PS Lab Manual2019
PS Lab Manual2019
MANUAL
FOR
POWER SYSTEMS LABORATORY
(B.TECH)
Third Edition
1
DEPARTMENT OF ELECTRICAL ENGINEERING
Dr. T. Rajeev
Prof. V. Vinod Dr. P. Sreejaya
Head of the Department
Prof. M.S. Jayasree
2
DEPARTMENT OF ELECTRICAL ENGINEERING
COLLEGE OF ENGINEERING TRIVANDRUM,
Thiruvananthapuram – 695017
VISION:
Be a centre of excellence and higher learning in electrical engineering and allied areas.
MISSION:
To mould ethically sound and socially responsible Electrical Engineers with leadership
qualities.
To inculcate research attitude among students and encourage them to pursue higher
studies.
3
Program Educational Objectives (PEOs)
Graduates will
Program outcomes
PO1 Apply the knowledge of mathematics, science and engineering fundamentals and
an engineering specialization to the solution of complex engineering problems.
PO2 Identify, formulate, review research literature and analyse complex engineering
problems reaching substantiated conclusions using first principles of mathematics,
natural sciences and engineering sciences
PO3 Design solutions for complex engineering problems and design system components
or processes that meet the specific needs with appropriate consideration for the
public health and safety, and the cultural, societal and environmental considerations
PO4 Use research based knowledge and research methods including design of
experiments, analysis and interpretation of data, and synthesis of the information to
provide valid conclusions.
PO5 Create, select and apply appropriate techniques, resources and modern engineering
and IT tools including predictions and modelling to complex engineering activities
with an understanding of the limitations.
PO6 Apply reasoning informed by the contextual knowledge to assess social, health,
safety, legal and cultural issues and the consequent responsibilities relevant to the
professional engineering practice.
PO7 Understand the impact of the professional engineering solutions in societal and
environmental contexts, and demonstrate the knowledge of and need for sustainable
development.
PO8 Apply ethical principles and commit to professional ethics and responsibilities and
norms of the engineering practice.
PO9 Function effectively as an individual and as a member or leader in diverse teams
and in multidisciplinary settings.
PO10 Communicate effectively on complex engineering activities with the engineering
community and with society at large, such as, being able to comprehend and write
effective reports and design documentation, make effective presentation and give
and receive clear instructions.
PO11 Demonstrate knowledge and understanding of the engineering and management
principles and apply these to one’s work, as a member and leader in a team to
manage projects and multidisciplinary environments.
PO12 Recognize the need for and have the preparation and ability to engage in
independent and life-long learning in the broadest context of technological change.
4
TABLE OF CONTENTS
INTRODUCTION TO HIGH VOLTAGE TESTING…………………………….………… 6
SAFETY REGULATIONS FOR HIGH VOLTAGE EXPERIMENTS……………………. 8
5
INTRODUCTION TO HIGH VOLTAGE TESTING
With a large number of high voltage and extra high voltage transmission systems
being constructing in our country, expensive electrical equipment are being put in
service. It is necessary to ensure that such equipment’s are capable of withstanding
the over-voltages normally encountered in service. The over-voltages may be either
due to natural causes like lightning or system originated ones such as switching
power frequency transient voltages. The over-voltage tests are classified into two
groups:
i) Power frequency voltage tests and
ii) Impulse voltage tests.
Definitions:
In test codes and standard specifications, certain technical terms are used to
specify and define conditions or procedures.
It is the voltage at which the electric field stress in the insulation causes a
failure resulting in a collapse of voltage and passage of current.
Withstand Voltage
This is the voltage which has a probability of 50% flash over, when applied
to a test object. This is normally applied in impulse tests in which the loss
of insulation strength is temporary.
6
100% Flash over Voltage
The voltage that causes flash over at each of its applications under specified
conditions when applied test objects is specified as 100% flash over voltage.
Creepage Distance
1) AC test voltages
2) Impulse Voltages
Impulse voltages are characterized by polarity, peak value, time to front ( t r ) and
time to half the peak value after the peak (tt) - The time to front is defined as. 1.67
times the time between 30% and 90% of the peak value in the rising portion of the
wave. According to IS: 2071 (1973), a standard impulse is defined as one with tr =
1.2 µs,
tt = 50 µs (called 1 /50 µs wave)
Temperature: 27oC
Since it is not always possible to do test under these reference conditions, correction
factors have to be applied
7
SAFETY REGULATIONS FOR HIGH VOLTAGE
EXPERIMENTS
Experiments with high voltages could become particularly hazardous for the
participants. So adequate safety precautions should be taken. Here any voltage
greater than 250V against earth is understood to be a high voltage.
Everyone must convince himself by personal observation that all the conductors
which can assume high potential and lie in the contact zone are earthed and that the
main leads are interrupted.
Earthing:
Fixing the earthing leads on to the parts to be earthed should be done with the aid of
insulating rods. Earthing may only follow after switching the current source off, and
may be removed only when there is no longer anyone present within the fence. All
metallic parts of the setup which do not carry potential during normal service must
be earthed reliably and with an adequate cross section of at least 1.5mm2 copper.
All components of the setup must be either rigidly fixed or suspended so that they
cannot topple during operation or be pulled down by the leads. A test set up may be
pulled into operation only after the circuit has been checked and permission to begin
work given by an authorized person.
8
Even during accidents with no unconsciousness, it is recommended that the
victim lie quietly and a doctor's advice be sought.
Every one carrying out experiments in the laboratory is personally responsible for the setup
placed at his disposal and for the experiments performed with it. For experiments during
working hours one should try, in the interest of personal safety, to make sure that a second
person is present in the testing room. If several persons are working with the same setup,
they must know who is to perform the switching operations for a particular experiment.
Before switching high voltage setups on, warning (“Attention! Switch on”) should be
given either by short term signals or by the call.
9
INTRODUCTION TO SIMULATION SOFTWARES
ETAP
ETAP is the most comprehensive solution for the design, simulation, and analysis of
generation, transmission, distribution, and industrial power-systems. It provides all
necessary tools and support for modeling and analyzing an electrical power system.
In this each project provides a set of users, user access controls, and a separate
database in which its elements and connectivity data is stored.
ETAP can utilize real-time operating data for advanced monitoring, real-time
simulation and optimization, and high speed intelligent load shedding. ETAP allows
you to work directly with graphical one-line diagrams, underground cable raceway
systems. Three dimensional cable systems, advanced time current coordination and
selectivity plots, geographic information system schematics (GIS), as well as three
dimensional ground grid systems. It incorporates new concepts for determining
protective device coordination directly from the online diagram
ETAP combines the electrical, logical, mechanical and physical attributes of system
elements in the same data base. ETAP keeps track of detailed data for each electrical
apparatus. ETAP one-line diagram supports a number of features to assist you in
constructing networks of various complexities; it also provides you with a variety of
options for presenting or viewing your electrical system
Among ETAP's most powerful features are the composite network and motor
elements. ETAP also contain built-in-libraries that are accessible from project files.
New libraries can be created of existing can be modified to include custom
manufacturer data
ETAP to be the fore-most integrated database for electrical systems allowing for
multiple presentations of a system for different analysis or design purposes
10
MATLAB
The name MATLAB stands for MATrix LABoratory. MATLAB was written
originally to provide easy access to matrix software developed by the LINPACK
(linear system package) and EISPACK (Eigen system package) projects. MATLAB
[1] is a high-performance language for technical computing. It integrates
computation, visualization, and programming environment. Furthermore, MATLAB
is a modern programming language environment: it has sophisticated data structures,
contains built-in editing and debugging tools, and supports object-oriented
programming. These factors make MATLAB an excellent tool for teaching and
research. MATLAB has many advantages compared to conventional computer
languages (e.g., C, FORTRAN) for solving technical problems. MATLAB is an
interactive system whose basic data element is an array that does not require
dimensioning. The software package has been commercially available since 1984
and is now considered as a standard tool at most universities and industries
worldwide. It has powerful built-in routines that enable a very wide variety of
computations. It also has easy to use graphics commands that make the visualization
of results immediately available. Specific applications are collected in packages
referred to as toolbox. There are toolboxes for signal processing, symbolic
computation, control theory, simulation, optimization, and several other fields of
applied science and engineering.
The order in which MATLAB performs arithmetic operations is exactly that taught
in high school algebra courses. Exponentiations are done first, followed by
multiplications and divisions, and finally by additions and subtractions. However, the
standard order of precedence of arithmetic operations can be changed by inserting
parentheses. For example, the result of 1+2×3 is quite different than the similar
expression with parentheses (1+2)×3. The results are 7 and 9 respectively.
Parentheses can always be used to overrule priority, and their use is recommended in
some complex expressions to avoid ambiguity. MATLAB by default displays only 4
decimals in the result of the calculations, for example −163.6667, as shown in above
examples. However, MATLAB does numerical calculations in double precision,
which is 15 digits. The command format controls how the results of computations are
displayed.
11
To view the online documentation, select MATLAB Help from Help menu or
MATLAB Help directly in the Command Window. The preferred method is to use
the Help Browser. The Help Browser can be started by selecting the ? Icon from the
desktop toolbar.
Features:
M-File Scripts:
A script file is an external file that contains a sequence of MATLAB statements.
Script files have a filename extension .m and are often called M-files. M-files can be
12
scripts that simply execute a series of MATLAB statements, or they can be functions
that can accept arguments and can produce one or more outputs.
M-File functions:
As mentioned earlier, functions are programs (or routines) that accept input
arguments and return output arguments. Each M-file function (or function or M-file
for short) has its own area of workspace, separated from the MATLAB base
workspace.
SIMULINK
SIMULINK is an interactive environment for modeling, analyzing and simulating a
wide variety of dynamic systems. SIMULINK provides a graphical user interface for
constructing block diagram models using drag and drop operations. A system is
configured in terms of block diagram representation using library of standard
components. A system in block diagram representation is built easily and simulation
results are displayed quickly.
13
Experiment no. 1
FORMATION OF Y BUS
Aim:
To formulate a Y-Bus using an appropriate algorithm for at least a Four Bus system.
Theory:
Most of the power system studies require the formation of bus admittance matrix. Y
bus may be formed by inspection method only, if there is no mutual coupling
between the lines. Shunt impedances are added to the diagonal elements
corresponding to the buses at which these are connected.
14
Y(p,p)=Y(p,p)+Yline(k)+Ycp(k)
Y(q,q)=Y(q,q)+Yline(k)+Ycq(k)
Y(p,q)=Y(p,q) - Yline(k)
Y(q,p)=Y(q,p) – Yline(k)
6. For i=1 to n
Y(i,i)= Y(i,i)+Yshunt(i)
7. Print Y(i,j) for i=1 to n, j= 1 to n
Procedure:
Enter the command window of the MATLAB.
Create a new M- file by selecting File New M- file.
Type and save the program in the editor window.
Execute the program by clicking on Tool Run.
View the results.
Sample data:
busdata= [ 0 1 0 1.0
0 2 0 0.8
1 2 0 0.4
1 3 0 0.2
2 3 0 0.2
3 4 0 0.08 ];
Y=ybus(busdata)
Problem 1:
Form the Y Bus matrix for the given network
15
Fig 2.1 Single Line Diagram
Result:
Inference:
16
Experiment no. 2
Aim:
To conduct load flow analysis of power system networks on any dedicated software platform
using the following methods and to verify by manual calculation at least for one iteration.
Gauss-Seidel method
Newton—Raphson Method
Fast Decoupled Method.
Theory:
Power flow programs are used to study power system under both normal operating
conditions and disturbance conditions. The essential requirements for successful
power system operation under normal conditions require the following:
Generators supply the load plus losses
Bus voltage magnitudes remain close to rated values
Generators operate within specified real and reactive power limits
Transmission lines and transformers are not overloaded
Power flow computer program commonly called as load flow is the basic tool for
investigating the above requirements. This program computes the voltage magnitude
and angle at each bus in a power system under balanced steady state condition. Real
and reactive power flows for all equipment interconnecting the buses, as well as
equipment losses are also computed. Both existing power systems and proposed
changes including new generation load growth are of interest.
ETAP
ETAP is Electrical Transient Analyzer Program. It is the most comprehensive
solution for the design, simulation and analysis of generation, transmission,
distribution and industrial power systems. It provides all necessary tools and support
for modeling and analyzing an electrical power system. In this each project provides
a set of users, user account controls and separate database in which its elements and
17
connectivity is stored. ETAP can utilize real time operating data for advanced
monitoring, real time simulation and optimization and high speed intelligent load
shedding. ETAP allows to work directly with graphical one line diagrams
underground cable race way systems.
Procedure:
Refer manual on ETAP .
Problem 1:
The transmission line impedances and line charging admittances in per unit on a 100
MVA base are given in table. The scheduled generation and loads and the assumed
per unit bus voltages are given. With bus 1 as the slack, use the following methods to
obtain a load flow solution.
Gauss-Seidel using YBUS, with acceleration factors of 1.4 and tolerances of
0.0001 and 0.0001 per unit for the real and imaginary components of voltage.
Newton-Raphson using YBUS, with tolerances of 0.0001 per unit for the
changes in the real and reactive bus powers.
Fast Decoupled.
Table I
Impedance and line charging
18
Table II
Scheduled generation and load
Bus Assumed Bus Generation Load
code Voltage (p.u.) MW Mvar MW Mvar
1 1.06+j0.0 Slack 0 0
2 1.00+j0.0 40 30 20 10
3 1.00+j0.0 0 - 45 15
4 1.00+j0.0 0 - 40 5
5 1.00+j0.0 0 - 60 10
Result:
Inference:
19
Experiment no. 3
Aim:
To conduct the fault analysis of power system networks on any dedicated software
platform to solve symmetrical and unsymmetrical faults and to verify by manual
calculation.
3 Phase L-G fault
L-L fault
L-L-G fault
Theory:
Short circuit studies are performed to determine the magnitude of currents flowing
throughout the power system at various time intervals after the occurrence of the
fault. The magnitude of the current flowing through the power system after a fault
varies with time until they reach steady state condition. This behavior is due to
system characteristics and dynamics during this time, the protective is called to
detect, interrupt and isolate these faults. The various types of faults occurring in a
system in the order of frequency of occurrence are
Single-line to ground
Line-to-line
Double line-to-ground
Three phase faults.
which can occur when conductors break or when one or two phases of a circuit breaker
inadvertently open.
The path for the fault current may have either zero impedance (dead short circuit) or
impedance.
20
The current which flows in different parts of a power system immediately after,
occurrence of a fault differs from that flowing a few cycles later just before circuit
breakers open the line on both sides of the fault. Both these currents differ widely
from the current which would flow under steady state conditions, if the fault were
not isolated from the rest of system by the operation of the circuit breakers. Two of
the factors upon which the proper selection of the circuit breakers depends are
Fault analysis consists of determining these currents for various type fault at various
location in the system. The short circuit information is used to select fuses breakers
and switchgear ratings in addition to setting protective relays. The short circuit
program computes the steady state current for the impedance considered.
Procedure:
Refer Manual on ETAP.
Problem 1:
Consider the 4-bus system shown in figure. Buses 1 and 2 are generator buses and
3 and 4 are load buses. The generators are rated 11kV, 100 MVA, with transient
reactance of 10% each. Both the transformers are 11/110 kV, 100 MVA with a
leakage reactance of 5%.
The reactance of the lines to a base of 100 MVA, 110 kV, are given. Obtain the short
circuit solution for a three-phase solid fault on bus 4 (load bus). The transformer and
generator details are given in table below:
21
Fig 3.1: Single line diagram
Result:
Inference:
22
Experiment no. 4
STABILITY ANALYSIS
Aim:
To find the critical clearing angle by applying equal area criterion for any
power system network and verify the same using any dedicated software.
Theory:
The transient behavior of a power system resulting from major disturbances such as
fault followed by switching operations, sudden rejection of load or generation, etc., is
referred to as transient stability. A transient stability solution is obtained in time
domain. Transient stability simulation studies are carried out to study these
phenomena and the results enable to plan and coordinate the protection and control
schemes efficiently. Critical clearing times of circuit breakers can be computed and
protection zones of distance relays during transient swings can be adjusted. Proper
restoration/islanding schemes can be suitably designed. Compared to load flow and
short circuit studies, transient stability studies are more complex since they involve
electromechanical dynamics of rotating machines and their associated controls viz.,
excitation and governor systems. The period of investigation varies from fraction of
a second when first swing stability is being determined, to over several seconds when
multiples in stability is to be examined.
The program requires the base case load flow solutions to establish the initial
conditions. The program uses Fast Decoupled Load Flow Method for the network
solution, and implicit trapezoidal rule of integration method for the solution of
differential equation representing the dynamics of machines, controllers, etc.
Procedure:
Refer manual on ETAP.
23
Problem 1:
Figure 4.1 shows a single line diagram of a 5-bus system with three generating units,
four lines and two transformers and two loads. Per-unit transmission line series
impedances and shunt susceptances are given on 100MVA base, generator’s
transient impedance and transformer leakage reactances are given in the
accompanying table.
Transformer details:
Generator details:
G1 = 400 MVA, 20 kV, X’d = 0.067 pu, H = 11.2 MJ / MVA
G2 = 250 MVA, 18 KV, X’d = 0.10 pu, H = 8.0 MJ / MVA
G3 = 1000 MVA, 230 KV, X’d = 0.00001 pu, H = 1000 MJ / MVA (Infinite Bus
Modelling)
24
Table I
Table II
Calculation:
To find the critical clearing time.
𝑷𝒎
𝒄𝒐𝒔 𝜹𝒄 = 𝑷 (𝜹𝒎𝒂𝒙 − 𝜹𝟎 ) + 𝐜𝐨𝐬 𝜹𝒎𝒂𝒙
𝒎𝒂𝒙
𝟐𝑯 (𝜹𝒄 − 𝜹𝟎 )
𝒕𝒄 = √
𝝅𝒇𝟎 𝑷𝒎
where,
H is the Inertia Constant
𝑓0 is the normal frequency
𝑃𝑚𝑎𝑥 is the Maximum power
𝛿𝑐 is the Initial torque angle
25
Swing curve:
Result:
Inference:
26
Experiment No. 5
Aim:
To determine the change in speed, frequency and steady state error corresponding to
a load disturbance in a single area and a two area power system, with and without
supplementary control using software.
Theory:
SIMULINK is an interactive environment for modelling, analyzing and simulating a
wide variety of dynamic systems. SIMULINK provides a graphical user interface for
constructing block diagram models using drag and drop operations. A system is
configured in terms of block diagram representation using library of standard
components. A system in block diagram representation is built easily and simulation
results are displayed quickly.
- ∆𝜔(𝑠)
Fig 5.1: Load frequency control block diagram of an isolated power system
27
Problem 1:
An isolated power system has the following parameters:
Turbine time constant, Tt = 0.5 Sec
Governor time constant, Tg = 0.2 Sec
Generator time constant, H = 5 Sec
Governor Speed regulator, R = R pu.
The load varies by 0.8% for 1% change in frequency, i.e., D=0.8. The governor
speed regulation is set to R= 0.05 pu. The turbine rated output is 250 MW. At normal
frequency of 50 Hz a sudden load change of 50MW (ΔPL= 0.2pu) occurs. Construct
a SIMULINK block 'diagram-and obtain the frequency deviation response for the
condition given above.
Fig 5.2: Two area system with only primary LFC Loop
Problem 2:
A two area system connected by a tie line has the same parameters on a 446 MVA
common base. The units are operating in parallel at normal frequency at 50 Hz. The
28
synchronizing power coefficient is computed from initial operating condition and is
given to be Ps = 2.0 pu. A load change of 187.5 MW occurs in area 2.
a) Determine the new steady state frequency and the change in the line
flow.
b) Construct SIMULINK block diagram and obtain the frequency deviation
response for the give condition
Result:
Inference:
29
Experiment No. 6
Aim:
To test the given power system component (Circuit Breaker/
Insulator/Lightning arrestor/ Air Blast Circuit Breaker) using ac voltage.
To test the given power system component (Circuit Breaker/
Insulator/Lightning arrestor/ Air Blast Circuit Breaker) using impulse
voltage
To test the power system component (Circuit Breaker/ Insulator/Lightning
arrestor/ Air Blast Circuit Breaker) using DC voltage
INSULATORS
b. Impulse Tests
Impulse withstand voltage test
30
made. If the test object has withstood the subsequent applications, it is said to
have passed the test.
The test is done as above with the specified "voltage. Usually, the probability
of failure is determined for 40% and 60% or 20% and 80% failure values,
since it is difficult to adjust the test voltage for the exact 50% flashover
values. The average value of-the upper and the lower limits is taken. The
insulator surface should not be damaged by these tests, but slight marking on
its surface or chipping off of the cement is allowed.
All power frequency tests shall be made with an AC voltage having a frequency
between the limits of 48 Hz and 52 Hz and an approximately sinusoidal shape. The
test piece shall withstand for one minute without flash over, the application of the
dry power frequency specified voltage. Usually a voltage of 1.5 times the rating is
applied for one minute. After that, it is checked whether the negative resistance
property of the arrester is retained by repeating the experiment after few minutes.
31
b. Standard lightning – Voltage impulse spark over test
With the test sample arrester in the circuit, the impulse generator is adjusted to give a
1.2/50𝜇s voltage wave shape with the correct peak value (75KV for 9/11KV
LA)With this adjustment five positive and five negative impulses shall be applied to
the test sample and the series gaps of the arrester shall spark over in every impulse. If
in either of the five impulses, the gap fails to spark over once only, additional
impulses of that polarity shall be applied and the gap shall spark over on all of these
pulses.
Instruments Required
HV Transformer:
Input: 0-220V
Output: 0-100 kV
Current : 75-200mA
Impulse Voltage Generator: 220/280kV
Earthing rod.
Procedure
220/280kV
10 kVA
32
INSULATORS- 11 kV
Withstand tests: Apply 35kV for 1 minute and see whether the test piece is
withstanding the voltage without flash over.
Apply 1.5 times 9kV (i.e., 13.5kV) for one minute, check for no flash over.
AB switches
Power frequency withstand test is to be done for closing and opening of contacts as
follows: For 11 kV; withstand voltage is 35kV between; line and| earth (closing the
contacts) for 1 minute and 45kV between open contacts for 1 minute.
Fuses
For LT fuses, apply 1.5kV withstand voltage to insulation for 1 minute.
Impulse tests:
PIN INSULATOR-11 KV
Connect a sphere gap across the test piece. Apply standard impulse voltage of 75kV
with both positive and negative polarities of the wave. If five consecutive waves do
not cause flashover or puncture, the insulator is deemed to have passed the test (this
is verified by the spark over in the sphere gap). If two applications cause flashover,
the insulator fails the test. If there is only one failure, additional ten applications of
the voltage wave are made. If the test object has withstood the subsequent
applications, it is said to have passed the test.
33
LIGHTNING ARRESTOR- 9KV
With the test sample arrester in the circuit, the impulse generator is adjusted to give
1.2/50𝜇s, 75kV voltage wave, and shape. With this adjustment five positive and five
negative impulses shall be applied to the test sample and the series gaps of the
arrester shall spark over in every impulse (the sphere gap connected across the test
piece should not spark over). If in any of the five impulses, the gap fails to spark
over once only, additional ten impulses of that polarity shall be applied and the gap
shall spark over on all of these pulses.
Result:
Inference:
34
Experiment No. 7
RELAY TESTING
Aim:
To test pick up, drop out and plot the time current characteristics of the relay.
PSM 2 3 4 5 7 10 12 18 20
Operating time in 10 6.3 5 4.4 3.6 3 2.75 2.3 2.2
sec
(TMS=1)
Theory:
In a power system consisting of generators, transformers, transmission and
distribution circuits, it is inevitable that some failure will occur somewhere in the
system. When a failure occurs on any part of the system, it must be quickly detected
and isolated from the system.
35
gear. The relays detect the fault and supply information to the circuit breaker, which
performs the circuit interruption
A Protective Relay is a device that detects the fault and initiates the operation of the
circuit breaker to isolate the defective element from the reset system. The relays
detect the abnormal conditions in the electrical circuits by constantly measuring the
electrical quantities which are different under normal and fault conditions. The
electrical quantities which may change under fault conditions are voltage, current,
frequency and phase angle.
The over current circuit protection can be given directional feature by adding
directional element in the protection system. Directional over-current
protection responds to over-currents for a particular direction.
If power flow is in the opposite direction, the directional over current
protection remains inoperative.
Directional over - current protection comprises of over-current relay and
power directional relay in a single relay casing. The power directional relay
does not measure the power but is arranged to respond to the direction of
power flow.
36
Test Setup for Directional Over-Current Relay
Directional power protection operates in accordance with the direction of power
flow. Reverse power protection operates when the power direction is reversed in
relation to the normal power flow. The construction of Reverse power relay is
different from that of directional over-current relay
In directional over-current relay, the directional current does not measure the
magnitude of power. It senses only direction of power flow. However in Reverse
power Relays, the directional element measures magnitude and direction of power
flow.
Relay-connection, (e.g.: 90°, 60°, 30° etc.) refer to the angle by which the current
applied in the relay is displaced from the voltage applied to the relay. The maximum
torque angle refers to the angle between the current voltages applied to the relay to
produce maximum torque
The choice of relax connection is basically to select the phase across which the
voltage coil is connected with respect to current coil. Number of different
connections can he used. The suitability of each connection should be examined by
considering the limiting conditions of voltage and current limiting fault conditions us
source and line impedances etc
Experimental procedure:
Relay operates when the voltage G1<G2, ie, the current reverses.
37
Instantaneous operation:
Set the voltage of G1 at a constant value. Instantaneous operation is for a current
range of 2.5 A to 20 A. Increase G2 till the current is greater than 2.5 A, then the
instantaneous operation flag of the relay operates.
Directional operation:
Set PSM =1 and TMS=1. Now adjust the voltage G2 to set a current value less than
2A as given in table. Note the time setting and PSM of the relay. Then reset the relay
and apply the current by start and stop switch. Note down the time taken when the
relay trips
Repeat this procedure by changing the values of G2 for different currents. Plot the
characteristics. Change the value of TMS (0.8) with the same PSM and repeat the
above procedure. Plot the characteristics.
Observation:
Table I:
38
TMS V1 (V) V2(V) Trip current (A) Trip Time(s)
1.0
1.2
0.8 1.4
1.6
1.8
2.0
39
Fig 7.2: Sample graph
Result :
Inference:
40
(B) OVER VOLTAGE RELAY
Aim:
To test the pick up, drop out, and plot the time current characteristics of the relay.
Theory:
Principle of operation of over voltage relay is that the relay operates and trips the
circuit when the voltage reaches above the specified value. The type of over voltage
relay employed in our test set up is the electromechanical type over voltage relay.
Relay timing is nothing but the duration from the instant when the actuating element
is energized to the instant when the relay contacts are closed. The over voltage relay
used here is inverse definite minimum time type. An inverse time relay is the one
where, operating time is approximately inversely proportional to the magnitude of
actuating parameter. The actuating parameter here is the voltage. In this relay,
inverse time delay can be introduced when voltage is just equal to normal value. In
this case movement of plunger will be very slow. But when voltage rises to higher
values the plunger moves faster with less time delay and stops when relay contact is
open.
Equipment required:
Procedure:
Set the voltage at any value from 190 to 250V (i.e., 190, 220, 230, 240. 250) using
voltage setting plunger in the left side of the unit. Switch on the trainer's power
ON/OFF switch. To connect the relay to the voltage source, press the start switch.
Then adjust the variac to set the fault voltage in the voltmeter. The fault voltage shall
be greater than the normal voltage. Reset and press the stop watch twice, for
initializing.
41
Press the start switch. Now the fault voltage is applied to the relay coil. At the same
time the clock starts counting the time in seconds taken for the relay coil to trip and
stops when the relay contact is open. Opening of the relay contact can be observed
by the lowering of the flag. Note down the time in seconds required for the relay to
operate, set voltage and fault voltage. Reset the trip flag and repeat the above
procedure for different fault voltages. Note down the readings in the tabular form.
Draw a graph for time versus fault voltage
42
Table I:
-
-
1 - -
-
-
-
2 - -
-
-
Result:
Inference:
43
Experiment No. 8
INSULATION TESTING
Aim:
Reference:
Apparatus required:
Theory:
The dielectric material in a cable is used to insulate the conductors from one
another and from ground as well as to provide mechanical support to the
components. Hence it is desirable that the insulation resistance be as high as
possible, consistent with acceptable mechanical, chemical and heat resistant
properties. During manufacturing, non - uniformities may develop in the dielectric,
affecting the quality of the cable. This test helps in detecting-such imperfections. The
volume resistivity and insulation resistance constants specified for various types of
PVC insulators are as follows
44
Type B: General purpose insulation with maximum conductor temperature of 70°C
intended for cables with rated voltages above 3.3 kV
Type C: Heat resistant insulation for maximum conductor temperature of 85° C and
rated voltages up to and including 1100 V
For carrying out this test at ambient temperature of 27°C ± 2°" C on single core
(armoured/screened) and multicore screened (armoured/unarmoured) cable, no
special conditioning is required except that the temperature of the specimen attains
the temperature of the test room.
45
Procedure:
The test specimen is connected to the insulation resistance measuring
equipment. The conductor is connected to the high voltage terminal and
the screen/armour or the water bath is earthed.
The insulation resistance of the test specimen is measured after
electrification has continued in a regular manner for 1min. The ambient
temperature is recorded when the test is performed at ambient
temperature but at the time of doing the test at elevated temperature, the
temperature of the water bath is recorded. The apparatus shall be checked
by comparing the values with standard resistance before taking every set
of reading.
The volume resistivity or insulation resistant constant is calculated from
the measured insulation resistance value.
Tabulation of Observations:
Sample Nominal Material of Length(m) Temperature(ºC) Observed
No. conductor Dielectric insulation
size resistance(MΩ)
Calculation:
The volume resistivity and insulation resistant constant are calculated from the
observed insulation resistance as indicated below.
Volume resistivity = 2πLR x 108 ohm cm
𝑙𝑜𝑔𝑒 (D/d)
46
Insulation resistance constant K = LR Mega ohm km
1000 𝑙𝑜𝑔10 (D/d)
Where
R = measured resistance (MΩ)
L = length of cable (m)
D = diameter over insulation (excluding screens if any), (mm) and
d = diameter over conductor (including screens if any), (mm)
Result:
Inference:
47
Experiment No. 9
EARTH RESISTANCE
Aim:
To determine the resistance to earth of the given earthing system and design an
earthing system from soil resistivity of the given area.
Reference:
IS-3043
Theory:
Resistance of earth connections are measured by a fall of potential method, as
illustrated by the figure. A current is passed through the electrode E to an auxiliary
electrode A in the earth at a distance away from the plate. A secondary auxiliary
electrode B is inserted between B and A and the potential difference between B and
A is measured for a given current I, so that the resistance of the earth connection is
V/I.
Procedure:
48
Two auxiliary electrodes are driven such that E, P and C are in a line and the distance
EC is 20m. For various values of ‘D’ (distance Ep) at an interval of 2 m.
The megger reading are taken noting the reading when the handle is driven at
maximum possible speed. The reading is plotted as shown. The graph shows a value
R at which the reading remains almost constant, when ‘D is varied. This value gives
the resistance of earth electrode
A four-terminal instrument is used to measure earth resistivity. Four rods are driven
down to the same depth and at equal distances apart in a straight line at a spacing of
‘A’meter as shown. The outer rods are connected to C1 and C2 and middle rods to
P1 and P2. The handle is rotated at maximum possible speed and Megger readings
are taken. Let it be “R” Ohms. The specific resistance is determined from the
formula
ρ= 2 π AR Ωm
49
Fig 9.3 : Specific resistance of earth in the locality determination
Observation
Sl No. R
ρ = 2 π AR Ωm
Result:
Inference:
50
EXPERIMENT NO. 10
Aim:
To measure the dielectric strength of the given sample of Transformer oil.
Reference:
Apparatus:
Theory:
Test for dielectric strength is a conventional test intended to reveal the extent of
physical pollution by water and other suspended matter in insulating oil. This test
gives an indication of the suitability of a sample for its use in the apparatus. The
permissible breakdown voltage for different voltage class of equipment are as
follows.
Any result below the permissible value will necessitate reconditioning of drying and
filtration to reduce the oil for water content and suspended matter.
51
The sample oil is prepared in a test cell made of glass or plastic with an effective
volume of 300 to 500 ml. The test electrodes are either spherical or spherical shaped.
The electrodes are mounted in a horizontal axis and the spacing between them is 2.5
mm. The recommended frequency of testing is as follows:
Procedure:
Agitate and turn over the vessel containing the sample oil several times, to ensure a
homogenous distribution of impurities, without causing formation of air bubbles.
Pour the sample oil in to the test ceil slowly, in order to avoid formation of air
bubbles. The oil temperature at the time of testing is to be the same as the
temperature of the ambient.
The level of oil in the test cell shall be such that the axis of the electrode is at a depth
of 40 mrn; Switch on the supply and increase the voltage at a uniform rate of 2 kV/s,
starting from zero to the value causing breakdown. The circuit will be opened
automatically if an established arc occurs. On the other hand if a transient spark
(audible or visible) occurs, the circuit may be opened manually. The breakdown
voltage is the voltage reached during the test at the time of the first spark, whether it
is transient or established spark. The test is to be carried out within 10 minutes of
first filling. After each breakdown, stir the oil gently between the electrodes by a
clean glass rod. Repeat the test for six times on the sample. Compute the electric
strength as the arithmetic mean of the six values.
52
B) MEASUREMENT OF DIELECTRIC-STRENGTH OF
SOLID INSULATING MATERIALS
Aim:
To measure the dielectric strength of different solid insulating materials using
appropriate methods.
Equipment required:
0-10kV HV. Breakdown Test Set.
Diagram:
53
Procedure:
Result:
Inference:
54
Experiment No. 11
Aim:
To calculate rating of capacitors for power factor correction for a load and verify it
experimentally.
Instruments Required:
Theory:
Power factor of the given R-L load is cos Φ1. In order to improve it to cos Φ2 a
shunt capacitor can be installed at the load end. As the power factor is improved to
cos Φ2 lagging, the in-phase component of current will remain constant as the load
is not changed, only reactive component will change.
55
Transmission line representation:
The ‘G’ shunt conductance is usually ignored because its value relative to other
parameters is significantly small. All these parameters are functions of the line
design i.e. conductor size, type, their bundles , inter-conductor spacing, phase
spacing, height above ground, frequency, temperature ,tower configurations etc.
1. Generating station
a. The line charging voltage Source 0-55-110-330V line-line.
b. Circuit Breaker for over load protection and switching on/off of the system
c. Digital Voltmeter with function indicator switch for sending end voltage
d. Digital Ammeter with function indicator switch for sending end current
measurement, phase value(line-line)
56
2. Transmission Line
3 phase Artificial Transmission line of 180km line length and each pi-section for
every 30 km.
3. Receiving station
a. Voltmeter digital with function indicator switch for measurement of receiving
end voltage line-line value.
b. Ammeter digital with function indicator switch for measurement of receiving
end voltage line-line value.
c. Circuit Breaker for over load protection and switching ON/OFF the load.
d. R-L loading terminals to connect externally the load to the systems.
4. VAR Compensators
a. Shunt Reactor 3 phase star connected 300 volts line-line, variable reactance
Procedure:
Ferranti effect: Switch on the system on no load, some low voltage. (200V L-
L) is applied and note down the rise in voltage at receiving end.
Shunt Reactor Compensation: Voltage rise at receiving end can be reduced by adding
shunt reactors. For the above condition (1), (Vs < VR) connect shunt reactor at the
receiving end in steps and note down the reduction in VR
Power Factor Improvement: Connect the RL load to the system, voltage is applied,
take the readings and calculate the power factor of the load applied (CosΦ1).
57
Problem 1:
Calculate the per phase value of Capacitance to be connected to improve the power
factor to the required value. Connecting 6 capacitors in parallel, find the new
power factor at the receiving end of the transmission line.
Observation:
Table I
VS IS VR IR W1 W2 W1 x mf W2 x mf P.F Remarks
Table II
Table III
P.F Remark
Without C
With C
58
Result:
Inferences:
Precaution:
• The maximum loading limit of the transmission line system training
simulator not to exceed 3A under normal loading conditions.
• During experiment, the receiving station bus voltage should be
controlled between 180V-280V line-neutral in all phases of the 3 phase
system.
59
Experiment No. 12
Aim:
To check the specifications of the given Current Transformer and Potential
Transformer.
Instruments required:
Theory:
When the current and voltages to be measured are high, then use instrument
transformer made with wattmeter just as with ammeters and voltmeters.
When the wattmeter is used in conjunction with instrument transformer, the
correction factor shall be applied for the ratio and phase angle errors of
instrument transformers.
Let the load voltage, current and load power factor be V, I and cos ø
respectively
Current in current coil of wattmeter = current in secondary of CT - Is
Voltage across pressure coil of wattmeter = Voltage across secondary
of PT = Vs
Current in pressure coil of wattmeter is lagging behind voltage by a small
angle ø due to inductance of pressure coil
Procedure:
Make the connections as per the circuit diagram.
Connect the given RL load. Apply rated voltage to the primary of the PT.
Vary the load and note down the readings of the meters. Repeat the
60
experiment with RC load also. Tabulate the readings and calculate the
true power. Measure the resistance of the load for each reading using
AVO meter.
CT secondary should not be opened while primary is energized.
RC LOAD
Result:
Inference:
61
Experiment No. 13
Aim:
Theory:
Stand-alone system is the one which can be used for both AC and DC loads and
installed near the location of the load. These systems are easy to install and
understand. These systems can be used without batteries also but they perform best
with battery bank. These systems are best suited for locations where grid
connectivity is not present and they fulfil the requirements of these locations.
They use DC power to charge the battery and run the Dc load but, use AC power to
run the Ac load. These are modules, charge controller, batteries, DC load, inverter
and AC load in this system. It runs the AC and DC load simultaneously and can
fulfill the demand of both types of pf loads.
The Solar PV Training & Research System is a mini-Solar PV Plant Prototype which
enables students and faculty to understand in-depth concepts about stand-alone PV
systems. The product also provides research orientation on several concepts such as
MPPT, inverter control etc. The system consists of individual plug-in units each with
components for different experimental arrangements. The conception of the system
allows indoor and outdoor experiments. Additional options are the change of slope
angle of the module to see the effect of tilt.
62
Features and Specification:
COMPONENTS SUBCOMPONENTS
Power generating unit Solar PV module
Artificial source of radiation Halogen- with regulator
Power conditioning unit DC-DC Converter- Auto/Manual mode
Inverter - Auto/Manual mode
Control and measuring unit Measuring meters
Battery bank
Load AC/DC
Accessories Radiation meter
Battery charger
Module cooling system
manual
Experimental setup:
It consists of a module stand, charge controller, inverter and meters for measurement
.The stand alone PV system to supply both AC and DC type of load can be achieved
by making the connections in the control board as shown in figure. The voltage and
current of the DC load, AC load and battery can be measured by the meters available
in the control board.
63
Fig 13.1: Control board connections for standalone PV system to supply both AC
and DC load
64
Observation:
Table for stand-alone PV system calculation:
S.no No of NO of Array Array Array DC load DC load DC
modules modules current voltage power(W) current(A) voltage(V) load
in series in (A) (V) power
parallel (W)
1. 1 1
2. 1 2
S.no Inverter I/P Inverter I/P Inverter I/P Battery Battery Battery
current (A) Voltage (V) Power (W) current (A) voltage (V) power (W)
1.
2.
Results:
Inference:
65
Experiment No. 14
Aim:
Perform the experiment of manually finding the MPP by varying the resistive load
across the PV panel.
Theory:
PV module is characterized by its I-V and P-V characteristics. At a particular solar
insolation and temperature module characteristics curves are shown in Fig.
In these curves maximum current at the zero voltage is called short circuit current
(Isc) and the maximum voltage is known as open circuit voltage (Voc). In P-V curve
the maximum power is achieved only at a single point which is called MPP
(Maximum Power Point ) and the voltage and current corresponding to this point fi
66
referred to as Vm amd Im. This single point is corresponding to a load resistance,
known as critical load resistance.
Experimental setup:
The circuit diagram to evaluate MPP of a module is shown in Fig. In this circuit,
modules will be connected to the variable resistance through ammeter and voltmeter.
In PVTR, connections will be done as shown in figure below which shows that the
module port(s) will be connected to module ammeter, module voltmeter and Pot
meter ports with the means of connecting cables. At the same time logger plotter box
ports will also be connected to the module ports through connecters and to the PC
through USB.
67
A
V
Plot meter
Observations:
For the fixed radiation and temperature note the following reading for different
values of load resistance R.
2.
3.
Results:
1. Draw the I-V curves (manually and with help of software) of all the sets on a
single graph and show the characteristics at different radiation and temperature
levels.
68
2. Draw the P-V curves (manually and with help of software) of all the sets on a
single graph and show the characteristics at different radiation and temperature
levels.
3. From the table find the value of maximum value of P. this will be corresponding to
a particular value of R. Note down the value of Pmax and corresponding R.
Vm =
Im =
Pm =
Ropt =
Inference:
Precautions:
1. Readings for one set should be taken within 1-2 minutes otherwise
temperature of the module can change as radiation source is halogen lamps.
2. Halogen lamp position should not be changed during one set otherwise
radiation on modules can be changed.
3. Connections should be tight.
4. Perform the experiment without battery in the circuit.
69
Experiment No. 15
Aim:
To calibrate the three phase energy meter at 0.6 pf, 0.7 pf (lead and lag) using phase
shifting transformer.
Procedure:
The current coils of wattmeter and energy meter are connected in series with the
input current terminals of phase shifting transformer (AA’,BB’,CC’).The current coil
of the energy meter is energized from a low voltage using three phase auto
transformer. Adjust the phase shifting transformer for the various power factor from
0-1 lag, 0-1 lead at 2A and 4A. Note the readings of the wattmeter and ammeter,
time taken for 5 impulses of the energy meter is also recorded.
Sample calculations:
Number of impulses =n
Load current 𝐼1 =…………….A
Time taken t = ……………s
E/m constant = …………….rev/kWh
Wattmeter reading = ………..…..W [𝑊1 + 𝑊2 ]
Actual reading (𝐸𝑎 ) = [W.t]/3600 Wh
Indicated reading (𝐸𝑖 ) = [n/k] *1000 Wh
% Error = (𝐸𝑎 -𝐸𝑖 )/ 𝐸𝑎 * 100 %
70
Circuit diagram:
3𝝓,500 V, 500 V,
10A 10A, upf
C1 C1’ M L
R A
3𝜙
A’
P1 P1
A
440V, 50 Hz, ’’
C V A
A
R
AC E
500 V, S
B1 10A, upf I
C21 C2’ M L 𝑃𝑆𝑇 B’ S
B
A
A
T
Y I
V
P2 P2 E
’ C V
L
500 V, O
10A, upf A
B2
M L C’ D
C3 C3’ C
A
A
B
P3 P3
’ C V
B3
R
Y 0
B 𝑃𝑆𝑇
0.5 0.5 Coarse
3𝜙 lag adjustment for
lead
415 V,
50 Hz, cos𝜙
0.866 0.866
S 1 lag
lead
U
P
P A B C
L
Y A’ B’ C’
Input current 5A
Fine
OUTPUT VOLTAGE adjustment for
cos𝜙
Y B
R N
Fig 15.1: Connection of three phase energy meter and phase shifting transformer.
71
Tabular column:
Result:
Inference:
72
Experiment No. 16
RELAY COORDINATION
Aim:
To perform the study of relay coordination for the radial system shown below.
CT Ratios:
Table I
Relay name CT 1 CT 2
Primary rating 200 1000
Secondary rating 1 1
73
System parameters:
Voltage 33 kV, 50Hz
Fault MVA level 800.2 MVAsc
Fault kA 14 kA
X/R ratio 40
Transformer details:
Primary 33 kV
Secondary 11 kV
Capacity 10 MVA
Impedance 8.35
Load details:
8 MVA
Relay data:
Type : ALSTOM
Model : P139
Functions : Overcurrent relay
Application : Protection, monitoring and control of motors, transformers and
lines
Theory:
74
Along with plotting protective device operating curves, ETAP Protective Device
Coordination software provides tools capable of plotting the starting, inrush, and
damage, curves for equipment like motors, transformers, generators, and cables.
Offering insight into troubleshooting false trips, relay and breaker mis-operation, and
mis-coordination.
Procedure:
1. Click the Overcurrent Relay button from Edit toolbar and drop it into
the OLV1 presentation.
2. Double-click the Overcurrent Relay element to open the Relay editor.
3. Go to the OCR page and then click the Library button. This will display the
Library Quick pick - Relay dialog box. Select manufacturer ALSTOM and
model P139 and click OK ALSTOM P139 relay data is populated in the OCR
page.
4. Set the relay as shown in the figure; ensure that ‘Link TOC + IOC and
instantaneous for this level is unchecked for OCR. Provide the necessary
pickup value.
75
5. Select the output button and add the circuit breaker to be opened by the selected
relay.
7. Select the circuit breaker from the toolbar and provide the ratings.
8. Select the bus from the toolbar and provide the ratings.
76
9. Select the current transformer from the toolbar and specify the transformation
ratio as given in data.
10. Select the two winding transformer from the toolbar and provide the ratings and
impedances (typical values) as shown in the figures.
77
11. Select the static load from the toolbar and provide the ratings as shown in
fig.16.11
78
Running Relay Coordination
1. From the Mode toolbar, click the Star – Protective Device Coordination button to
switch to the Star mode 1.
2. To generate the Star View, select the relay, and then click the Create Star View
button from the right-hand side Star Mode toolbar.
3. This opens a new Star TCC View with the selected Relay1 curve. Star Views for
other protective devices can be generated in a similar manner.. Right click on the
79
label tag associated with the curve and check the Settings options. This will show
more information related to the relay settings in the label tag.
4. Switch to Star Mode using the Mode toolbar. Select Fuse1 and click
on Append to Star view button to open the Star View Selection editor.
Select Star1to append Fuse1 to Star1 view and click OK.
80
Problem 1:
Repeat the relay coordination experiment for a three phase grid system if a 3 phase
fault occurs at bus 3.
Observation:
The sequence of operation is as follows:
Time(ms) ID If(kA)
Relay2
CB2
Relay1
CB1
Result:
Inference:
81
Experiment No. 17
Aim:
Determine
i. Power transfer capability of the transmission line with and without series
compensation.
ii. Effects of series compensation on power transfer capability and system
stability.
Specifications:
Transmission line 1 (non-compensated):
Simulated length…………………………...………200 km
Impedance
𝑅𝐿1 ………………………………….………8.9 Ω
𝑋𝐿1………………………………….………50 Ω
𝑋𝑐1………………………………….……....750 Ω
𝑋𝑐2………………………………….………750 Ω
Transmission line 2 (compensated):
Simulated length……………………………………300 km
Impedance
𝑅𝐿1 ………………………………………….10 Ω
𝑋𝐿1………………………………………….75 Ω
𝑋𝑐1………………………………………….500 Ω
𝑋𝑐2………………………………………….500 Ω
Series capacitors
17% compensation…………………………173.4µF, 15.3 Ω, @60Hz
25% compensation…………………………117.9µF, 22.5 Ω, @60Hz
34% compensation…………………………86.7µF, 30.6 Ω, @60Hz
Shunt capacitors
100 Mvar………………….......……………0.49µF, 5.4kΩ, @60Hz
200 Mvar……………………...……………0.98µF, 2.7kΩ, @60Hz
400 Mvar………………………...…………1.96µF, 1.35kΩ, @60Hz
800 Mvar…………………………...………3.93µF, 675Ω, @60Hz
Shunt Inductors
150 Mvar…………………………….……...9.55 H, 3.6 kΩ, @60 Hz
300 Mvar…………………………………...4.77 H, 1.8 kΩ, @60 Hz
600 Mvar………………………………..….2.39 H, 900 Ω, @60 Hz
82
Resistance loads
225 Mvar……………..…………………….2.4 kΩ
450 Mvar……………….…………………..1.2 kΩ
900 Mvar…………….…….………………600 kΩ
1800 Mvar…………………………………300 kΩ
3600 Mvar……………………...………….150 kΩ
Theory:
The circuit representation of the transmission lines operating at very high
voltage and running for many kilometers can me simplified to one resistance 𝑅𝐿 , one
inductance 𝑋𝐿 , and two equal capacitances 𝑋𝑐 located at the end of the line.
Fig 17.1 shows the circuit representing one phase of transmission lines 1 and 2 of the
demonstrator.
Because very long high voltage lines are mainly inductive, it is possible to
demonstrate that the active power transferred through such lines is given by:
𝐸𝑠 𝐸𝑅
𝑃𝑇 = sin 𝜃
𝑋𝐿
Where
𝑃𝑇 is the transferred power (W)
𝐸𝑠 is the line-to-line sender voltage (V)
𝐸𝑅 is the line-to-line receiver voltage (V)
𝑋𝐿 is the reactance of the line (ohm)
𝜃 is the phase shift between the sender and receiver voltages (°)
The transferred power id maximum when the sender and receiver voltages are equal
and when the phase shift between these voltages is 90°. However because of the need
to provide safety factors, phase shifts greater than 30° are not normally exceeded
deliberately. For a given line reactance and sender voltage, this sets a limit on the
maximum power a transmission line can transfer.
83
When the compensation demand becomes high there will come a time when an
additional transmission line is required. Obtaining a corridor, environmental impact
limitations, and line cost can all make provision of a new line difficult. A preferred
option is to increase the power transfer capability of an already existing line by
means of series compensation.
Series compensation consists in reducing the inductive reactance of a transmission
line by connecting a capacitor in series with the line as in figure. With this method
the active power transferred through line becomes,
𝐸𝑠 𝐸𝑅
𝑃𝑇 = sin 𝜃
𝑋𝐿 −𝑋𝐶𝑆
Where
𝑃𝑇 is the transferred power (W)
𝐸𝑠 is the line-to-line sender voltage (V)
𝐸𝑅 is the line-to-line receiver voltage (V)
𝑋𝐿 is the reactance of the line (Ω)
𝑋𝐶𝑆 is the reactance of the series capacitor(Ω)
𝜃 is the phase shift between the sender and receiver voltages (°)
If for example the line is compensated 34%, the increase in power transfer capability
will be 51.1%. Compensation factors between 20% and 70% are generally used,
thereby providing an increase in power transfer capability between 25 and 33%.
Because the series compensation increase the power transfer capability, it also
improves the system stability. In effect for any given phase shift between the sender
and receiver voltages, the amount of transferred power is greater with a compensated
line. The figure shows the power transfer capability of a line without compensation
and with 50% compensation.
84
Fig 17.3 Power transfer capability of a transmission line with and without series
compensation.
If the maximum power demand is 0.5𝑃𝑀𝐴𝑋 , the phase shift between the sender and
receiver voltages will be 30° for the compensated line, which corresponds to a very
stable operating point. However the phase shift will be 90° for the uncompensated
line, which is just on the edge of instability. In all likelihood, the uncompensated line
will be unstable to carry the load and its breaker will open.
Procedure:
WITHOUT SERIES COMPENSATION:
1. Open all the demonstrator switches. Put transmission line 1 in service by
closing both switches S1 and S2.
2. Adjust the sender voltage to 735 kV using the SOURCE adjustment.
3. Connect a resistive load of 900 MW to line 1.
4. Observe that the receiver voltage exceeds the sender end voltage due to
reactive power being generated in excess by the line capacitance𝑋𝐶2.
5. Compensate the line 1 so that the sender and receiver voltages are equal. To
do so, connect the required shunt inductor (about 450 Mvar) across the load
in order for the receiver voltage to be as close as possible to the sender end
voltage of 735 kV.
85
6. On the phasemeter, observe the phase shift between the sender and receiver
voltages. The phase shift is about 6° , which is much less than 30°. Therefore
the power demand is well below the power transfer capability of line 1.
7. Increase the load on line 1 to 1800 MW.
8. Readjust the shunt inductor across the load so that the receiver voltage is as
close as possible to the sender voltage of 735 kV. The receiver shunt inductor
should be around 150 Mvar.
9. The phase shift now observed on the phasemeter is about 12°, which is less
than 30°. Therefore the power demand is still below the power transfer
capability of line 1.
10. Further increase the load on line 1 to 3600 MW.
11. Compensate the line 1 so that the sender and receiver voltages are equal. First
disconnect the shunt inductor from the load. Then connect the required shunt
capacitor (around 800 Mvar) across the load in order for the receiver voltage
to be as close as possible to the sender voltage pf 735 kV.
12. The phase shift now observed on the phasemeter is about 25°. Therefore the
power transfer capability of line 1 has not been reached yet.
13. Further increase the load on line 1 to 4500 MW.
14. Readjust the shunt capacitor across the load so that the receiver voltage is as
close as possible to the sender voltage of 735 kV. The required shunt
capacitor should not be about 1500 Mvar.
15. The phase shift now observed is about 30°. Therefore the power transfer
capability of line 1 has been reached and is 4500 MW.
16. Open all the demonstrator switches.
17. Put the transmission line 2 in service by closing switches S3 and S4. Set the
series- compensation selector to 0%.
18. Connect a resistive load of 1800 MW to line 2.
19. Compensate the line 2 so that the sender and receiver voltages are equal. To
do so connect the required shunt inductor (about 300Mvar) across the load in
order for the receiver voltage to be as close as possible to the sender voltage
of 735kV.
86
20. On the phasemeter observe the phase shift between the sender and receiver
voltages. The phase shift is about 17° , which is much less than 30°.
Therefore the power demand is below the power transfer capability of line 2.
21. Increase the load on line 2 to 3600 MW.
22. Compensate the line 2 so that the sender and receiver voltages are equal. First
disconnect the shunt inductor from the load. Then connect the required shunt
capacitor (about 1000 Mvar) across the load in order for the receiver voltage
to be as close as possible to the sender voltage of 735kV.
23. The phase shift now observed on the phasemeter is about 38° , which is much
more than 30° . Therefore the power demand exceeds the power transfer
capability of line 2.
24. Decrease the load on line 2 to 2925MW.
25. Readjust the shunt capacitor across the load so that the receiver voltage is as
close as possible to the sender voltage of 735 kV. The required shunt
capacitor should be about 400 Mvar.
26. The phase shift now observed is about 30°. Therefore, the power transfer
capability of line 2 is 2925 MW.
NOTE: If the displayed phase shift differs from 30° by more than 3° ,
you may want to readjust the load on line 2 in order to accurately
measure its power transfer capability at 30°.
87
decreased the phase shift required to transfer the same amount of power which, in
turn, has improved the stability of the system.
8. Increase the load on line 2 to 3600 MW.
9. Readjust the shunt capacitor across the load so that the receiver voltage is as close as
possible to the sender voltage of 735 kV.
10. The phase shift now observed is about 31°. Therefore, the 17% - series
compensation has increased the power transfer capability of line 2 by
3600 𝑀𝑊 − 2925 𝑀𝑊
𝑥 100 = 23%
2925 𝑀𝑊
11. Set the series-compensation selector to 34%.
12. Observe that the phase shift has decreased from 31° to about 25°. The power
demand on line 2, however is till 3600 MW. Therefore the increase in compensation
factor has improved the stability of the system.
13. Increase the load on the line 2 to 4500 MW.
14. Readjust the shunt capacitor across the load so that the receiver voltage is as cloase
as possible to the sender voltage of 735 kV.
15. The phase shift now observed is about 32°. Therefore, the 34% series-compensation
has increased the power transfer capability of line 2 by
4500 𝑀𝑊 − 2925 𝑀𝑊
𝑥 100 = 54%
2925 𝑀𝑊
Result:
Inference:
88