, which would, as such, be unaffected by a succession of
States. The 1977 Treaty was, Hungary insisted, simply a joint investment.
Hungary's conclusion was that there is no basis on which the Treaty
could have survived the disappearance of Czechoslovakia so as to be
binding as between itself and Slovakia.
120. According to Slovakia, the 1977 Treaty, which was not lawfully
terminated by Hungary's notification in May 1992, remains in force
between itself, as successor State, and Hungary.
Slovakia acknowledged that there was no agreement on succession to
the Treaty between itself and Hungary. It relied instead, in the first place,
on the "general rule of continuity which applies in the case of dissolu-
tion"; it argued, secondly, that the Treaty is one "attaching to [the] ter-
ritory" within the meaning of Article 12 of the 1978 Vienna Convention,
and that it contains provisions relating to a boundary.
121. In support of its first argument Slovakia cited Article 34 of the
1978 Vienna Convention, which it claimed is a statement of customary
international law, and which imposes the principle of automatic succes-
sion as the rule applicable in the case of dissolution of a State where the
~redecessorState has ceased to exist. Slovakia maintained that State
practice in cases of dissolution tends to support continuity as the rule to
be followed with regard to bilateral treaties. Slovakia having succeeded
to part of the territory of the former Czechoslovakia, this would be the
rule applicable in the present case.
122. Slovakia's second argument rests on "the principle of ipso jure
continuity of treaties of a territorial o r localized character". This rule,
Slovakia said, is embodied in Article 12 of the 1978 Convention, which in
part provides as follows :
71 GABCIKOVO-NAGYMAROS
PROJECT (JUDGMENT)
"Article 12
Other Territorial Regimes
. . . . . . . . . . . . . . . . . . . . . . . .
2. A succession of States does not as such affect:
( a ) obligations relating to the use of any territory, or to restrictions
upon its use, established by a treaty for the benefit of a group of
States or of al1 States and considered as attaching to that terri-
tory;
( h ) rights established by a treaty for the benefit of a group of States
or of al1 States and relating to the use of any territory, or to
restrictions upon its use, and considered as attaching to that
territory."
According to Slovakia, "[this] article [too] can be considered to be one
of those provisions of the Vienna Convention that represent the codifica-
tion of customary international law". The 1977 Treaty is said to fall
within its scoDe because of its "suecific characteristics . . . which ulace it
in the category of treaties of a localized or territorial character". Slovakia
also described the Treaty as one "which contains boundary provisions
and lays down a specific territorial régime" which operates in the interest
of al1 Danube riparian States, and as "a dispositive treaty, creating rights
in rem, independently of the legal personality of its original signatories".
Here, Slovakia relied on the recognition by the International Law Com-
mission of the existence of a "special rule" whereby treaties "intended to
establish an objective régime" must be considered as binding on a suc-
cessor State (OfJicial Records of the United Nations Conferencc on the
Succession ofStutes in respect of Treaties, Vol. I I I , doc. AICONF.80I16I
Add.2, p. 34). Thus, in Slovakia's view, the 1977 Treaty was not one
which could have been terminated through the disappearance of one of
the original parties.
123. The Court does not find it necessary for the purposes of the
present case to enter into a discussion of whether or not Article 34 of the
1978 Convention reflects the state of customary international law. More
relevant to its present analysis is the particular nature and character of
the 1977 Treaty. An examination of this Treaty confirms that, aside from
its undoubted nature as a joint investment, its major elements were the
proposed construction and joint operation of a large, integrated and indi-
visible complex of structures and installations on specific parts of the
respective territories of Hungary and Czechoslovakia along the Danube.
The Treaty also established the navigational régime for an important sec-
tor of an international waterway, in particular the relocation of the main
international shipping lane to the bypass canal. In so doing, it inescap-
ably created a situation in which the interests of other users of the Dan-
72 GABCIKOVO-NAGYMAROS
PROJECT (JUDGMENT)
ube were affected. Furthermore, the interests of third States were expressly
acknowledged in Article 18, whereby the parties undertook to ensure
"uninterrupted and safe navigation on the international fairway" in
accordance with their obligations under the Convention of 18 August
1948 concerning the Régime of Navigation on the Danube.
Taking al1 these factors into account, the Court finds that the content
of the 1977 Treaty indicates that it must be regarded as establishing a
territorial régime within the meaning of Article 12 of the 1978 Vienna
Convention. It created rights and obligations "attaching tomthe parts of
the Danube to which it relates; thus the Treaty itself cannot be affected
by a succession of States. The Court therefore concludes that the 1977
Treaty became binding upon Slovakia on 1 January 1993.
124. It might be added that Slovakia also contended that, while still a
constituent part of Czechoslovakia, it played a role in the development of
the Project, as it did later, in the most critical phase of negotiations with
Hungary about the fate of the Project. The evidence shows that the Slo-
vak Government passed resolutions prior to the signing of the 1977
Treaty in preparation for its implementation; and again, after signature,
expressing its support for the Treaty. It was the Slovak Prime Minister
who attended the meeting held in Budapest on 22 April 199 1 as the Pleni-
potentiary of the Federal Government to discuss questions arising out of
the Project. I t was his successor as Prime Minister who notified his Hun-
73 GABCIKOVO-NAGYMAROS
PROJECT (JL'DC~MENT)
125. The Court now turns to the other legal consequences arising from
its Judgment.
As to this, Hungary argued that future relations between the Parties, as
far as Variant C is concerned, are not governed by the 1977 Treaty. It
claims that it is entitled, pursuant to the Convention of 1976 on the
Regulation of Water Management Issues of Boundary Waters, to "50%
of the natural flow of the Danube at the point at which it crosses the
boundary below ~ u n o v o "and considers that the Parties
"are obliged t o enter into negotiations in order to produce the result
that the water conditions along the area from below Cunovo to
below the confluence at Sap become jointly defined water conditions
as required by Article 3 (u) of the 1976 Convention".
and that: "The overall situation is a complex one, and it may be most
easily resolved by some form of lump sum settlement."
It indicated that the Gabtikovo power plant would not operate in peak
mode "if the evidence of environmental damage [was] clear and accepted
by both Parties". Slovakia noted that the Parties appeared to agree that
an accounting should be undertaken "so that, guided by the Court's find-
ings on responsibility, the Parties can try to reach a global settlement". It
added that the Parties would have to agree on how the sums due are to be
paid.
129. Slovakia stated that Hungary must make reparation for the
deleterious consequences of its failures to comply with its obligations,
"whether they relate to its unlawful suspensions and abandonments of
works o r to its formal repudiation of the Treaty as from May 1992", and
that compensation should take the form of a rrstitutio in integrum. It
indicated that "Unless the Parties come to some other arrangement by
concluding an agreement, restitutio in integrurn ought to take the form of
a return by Hungary, ut a future tirne, to its obligations under the
Treaty" and that "For compensation to be 'full' . . ., to 'wipe out al1 the
consequences of the illegal act' . . ., a payment of compensation must . . .
be added to the rcstitutio . . ." Slovakia claims compensation which must
include both interest and loss of profits and should cover the following
heads of damage, which it offers by way of guidance:
(1) Losses caused t o Slovakia in the GabCikovo sector: costs incurred
from 1990 to 1992 by Czechoslovakia in protecting the structures of
the GIN project and adjacent areas; the cost of maintaining the old
bed of the River Danube pending the availability of the new naviga-
tion canal, from 1990 to 1992; losses to the Czechoslovak navigation
authorities due to the unavailability of the bypass canal from 1990 to
1992 ; construction costs of Variant C (1 990- 1992).
(2) Losses caused to Slovakia in the Nagymaros sector: losses in the field
of navigation and flood protection incurred since 1992 by Slovakia
due to the failure of Hungary to proceed with the works.
130. The Court observes that the part of its Judgment which answers
the questions in Article 2, paragraph 1 , of the Special Agreement has a
declaratory character. 1t deals with the past conduct of the Parties and
determines the lawfulness o r unlawfulness of that conduct between 1989
and 1992 as well as its effects on the existence of the Treaty.
131. Now the Court has, on the basis of the foregoing findings, to
76 GABCIKOVO-NAGYMAROS
PROJECT (JUDGMENT)
determine what the future conduct of the Parties should be. This part of
the Judgment is prescriptive rather than declaratory because it deter-
mines what the rights and obligations of the Parties are. The Parties will
have to seek agreement on the modalities of the execution of the Judg-
ment in the light of this determination, as they agreed to d o in Article 5
of the Special Agreement.
135. As the Court has already had occasion to point out, the 1977
Treaty was not only a joint investment project for the production of
77 GABC~KOVO-NAGYMAROS
PROJECT (JUDGMENT)
energy, but it was designed to serve other objectives as well: the improve-
ment of the navigability of the Danube, flood control and regulation of
ice-discharge, and the protection of the natural environment. None of
these objectives has been given absolute priority over the other, in spite
of the emphasis which is given in the Treaty to the construction of a
System of Locks for the production of energy. None of them has lost its
importance. In order to achieve these objectives the parties accepted obli-
gations of conduct, obligations of performance, and obligations of result.
Throughout the ages, mankind has, for economic and other reasons,
constantly interfered with nature. In the past, this was often done with-
out consideration of the effects upon the environment. Owing to new
scieritific insights and to a growing awareness of the risks for mankind -
For the purposes of the present case, this means that the Parties
together should look afresh at the effects on the environment of the
operation of the GabCikovo power plant. In particular they must find a
satisfactory solution for the volume of water to be released into the old
bed of the Danube and into the side-arms on both sides of the river.
141. It is not for the Court to determine what shall be the final result
of these negotiations to be conducted by the Parties. It is for the Parties
themselves t o find a n agreed solution that takes account of the objectives
of the Treaty, which must be pursued in a joint and integrated way, as
well as the norms of international environmental law and the principles
of the law of international watercourses. The Court will recall in this con-
text that, as it said in the North Seu Continental Shelfcases:
145. Article 10, paragraph 1 , of the Treaty states that works of the
System of Locks constituting the joint property of the contracting parties
shall be operated, as a co-ordinated single unit and in accordance with
jointly agreed operating and operational procedures, by the authorized
operating agency of the contracting party in whose territory the works
are built. Paragraph 2 of that Article states that works on the System of
Locks owned by one of the contracting parties shall be independently
operated or maintained by the agencies of that contracting party in the
jointly prescribed manner.
The Court is of the opinion that the works at ~ u n o v oshould become
a jointly operated unit within the meaning of Article 10, paragraph 1, in
view of their pivotal role in the operation of what rem+ of the Project
and for the water-management régime. The dam at Cunovo has taken
over the role which was originally destined for the works at Dunakiliti,
and therefore should have a similar status.
146. The Court also concludes that Variant C, which it considers oper-
ates in a manner incompatible with the Treaty, should be made to con-
form to it. By associating Hungary, on an equal footing, in its operation,
management and benefits, Variant C will be transformed from a de facto
status into a treaty-based régime.
It appears from various parts of the record that, given the current state
151. The Court has been asked by both Parties to determine the con-
sequences of the Judgment as they bear upon payment of damages.
According to the Preamble to the Special Agreement, the Parties agreed
that Slovakia is the sole successor State of Czechoslovakia in respect of
rights and obligations relating to the GabCikovo-Nagymaros Project.
Slovakia thus may be liable to pay compensation not only for its own
wrongful conduct but also for that of Czechoslovakia, and it is entitled to
be compensated for the damage sustained by Czechoslovakia as well as
by itself as a result of the wrongful conduct of Hungary.
152. The Court has not been asked at this stage to determine the quan-
tum of damages due, but to indicate on what basis they should be paid.
Both Parties claimed to have suffered considerable financial losses and
both claim pecuniary compensation for them.
It is a well-established rule of international law that an injured State is
entitled to obtain compensation from the State which has committed an
internationally wrongful act for the damage caused by it. In the present
Judgment, the Court has concluded that both Parties committed interna-
tionally wrongful acts, and it has noted that those acts gave rise to the
damage sustained by the Parties; consequently, Hungary and Slovakia
are both under an obligation to pay compensation and are both entitled
to obtain compensation.
Slovakia is accordingly entitled to compensation for the damage suf-
fered by Czechoslovakia as well as by itself as a result of Hungary's deci-
sion to suspend and subsequently abandon the works at Nagymaros and
Dunakiliti, as those actions caused the postponement of the putting into
operation of the GabCikovo power plant, and changes in its mode of
operation once in service.
Hungary is entitled to compensation for the damage sustained as a
result of the diversion of the Danube, since Czechoslovakia, by putting
into operation Variant C , and Slovakia, in maintaining it in service,
deprived Hungary of its rightful part in the shared water resources, and
exploited those resources essentially for their own benefit.
153. Given the fact, however, that there have been intersecting wrongs
by both Parties, the Court wishes to observe that the issue of compen-
sation could satisfactorily be resolved in the framework of an overall
settlement if each of the Parties were to renounce or cancel al1 financial
claims and counter-claims.
154. At the same time, the Court wishes to point out that the settle-
ment of accounts for the construction of the works is different from the
issue of compensation, and must be resolved in accordance with the 1977
Treaty and related :instruments. If Hungary is to share in the operation
and benefits of the Cunovo complex, it must pay a proportionate share of
the building and running costs.
82 GABCIKOVO-NAGYMAROS PROJECT (JUDGMENT)
(Initiullcd) S.M.S.
(Initialled) E.V.O.
DECLARATION O F PRESIDENT SCHWEBEL
all, the very principle of good faith which must lead here to the fulfilment
of reciprocal duties remaining from a treaty which has not been applied
through the joint fault of the parties.
In the present case we have, on the one hand, a scheme which, even in
the attenuated form in which it now remains, is important to the welfare
of Slovakia and its people, who have already strained their own resources
and those of their predecessor State to the extent of over two billion dol-
lars to achieve these benefits. Slovakia, in fact, argues that the environ-
ment would be improved through the operation of the Project as it would
help to stop erosion of the river bed, and that the scheme would be an
effective protection against floods. Further, Slovakia has traditionally
been short of electricity, and the power generated would be important to
its economic development. Moreover, if the Project is halted in its tracks,
vast structural works constructed at great expense, even prior to the
repudiation of the Treaty, would be idle and unproductive, and would
pose an economic and environmental problem in themselves.
How does one handle these considerations? Does one abandon the
Project altogether for fear that the latter consequences might emerge?
Does one proceed with the scheme because of the national benefits it
brings, regardless of the suggested environmental damage? O r does one
steer a course between, with due regard to both considerations, but
ensuring always a continuing vigilance in respect of environmental harm?
1 would observe, moreover, that both Parties in this case agree on the
90 GABCIKOVO-NAGYMAROS PROJECT (SEP.OP.WEERAMANTRY)
Each principle cannot be given free rein, regardless of the other. The
law necessarily contains within itself the principle of reconciliation. That
principle is the principle of sustainable development.
This case offers a unique opportunity for the application of that prin-
ciple, for it arises from a Treaty which had development as its objective,
and has been brought to a standstill over arguments concerning environ-
mental considerations.
The people of both Hungary and Slovakia are entitled to development
for the furtherance of their happiness and welfare. They are likewise
entitled to the preservation of their human right to the protection of
their environment. Other cases raising environmental questions have been
considered by this Court in the context of environmental pollution arising
from such sources as nuclear explosions, which are far removed from
development projects. The present case thus focuses attention, as no
other case has done in the jurisprudence of this Court, on the question of
the harmonization of developmental and environmental concepts.
(a) Development as a Principle of lnternutional Luw
Article 1 of the Declaration on the Right to Development, 1986,
asserted that "The right to development is an inalienable human right."
This Declaration had the overwhelming support of the international
'
community and has been gathering strength since then2. Principle 3 of
the Rio Declaration, 1992, reaffirmed the need for the right to develop-
ment to be fulfilled.
"Development" means, of course, development not merely for the sake
of development and the economic gain it produces, but for its value in
increasing the sum total of human happiness and welfare'. That could
perhaps be called the first principle of the law relating to development.
T o the end of improving the sum total of human happiness and wel-
fare, it is important and inevitable that development projects of various
descriptions, both minor and major, will be launched from time to time
in al1 parts of the world.
General Assembly resolution 642 (VII) of 1952, likewise, referred expressly to "inte-
grated economic and social development".
The Preamble to the Declaration on the Right to Development (1986) recites that
development is a comprehensive, economic. social and cultural process which aims ai the
constant improvement and well-being of the entire population and of al1 individuals on
the basis of their active, free and meaningful participation in development and in the fair
distribution of the benefits resulting therefrom.
92 GABC~KOVO-NAGYMAROSPROJECT (SEP.OP.WEERAMANTRY)
See Sustuinable Dri~rlopmrntand Intc,rnational Lait,, Winfried Lang (ed.), 1995. p. 143.
For example, the United Nations Convention to Combat Desertification (The United
Nations Convention to Combat Desertification in those Countries Experiencing Serious
Droughts andlor Desertification, Particularly in Africa). 1994, Preamble, Art. 9 (1); the
United Nations Framework Convention on Climate Change, 1992 (ILM. 1992,
Vol. XXXI, p. 849. Arts. 2 and 3); and the Convention on Biological Diversity (ILM,
1992. Vol. XXXI, p. 818, Preamble, Arts. I and 10 - "sustainable use of biodiversity").
"' For example, the Rio Declaration on Environment and Development, 1992, empha-
sizes sustainable development in several of its Principles (e.g., Principles 4, 5, 7, 8, 9, 20,
21, 22. 24 and 27 refer expressly to "sustainable development" which can be described as
the central concept of the entire document); and the Copenhagen Declaration, 1995
(paras. 6 and 8). following on the Copenhagen World Summit for Social Development,
1995.
' ' For example, the North American Free Trade Agreement (Canada, Mexico, United
States) (NAFTA, Preamble, ILM, 1993. Vol. XXXII, p. 289); the World Trade Organiza-
tion (WTO) (paragraph 1 of the Preamble of the Marrakesh Agreement of 15 April 1994,
establishing the World Trade Organization, speaks of the "optimal use of the world's
resources in accordance with the objective of sustainable development" - ILM, 1994.
Vol. XXXIII. pp. 1143-1 144); and the European Union (Art. 2 of the ECT).
l 2 For example, the World Bank Group, the Asian Development Bank. the African
Development Bank, the Inter-American Development Bank, and the European Bank for
Reconstruction and Development al1 subscribe to the principle of sustainable develop-
ment. Indeed, since 1993, the World Bank has convened an annual conference related to
advancing environmentally and socially sustainable development (ESSD).
l 3 For example, the Langkawi Declaration on the Environment, 1989, adopted by the
"Heads of Government of the Commonwealth representing a quarter of the world's popu-
lation" which adopted "sustainable development" as its central theme; Ministerial Dec-
laration on Environmentally Sound and Sustainable Development in Asia and the Pacific,
Bangkok, 1990 (doc. 38a. p. 567); and Action Plan for the Protection and Management of
the Marine and Coastal Environment of the South Asian Seas Region. 1983 (para. 10:
"sustainable, environmentally sound development").
l 4 For example, in 1990. the Dublin Declaration by the European Council on the Envi-
ronmental Imperative stated that there must be an acceleration of effort to ensure that
economic development in the Community is "sustainable and environmentally sound"
94 GABCIKOVO-NAGYMAROS PROJECT (SEP. OP. WEERAMANTRY)
(Bulletin of' the Europeun Cornmuniries, 6, 1990, Ann. II. p. 18). It urged the Commu-
nity and Member States to play a major role to assist developing countries in their efforts
to achieve "long-term sustainable development" (ibid., p. 19). I t said, in regard to coun-
tries of Central and Eastern Europe, that remedial measures must be taken "to ensure
that their future economic development is sustainable" (ihid.). It also expressly recited
that :
As Brierly observes :
"lt would hardly ever be practicable, and al1 but the strictest of
positivists admit that it is not necessary, to show that every state has
recognized a certain practice, just as in English law the existence of a
valid local custom or custom of trade can be established without
proof that every individual in the locality, or engaged in the trade,
has practised the custom. This test of generul recognition is neces-
sarily a vague one; but it is of the nature of customary law, whether
national or international . . ." l 7
I y Julius Stone, Human Law and Humun Justice, 1965, p. 6 6 : "It was for this reason
that Grotius added to his theoretical deductions such a mass of concrete examples from
history."
*" Sir Robert Y. Jennings, "Universal International Law in a Multicultural World", in
International Law and the Grotiun Heritage: A Cornmernorative Colloquiurn on tlze Occa-
sion of the Fourth Centrnary of the Birth o f Hugo Grotius. edited and published by the
T.M.C. Asser Institute, The Hague, 1985, p. 195.
97 GABCIKOVO-NAGYMAROS PROJECT (SEP.OP. WEERAMANTRY)
This case touches an area where many such insights can be drawn to
the enrichment of the developing principles of environmental law and to
a clarification of the principles the Court should apply.
It is in this spirit that 1 approach a principle which, for the first time in
its jurisprudence, the Court is called upon to apply - a principle which
will assist in the delicate task of balancing two considerations of enor-
mous importance to the contemporary international scene and, poten-
tially, of even greater importance to the future.
As the Court has observed, "Throughout the ages mankind has, for eco-
nomic and other reasons, constantly interfered with nature." (Judgment,
para. 140.)
The concept of reconciling the needs of development with the protec-
tion of the environment is thus not new. Millennia ago these concerns
were noted and their twin demands well reconciled in a manner so mean-
ingful as to carry a message to Our age.
25 It is an aid to the recapitulation of the matters mentioned that the edicts and works
1 shall refer to have been the subject of written records, maintained contemporaneously
and over the centuries. See footnote 38 below.
99 GABC~KOVO-NAGYMAROS PROJECT (SEP.OP.WEERAMANTRY)
The concern for the environment shown by this ancient irrigation system
has attracted study in a recent survey of the Social and Environmental
Effects of Large Dams3(', which observes that among the environmentally
related aspects of its irrigation systems were the "erosion control tank"
which dealt with the problem of silting by being so designed as to collect
deposits of silt before they entered the main water storage tanks. Several
erosion control tanks were associated with each village irrigation system.
The significance of this can well be appreciated in the context of the present
case, where the problem of silting has assumed so much importance.
2y The technical sophistication of this irrigation system has been noted also in Joseph
Needham's monumental work on Science and Civilizution in China. Needham, in describ-
ing the ancient irrigation works of China. makes numerous references to the contempo-
rary irrigation works of Ceylon, which he discusses at some length. See especially, Vol. 4,
Physics und Phy.c.icu1 Technology, 1971, pp. 368 et .seq. Also p. 215: "We shall see how
skilled the ancient Ceylonese were in this art."
30 Edward Goldsmith and Nicholas Hildyard, The Social und Eni~ironmentulEffrcts o f
Large Danzs, 1985, pp. 291-304.
' For these details. see Goldsmith and Hildyard, ibid., pp. 291 and 296. The same
authors observe :
"Sri Lanka is covered with a network of thousands of man-made lakes and ponds,
known locally as tanks (after tanque, the Portuguese word for reservoir). Some are
truly massive, many are thousands of years old, and almost al1 show a high degree of
sophistication in their construction and design. Sir James Emerson Tennent, the nine-
teenth century historian, marvelled in particular at the numerous channels that were
dug underneath the bed of each lake in order to ensure that the flow of water was
'constant and equal as long as any water remained in the tank'."
100 GABCIKOVO-NAGYMAROS PROJECT (SEP.OP. WEERAMANTRY)
This system of tanks and channels, some of them two thousand years
old, constitute in their totality several multiples of the irrigation
works involved in the present scheme. They constituted development as it
was understood at the time, for they achieved in Toynbee's words, "the
arduous feat of conquering the parched plains of Ceylon for agricul-
turemS2.Yet they were executed with meticulous regard for environmen-
ta1 concerns, and showed that the concept of sustainable development
was consciously practised over two millennia ago with much success.
Under this irrigation system, major rivers were dammed and reservoirs
created, on a scale and in a manner reminiscent of the damming which
the Court saw on its inspection of the dams in this case.
32 Toynbee, op. cit., p. 81. Andrew Carnegie, the donor of the Peace Palace, the seat of
this Court, has described this ancient work of development in the following terms:
"The position held by Ceylon in ancient days as the great granary of Southern Asia
explains the precedence accorded to agricultural pursuits. Under native rule the
whole island was brought under irrigation by means of artificial lakes. constructed by
dams across ravines, many of them of great extent one still existing is twenty miles
-
in circumference - but the system has been allowed to fall into decay." (Andrew
Carnegie, Round the World, 1879 (1933 ed.), pp. 155-160.)
33 The first of these major tanks was thought to have been constructed in 504 BC (Sir
James Emerson Tennent, Crqlon, 1859, Vol. 1, p. 367). A few examples, straddling 15 cen-
turies, were :
the Vavunik-kulam (3rd c. BC)(1,975 acres water surface, 596 million cubic feet water
capacity); the P a ~ ~ u t k u l a(3rd
m or 2nd c. BC)(2,029 acres water surface, 770 million
cubic feet water capacity) - Parker, Ancic~ntCeylun, 1909. pp. 363, 373;
- the Ti.~suwei.ia(3rd c. BC);and the Nuivuraiven'a (3rd c. RC),both still in service and
still supplying water to the ancient capital Anuradhapura. which is now a provincial
capital;
- the Minneriya tank (275 AD)("The reservoir upwards of twenty miles in circumference
. . . the great embankment remains nearly perfect") (Tennent, op. rit., Vol. II. p. 600);
the T o p a ~ c r ~ v(4th
u c. AD).area considerably in excess of 1,000 acres;
the Kaluiveli~a(5th c. A D )
- embankment 3.25 miles long, rising to a height of 40 feet,
tapping the river Kala Oya and supplying water to the capital Anuradhapura through
a canal 50 miles in length;
the Yodaiveiva (5th c. AD).Needham describes this as "A most grandiose conception
. . . the culmination of Ceylonese hydraulics . . . an artificial lake with a six-and-a-half
mile embankment on three sides of a square, sited on a sloping plain and not in a river
valley at all." It was fed by a 50-mile canal from the river Malvatu-Oya;
7 4 On the irrigation systems, generally, see H. Parker, Anrient Crylon, op. cit.: R. L.
Brohier, Ancient Irrigation Works in Cejdon, 1934; Edward Goldsmith and Nicholas
Hildyard, op. rit., pp. 291-304. Needham, describing the ancient canal system of China,
observes that "it was comparable only with the irrigation contour canals of Ceylon, not
with any work in Europe" (op. rit., Vol. 4. p. 359).
" "so vast were the dimensions of some of these gigantic tanks that many still in exist-
ence cover an area from fifteen to twenty miles in circumference" (Tennent, op. cit., Vol. 1,
p. 364).
36 King Parakrama Bahu (1 153-1 186 AD). This monarch constructed or restored 163
major tanks, 2,376 minor tanks, 3,910 canals, and 165 dams. His masterpiece was the Sea
of Parakrama, referred to in footnote 33. All of this was conceived within the environ-
mental philosophy of avoiding any wastage of natural resources.
a sermon on Buddhism which converted the king. Here are excerpts from
that sermon :
"O great King, the birds of the air and the beasts have as equal a
right to live and move about in any part of the land as thou. The
land belongs to the people and al1 living beings; thou art only the
guardian of it."4'
The sermon also pointed out that even birds and beasts have a right to
freedom from fear43.
The notion of not causing harm to others and hence sic utere tuo ut
alienum non luedus was a central notion of Buddhism. It translated well
into environmental attitudes. "Alienurn "in this context would be extended
by Buddhism to future generations as well, and to other component ele-
ments of the natural order beyond man himself, for the Buddhist concept
of duty had an enormously long reach.
"Of al1 Ceylon's architectural wonders, however, the most remarkable - and cer-
tainly the most u s e f u l is the enormous irrigation system which, for over two thou-
Sand years, has brought prosperity to the rice farmers in regions where it may not
rain for six months at a time. Frequently ruined, abandoned and rebuilt, this legacy
of the ancient engineers is one of the island's most precious possessions. Some of its
artificial lakes are ten o r twenty kilometres in circumference, and abound with birds
and wildlife." (The View frorn Serendip, 1977, p. 121.)
and the law has often lagged behind other disciplines in so doing.
Happily for international law, there are plentiful indications, as recited
earlier in this opinion, of that degree of "general recognition among
States of a certain practice as 0b1igatory"~Oto give the principle of sustain-
able development the nature of customary law.
Sir Charles Dundas, who visited the Chagga in the first quarter of this
century, was much impressed by the manner in which, throughout the
long course of the furrows, society was so organized that law and order
prevailed5j. Care of the furrows was a prime social duty, and if a furrow
was damaged, even accidentally, one of the elders would sound a horn in
the evening (which was known as the cal1 to the furrows), and next morn-
ing everyone would leave their normal work and set about the business of
r e ~ a i rThe
~ ~ .furrow was a social asset owned by the clan5'.
By way of contrast, where the needs of the land were neglected, and
massive schemes launched for urban supply rather than irrigation, there
was disaster. The immense works in the Euphrates Valley in the third
millennium BC aimed not at improving the irrigation system of the local
tribesmen, but at supplying the requirements of a rapidly growing urban
society (e.g., a vast canal built around 2400 BC by King Entemenak) led
to seepage, flooding and over-irrigation6'. Traditional farming methods
and later irrigation systems helped to overcome the resulting problems of
waterlogging and salinization.
China was another site of great irrigation works, some of which are
still in use over two millennia after their construction. For example, the
ravages of the Mo river were overcome by an excavation through a
Regarding the Inca civilization at its height, it has been observed that
it continually brought new lands under cultivation by swamp drainage,
expansion of irrigation works, terracing of hillsides and construction of
irrigation works in dry zones, the goal being always the same - better
utilization of al1 resources so as to maintain an equilibrium between pro-
duction and c o n ~ u m p t i o n In
~ ~the
. words of a noted writer on this civi-
lization, "in this respect we can consider the Inca civilization triumphant,
since it conquered the eternal problem of mu'cimum use and conservation
of soir6('. Here, too, we note the harmonization of developmental and
environmental considerations.
Traditional wisdom which inspired these ancient legal systems was able
to handle such problems. Modern legal systems can d o no less, achieving
a blend of the concepts of development and of conservation of the envi-
ronment, which alone does justice to humanity's obligations to itself and
to the planet which is its home. Another way of viewing the problem is to
look upon it as involving the imperative of balancing the needs of the
present generation with those of posterity.
67 On Native American attitudes to land, see Guruswamy, Palmer and Weston (eds.),
Inrernutionul Environmenral Luic and World Order, 1994, pp. 298-299. On American
Indian attitudes, see further J. Callicott, "The Traditional American Indian and Western
European Attitudes towards Nature: An Overview", Environmental Erhics. 1982, Vol. 4,
p. 293; A. Wiggins, "lndian Rights and the Environment", Yule J. Inr'l Law, 1993,
Vol. 18, p. 345; J. Hughes, Americun Indiun Ecology, 1983.
A Pacific Islander, giving evidence before the first Land Commission in the British
Solomons (1919-1924), poured scorn on the concept that land could be treated "as if it
were a thing like a box" which could be bought and sold, pointing out that land was
treated in his Society with respect and with due regard for the rights of future generations.
(Peter G. Sack, Land hetic,een TWOLun:r, 1993, p. 33.)
At Lake Condah, thousands of years before Leonardo da Vinci studied the hydro-
logy of the northern Italian lakes, the original inhabitants of Australia perfectly
understood the hydrology of the site. A sophisticated network of traps, weirs and
sluices were designed . . ." (Stephen Johnson et (il., Engineering and Society: An Aus-
fralian Perspective, 1995, p. 35.)
108 GABcIKOVO-NAGYMAROS PROJECT (SEP. OP. WEERAMANTRY)
This survey would not be complete without a reference also to the prin-
ciples of Islamic law that inasmuch as al1 land belongs to God, land is
never the subject of human ownership, but is only held in trust, with al1
the connotations that follow of due care, wise management, and custody
for future generations. The first principle of modern environmental law
- the principle of trusteeship of earth resources is thus categorically
-
The ingrained values of any civilization are the source from which its
legal concepts derive, and the ultimate yardstick and touchstone of their
validity. This is so in international and domestic legal systems alike, Save
that international law would require a worldwide recognition of those
values. It would not be wrong to state that the love of nature, the desire
for its preservation, and the need for human activity to respect the
Nagendra Singh, Humun Rights and the Future of'Mankind, 1981, p. 93.
Commenting on the rise of naturalism in al1 the arts in Europe in the later Middle
Ages, one of this century's outstanding philosophers of science has observed:
"The whole atmosphere of every art exhibited direct joy in the apprehension of the
things around us. The craftsmen who executed the later mediaeval decorative sculp-
ture. Giotto, Chaucer, Wordsworth, Walt Whitman, and at the present day the New
England poet Robert Frost, are al1 akin to each other in this respect." (Alfred North
Whitehead, Science and the Modern World, 1926, p. 17.)
'* See the Georgics, Book I I , 1. 36ff.; 1. 458 ff. Also Encjclopaedia Britunnica, 1992,
Vol. 29, pp. 499-500.
109 GABCIKOVO-NAGYMAROS PROJECT (SEP.OP. WEERAMANTRY)
requisites for its maintenance and continuance are among those pristine
and universal values which command international recognition.
Among those which may be extracted from the systems already referred
to are such far-reaching principles as the principle of trusteeship of earth
resources, the principle of intergenerational rights, and the principle that
development and environmental conservation must go hand in hand.
Land is to be respected as having a vitality of its own and being integrally
linked to the welfare of the community. When it is used by humans, every
opportunity should be afforded to it to replenish itself. Since flora and
fauna have a niche in the ecological system, they must be expressly pro-
tected. There is a duty lying upon al1 members of the community to pre-
serve the integrity and purity of the environment.
Most of them have relevance to the present case, and al1 of them can
greatly enhance the ability of international environmental law to cope
with problems such as these if and when they arise in the future. There
are many routes of entry by which they can be assimilated into the inter-
national legal system, and modern international law would only diminish
itself were it to lose sight of them - embodying as they d o the wisdom
which enabled the works of man to function for centuries and millennia
in a stable relationship with the principles of the environment. This
approach assumes increasing importance at a time when such a harmony
between humanity and its planetary inheritance is a prerequisite for
human survival.
The Court has indicated in its Judgment (para. 155 (2) (C)) that a joint
operational régime must be established in accordance with the Treaty
of 16 September 1977. A continuous monitoring of the scheme for its
environmental impacts will accord with the principles outlined, and be
a part of that operational régime. Indeed, the 1977 Treaty, with its
contemplated régime of joint operation and joint supervision, had itself
a built-in régime of continuous joint environmental monitoring. This
principle of environmental law, as reinforced by the terms of the Treaty
and as now incorporated into the Judgment of the Court (para. 140),
would require the Parties to take upon themselves an obligation to set up
the machinery for continuous watchfulness, anticipation and evaluation
If the Treaty was to operate for decades into the future, it could not
" Oppenheim's Internurionul Law, R. Y . Jennings and A. Watts (eds.), 1992, p. 1275,
note 21.
unsound, even though it is taken under an instrument of more than
20 years ago.
8 5 Judgment of the Court. Tyrer case, 25 April 1978, para. 31, publ. Court A, Vol. 26,
at 15, 16.
86 See further Rosalyn Higgins, "Some Observations on the Inter-Temporal Rule
in International Law", in Theory of International Law ut the Threshold of the 2lst
Centurj, op. rit., p. 173.
1 16 GABC~KOVO-NAGYMAROSPROJECT (SEP.OP. WEERAMANTRY)
Ninety-six days after the 1989 Protocol took effect, Le., on 13 May
1989, the Hungarian Government announced the immediate suspension'
for two months of work at the Nagymaros site. It abandoned perform-
ance on 20 July 1989, and thereafter suspended work on al1 parts of the
Project. Forma1 termination of the 1977 Treaty by Hungary took place
in May 1992.
It seems to me that al1 the ingredients of a legally binding estoppel are
here present *'.
The other Treaty partner was left with a vast amount of useless project
construction on its hands and enormous incurred expenditure which it
had fruitlessly undertaken.
87 On the application of principles of estoppel in the jurisprudence of this Court and its
predecessor, see Legal Status of Eastern Greenland, P. C.I.J . , Series A/B. No. 53, p. 2 2 ;
Fisheries (United Kingdom v. Norivuy), I.C.J. Reports 1951, p. 116; Temple of Preuh
Vihear, I. C .J . Reports 1962, p. 15 1 . For an analysis of this jurisprudence, see the separate
opinion of Judge Ajibola in Territorial Dispute (Libyan Arab Jamahiriya/Chad), I. C.J.
Reports 1994, pp. 77-83.
to the epochal events that had recently taken place in Eastern Europe.
Such historic events necessarily leave their aftermath of internal tension.
This may well manifest itself in shifts of officia1 policy as different emer-
gent groups exercise power and influence in the new order that was in the
course of replacing that under which the country had functioned for close
on half a century. One cannot but take note of these realities in under-
standing the drastic officia1 changes of policy exhibited by Hungary.
Whatever be the reason for the internal changes of policy, and what-
ever be the internal pressures that might have produced this, the Court
can only assess the respective rights of the two States on the basis of their
official attitudes and pronouncements. Viewing the matter from the
standpoint of an external observer, there can be little doubt that there
was indeed a marked change of official attitude towards the Treaty,
involving a sharp shift from full officia1 acceptance to full officia1 rejec-
tion. It is on this basis that the legal consequence of estoppel would
follow.
88 See, for example, Peter Brett, "Implications of Science for the Law", McGill Luiv
Journal, 1972. Vol. 18, p. 170, at p. 191. For a well-known comment from the perspective
of sociology, see Jacques Ellul, The Technologicul Society, trans. John Wilkinson, 1964,
pp. 251, 291-300.
As this vital branch of law proceeds to develop, it will need al1 the
insights available from the human experience, crossing cultural and
disciplinary boundaries which have traditionally hemmed in the disci-
pline of international law.
[Translation]
3. 1 agree with the majority of the Court on its general approach to the
question of the applicable law. 1 shall refer to only one aspect of this
question that 1 coinsider to be fundamental and that touches upon the
applicability in this case of the conventions and other instruments sub-
sequent to the 197;' Treaty, and concerning the environment and the law
of international watercourses.
4. Hungary asks; the Court to interpret the 1977 Treaty in the light of
the new, more developed and more exacting law of the environment, and
of the law of international watercourses. In support of its argument, it
principally relies upon the Advisory Opinion rendered by the Court in
1971 in the Namibia case (Legal Consequences for States of the Con-
tinued Presence of South Africu in Namibia (South West Africa) not-
withstanding Security Council Resolution 276 (1970), Advisory Opinion,
I.C.J. Reports 1971, p. 16). In that case, the Court stated that a treaty
should be interpreted "within the framework of the entire legal system
prevailing at the time of the interpretation" (ibid., p. 31).
CABC~KCIVO-NAGYMAROS
PROJECT (SEP.OP. BEDJAOUI) 121
6. (i) It may be iiseful first to restate the obvious: pactu sunt servundu.
Inasmuch as the 1997 Treaty is regarded as being in force for the pur-
poses of a judicial interpretation, it is necessarily binding upon the
parties. They are under a n obligation to perform it in good fuith
(Article 26 of the 1969 Vienna Convention).
(ii) Moreover the parties cannot, in principle, evade a traditional inter-
pretation based on Article 31 of the Vienna Convention unless the Treaty
which they concluded in the past has become incompatible with a norm
ofjus cogens. Both Hungary and Slovakia appear to agree that this is not
the case of the 197'7 Treaty.
(b) The lnterpretution of' the Treury Must Comply ivith the Intentions
of' the P<nrtiesE.~pres.sedut the Time of' Its Conclusion
when the Treaty vvas concluded "could influence the intention of the
Contracting States . . ., as the law which did not yet exist at that time
could not logically have any influence on this intention" '.
9. In the Namibia case, the Court had to interpret a very special situa-
tion. Among the obligations of the Mandatory Power, the treaty institut-
ing a "C" Mandate over South West Africa referred to that of a "sacred
trust ". It was then for the Court to interpret that phrase. It could only d o
so by observing the reality, which shows that this notion of a "sacred
trust ", fashioned ini 1920 in the era of colonization, was not comparable
to the idea people had of it half a century later in the period of successive
decolonizations. The Court thus considered that the matters to be inter-
preted, such as the "sacred trust", "were not static, but were by definition
evolutionary" (I.C.J. Reports 1971, p. 3 1). This being so, the method of'
the mobile reference, in other words the reference to new contemporary
law, was wholly suitable for an interpretation seeking to avoid archaic
elements, was in tune with modern times and was useful as regards the
action of the Applicant, which in this case was the Security Council.
10. But the Court patently knew that it was pursuing this approach
because the situation was special. Nowhere did it state that its method of
the mobile reference was subsequently to become mandatory and extend
to al1 cases of interpretation. The deJinition of the "sucrrd trust" is evo-
lutionary. It is the luw corresponding to the period when this concept is
20. It seems t o nie that the issue of the nature of the 1977 Treaty and
its related instruments warranted more attention from the majority of the
Court. Actually, it is a crucial question. The nature of the Treaty largely
conditions the succession of Slovakia to this instrument, which consti-
tutes the substance of the applicable law, and which remains in force
despite intersecting violations by both Parties.
21. The 1977 Treaty (including its related instruments) has the three-
fold characteristic
- of being a terrilorial treaty;
- of being a treaty to which Slovakia validly succeeded; and
- of being a treaty which is still in force today.
27. As for the breaches of the Treaty, 1 entirely share the views of the
majority of the Court in declaring that Hungary was manifestly in breach
of its contractual obligations in suspending then abandoning work and
GABCIKO\~O-NAGYMAROS
PROJECT (SEP.OP. BEDJAOUI) 127
34. The contrary can only be asserted if the State has shown bad faith
and if it has been clemonstrated beyond doubt that it only pretended to
negotiate, whereas its Jirm intention was to sabotage the seeming nego-
tiations in order to impose ut al1 costs u unilateral solution ulready
decided on.
This then raises the problem as to hvhether Czechoslovakiu respected
C A B C I K O ~ ~ O - N A G Y M A R OPROJECT
S (SEP.OP. BEDJAOUI) 129
the principle of gootd fuith. 1 shall not venture to examine this question
since, in my view, both Czechoslovakia and Hungary showed good faith,
whilst each presenting the image of their own anxiety to the other. O n
either side, good fai1.h was eroded by the "drip" effect of anxiety and dis-
trust vis-à-vis the other Party.
39. At this point 1 must recall what 1 said above on the subject of the
territorial nature o r 1977 Treaty, which lays various mutual obligations
on the two contracting States relating either to the use of a part of the
territory of each of the two States, or to restrictions on i f s use. The Treaty
creates a "territorial dependency" of one State in relation to the other.
This being so how can it be asserted that the State is free to act as it
wishes?
40. It is important to ascertain exactly what Variant C is. Para-
graph 66 of the Judgment gives a detailed description of it and the Work-
ing Group of Independent Experts presents it in the following terms:
"Variant C consists of a complex of structures, located in Czecho-
Slovakia . . . The structures include . . .:
(2) By-pass weir controlling the flow into the river Danube.
43. That, for the majority of the Court, is a way of denying the exist-
ence of the "continiling", "composite" or "complex wrong". It seems to
me that al1 the effort expended in the literature and in the case-law are
compromised by this stand, as is the attempt a t codification by the Inter-
national Law Co~~imission. The unlawful nature of the "continuing
wrong" is indeed determined once the last piece of the jigsaw is in place.
Yet in the literature and in the case-law the declaration of the unlawful-
ness of the final link results, in most categories of wrongs, in the unlaw-
fulness of the entire chain. It therefore seems wrong to me to set the
allegedly lawful con~structionof Variant C against its allegedly unlawful
final commissioning.
44. The Judgmen.t of the Court refers to the proceedings of the Inter-
national Law Comrnission on State Responsibility. However, one of the
paragraphs in the commentaries of the Commission to which the Court
specially refers reads :
"unlike wrongful acts of national law, the internationally wrongful
act of a State is quite often - and probably in most cases - the
result of a concatenation of a number of individual actions or omis-
sions which, however legally distinct in terms of municipal law, con-
stitutes one compact ivhole so to speak from the point of v i e , ~of
internutional lu'iu" ( Yearbook of the Internaiional Law Commission,
1993, Vol. I I , Part 2, p. 57, para. 14; emphasis added).
had no intention of performing the 1977 Treaty, and had then taken the
decision to divert the waters of the river. The chain of operations designed
to achieve this aim was unbroken, with n o missing links, from the com-
mencement of construction to the commissioning of Variant C by the
actual diversion of the waters in October 1992. Nevertheless the majority
of the Court held tl-iat the work concerned might "have been abandoned
[by Czechoslovakia] if an agreement had been reached between the
parties" (para. 79). 1 d o not think one can engage in speculation of this
sort with impunity. When construction began in November 1991 and
throughout this phalse of the works, it was clearly apparent, particularly
from the diplomatic: exchanges between the Parties, that each Party had
adopted a n entrenched position. That being so, the idea mooted by the
Court of an abandonment of the works could be only hypothetical and
unrealistic.
national law: lawful and unlawful. It does not recognize any intermediate
situation. Such a situation may exist but is and will be nothing more than
a fact. In relation to the Treaty. this fact may be considered only as a
non-application of the Treaty, being unlawful in nature.
52. In any event., and here 1 concur with the majority of the Court,
Variant C is not a countermeasure capable of excusing its unlawfulness.
Nor indeed is it proportionate, since from the outset it deprives Hungary
of the waters of the: Danube as a shared resource and also of any control
over a joint investcnent laid down in the 1977 Treaty. Moreover Variant
C is neither provisional nor deterrent, as a countermeasure should be. It
constitutes a definitive, irreversible breach of the 1977 Treaty.
* Charles De Visscher, Th6orir.s ct rc;alité.~rn droif intrrnational public, 4th ed., 1970,
p. 319.
132
while the case was before the Court. Today it is a n almost complete
structural effectivitc;.
The second singularity of the Slovak eJlfectivitc5is that it draws its
strength,from thcJ;lcts but also, in part, from the latt,.This is a striking
characteristic of this ejJectivité, which is constructed, like any ejTec-
tivité, ugainsr the law (in this case treaty law), but which is nevertheless
reinforced by a partial application of the Treaty, enabling Slovakia
to contend that its Variant C was nothing more than an "approximate
application" of the Treaty.
In fact :
(i) the dam and hydroelectric power plant at Gabtikovo, now con-
structed, were provided for in the Treaty;
(ii) the diversion of the Danube was provided for in the Treaty (the
major difference being that the river was closed at Cunovo instead
of Dunakiliti): and
(iii) the Danube still flows along its original bed (with the twofold dif-
ference that it has been closed at Cunovo and above al1 that Slova-
kia releases a n insufficient volume of water daily into the Danube, a
situation which Slovakia considers might be improved).
58. As for Hungary, it has abandoned work on al1 fronts and has
decided not to buil'd the Nagymaros dam. The nature of the Hungarian
<ffectivités is rather curious.
Firstly, a n eflectivifé may express a certain order established by the
act. This is not the case here. The Hungarian effectivités express, quite
the contrary, a kind of "disorder" arising from the abandonment of the
works. They are exf'ectivités not "in action" but in a state of prolonged
"malformation".
As for the Nagynnaros site, it presents a picture of a kind of "negative"
elfectivité through the abandonment of the construction of the dam. This
means that the "negative" efictivité of Nagymaros has created a defini-
tive situation, for Hungary's will appears irrevocable.
The other Hunp;arian efictivités have generated a state of affairs
unsatisfactory for all. This situation is waiting to be taken in hand o r
"recycled" by another law, whether treaty law (a renegotiated 1977
Treaty), o r domestic law (a Hungarian decision to destroy o r redeploy
the uncompleted sh.ells).
59. Both the Slovak and Hungarian effectivités share the characteristic
of enjoying a significant degree of mutual recognition by the Parties. Despite
the difficulties there are in grasping al1 the nuances of the Hungarian posi-
tion from one writttzn pleading to another and from one oral argument to
another, 1 think that Hungary is not calling for the dismantling of Variant C.
As for Slovakia, it seems on the one hand to be seeking to adjust to the
fact that the Nagymiaros dam does not exist by, among other things, modi-
fying the way Gabëikovo operates and on the other hand avoiding calling
for the completion of the "large reservoir" a t Dunakiliti, which is very
costly and heavily polluting, but above al1 duplicates the Cunovo reservoir.
GABC~KCI~O-NAGYMAROS
PROJECT (SEP.OP.BEDJAOUI) 137
These were valuable pointers for the Court, "signals" one might Say in
the attempt to find i~ppropriatesolutions, heuring in mind the law and the
facts.
60. Whut is the kiiv? What are the facts? First, the facts. They are con-
stituted by the reality on the ground, which 1 have just analysed as ef;fc-
tivités. Second, the law. The law is constituted by the 1977 Treaty and its
related instruments, which the intersecting violations of both parties have
been powerless to terminate. Consequently, there is no point in conceal-
ing the extremely delicate nature of the task conferred upon the Court in
this case where the facts clash head on with the law. which ourrht." , how-
ever, to have the firial Say. The situation may be analysed as follows: on
the one hand the 1977 Treaty has largely been stripped of its materiul
content, but remains a jbrmul instrument, a receptacle or shell ready to
accommodate new commitments bv the Parties: on the other hand. in
parallel, ej;fi?ctivitéshave come into being which are mutually recognized
bv the Parties. So iit was for the Court to declare that both Parties were
under an obligation to negotiate in good faith a new content to their
Treaty, taking account of what remained of the Treaty and also the ejfec-
tivitbs on the ground. However it was important to emphasize above al1
that in taking thest: efictivités into account the Court clearly had no
intention whatsoever of legitimizing the unluivful fucts estuhlished. All it
had to do, in a spirit of legal realism, was to take note (together with the
Parties themselves to some extent) of the effects resulting from a wholly
singular succession of intersecting violations, each of which remained
reprehensihle as suc,h.
61. In order to d o so, we must first examine the consideration given to
the maintenance in force of the 1977 Treaty and its significance, then the
consideration of the effectivités and its significance, before attempting to
make these two eleiments "CO-exist" within the framework of a renewed
treatv.
62. The maintenance in force of the Treaty does not mean the enforced
performance of the obligations it imposed on Hungary, obligations
which to date had not been fulfilled. It is neither necessary nor justified
to infer al1 the logiical consequences from the maintenance in force of
the Treaty. There is no question of obliging Hungary to construct the
Nagymaros dam, to complete the works at Dunakiliti, t? put the diver-
sion dam at Dunakiliti into operation and to flood the Cunovo installa-
tions, nor to compbete, upstream of Gabëikovo, that part of the work it
was to carry out under the Treaty, provided Slovakia had not already
done so.
At the same time, however, any idea of legitimizing the abandonment
by Hungary of its treaty obligations must be totally excluded. Whilst
accepting the effectivités as inescapable acts, their nature as internation-
ally unlawful acts inust nonetheless be noted, acts for which Hungary
GABC~KOVO-NAGYMAROSPROJECT (SEP.OP. BEDJAOUI) 138
must answer by assuming its responsibility. The same holds true for the
consideration of the Slovak ejjectivités, whose unlawful nature has also
not been eradicated.
63. The survival of the Treaty in the face of al1 the violations shows
well enough that tl-iere is n o question of legalizing the infringements of
the principle pacto sunt servunda. Although it is prudently realistic
to take account of the ejfectivités and not to "run headlong into" an
inescapable reality, it seems even more essential, especially for a world
judicial organ concerned to ensure that international law is respected,
to show urbi et orbi that treaties are not "scrups of paper" and that they
cannot be destroyetl by violating them. Save by mutual consent, States
cannot and may noi. rid themselves of their treaty obligations so easily. It
is vital to reinforce the legal certainty of international commitments.
64. The survival of the Treuty ulso mukes it possible to sulvuge its
Articles 15, 19 und 20, relating respectively to the protection of water
quality, the protection of nature and fishing interests. They are of course
extremely general, unsatisfactory articles. However they concern essential
matters which lie at the root of the current dispute between the two
States. It will therefore be for the two States to settle these vital matters
of the environmerit, water quality and fishing, by negotiation. In
Articles 15, 19 and 20 they will find the basis for that renegotiation.
65. L u s t h , the survival of the Treuty provides a context, and even more
a specijïc jirumeivor/r, for the ivishes of' the t ~ States
o in negotiution. It is
not only Articles 15, 19 and 20 which the survival of the Treaty will sal-
vage. More than that, the 1977 Treaty will make it possible to conserve
the gencrul plzilo.sq~h~~ und the major principles which have inspired this
association betweeni two States with a view to a joint investment, from
which they could t:xpect mutual benefits. The Treaty will serve as a
framework, and the wishes of the two States will thus be channelled in
order to avoid undesirable excesses, or, conversely, any reluctance, by
either Party. The Treaty which survives already contains a number of
accepted guidelines and useful principles to point the way for future
negotiation. In particular, apart from Articles 15, 19 and 20, the follow-
ing points need to be further developed and adjusted, but in principle are
already accepted. These are:
(e) "deepened ana' regulated bed of the Danube, in both its branches. . . "
(Art. 1, para. 3 ( c ) ) ;
( f ) the principles which have presided over the distinction betwleen joint
investment und national investment (Art. 2);
( g ) the "re.spon.si/~ility,for the costs of the joint investment" (Art. 5),
which will enable the future negotiators t o assess the costs and to
calculate how much of these costs each Party has already paid and
for how muci-i it still remains reswonsible:
( h ) the determination of the joint and separate owvzership of each State
with respect t(3 each of the structures already built (Article 8 of the
Treaty). The lbypass canal constructed by Czechoslovakia alone is
regarded as joint property by Article 8 ( b ) , which is normal in this
system of joint investment and operation, but Hungary, which must
legitimately accede to this joint property, will have to pay its part of
the construction of that canal;
(i) the method for the joint operation of the works (Arts. 9 and 10) and
the principle of participation "in the use und in the benejts of the
system . . . in equal measure" (Art. 9 , para. 1);
( j ) the ~lithdraivalofwater from the Danube and the rules and guaran-
tees which apply to the Parties;
( k ) the protection ofivater quality (Art. 15, cited above), the maintenance
of the hed of tlhe Danube (Art. 16); the rules for nuvigation (Art. 18);
the protection of the environment (Arts. 19 and 20, cited above);
(1) the determination of the State houndary line between the two
Parties (Art. ;!2); and lastly
( m ) joint liability und .sc.parate liability in the event of damage (Arts. 25
and 26).
So much for the survival of the 1977 Treaty and its significance. Let us
now examine the consideration of the effectivités and then its signifi-
cance.
66. The signiJîcuizce to be attached to taking account of the effectivités
must be indicated, which is a way of highlighting the conditions placed
upon their ultima1.e harmonization with the law. In the traditional
scenarios, the State invokes an effectiilité ugainst a title, in other words
against the luiv itself. In this case on the other hand, taking account of
the effectivités is not tantamount to a negation of the title. The title does
not disappear; it merely adapts and does so, moreover, through involving
the responsibility of the authors of these effectivités, who will be liable
for al1 the necessary compensation. The law, trampled by the effectivités,
is thus "avenged" by the price paid by the Parties in the form of com-
pensation for the elfectivités created. It is on this condition, in particular,
that CO-existencewiill develop between these effectivités which have been
"paid for" and the law which has been "avenged".
67. With this in mind, we shall first see how the Parties could adapt
these effectivités in their negotiations to incorporate them into the new
GABCIKCIVO-NAGYMAROS PROJECT (SEP. OP. BEDJAOUI) 140
Thus it is not as if the Court did not take into consideration the
scientific evidence presented by Hungary in particular regarding the effects
on its environment of the Project, but the Court reached the conclusion
that such evidence was not sufficient to allow Hungary unilaterally to
suspend or terminate the Treaty. This finding, in my view, is not only of
significance to Slovakia and Hungary - the Parties to the dispute - but
it also represents a significant statement by the Court rejecting the argu-
ment that obligations assumed under a validly concluded treaty can no
longer be observed because they have proved inconvenient or as a result
of the emergence of a new wave of legal norms, irrespective of their legal
character or quality. Accordingly, not for the first time and in spite of
numerous breaches over the years, the Court has in this case upheld and
reaffirmed the principle that every treaty in force is binding upon the
parties and must be performed in good faith (Article 26 of the Vienna
Convention on the Law of Treaties).
It is against th:is background that the Court also reaffirmed the prin-
ciple of international law that, subject to the appropriate limitations, a
State party to a treaty, when confronted with a refusal by the other party
to perform its pa1.t of an agreed project, is free to act on its own territory
and within its ovin jurisdiction so as to realize the original object and
purpose of the treaty, thereby limiting for itself the damage sustained
and, ultimately, the compensatory damages to be paid by the other party.
Variant C, the Court found that, though there was a strong factual simi-
larity between Variant C and the original Project in its upstream compo-
nent (the GabCikovo System of Locks), the difference from a legal point
of view was striking. It observed that the basic characteristics of the 1977
Treaty provided for a "joint investment", "joint ownership" of the most
important construction of the GabCikovo-Nagymaros Project and for the
operation of this "joint property" as a "CO-ordinated single unit". The
Court reasoned that al1 this could not be carried out by unilateral action
such as that involving Variant C and that, despite its physical similarity
with the original Project, it differed sharply in its legal characteristics.
The Court also found that, in operating Variant C, Slovakia essentially
appropriated for its own use and benefit between 80 and 90 per cent of
the waters of the Danube before returning them to the main bed of the
river downstream of GabCikovo. This act. in the Court's view., d e ~ r i v e d
L
realized. It should be recalled that but for the suspension and abandon-
ment of the works, there would have been no Variant C , and without
Variant C, the objective of the act of Hungary which the Court has quali-
fied as unlawful would have been realized thus defeating the object and
purpose of the Treaty. In my view Variant C was therefore a genuine
application of the Treaty and it was indispensable for the realization of
its object and purpose. If it had not proceeded to its construction,
according to the material before the Court, Czechoslovakia would have
been stranded with a largely finished but inoperative system, which had
been very expensive both in terms of cost of construction and in terms of
acquiring the necessary land. The environmental benefits in terms of
flood control, which was a primary object and purpose of the Treaty,
would not have been attained. Additionally, the unfinished state of the
constructions would have exposed them to further deterioration through
continued inoperation.
have been necessary if the works had not been suspended and terminated
in the first place. It was this original breach which triggered the whole
chain of events. At least a distinction should have been drawn between
the consequences of the "wrongful conduct" of each Party, hence my
unwillingness to concur with the finding. While Article 38, paragraph 2,
of its Statute allows the Court to decide a case e x aequo et horzo, this
can only be done with the agreement of the parties to a dispute.
The Judgment also alluded to "the continuing effects of the diversion
of these waters on the ecology of the riparian area of the Szigetkoz". It is
not clear whether by this the Court had reached the conclusion that sig-
nificant harm had been caused to the ecology of the area by the operation
of Variant C.
In the light of the foregoing considerations, 1 take the view that the
operation of Variant C should have been considered as a genuine attempt
by an injured party to secure the achievement of the agreed objectives of
the 1977 Treaty, in ways not only consistent with that Treaty but with
international law and equity.
In his separate opinion in the case concerning the Diilersion of Water
Jiom tlze Meu.~e,Judge Hudson stated that
"[Wlhat are widely known as principles of equity have long been
considered t o constitute a part of international law, and as such they
have often been applied by international tribunals, . . ." (Jir~/gtnent,
1937. P.C. I. J., Series A/B, No. 70, p. 76).
The Project would have entailed the construction of (i) a bypass canal
to receive water diverted at the Dunakiliti dam (to be constructed on
Hungarian territory) and (ii) two power pla.nts (one at GabEikovo on the
bypass canal on Czechoslovak territory and one a t Nagymaros on Hun-
garian territory). It may well have been the case that the bypass canal was
also required for the future management of the river Danube with respect
to flood prevention and the improvement of international navigation
facilities between Bratislava and Budapest. However, the bypass canal
was aimed principally a t the operation of the GabEikovo power plant on
Czechoslovak territory and the Dunakiliti dam, mostly on Hungarian
territory, was seen as essential for the filling and operation of that canal,
while the Nagymaros System of Locks on Hungarian territory was to
have been built for the express purpose of generating electric power at
Nagymaros and partially for the purpose of supporting the peak-mode
operation of the GabEikovo power plant.
The 1977 Treaty was signed by the Heads of each Government (for
Czechoslovakia, the Prime Minister; for Hungary, the Chairman of the
Council of Ministers), and registered with the United Nations Secretariat
(UNTS, Vol. 236, p. 241). It gave, on the one hand, an overall and gen-
eral picture (as well as some details of the construction plan) of the
Project for the GabEikovo-Nagymaros System of Locks (which would,
however, have in essence constituted a "partnership" according to the
concept of municipal law) (see 1977 Treaty, Chaps. I-IV), while, on
the other hand, it aimed, as a n ordinary international treaty, to serve
as a n instrument providing for the rights and duties of both parties in
relation to the future management of the river Danube (see 1977 Treaty,
Chaps. V-XI).
Under the plan described in the 1977 Treaty, the cost of the "joint
investment" in the system of locks was to have been borne by the respec-
tive parties and the execution of the plan, including labour and supply,
was to have been apportioned between them (1977 Treaty, Art. 5 ) . The
Dunakiliti dam, the bypass canal, the GabEikovo series of locks and the
Nagymaros series of locks were to have been owned jointly (1977 Treaty,
Art. 8) and the parties assumed joint responsibility for the construction
of those structures. More concretely, the project for the diversion of the
waters of the river Danube at Dunakiliti (on Hungarian territory) into
155 GAB~~KOVO-NAGYMAROS
PROJECT (DISS.OP. ODA)
the bypass canal (on the territory of Czechoslovakia), and the construc-
tion of the dams together with the power stations at GabEikovo and
Nagymaros were to have been funded jointly by the parties. The electric
power generated by those two power stations was to have been available
to them in an equal measure (1977 Treaty, Art. 9).
It must be noted, however, that the 1977 Treaty does not seem to have
been intended to prescribe in detail the content of the construction plan,
that being left to the Joint Construction Plan to be drafted by the parties
- which, for the sake of convenience, 1 shall refer to as the JCP. While
some detailed provisions in Chapters I-IV of the 1977 Treaty concerning
the completion of the Project did in fact, as stated above, correspond to
provisions subsequently incorporated into the JCP, the Preamble to the
1977 Treaty confines itself to stating that "[Hungary and Czechoslovakia]
decided to conclude a n Agreement concerning the construction and
operation of the Gabtikovo-Nagymaros System of Locks". The 1977
Treaty lacks the form of words usually present in any international treaty
which generally indicates that the parties have tllus ugrrrd the,follo~z,ing
te.\-t (which text usually constitutes the main body of the treaty). This fact
further reinforces the view that the 1977 Treaty is intended only to indi-
cate the basic construction plan of the Project and to leave the details of
planning to a separate instrument in the form of the JCP.
' This Agreement is not to be found, cven in the Worlti Trc.~rtj,Inde\. 1983. The Englisli
texi is to be found in the documents prcsciitcd by both Parties but they are not identical
(Memorial of Slovakia, Vol. 2. p. 25; Memorial of Hungary, Vol. 3. p. 219).
156 GABCIKOVO-NAGYMAROS
PROJECT (DISS.OP.ODA)
' This Agreement is not to be found. even in the World Trcuty Index, 1983. The English
text is to be found in the documents presented by both Parties but they are not identical
(Memorial of Slovakia, Vol. 2, p. 71 : Mcmorial of Hungary, Vol. 3. p. 293).
' The time-limit for the construction plan was revised in the Protocol concerning the
Amendment of the [1977] Treaty signed on 10 October 1983; see also the Protocol con-
cerning the Amendment of the 1977 Agreement signed on 10 October 1983 and the Pro-
tocol concerning the Amcndment of the 1977 Agreement aigiled on 6 February 1989.
157 GABC~KOVO-NAGYMAROSPROJECT (DISS.OP.ODA)
Those two instruments, that is, the 1977 Treaty and the JCP (which
was designed and modified after 1977), should be considered as separate
instruments of differing natures from a legal point of view.
158 GABCIKOVO-NAGYMAROS
PROJECT (DISS.OP. ODA)
and that Hungary's wrongful act could not have been justified in any
way.
Let me examine the situation in more detail. Hungary relies, in connec-
tion with the Dunakiliti dam and the diversion of waters into the bypass
canal at Dunakiliti, upon the deterioration of the environment in the
Szigetkoz region owing to the reduced quantity of available water in the
old Danube river bed. ln my view, however, the decrease in the amount
of water flowing into the old bed of the Danube as a result of the opera-
tion of the bypass canal would have been an inevitable outcome of the
whole Project as provided for in the 1977 Treaty.
1 particularly endorse the view taken by the Court when rejecting the
argument of Hungary, that ecological necessity cannot be deemed to jus-
tify its failure to complete the construction of the Nagymaros dam. and that
Hungary cannot show adequate grounds for that failure by claiming that
the Nagymaros dam would have adversely affected the downstream water
which is drawn to the bank-filtered wells constructed on Szentendre
Island and used as drinking water for Budapest (Judgment, para. 40).
12. (Environment of'thc river. Dunuhc.) The 1977 Treaty itself spoke
of the importance of the protection of water quality, maintenance of the
bed of the Danube and the protection of nature (Arts. 15, 16, 19), and the
whole structure of the GabEikovo-Nagymaros Systern of Locks was cer-
tainly founded on an awareness of the importance of environmental pro-
tection. It cannot be said that the drafters of either the Treaty itself o r of
160 GABCIKOVO-NAGYMAROS
PROJECT (DISS.OP. ODA)
not the 1977 Treaty itself- that concern the concrete planning o r opera-
tion of the whole System of Locks. In this respect, 1 d o not see how any
of the grounds advanced by Hungary for its failure to perform its Treaty
obligations (and hence for its violation of the Treaty by abandoning the
construction of the Dunakiliti dam) could have been upheld as relating to
a state of "ecological necessity".
ment on the one hand and preservation of the environment on the other,
with a view to maintaining sustainable development. Any construction
work relating to economic development would be bound to affect the
existing environment to some extent but modern technology would, 1 am
sure, be able to provide some acceptable ways of balancing the two con-
flicting interests.
18. f Tlze Dunakiliti dum und the Guhtikovo plunt.) The construction
of the Dunakiliti dam and of the bypass canal, which could have been
filled only by the diversion of the Danube waters at that point, form the
cornerstone of the whole Project. Without the Dunakiliti dam the whole
Project could not have existed in its original form. The abandonment of
work on the Dunakiliti dam meant that the bypass canal would be
unusable and the operation of the Gabtikovo power plant impossible.
Hungary must assume full responsibility for its suspension of the
works at Dunakiliti in violation of the 1977 Treaty.
20. (The Nugymaros dam - I I . ) The matter of the equal shares of the
electric power from the Nagymaros power plant to be guaranteed to
Czechoslovakia and the feasibility of the operation of the Gabtikovo
power plant in peak mode could have been settled as modalities for the
execution of the JCP, even in the event of the abandonment of the Nagy-
maros power plant, as technical questions could be dealt with in the
framework of the JCP without any need to raise the issue of reparations
to be paid by Hungary to Czechoslovakia in connection with the aban-
donment of the Nagymaros dam.
There can be no doubt that the construction of the Nagymaros System
of Locks was seen as a major link in the chain of the whole Project in
connection with the construction of the GabCikovo System of Locks on
Czechoslovak territory. The construction of the Nagymaros System of
Locks was, however, essentially a matter that fell within Hungary's exclu-
sive competence on ils own territory. l n the late 1980s, Hungary found it
no longer necessary to produce electricity from the Nagymaros power
plant on its own territory, and the abandonment of the Nagymaros dam
did not, in fact, cause any significant damage t o Czechoslovakia and
did not have any adverse affect on interests that Czechoslovakia would
otherwise have secured.
In this connection, 1 must add that Czechoslovakia would have been
permitted under international law as prescribed in the Vienna Conven-
tion on the Law of Treaties to terminate the 1977 Treaty on the ground
of Hungary's failure to perform the obligations of that Treaty. In fact,
however, Czechoslovakia did not d o so but chose to implement the 1977
Treaty without Hungary's co-operation because the completion of the
Project, as envisaged in the 1977 Treaty, would be greatly to its benefit.
Thus, although Hungary has to bear the responsibility for its abandon-
ment of the Nagymaros dam as a part of the joint project of the
GabEikovo-Nagymaros System of Locks, the reparations that Hungary
should pay to the present-day Slovakia as a result are minimal (see para. 34
below).
21. The Court is requested under the terms of the Special Agreement
to decide
"whether [Czechoslovakia] was entitled to proceed. in November
1991, to the 'provisional solution' and to put into operation
from October 1992 this system" (Art. 2, para. I i h ) ) .
22. (Provi.sionu1 .sol~rtion= Vr~rirrntC.) As Hungary had suspended
work on part of the GabEikovo Project, more particularly the work at
Dunakiliti, thus preventing the diversion of the water into the bypass
canal. the finalization of the whole Project, which was already nearly
70 per cent complete, was rendered impossible.
Treaty had been jeopardized by Hungary, and since the benefit which
Czechoslovakia would have enjoyed as a result of the power plant at
Gabtikovo and al1 the benefits which would have been available to both
States with regard to international navigation as well as water manage-
ment (including flood prevention) of the river Danube had thereby been
threatened, it was permissible and not unlawful f o r Czechoslovakia to
start work on Variant C (the construction of the Cunovo dam). This
would have an effect similar to the original plan contemplated in the 1977
Treaty, that is, the diversion of water into the bypass canal. Hungary, for
its part, had from the outset given its full agreement to the diversion of
the Danube waters into a bypass canal at Dunakiliti on its own territory.
revise the J C P in order to implement the 1977 Treaty, although the con-
sent of Hungary to that solution was not obtained. Czechoslovakia had
the right to take that action.
This matter, however, might well have been rectified by soine mutually
acceptable arrangement. It may well be possible to control the distribu-
tion of the water at Cunovo by the use of sluice-gates or by a moditica-
tion to the design of the dyke separating the waters in the Cunovo reser-
voir. The control of the water was /lot the essence of the Variant C
project and could still be dealt with in a more flexible manner through a
revision o r redrafting of the relevant texts of the JCP.
"to determine the legal consequences, including the rights and obli-
gations of the Parties, arising from its Judgment on the questions in
paragraph 1 of this Article".
26. ( T h e lu~tlfulnessof Vuriant C.) The construction of Variant C was
not unlawful and Slovakia did not incur any responsibility to Hungary,
except that the way in which the Cunovo dam was controlled by Czecho-
slovakia seems to have led to a n unfair division of the waters between the
old Danube river bed and the bypass canal. Slovakia is entitled to repara-
tion in the form of monetary compensation from Hungary for some por-
tion of the cost of the construction work on the Cunovo dam met by
Czechoslovakia alone as a result of Hungary's failure to execute its
Treaty obligations concerning the completion of the Gabeikovo-
Nagymaros System of Locks. The cost of the construction of the Cunovo
dam and the related works should in part be borne by Hungary but, in
exchange, it should be offered CO-ownershipof it. On the other hand, if
the operation of the ~ u n o v odam diverting waters into the old Danube
river bed has caused any tangible damage to Hungary, Slovakia should
bear the responsibility for this mishandling of the division of waters. It
must be noted, however, that, as a result of the planning of this whole
Project (especially the bypass canal), the volume of water flowing into the
old river bed could not be as great as before the Project was put into
operation.
27. The Court is requested under the terms of the Special Agreement
to decide "what are the legal effects of the notification, on 19 May 1992,
of the termination of the Treaty by [Hungary]" (Art. 2, para. 1 (c)).
28. (Hungary's notijicution of terminution of the 1977 Treuty.) This
question concerns nothing other than the interpretation of the law of
treaties, as the Judgment properly suggests. The termination of the 1977
Treaty is essentially different from an amendment of the JCP. Hungary
claims that, as Variant C was in contradiction of the Plan and thus con-
stituted a wrongful act, the 1977 Treaty could be terminated because of
that alleged violation of the Treaty by Czechoslovakia.
V. THE F I N A LSETTLEMENT
(Special Agreement, Article 5)
30. Hungary and Slovakia have agreed under Article 5 of the Special
Agreement, that: "Immediately after the transmission of the Judgment
the Parties shall enter into negotiations on the modalities for its execu-
tion."
31. (Negofiations under Article 5 of the Special Agreement.) As 1 have
already said, my views differ from those set out in the Judgment in that
1 believe that Czechoslovakia was entitled to proceed to the provisional
solution, namely, not only t h e construction of the Cunovo dam but also
the operation of that dam at Cunovo in November 1992 for diversion of
water into the bypass canal. As 1 see it, Czechoslovakia did not violate
the 1977 Treaty. It is my opinion that the "negotiations" between Hun-
gary and Slovakia under Article 5 of the Special Agreement should be
based on this understanding and not on the finding stated in the Judg-
ment in its operative paragraph 155, points 1 C and 2 D.
maintenance of the bypass canal for flood prevention and the improve-
ment of navigation facilities. 1 would suggest that the J C P should be
revised o r some new version drafted during the negotiations under
Article 5 of the Special Agreement in order to comply with the moda-
lities which 1 have set out above.
[TranslationJ
The dual purpose of the Court's task under the terms of Article 2 of
the Special Agreement is the subject of an excellent analysis in para-
graphs 130 and 131 of the present Judgment. My disagreement, though,
relates to the place of the intersecting wrongs which, in the eyes of the
majority of the Members of the Court, is pertinent only to the prescrip-
tive part of the J~udgment,whereas in my opinion it constitutes the
cornerstone of the declaratory part.
The question which the Court could, or even should, have asked itself
is whether in the absence of Hungary's first act of unlawfulness in 1989,
the subsequent wrongs would have occurred and in particular whether
the decision to abandon the works would have been taken in November
GABCIKOVO-NAGYMAROS PROJECT (DISS.OP. RANJEVA) 171
With al1 the respect 1 have for the Court, 1 d o not believe that the obli-
gation of reparation is the only area on which the intersecting nature of
the wrongs has had a bearing. The concept of violation of a norm, by the
commission of unlawful acts, is meaningless in absolute terms; it is only
meaningful in relation to the rights of each Party under the 1977 Treaty
and to the discretionary power of subjective characterization by a party
itself which is ascribed to it in law. The idea of violation thus enables
each party to infer the consequences from a course of conduct which it
has characterized as unlawful beforehand, in a discretionary manner.
These consideratioris lead on the one hand to consideration of the con-
sequences of the Hungarian wrong (para. 155 (1) (A)) for the sequence of
events and on the other hand to criticism of paragraph 155 (1) (B) of the
present Judgment.
N o peremptory conclusion can be formulated as to the sequence of
facts which make up the conduct of each Party. The concept of original
cause may only be established, in the present case, on two conditions:
first, that of its appearance ex nihilo in the chain of events and, second,
that of its effectiveiness as far as the actual "
eenesis of the events is con-
cerned. In order to satisfy these requirements, it would have been neces-
sary for the wrong committed by Hungary to have borne no relation
whatsoever to any conduct on the part of Czechoslovakia. But, in the
present case, given the chaotic nature of the relations between the two
Parties in dispute, it is difficult to seek to introduce a more o r less un-
differentiated mechanistic analysis into this discussion. Contrary to the
requirements inherent in the law of liability in domestic law, the case is
not about finding at al1 costs who is liable, nor about making a finding of
unlawfulness per sr which is not the cause of the sequence of respective
actions of the Parties. Evidence of unlawfulness is not sufficient to estab-
lish a link of direct causality between the Hungarian conduct and the
Czechoslovak reaction.
The his~oricalarid technical details show that projects for regulating
the Danube in that portion of the river's course had been envisaged since
the end of the Second World War. In the framework of such programmes
of CO-operation, each party was pursuing objectives which were not
necessarily the sarne of those of its partner. Thus the Czech and Slovak
Federal Republic expressed a particular interest in hydroelectricity and
' The zero option is linked to a certain interpretation of the rule of Pomponius accord-
ing to which "Quod si quis ex culpa sua sentit. non intelligitur damnum sentire" (Digest.
"De regulu juris". 50. 17). In other words, a claimant is deprived of his right to reparation if
he can be accused of wrongdoing, whether o r not it is the cause of the loss he has suffered.
The proposition of Pomponjus was ruled out by canon law as individualization of liability
for fault gradually developed and mechanisms for presuming liability weakened.
G A B C ~ K ~ V O - N A G Y M A R OPROJECT
S (DISS.OP. RANJEVA) 173
Once, though, l.he Court has accepted the intersecting nature of the
wrongs committecl by the Parties, the distinction between the construc-
tion of Variant C on the one hand and putting it into operation on the
other is purely art.ificial in the context of the pressureinegotiations rela-
tionship game.
GABCIKCIVO-NAGYMAROS PROJECT (DISS.OP. RANJEVA) 174
This Judgment of the Court cites that passage and stresses the impor-
tance of respecting the environment, but then does not take due account
of the application of that principle to the construction and operation of
the GIN Project.
The Court only grants a very modest place to ecological considerations
GAHCIKOVO-NAGYMAROS PROJECT (DISS.OP. HERCZEGH) 177
That mode of operation involved and involves risks which were not
altogether unknowri to those responsible for drawing up the plans for the
GIN Project, but its designers reasoned within the confines of what was
known in the 1960s and 1970s - and that way of thinking is today con-
sidered outmoded, and rightly so. They accordingly minimized the risks,
whilst at the same time having an imperfect understanding of the damage
they could cause, and therefore of the possible solutions. T o give just one
example, the fact thiat the Joint Contractual Plan only provided for a dis-
charge of 50 cubic metres per second in the old channel of the Danube
during the months of March to November shows clearly that the most
basic ecological considerations were not accorded the weight they
deserved. The original Project was criticized not only by the Hungarian
Party, but also by the Czechoslovak leaders. Paragraph 38 of the Judg-
ment quotes the C:zechoslovak President, Mr. Havel, as saying that the
GIN Project was a "totalitarian, gigomaniac monument which is against
nature" (Counter-Fdemorial of Hungary, Vol. 3, Ann. 88), together with
part of a statement made by the Czechoslovak Minister for the Environ-
ment, Mr. Vavrouliek, for whom "the GIN Project was an old, obsolete
one", and who weint on to say that "there is n o doubt that if we could
turn the course of time, we would never approve the original project . . ."
but that even though there were "many reasons to change, modify the
Treaty . . . it [was] not acceptable to cancel the Treaty . . . and negotiate
later on" (Mernorial of Slovakia, Vol. IV, Ann. 97, pp. 248-249).
so forth, whereas it could and should have concerned itself with the prob-
lems which the interpretation and implementation of these provisions
might raise in the field. However, the Judgment merely mentions the aims
of the Project and the advantages it was presumed to offer.
It is regrettable that the Court did not follow this principle even in the
reasoning which led to its reply to the first question put to it in the
Special Agreement.
T o have perceived the shortcomings of a project - to avoid using the
word "error" - anid to recognize that one is the source of those short-
comings are two very different things which may sometimes be very far
apart. The principal argument put forward, in 1991, by the Czechoslovak
party in favour of tlhe GIN Project, was based on the fact that the Project
was almost compleied. By the acceleration of the works laid down in the
Protocol of 6 Febr~iary1989, certain Hungarian leaders wanted to d o the
same thing -- to claim that a point of no return had been reached - in
order to deal with increasing opposition and resistance. Political changes
during that year prevented them from achieving that aim.
The crucial probllem posed by the GIN Project was that of peak mode
operation, for which the 1977 Treaty makes no provision. Slovakia con-
firmed repeatedly that there was no agreement between the contracting
parties with regard to the peak mode operation of the system of locks. It
maintained that the operational rules relating to peak mode operation
had still not been established at the start of 1989, and that without the
agreement and CO-operation of the parties n o plan to operate in peak
mode could be implemented. In its Reply (Vol. II, pp. 8-9), Slovakia
states "the Gabëikovo plant would have operated a t a level of maximum
peak mode operation that was never agreed between the Treaty parties"
and "Czechoslovakia offered its pledge to limit o r exclude [that mode of
operation] in October 1989 ifjustijied by suhsequent studies" (emphasis
added). A few lines further on, it reaffirms that:
In that case, the danger which the construction of the Nagymaros dam
posed for Budapest"~drinking water supply - a point 1 shall return to
later - was a sufficient ground for amending the 1977 Treaty and
the international agreements linked to it, as Hungary suggested in its
Note Verbale dated 3 November 1989 (Memorial of Hungary, Vol. 4,
Ann. 29).
Before replying to the question "whether the Republic of Hungary was
entitled to suspend and subsequently abandon, in 1989, the works on the
Nagymaros Project and on the part of the GabCikovo Project" for which
it was responsible, it should be noted that that question covers several
actions taken by the Hungarian Government which must be assessed
individually. Those actions are the following:
- in May 1989, the suspension of work on the Nagymaros dam;
- in July 1989, the suspension of work at Dunakiliti;
- in October 1989.,the abandonment of work at Nagymaros.
At the same time, it should be noted that, towards the end of 1991,
Hungary carried on, with and even completed the work relating to the
GABC~KOVO-NAGYMAROS
PROJECT (DISS.OP. HERCZEGH) 182
The "deliberate nature of the conduct, the intentional aspect of its failure
to conform with the international obligation" - according to the
Report -
"are not only undeniable but in some sense logically inherent in the
justification alleged; invoking a state of necessity implies perfect
awareness of having deliberately chosen to act in a manner not in
conformity wilth an international obligation" (ihid., p. 34, para. 3).
The dredging of the bed of the Danube in the two branches around the
island of Szentendre - as laid down by Article 1, paragraph 3 ( c ) , of the
1977 Treaty - had already caused serious damage. After the water
services of the Hungarian capital had raised the alarm, those works
CABCIKOVO-NAGYMAROS PROJECT (DISS. OP. HERCZEGH) 184
The Nagymaros dam could only have had the same effects, down-
stream, on the bed of the Danube, as the dams built in Austria had had
on the sector of the Slovak capital: the erosion of the river bed. As a
result of such erosion, the production of drinking water from the bank-
filtered wells on the banks of the island of Szentendre could only dimin-
ish, and the quality deteriorate. Certus un incertus yuundo. It was impos-
sible to predict exactly that that diminution would amount to such-and-
such a percentage of the former production of those wells, and whether it
would occur over five o r ten years, but it was certain that the quantity of
water would diminish and its quality deteriorate in the relatively near
future.
The imminence of the peril in question depended on the construction
of the Nagymaros clam: without the dam, there would be no grave peril,
either imminent o r long-term; once the dam had been constructed, it
would no longer have been appropriate to speak of a peril, but rather of
grave and permanent damage occurring for so long as the dam existed -
a dam built by the very State whose population and territory would have
been its victims. T o claim that the suspension of works on the Nagy-
maros dam was not justified by a state of necessity, since the peril was not
imminent, means in reality that Hungary should have completed the dam
and waited for the bank-filtered wells on the island of Szentendre to dry
out because of the erosion of the river bed and for the supply of drinking
water to the Hungarian capital to be called critically into question. The
Court, in deciding the case, ought to have taken account of the damage
that would have occurred if the Partv in auestion had not taken the
necessary preventive measures. States are under a n obligation of preven-
tion and not merely of reparation.
Slovakia did not deny that the effectiveness of the wells would be
reduced, but it claimed that they would not be entirely lost and suggested
measures designed to deal with such a situation, but without taking
account of the cost of such measures (see Slovakia's reply, dated 7 May
1997, to the question asked by the Vice-President (CR97115, p. 64).
Indeed, the surface waters could have been purified and rendered fit for
human consumptioin; however, that would have been enormously expen-
sive in view of the reauirements of a citv of two million inhabitants. The
other solution proposed, namely the discharging of large quantities
of gravel into the river bed, did not seem very realistic: both branches of
the Danube arourid the island of Szentendre, taken together, are
1,000 metres wide and 70 kilometres long. How much gravel would there-
fore have been necessary to counteract the erosion of the river bed caused
by the Nagymaros d a m ? The third solution raised, the construction of a
second dam downstream of Budapest, would have cost n o less and, in the
end, a third dam would have been needed, at Paks o r at Mohacs, not to
mention the potential consequences of such a series of dams on the
Yugoslav sector of the Danube. In theory, al1 three solutions were pos-
sible - the argument of impossibility does not stand up - but the imple-
mentation of these measures would have radically transformed the scope
of Hungary's remaining obligations under the Treaty. Such a solution
denotes a fundamental change of circumstances which may be relied
GABCIKOVO-NAGYMAROS PROJECT (DISS. OP. HERCZEGH) 186
The Court held that the state of necessity, as a ground for precluding
the wrongfulness of a n act not in conformity with an international obli-
gation, can only be accepted on a n exceptional basis and, referring to the
relevant International Law Commission Report, added that
"the state of riecessity can only be invoked under certain strictly
defined conditlions which must be cumulatively satisfied; and the
State concerned is not the sole judge of whether those conditions
have been met" (para. 51).
1 entirely concur with that approach, but 1 cannot accept the conclu-
sions drawn in this case by the Court. It has concluded that, with respect
to both Nagymaros and Gabtikovo,
"the perils invoked by Hungary, without prejudging their possible
gravity, were not sufficiently established in 1989, nor were they
'imminent'; and . . . Hungary had available to it at that time means
of responding to these perceived perils other than the suspension and
abandonment of works with which it had been entrusted" (para. 57).
This is absolutely not the case. As far as Hungary was concerned, what
was at stake was the safeguarding of a n essential interest against a peril
which was grave and imminent, that is to Say certain and inevitable, and
any measures takeri to counteract that peril would have radically trans-
formed the scope of the obligations to be performed under the Treaty. By
suspending and abandoning the works at Nagymaros, Hungary has not
impaired an essential interest of Czechoslovakia, and it is precisely by
constructing the dam at Nagymaros that it would have contributed to
an unequalled state of necessity and to a situation catastrophic for its
capital. The existence of the peril alleged by Hungary was recognized -
at least in part- by the other Party, and Hungary therefore did not act
in a n arbitrary mariner.
The first question asked in the Special Agreement was whether the
Republic of Hungary was entitled to suspend certain works for which it
was responsible under the 1977 Treaty. The Vienna Convention on the
Law of Treaties is silent as to the state of necessity. However, interna-
tional law - and particularly the law of responsibility - recognizes it.
The state of necessity exists not only in theory, but also in reality. In the
present case, even the strictest criteria applied cumulatively prove that, as
far as the construction of the Nagymaros dam is concerned, Hungary
was entitled to rely on that ground precluding its responsibility for not
having fulfilled one of its obligations under the 1977 Treaty. It was there-
fore entitled to suspend and subsequently abandon the works at Nagy-
maros. As far as the suspension of the works at Dunakiliti is concerned,
the existence of a siate of necessity is debatable, but Hungary's anxieties
GABCIKO'IO-NAGYMAROSPROJECT (DISS.OP. HERCZEGH) 189
The Court, whi1s.t refusing to accept that Hungary was entitled to sus-
pend and subsequently abandon, in 1989, the works on the GIN Project
relating to Nagymaros, recognizes - albeit indirectly - that Hungary's
position is well founded, when it manages to assert, in the "prescriptive"
part of its Judgmecit, that the Nagymaros dam should not be built: "with
the effective discartiing by both Parties of peak power operation, there is
no longer any poirit in building it" (para. 134); "the construction of the
Nagymaros dam would have become pointless" (para. 138). Moreover, it
must be a~knowled~ged that the ecological considerations that now weigh
against the dam are the same as those holding in 1989. If it has finally
been concluded thrit the dam should not have been built in 1997, this is
because in reality it should not have been built in 1989, either.
The dispute between the two Parties is very much the result of their
geographical situations. The harmonization of the interests of the coun-
tries upstream and downstream is the crucial problem of the law govern-
ing international watercourses. During the work done by the United
Nations on the Draft Convention on the Law of the Non-Navigational
Uses of International Watercourses, the upstream countries complained
that the provisions of the draft limited their right to use and develop the
resources of those watercourses, whereas the downstream countries criti-
cized the provisions of the draft by maintaining that they failed to protect
their interests adequately and even allowed significant damage to be
inflicted upon thein. As far as the course of the Danube is concerned,
Slovakia is an upstream country and Hungary a downstream country. In
this Judgment the Court should have maintained a balance, admittedly
hard to achieve, between the interests of the upstream and the down-
Stream countries, and have ensured that harmonious progress in enhance-
ment of the natural resources would be carefully organized to prevent the
long-term disadvantages from outweighing the immediate advantages.
Unfortunately, in the present case, it has not succeeded in doing so.
1 have found it necessary to stress this question since the position to be
taken, in particular, on whether Hungary was entitled to suspend and
subsequently abandon the works at Nagymaros, and to suspend those at
Dunakiliti, to a lairge extent determines the replies, or at least the reason-
ing, for the questions which follow.
GABCIKO~O-NAGYMAROS PROJECT (DISS.OP. HERCZEGH) 190
draw water from the Danube a t its own convenience. The old project,
with al1 its drawbacks and defects, was a joint enterprise under the joint
control of both parties. Variant C no longer had or has anything in com-
mon between the two parties, as a result of the exclusive control exercised
by Czechoslovakia - now Slovakia - and was never given any kind of
approval by Hungary.
According to the well-known maxim sic utere tuo ut ulienum non lue-
dus, one's property may not be used in such a way as to cause significant
damage to another. Furthermore, in the present case, Czechoslovakia did
not, and Slovakia today does not use its property in an unlawful manner,
but it has appropriated - and this is one of the key factors in the dispute
-- something whichi did not belong to it, namely almost al1 the waters of
the Danube. It follows from Article 3 of the 1976 Agreement on Bound-
arv Waters that the Parties to the disnute "are entitled. unless otherwise
a&eed, to one-half of the natural dis'charge of water not augmented by
technical means". The Parties have not agreed otherwise. since there has
been no agreement between them as to ~ i r i a n C.
t variant C is therefore
a grave breach both of the 1977 Treaty and of the 1976 Treaty on Bound-
ary Waters.
The Hungarian Government took its decision on the basis of the fol-
lowing consideratic)ns: ( a j state of necessity; ( b ) impossibility of per-
formance; (c) fundamental change of circumstances; ( d i substantial
breach of the Treaty by the other party; and, finally, ( e ) protection of
the environment which had become mandatory in international law.
As a preliminary., I would observe that in reality one does not often see
"pure" or unequivocal cases, in the sense that they require only one single
abstract type of legal settlement o r solution. More often than not, the
legal situation in which the parties find themselves falls within the ambit
of several rules of international law at the same time.
1 shall not examine al1 the arguments put forward by Hungary. Its
main argument to justify termination of the 1977 Treaty is clearly that
the construction 01' Variant C constituted a breach of that Treaty, for
the reasons given bsefore the Court. Hungary described the grave breach
constituted by Variant C as a "repudiation" by Czechoslovakia of the
Treaty, constitutin;: a fundamental change of circumstances (CR 97113,
p. 42, Crawford). The aforementioned concepts and expressions reflect
the situation which prevailed in May 1992, viewed from different angles.
Hungary further contended that that situation could be characterized as
a case of impossibility of performance and, of course, that the develop-
ment of international environmental law ought to be taken into consid-
eration in this context.
From among these different approaches, 1 shall select the one which
seems to me to be the most adequate and the result of which best reflects
the legal points characterizing the situation. That will render superfluous
(;ABCIKOVO-NAGYMAROS PROJECT (DISS.OP. HERCZEGH) 197
the examination of the other arguments put forward, which 1 d o not think
d o more than "reorganize" those points differently and less precisely.
Article 60, paragiraph 1, of the Vienna Convention on the Law of
Treaties provides :
"A material breach of a bilateral treaty by one of the parties
entitles the othr:r to invoke the breach as a ground for terminating
the treaty o r suspending its operation in whole or in part."
Article 60, paragraph 3, provides as follows:
"A material breach of a treaty, for the purposes of this article,
consists in:
(a) a repudiation of the treaty not sanctioned by the present Con-
vention; o!r
( b ) the violation of a provision essential to the accomplishment of
the object or purpose of the treaty."
Variant C constitiited a violation of the provisions of the 1977 Treaty
and other rules of international law, since Hungary was deprived of the
Danube waters whi~rhbelonged to it. As joint operation was the very
essence of the Project provided for by the Treaty, the unilateral diversion
precluded the acconiplishment of the object and purpose of the Treaty.
Notwithstanding the ecological effects that the diversion of the Danube is
alleged to have had, predictably, on Hungary, the mere fact of a uni-
lateral diversion - taken on its own - was so serious that it justified
termination of the Treaty. The main and decisive reason for the termina-
tion is to be found in the construction of Variant C and its unlawfulness,
which must be described as a fundamental violation withiri the meanirig
of Article 60, paragi-aph 3 (b), of the Vienna Convention. The question
falls clearly within t:he ambit of the law of treaties. All the other reasons
put forward are merely subsidiary.
If Variant C truly constituted a grave breach, a fundamental violation
of the Treaty - whi'ch the Court itself has noted - Hungary was entitled
to terminate the Tre:aty.
Was Hurigary's decision premature?
It is true that the diversion of the waters of the Danube had not yet
been completed in May 1992, but the grave breach of the Treaty had
already begun - as 1 have shown earlier - when Czechoslovakia started
constructing Variant C in November of the preceding year. It is difficult
to accept that Hungary should have passively awaited completion of the
construction of Variant C. Czechoslovakia had on several occasions
stated that it was determined to implement the "provisional" solution.
The bilateral negotiations were deadlocked; work on Variant C was pro-
gressing well and Cs:echoslovakia made no secret of its intention to carry
out a unilateral diversion of the Danube waters at Cunovo on the
planned date, while refusing, even for a strictly limited time, to suspend
the works whose objective was no longer a mystery.
GAS~.~KOVO-NAGYMAROSPROJECT (DISS.OP. HERCZEGH) 198
The Court in it:i Judgment has taken the view, however, that the
16 September 1977 Treaty remained in force and that the Slovak Repub-
lic, as successor Sitate to the Federal Czech and Slovak Republic,
became a party to the Treaty as from 1 January 1993. With regard t o the
legal consequences of the Judgment, including the rights and obligations
for the Parties whic:h the Court was asked to determine under Article 2,
paragraph 2, of the Special Agreement, the Court, in paragraph 2 of the
operative part of the Judgment, states at point B that
"Hungary and Slovakia must . . . take al1 necessary measures to
ensure the achievement of the objectives of the Treaty of 16 Septem-
ber 1977, in a.ccordance with such modalities as they may agree
upon".
For its part, point (Iof paragraph 2 of the operative part uses the words
"in accordance witli the Treaty", and point E the expression "in accord-
ance with the relevimt provisions of the Treaty".
By deciding that the 1977 Treaty is still in force, the Court made its
own task more difficult and did nothing to ease that of the Parties since
they have to reachi a n agreement on the resolution of questions over
which they have been in dispute. According to its reasoning,
"The Court would set a precedent with disturbing implications for
treaty relation:; and the integrity of the rule pactu sunt .servunda if it
were to conclude that a treaty in force between States . . . might be
unilaterally set aside on grounds of reciprocal non-compliance."
(Para. 114.)
1 must observe that the expression "reciprocal non-compliance" does
not adequately reflect the cause o r causes of the termination of the treaty.
However, that is not my essential objection regarding that part of the
Judgment; rather a.m 1 concerned at the divergences - not to say con-
tradictions - between its "declaratory" part and its "prescriptive" part.
The Court, while rriaintaining the Treaty in force, wanted to avoid being
GABCIKOVO-NAGYMAROS
PROJECT (DISS.
OP. HERCZEGH) 200
set against the maxiim summum jus sunzma injuria, and it recognized that
the 1977 Treaty, in its originul fornl, did not apply. 1 will cite the perti-
nent passages of the Judgment in extenso:
"133. The Court, however, cannot disregard the fact that the
Treaty has not been fully implemented by either party for years, and
indeed that their acts of commission and omission have contributed
to creating the factual situation that now exists. Nor can it overlook
that factual situation - or the practical possibilities and impossibili-
ties to which it gives rise- when deciding on the legal requirements
for the future conduct of the Parties.
The reasoning of the Court in that context is based above al1 on the
role of the time factor - the eight years that have elapsed between 1989
and 1997: "What inight have been a correct application of the law in
1989 or 1992, if the case had been before the Court then, could be a mis-
carriage of justice if prescribed in 1997." (One should not forget, in this
context, that Hungary proposed, as early as November 1989, that the dis-
putes which the parties could not resolve themselves should be decided by
arbitration or by recourse to the International Court of Justice.) In my
opinion, however, the approach limiting the impact of the time factor to
the period that has elapsed since the dispute arose does not enable the
Court, against the background of a complex case, to incorporate al1 of its
relevant aspects.
Time passed, nof only between 1989 and 1997, but also between 1977
GABCIKOVO-NAGYMAROS
PROJECT (DISS.OP. HERCZEGH) 20 1
The Judgment of the Court puts those Parties back in the context of an
"old", "out-of-date" Treaty, whilst prescribing sensible, reasonable and
even essential changes: to exclude definitively the peak mode operation
of the Gabtikovo power plant; not to build the Nagymaros works since
"there is no longer any point in building [them]"; and, with regard to
environmental protection, to take "new norms" into consideration and to
assess "new require.mentswappropriately, "not only when States contem-
plate new activities but also when continuing with activities begun in the
past" (para. 140).
Those norms would be more effective and the Parties to the dispute
could apply them more easily without the references to the 1977 Treaty.
The Court could and should have founded the prescriptive part of its
Judgment not upon an obsolete Treaty which could not be implemented
- and which in my opinion had been terminated - but on the uncon-
tested rules of general international law and on other treaties and con-
ventions in force between the Parties, in order to resolve the problems
they had inherited jTom the old GIN Project.
One may be certain that the termination of the 1977 Treaty would not
have left the Parties to the dispute in a legal vacuum. Their "relation-
ship", as the Court noted,
"is also determined by the rules of other relevant conventions to which
the two States are party, by the rules of general international law and,
in this particular case, by the rules of State responsibility" (para. 132).
The preamble to the Special Agreement concluded by Slovakia and Hun-
gary states that the Slovak Republic is the "sole successor State" of the
Czech and Slovak E'ederal Republic "in respect of rights and obligations
relating to the GabEikovo-Nagymaros Project". The rights and obliga-
tions created by the: performance of the 1977 Treaty before it was termi-
nated are not affected by the termination of the Treaty. Under Article 70,
paragraph 1, of the Vienna Convention on the Law of Treaties:
"Unless the treaty otherwise provides o r the parties otherwise
agree, the termination of a treaty under its provisions or in accord-
ance with the present Convention :
( a ) releases the parties from any obligation further to perform the
treaty;
( b ) does not izffect u n j right, obligation or legul situation of' the
parties created through the execution oj'the treuty prior to its
ternîination. " (Emphasis added.)
The installations constructed in good faith in fulfilment of the 1977
Treaty - such as (3abEikovo and Dunakiliti - are not affected by the
ultimate fate of that Treaty. Slovakia may therefore keep u p and use the
GabEikovo power plant in a manner not causing significant damage to its
neighbour. that is to say, in particular, by operating it in run-of-the-river
mode. As to the problems resulting from construction of the Cunovo
dam and the diversion of the Danube waters, they should be settled in
accordance with otlier treaties in force between the Parties, in particular
the 1976 Boundary Waters Convention, and with the other principles and
rules of international law in force between the Parties and placing them
under certain binding obligations. It follows that each of the Parties is
obliged to refrain from any act or any conduct having harmful effects on
the environment and causing significant damage to the other Party.
The most important point in that regard is the equitable and reason-
able sharing of the Danube waters. The Judgment of the Court cites
Article 5 , paragraph 2, of the Convention on the Law of the Non-
Navigational Uses of International Watercourses, according to which:
Finally, 1 reiterate my conclusion that the 1977 Treaty was lawfully ter-
minated and that iit is no longer in force. The prescriptive part of the
Judgment of the Court would, in my opinion, have been more logical and
more convincing if the Court had not based it on the 1977 Treaty but
rather on the rules of general international law and on the other treaties
and conventions binding on the Parties.
These considerations forced me to vote against points A, B and D of
paragraph 1 of the operative part.
As regards the points of paragraph 2 of the operative part, it goes with-
out saying that, ha.ving voted against point D of the first paragraph,
1 had to vote against point A of the second paragraph. 1 am firmly con-
vinced that Hungary and Slovakia must negotiate in good faith, on the
basis of the international law in force, to implement the rights and obli-
gations relating to the shared natural resources of the Danube. These
shared resources should be exploited jointly and in accordance with
mutually agreed arrangements. However, the fact that point R of para-
graph 2 refers expressly to the objectives of the Treaty of 16 September
1977, point C to a joint operational régime in accordance with that
Treaty, and point E to the relevant provisions of the said Treaty - which
Treaty in iny opinion, and having regard to the arguments put forward
above, is no longer in force - prevented me from voting in favour of
these points. At the same time, 1 voted in favour of point D on the
reciprocal compen~~ation of Slovakia and Hungary - unless the Parties
otherwise agree - for the damage they have sustained on account
of the construction of the System of Locks, since 1 considered that point
to be fair and in aclîordance with the relevant rules of international law.
1 a m also in agreement with the reasons that led the Court to this finding
(paras. 27-59).
1 have, moreover, voted in favour of paragraph 1 C of the dispositif,
according to which "Czechoslovakia was not entitled to put into opera-
tion, from October 1992, this 'provisional solution' " (para. 155). 1 share
the view of the majority that
"Czechoslovakia, in putting Variant C into operation, was not apply-
ing the 1977 Treaty but, on the contrary, violated certain of its
express provisions, and, in so doing, committed an internationally
wrongful act" (para. 78).
As to the reasoning which led the Court to its findings in this respect
(paras. 72-88), 1 note, in particular, that the Court has not endorsed jus-
tification of Czechoslovakia's recourse to Variant C by an alleged prin-
ciple of "approximate application" (para. 76) and that "[tlhe Court thus
considers that the diversion of the Danube carried out by Czechoslovakia
was not a lawful countermeasure because it was not proportionate"
(para. 87). 1 am in agreement with these positions of the Court.
1 cannot agree, however, with most of the rest of the Judgment, and in
particular not with its central finding that
"the notification, on 19 May 1992, of the termination of the Treaty
of 16 September 1977 and related instruments by Hungary did
not have the legal effect of terminating them" (conclusion 1 D ,
para. 155).
1 a m of the view that Hungary has validly terminated that Treaty by its
notification of termination of 19 May 1992, with effect from 25 May
1992, or - alternatively
- as from 23 October 1992, Le., the date of the
actual damming. Accordingly, 1 regard the consequences, which the
majority of the Court draws in the five conclusions in part 2 of para-
graph 155 as legally flawed, inasmuch as they are based on the concept of
205 GABc~KOVO-NAGYMAROS
PROJECT (DISS.
OP. FLEISCHHAUER)
the continuing validity of the 1977 Treaty. 1 have therefore voted against
four of them (i.e., conclusions 2 A, 2 B, 2 C and 2 E); my vote in favour of
conclusion 2 D has to be seen in the light of my considerations on the
legal consequences of the Judgment set forth in Part II below.
My reasoning is as follows.
. . . . . . . . . . . . . . . . . . . . . . . . . . . . .
The Czechoslovak Party is willing to take into consideration the
conclusions of the work done by such a committee of experts in any
further procedures regarding the GabCikovo-Nagymaros Barrage
System. It is also known that the Government of the CSFR is willing
to suspend the provisional solution on its own sovereign territory
insofar as the Government of the Republic of Hungary is able to
find an opportunity to enter into a joint solution." (Ibid., Ann. 72,
p. 132.)
In the light of these circumstances, when the construction work for Vari-
ant C got under way, on both sides the point of no return was passed.
There was a continuum and the Czechoslovak action of November 1991
and its action undertaken in October 1992 share the same legal defi-
ciency. The putting into operation of Variant C was an internationally
wrongful act extended over time between November 1991 and October
1992.
Since 1 am thus - contrary to the opinion expressed in the Court's
Judgment - of the view that Czechoslovakia was not entitled to proceed,
in November 1991, to Variant C, 1 am also in disagreement with the con-
clusion in paragraph 1 B of the dispositifof the Judgment: "that Czecho-
slovakia was entitled to proceed, in November 1991, to the 'provisional
solution"' (para. 155). Nor can 1 agree with paragraph 1 D of the dis-
positif':
"that the notification, on 19 May 1992, of the termination of the
Treaty of 16 September 1977 and related instruments by Hungary
did not have the legal effect of terminating them" (ihid.)
in so far as it is based on the allegedly premature giving of the notifica-
tion of termination by Hungary (para. 108).
2. 1 ivould disagrec ivith the conclusion draivti hy the tnujority based on
the point in time ut which Hungarjl made its notification of'termination
even i f / shured - quod non - the vieiv thut Czecl~oslovukiavioluted thc
1977 Treuty only in October 1992. What that view means is that the noti-
fication of termination was not warranted in May, as no breach of the
Treaty had yet occurred (para. 108), but that when the damming of the
Danube happened, in October, the event occurred too late as far as the
Hungarian notification is concerned. This view amounts, in its practical
consequence, to a n extraordinary formalism: a unilateral legal act, the
notification, is discounted because a certain event, although expected and
foreseen, had not yet happened. The event happens, nothing else changes,
but still legal effects of the earlier act are said not to arise as it had been
premature. This approach to a matter of international law does not
correspond to the requirements of good faith. As the Court has said:
1 d o not want to put into doubt this general rule; however, 1 d o not
think that the principle applies in the circumstances of the present case.
My objection to the Judgment in this respect is twofold: firstly, the
Court overlooks that recourse to Variant C was neither automatic nor
the only possible reaction of Czechoslovakia to Hungary's violations of
the 1977 Treaty. Czechoslovakia would have been entitled to terminate
the Treaty. If it did not want to d o this, it could, for example, have pro-
vided unilaterally for participation of Hungary in the realization of Vari-
ant C, possibly in combination with a third party dispute settlement
clause. Secondly, the Court, in basing its negation of a right of Hungary
to terminate the 1977 Treaty in response to the realization by Czechoslo-
vakia of Variant C, on the fact that Hungary itself had violated the
Treaty first, does not take account of its own conclusion that
In these circumstances the fact that Hungary, in May 1992, gave only six
days' notice cannot be regarded as contravening the requirements of
good faith in the application of international law.
These are the reasons which lead me to the conclusion that Hungary
has validly terminated the 1977 Treaty as from 25 May 1992 or - alter-
natively - as from 23 October 1992.
II. T H ELEGALCONSEQUENCES
OF THE JUDGMENT
The fifth starting point for the determination of the legal consequences of
the Court's Judgment must be the fact that as a consequence of the Judg-
ment the flow of water in the old bed of the Danube will be increased
again. lrrespective of whether and to what extent navigation will use the
old Danube again, there will be a discernible principal channel. There
will therefore be no necessity for new or additional boundary arrange-
ments. However, Slovakia, as a riparian State of the Danube and a party
to the 1948 Danube Convention, will be under the legal obligation to
make binding arrangements with the other States parties t o the Danube
Convention in order to secure for their navigation through the bypass
canal, the Gabtikovo locks and the Cunovo reservoir, conditions corre-
sponding to those provided for in the Danube Convention. On the same
line, Slovakia will also be under a legal obligation to provide for the
application, in the bypass canal and in the reservoir, of the provisions
concerning fisheries of the 1956 Treaty concerning the Régime of State
Boundaries as well as of the 1958 Convention concerning Fishing in the
Waters of the Danube.
1 regret that 1 cannot associate myself with those parts of the Judgment
according to which Czechoslovakia was not entitled to put the so-called
Variant C ("provisional solution") into operation from October 1992
(Judgment, para. 1.55, point 1 C ) and :
Slovakia takes the view that Variant C was a lawful, temporary and
reversible solution necessitated by the action of its partner and prefers to
defend its decision on the basis of the doctrine of "approximate applica-
tion". However, a subjective view or belief of Slovakia cannot preclude
the Court from taking a different view on the matter. The Court is bound
by the questions put to it by the Parties in the Special Agreement, but not
by the arguments they advanced in their pleadings.
Thus, to require that Variant C should have been the only means avail-
able in the circumstances to Czechoslovakia would amount to applying
to countermeasures the criterion which the ILC considers to be indispen-
sable for the invocation of "the state of necessity", but does not specifi-
cally mention in the text of the Articles dealing with countermeasures.
But even assuming this criterion should be applied to countermeasures
as well, what other possible legal means allegedly open to Czechoslovakia
could there be apart from countermeasures? Since the Court has found
that Czechoslovakia was not entitled to put Variant C into operation, it
should in al1 fairness have clearly indicated some other legal option o r
options whereby Czechoslovakia could effectively have asserted its rights
under the Treaty and induced its partner t o return to the performance of
its obligations. In my analysis of the case, 1 have been unable to find any
such effective alternative option available for Czechoslovakia in 1991 o r
1992.
221 GABC~KOVO-NAGYMAROS
PROJECT (DISS.OP. VERESHCHETIN)
Would it be any more legally correct or, for that matter, realistic to
insist that Czechoslovakia should have come to the Court before putting
Variant C into operation in October 1992? Apart from the fact that
Czechoslovakia was not legally bound to d o so, it should be recalled that
more than four years elapsed between the filing of the Application in the
present case and the commencement of the hearings. One can easily
imagine the amount of economic and environmental damage as well as
the damage relating t o international navigation that could have been
caused by such a delay.
What should be borne in mind, however, is the fact that Czechoslova-
kia respected the obligation to negotiate prior to taking countermeasures.
The time between the first suspension of works by Hungary in May 1989
and the proceeding to Variant C in November 1991 and subsequently
putting this system into operation in October 1992 was replete with fruit-
less negotiations at different levels aimed a t finding a resolution of the
dispute (see paragraphs 61-64 of the Judgment). The history of these
negotiations clearly shows that, at least from the end of 1990, the sole
purpose of these negotiations for Hungary was the termination of the
Treaty and the conclusion of a new agreement dealing only with the con-
sequences of this termination, while for Czechoslovakia the purpose of
negotiations was the continuation and completion of the Joint Project in
some agreed form within the Treaty framework. Hungary's gradua1 with-
drawal from the Joint Project in defiance of the 1977 Treaty led to the
putting into operation of Variant C.
The basic conditions for the lawfulness of a countermeasure are (1) the
presence of a prior illicit act, committed by the State a t which the
countermeasure is targeted; (2) the necessity of the countermeasure;
and (3) its proportionality in the circumstances of the case. Certain
kinds of acts are entirely prohibited as countermeasures, but they are not
relevant to the present case (these acts being the threat or use of force,
extreme economic or political coercion, infringement of the inviolability
of diplomatie agents, derogations from basic human rights or norms
of j u s cogens).
1 believe al1 the above-mentioned conditions were met when Czecho-
slovakia put Variant C into operation in October 1992. As to the first
condition, it has been satisfied by the Court's findings that Hungary was
not entitled to suspend and subsequently abandon the works relating to
the Project or to terminate the Treaty (Judgment, para. 155, points 1 A
and D). The unilateral suspension of the works by Hungary at Nagy-
maros and at Dunakiliti (initial breaches of the 1977 Treaty by way of
non-performance) and later the abandonment of the work on the Project
occurred before November 1991 - the date when, according to the Spe-
cial Agreement, Czechoslovakia proceeded to the "provisional solution".
The illicit termination of the Treaty by Hungary (19 May 1992) preceded
the date when Czechoslovakia put Variant C into operation (October
1992 according to the Special Agreement).
Countermeasures may be seen as "necessary" only if they are aimed at
bringing about the compliance of the wrongdoing State with its obliga-
tions and must be suspended once the illicit act has ceased. This require-
ment therefore presupposes that countermeasures are reversible by nature.
In the course of the pleadings Slovakia stated and repeated over and
over again that Variant C was conceived as a provisional and reversible
solution, as an attempt to induce Hungary to re-establish the situation
which existed before its wrongful act. Significantly, the Working Group
of Independent Experts of the Commission of the European Communi-
ties, in its report of 23 November 1992, did not deny the technical feasi-
bility of the return to the Treaty Project :
This statement confirms that, at least a t the time of the damming of the
Danube, Variant C was a reversible measure and a return to some agreed
joint scheme of the Treaty Project was possible.
reversibility of Variant C.
The existence of such intentions at the governmental level and the
readiness to realize them would hardly be compatible with Czechoslo-
vakia's conduct after the suspension of works under the Treaty by Hun-
gary. The Government of Czechoslovakia did not seize upon the oppor-
tunity which had emerged to terminate the 1977 Treaty and to complete
the Project unilaterally, but instead tried to persuade its Hungarian
counterpart to return to the performance of its treaty obligations. At the
same time, the Government of Czechoslovakia expressed its willingness to
meet many of Hungary's environmental concerns, proposing in October
1989 negotiations on agreements relating to technological, operational
and ecological guarantees as well as to the limitation o r exclusion of the
peak mode operation of the GabCikovo-Nagymaros Barrage System. In
any event, the veracity and fairness of the public commitments of Czecho-
slovakia and Slovakia to return to the Joint Project may not be refuted
on the basis of inere conjectures, but could be tested only by the response
of Czechoslovakia and Slovakia to the positive actions by Hungary.
It remains for us to examine one more basic condition for the lawful-
ness of a countermeasure, namely its proportionality in the circumstances
of the case. It is widely recognized, in both doctrine and jurisprudence
that the test of proportionality is very important in the régime of counter-
measures and at the same time it is very uncertain and therefore complex.
T o begin with, according to the ILC:
"there is no uniformity . . . in the practice or the doctrine as to the
formulation of the principle, the strictness or flexibility of the prin-
ciple and the criteria on the basis of which proportionality should be
assessed" (United Nations, Officiul Records of the Generul Assem-
hly, Fiftieth Session, Supplement No. 10 (Ai50110), p. 146).
The ILC also observes that "reference to equivalence o r proportional-
ity in the narrow sense . . . is unusual in State practice" (ibid,p. 147).
That is why in the literature and arbitral awards it is suggested that the
lawfulness of countermeasures must be assessed by the application of
such negative criteria as "not [being] manifestly disproportionate", o r
"clearly disproportionate", 'pus hors de toute proportion"', "not out of
proportion", etc. The latter expression ("not out of proportion") was
employed by the ILC in its most recent draft on State Responsibility. The
text of the corresponding Article reads:
The task is not an easy one and may be achieved only by way of
approximation, which means with a certain degree of subjectivity. Weigh-
ing the gravity of the prior breach and its effects on the one hand, and the
gravity of the countermeasure and its effects on the other, the Court
should, wherever possible, have attempted in the first place to compare
like with like and should have done so with due regard to al1 the attend-
ant circumstances against the background of the relevant causes and con-
sequences. Following this approach, the Court should have assessed by
approximation and compared separately:
( 1 ) the economic and financial effects of the breach as against the eco-
nomic and financial effects of the countermeasure;
(2) the environmental effects of the breach as against the environmental
effects of the countermeasure; and
(3) the effects of the breach on the exercise of the right to use commonly
shared water resources as against the effects of the countermeasure
on the exercise of this right.
All these assessments and comparisons should have specifically been
confined to the span of time defined by the question put to the Court by
the Parties, namely November 1991 to October 1992. It should not be
forgotten that the very idea and purpose of a countermeasure is to induce
the wrongdoing State to resume performance of its obligations. The
sooner it does so the less damage it will sustain as a result of the
countermeasure.
On the first point of comparison, according to Slovakia "by May 1989,
a total of US$2.3 billion (CSK 13.8 billion) had been spent by Czecho-
slovakia on the GIN Project" (Memorial of Slovakia, para. 5.01). These
figures, which naturally d o not include the loss of energy production and
the cost of the protection, maintenance and eventual removal of the exist-
ing structures, give the idea of the economic and financial losses which
would inevitably have been sustained by Czechoslovakia in the event of a
complete abandonment of the Project.
For its part, Hungary did not, either in its written pleadings or in its
oral arguments, give any concrete figures evincing in monetary terms the
amount of actual material damage sustained as a result of Czechoslova-
kia's resort to Variant C . Hungary claimed its entitlement to the payment
by Slovakia of unspecified sums in compensation for possible future
damage, or potential risk of damage, which might be occasioned by
Variant C. Although it is true that "[n]atural resources have value that is
not readily measured by traditional means" (Reply of Hungary, Vol. 1,
para. 3.170), uncertain long-term economic losses, let alone the mere
potential risk of such losses, may not be seen as commensurable with the
real and imminent threat of having to write off an investment of such
magnitude.
For the reasons stated above, 1 could not vote for paragraph 155,
point 1 C, of the Judgment. Nor could 1 support paragraph 155,
point 2 D, in so far as it does not, regrettably, differentiate between the
obligation of the State which had committed a prior illicit act and that of
the State which responded by way of a countermeasure. It goes without
saying that my negative vote on paragraph 155, point 2 D , as a whole
must not be understood as a vote against the first part of this paragraph.
1. Although 1 have voted for the operative part of the Judgment, with
the exception of paragraph 1, point C, my favourable vote does not mean
that 1 share each and every part of the reasoning followed by the majority
of the Court in reaching its conclusions.
12. Hungary has pointed out that those are not the only differences
between Variant C and the 1977 Treaty Project, because Variant C is not
operated jointly and because Hungary was never informed, even less con-
sulted, by Czechoslovakia as to its specifications and al1 other technical
details, before and during its construction and putting into operation.
because of the right of Czechoslovakia to put into effect the 1977 Treaty
as best it could, when Hungary violated its treaty obligations.
1. While agreeing with the Court in al1 its other holdings, 1 am unable
to concur in the broad finding that Czechoslovakia was not entitled to
put Variant C into operation from October 1992 (Judgment, para. 155,
point 1 C). The finding is too general. In my view the Court should have
distinguished between, on the one hand, Czechoslovakia's right to take
steps to execute and operate certain works on its territory and, on the
other, its responsibility towards Hungary resulting from the diversion of
most of the waters of the Danube into Czechoslovak territory, especially
in the period preceding the conclusion of the 1995 Agreement (Judgment,
para. 25).
3. This difference in the stance and the actions of the two Parties with
regard to the Treaty should not be blurred. T o simply Say that, in fact,
the two contracting States (and not only one of them, Le., Hungary) con-
formed to rules other than those laid down by the Treaty does not cor-
233 GAB~IKOVO-NAGYMAROSPROJECT (DISS.OP. SKUBISZEWSKI)
action based on general law does not derogate from the binding force of
the Treaty. The shift ont0 the plane of general law results from the Hun-
garian rejection of the Project. There was, actually, n o "single and indi-
visible operational system of works" (Art. 1, para. 1, of the 1977 Treaty)
in which first Czechoslovakia and subsequently Slovakia could partici-
pate. The conduct of Hungary led t o a factual situation which, as long as
it lasted, prevented the implementation of binding agreements. A full
application of the Treaty required bilateral action. Thus, for the time
being, the treaty relationship of the two States found itself in a state of
abeyance o r inactivity. As the objectives of the Treaty did not disappear,
a temporary solution would be based on general law and equity, until
there was a return to the bilateral enforcement of the Treatv. That is the
essence of the concept of the Czechoslovak "provisional solution", main-
tained bv Slovakia.
8. In the present case one should draw a distinction between, on the
one hand, the "provisional solution" which, as a whole, is lawful, espe-
cially under the existing circumstances (i.e., the advanced stage of com-
pletion of the works on Czechoslovak territory at the beginning of the
1990s), and, on the other, one element of the implementation of that
solution that calls for redress and remedy; that element is the sharing of
the waters of the Danube. It is not enough to dismiss the Slovak argu-
ments (that is, the principle of approximate application; the duty to miti-
gate damages; and, as a possibility, the plea of countermeasures, Judg-
ment, paras. 75-87). The situation is more complex. A legal evaluation of
Variant C cannot be limited to the Treaty alone. As a result of Hungar-
ian action, the implementation of the Treaty became paralysed. Czecho-
slovakia responded by putting into effect its "provisional solution". In
the proceedings before the Court Slovakia's emphasis was on what
1 would term as the Treaty approach. But Slovakia has also referred,
though in a somewhat subsidiary mannes, to general law. Under that
law, as applied by the Court, Slovakia bears responsibility for withhold-
ing from Hungary that part of the Danube's waters to which the latter
was entitled. By saying that Hungary did not forfeit "its basic right to an
equitable and reasonable sharing of the resources of an international
watercourse" the Court applies general law (Judgment, para. 78). The
Court likewise applies general law (cf. para. 85) when, in particular, it
refers to the concept of the "community of interest in a navigable river",
as explained by the Permanent Court in the case relating to the Tervito-
235 GABCKKOVO-NAGYMAROSPROJECT (DISS.OP. SKUBISZEWSKI)
9. The Award in the case of Lake Lanoux between Spain and France
states the law which is relevant to the evaluation of Variant C, though for
various reasons that case must be distinguished from the case before the
Court. In the Lake Lanoux case, the Arbitral Tribunal considered the
question whether the French development scheme for Lake Lanoux
(involving the diversion of waters) required, for its execution, a prior
agreement between the two Governments, in the absence of which the
country proposing the scheme would not have freedom of action to
undertake the works (Reports of International Arbitral Awurds ( R I A A ) ,
Vol. X I I , p. 306, para. 10; Internutional Law Reports ( I L R ) , Vol. 24,
1957, p. 127, para. 10).
10. The Tribunal said:
11. In the Luke Lunoux case the Tribunal expressed its position on the
right of each riparian State to act unilaterally in the following terms:
III
16. In paragraph 72 of its Judgment the Court makes clear that it is
aware of the serious problems with which Czechoslovakia was con-
fronted as a result of Hungary's action. That is another reason for dis-
tinguishing between various elements of Variant C. Having said what it
did the Court should have made a step further and applied equity as part
of international law. It would then have arrived at a holding that would
have given more nuance to its decision.
17. In the case relating to the Diversion of Water from the Meuse
Judge Hudson observed :
"It would seem to be an important principle of equity that where
two parties have assumed a n identical or a reciprocal obligation, one
party which is engaged in a continuing non-performance of that
obligation should not be permitted to take advalitage of a similar
non-performance of that obligation by the other party.
. . . . . . . . . . . . . . . . . . . . . . . . . . . . .
The general principle is one of which an international tribunal
should make a very sparing application. It is certainly not to be
thought that a complete fulfilment of al1 its obligations under a
treaty must be proved as a condition precedent to a State's appear-
ing before an international tribunal to seek an interpretation of that
treaty. Yet, in a proper case, and with scrupulous regard for the limi-
tations which are necessary, a tribunal bound by international law
ought not to shrink from applying a principle of such obvious fair-
ness." (P.C.I. J., Serics A/B, No. 70, Judgment, 1937, p. 77.)
18. The foregoing quotation does not mean that one may close one's
eyes to the differences between the Diversion of Water from the Meuse
case and the present case. According to Judge Hudson the two locks (Le.,
the one operated by the Netherlands and the one operated by Belgium)
were in law and in fact in the same position. "This seems to cal1 for an
application of the principle of equity stated above" (P.C.I.J., Series A/B,
No. 70, Judgment, 1937, p. 78). But the more complex facts in the present
case d o not by themselves eliminate the relevance of the learned judge's
opinion.
19. The impossible situation in which Hungarian action put Czecho-
slovakia speaks strongly in favour of the application of equitable prin-
ciples by the Court in evaluating Variant C. For "[elquity as a legal con-
cept is a direct emanation of the idea ofjustice. . . . [Tlhe legal concept of
equity is a general principle directly applicable as law" (Continental S h e y
( Tunisia/Lihyun Arah Jarnuhiriyu), Judgtncnt, I. C.J. Reports 1982,
p. 60, para. 71). The Court's "decisions must by definition be just, and
therefore in that sense equitable" (North Secl Continental Shelf; Judg-
ment, I. C.J. Reports 1969, pp. 48-49, para. 88). "[Aln equitable solution
derive[s] from the applicable law" (Fisherics Juri.sdiction, Mrrits, Judg-
ment, I.C.J. Reports 1974, p. 33, para. 78; p. 202, para. 69). Both "the
result to be achieved and the means to be applied to reach the result"
must be equitable. "It is, however, the result which is predominant; the
principles are subordinate to the goal" (Contzrzental Shelf (Tunisia/
Libyan Arab Jamahiriya), Judgment, I.C.J. Reports 1982, p. 59,
para. 70).
20. In its resolution of 1961 on the utilization of non-maritime inter-
national waters the Institute of International Law has stated (Art. 3):
"If the States are in disagreement over the scope of their rights of
utilization [of the said waters], settlement will take place on the basis
of equity, taking particular account of their respective needs, as well
as of other pertinent circurnstances." (Annuaire de l'Institut de droit
international, 1961, Vol. I I , p. 382.)
21. The degree t o which Czechoslovakia has implemented the Treaty
has reached such proportions that it would be both unreasonable and
harmful to stop the completion of certain works and to postpone indefi-
nitely the operation of the bypass canal, the GabCikovo hydroelectric
power plant, navigation locks -and appurtenances thereto, in so far as
that operation was possible without Hungarian CO-operationor partici-
pation. T o find, as the Court does, that such operation is unlawful over-
looks the considerations of equity. At the same time Hungary's right
under general international law to an equitable and reasonable sharing
of the waters of the Danube had to be preserved notwithstanding its
repudiation of the Project and the Treaty.
22. A State that concluded a treaty with another State providing for
the execution of a project like GabCikovo-Nagymaros cannot, when that
project is near completion, simply Say that al1 should be cancelled and the
240 GABcIKOVO-NAGYMAROS PROJECT (DISS.OP. SKUBISZEWSKI)
23. Thus, pecuniary compensation could not, in the present case, wipe out
even some, not to speak of all, of the consequences of the abandonment
of the Project by Hungary. How could an indemnity compensate for the
absence of flood protection, improvement of navigation and production
of electricity? The attainment of these objectives of the 1977 Treaty was
legitimate not only under the Treaty but also under general law and
equity. The benefits could in no way be replaced and compensated by the
payment of a sum of money. Certain works had to be established and it
was vital that they be made operational. For the question here is not one
of damages for loss sustained, but the creation of a new system of use and
utilization of the water.