Concrete Canvas Material Data Post Set CC Properties: Strength
Concrete Canvas Material Data Post Set CC Properties: Strength
Pre-Set CC Properties CBR Puncture Resistance EN ISO 12236: 2007 (CC8 & CC13 only)
- Min. Push-through force 2.69kN
Setting - Max. Deflection at Peak 38mm
Working Time 1-2 hours subject to ambient temperature
Resistance to Imposed Loads on Vehicle Traffic Areas
CC will achieve 80% strength at 24 hours after hydration. EN 1991-1-1:2002 (CC8 & CC13 only)
- Category G compliant
Method of Hydration
- Gross weight of 2 axle vehicle 30 to 160kN
Spray the fibre surface with water until it feels wet to touch - Uniformly distributed load not exceeding 5kN/sqm
for several minutes after spraying.
Standard Test Method for Impact Resistance of Pipeline Coatings
Re-spray the CC again after 1 hour if: ASTM G13 (CC13 only) Passed
- Installing CC5
Other
- Installing CC on a steep or vertical surface
- Installing in warm climates Freeze-thaw testing (BS EN 12467:2004 part 5.5.2) Passed