Lecture 10. P-F Control 2016 PDF
Lecture 10. P-F Control 2016 PDF
P/f control
2
Ways to control power flow (cont.)
3 5/12/06
Ways to control power flow (cont.)
Transformers
Tap-Changing-Under-Load (TCUL) Transformers
Ability to change the ratio of transformation while energized
Requires additional circuitry
Phase shifting transformer
Addition of “90° out of phase” voltage
Useful for controlling real power
Most cases there is a fixed range
4 5/12/06
Drawbacks of These Methods
Set minimum and maximum constraints
Fixed change
Power transfer frequency requirement
Harmonics
5 5/12/06
Power and
frequency control
Asynchronous connection
The interconnected AC networks that tie the power
generation plants to the consumers are in most cases
large. The map below shows the European situation.
51,50 Hz
Całkowita redukcja mocy FW
50,20 Hz
- możliwa zmiana trybu pracy RC (blokowanie)
Stan
NORMALNY 50,15 Hz
Aktywacja podstawowego
[NORMAL] pasma regulacji pierwotnej
50,00 Hz
Rafał Kuczyński
Polskie Sieci Elektronergetyczne
Operator Spółka Akcyjna
Increase of Active Power Consumption
f1 = 50 Hz (3000 RPM)
2
1 1 E1 200 f1 502
E J 2 J 4 2 f 2 2 J 2 f 2
E2 190 f 2 2
2 f 2 48.73 Hz
f2
2 2
The frequency will drop to 48.7 Hz
• P remains 2 MW
• Q increases from 969 kvar 1.5 Mvar
• I increases from 128 A ∠-26° 147 A ∠-37°
• V drops with 100 V
S P jQ V I
V11 V2 2
I
Z
V1(1 ) V2 ( 2 )
I
Z( )
Electrical Power System Essentials
Increase of Reactive Power Consumption
R X Z Z X( / 2)
S P jQ V I
V1 V2 V1 V2
P ReS sin1 2 1 2
X X
V1 V2
2
Q ImS cos1 2 V1 V2
V2 V2
X X X
Conclusion:
• The voltage depends on the reactive power
• The angle of transmission depends on the active power
Electrical Power System Essentials
Relations between basic parameters in
power system
P – active power
P f f- frequency
Q – reactive
power Q U U - voltage
f n P
n m
df P Pgi Poj
i 1 j 1
• Secondary control
• To bring tie-line flows to scheduled.
• Corrective actions are done by operators.
• Economic dispatch
• Make sure that the units are scheduled in the most
economical way.
AVR
LPC
Primary Speed Controls
Isochronous speed governor
an integral controller resulting in constant speed
not suitable for multimachine systems; slight differences in speed
settings would cause them to fight against each other
can be used only when a generator is supplying an isolated load or
when only one generator in a system is required to respond to load
changes
where
ωNL = steady-state speed at no load
ωFL = steady-state speed at full load
ω0 = nominal or rated speed
f / f r
Rgi
Speed governor characteristics Pgi / Pgi ,r
f=1
f / f r
Rgi
Pgi / Pgi ,r
ΔP 50
f R f r 0.02 50 0.25 Hz
Pr 200
f / f r 0.5 / 50
P Pr 200 33.3 MW
R 0.06
Primary Control
Load Sharing by Parallel Units
f f
P1 P1 P1 P2 P2 P2
R1 R2
Load sharing by parallel units with Response of a generating unit with a governor
drooping governor characteristics having speed-droop characteristics
Load sharing by parallel generating units
P1 R2
P2 R1
Primary Control
Two generators in parallel
1 Pgi ,r P 1 Pgi ,r
P Pg1 f
i i Rgi f r f i Rgi f r
Example
d d 2 1 d
J J 2 Mm Me MD MD D D
dt dt s s dt
Tm S n Mm – mechanical Me – electromagnetic
s 2 J
MJ Tm rotor driving torque torque of the generator
s Sn
Tm J m TD Te ( )
Tm mechanical input torque (N-m)
J moment of inertia of turbine & rotor
m angular acceleration of turbine & rotor
TD damping torque
Te ( ) equivalent electrical torque
Generator Mechanical Model, cont’d
In general power = torque angular speed
Hence when a generator is spinning at speed s
Tm J m TD Te ( )
Tm s ( J m TD Te ( )) s Pm
Pm J ms TDs Pe ( )
Initially we'll assume no damping (i.e., TD 0)
Then
Pm Pe ( ) J ms
Pm is the mechanical power input, which is assumed
to be constant throughout the study time period
Generator Mechanical Model, cont’d
Pm Pe ( ) J ms
m st rotor angle
d m
m m s
dt
m m
Pm Pe ( ) J s m J s
J s inertia of machine at synchronous speed
Convert to per unit by dividing by MVA rating, S B ,
Pm Pe ( ) Js 2s
SB SB S B 2s
Generator Mechanical Model, cont’d
Pm Pe ( ) J s 2 s
SB SB S B 2 s
Pm Pe ( ) J s2 1
(since s 2 f s )
SB 2S B f s
J s2
Define H per unit inertia constant (sec)
2S B
All values are now converted to per unit
H H
Pm Pe ( ) Define M
fs fs
Then Pm Pe ( ) M
Generator Swing Equation
This equation is known as the generator swing equation
Pm Pe ( ) M
Adding damping we get
Pm Pe ( ) M D
This equation is analogous to a mass suspended by
a spring
k x gM Mx Dx
Load as a function of frequency (load
damping)
Governor and load characteristic curve intersection
Composite System Regulating Characteristics
System load changes with frequency. With
a load damping constant of D, frequency
sensitive load change:
PD = D f
When load is increased, the frequency
drops due to governor droop;
Due to frequency sensitive load, the net
reduction in frequency is not as high.
The composite regulating characteristic
includes prime mover characteristics and
load damping. An increase of system load
by PL results in a generation increase of
PG due to governor action, and a load
reduction of PD due to load characteristic
PL
f SS
1 R1 1 R2 1 Rn D
PL PL
(PL )
1 Req D
β is the stiffness or composite frequency
response characteristic of the system.
Secondary Control
AGC for Single and
Multi Areas
53
From a central site, you increase or
decrease the 60Hz set-points until the
sum of the 60Hz set-points is equal to
the system load. Then the frequency will
stabilize at 60Hz.
This form of supplemental control is
called Automatic Generation Control
(AGC) and more specifically, Load
Frequency Control (LFC).
Secondary Control
Static Speed-Power Curve
Slope = -R From,
1
PM PC
0 R
Primary control: Immediate
2
change corresponding to
1 sudden change of load
(frequency)
Secondary control: Change
in setting control power to
PM maintain operating frequency.
PC1 = PM 1 PC 2 = PM 2 The higher R (regulation), the
better.
55
Secondary Control
Steady-state speed characteristic with speed changer
Secondary Control 2 – work point after the
secondry control
61
Overview of AGC
Secondary control
To bring tie-line flows to scheduled.
Corrective actions are done by operators.
Economic dispatch
Make sure that the units are scheduled in the most economical
way.
• We will consider:
• AGC for single generator
• AGC for 2 generators
• AGC for multi generators
• Area Control Error (ACE)
63
Supplementary Control of Isolated Systems
With primary speed control, the only way a change in generation
can occur is for a frequency deviation to exist.
Restoration of frequency to rated value requires manipulation of the
speed/load reference achieved through supplementary control
69
ACE: Tie-Line Bias Control
Use ACE to adjust setting control power, PCi , of each
area.
Goal:
To drive ACE in all area to zero.
To send appropriate signal to setting control power,
The following summarizes the two basic LFC objectives for an interconnected power
system:
1. Following a load change, each area should assist in returning the steady-state
frequency error Δf to zero.
2. Each area should maintain the net tie-line power flow out of the area at its scheduled
value, in order for the area to absorb its own load changes.
70
Power Pool Operation
Power pool is an interconnection of the power
systems of individual utilities.
Each company operates independently, BUT,
They have to maintain
contractual agreement about power exchange of
different utilities, and,
same system frequency.
Basic rules
Maintainscheduled tie-line capacities.
Each area absorbs its own load changes.
71
AGC for Multi Areas
During transient period, sudden change of load causes
each area generation to react according to its frequency-
power characteristics.
This is “called primary control”.
72
Supplementary Control of Interconnected
Systems
The objectives of automatic generation control are to maintain:
system frequency within desired limits
area interchange power at scheduled levels
correct time (integrated frequency)
This is accomplished by using a control signal for each area referred
to as area control error (ACE), made up of:
tie line flow deviation, plus
frequency deviation weighted by a bias factor Figure 11.27
illustrated calculation of ACE
Bias factor, B, set nearly equal to regulation characteristic (I/R + D)
of the area; gives good dynamic performance
A secondary function of AGC is to allocate generation economically
Area Control Error (ACE)
75
AGC for 2-Area with Tie-line Bias Control :
Static Speed-Power Curve
Load in area 2 increases.
Frequency of both area
drops.
ACE makes Control 0
power of area 2 2’
2
increases.
1
Steady state is reached = Change in load 2
+
when frequency is back
at the operating point and
PM
generator in area 2 take
its own load. PM 1 PM 1 PM 2 PM 2 PM 2
PM 1
76
Functional diagram of a typical
Automatic Generation Control (AGC)
system
ACE ptie ptie sched B f ,i f 50
ptie B f ,i f
1 1
....
R1 R2
1
pm pref f pref f
R
Secondary Control or
Load Frequency Control
Power exchange between three control areas
a)The original (scheduled)
situation
b) Incremental generation after
losing 400 MW of generation
in control area B
P 1 Pgi ,r
A B C 40 000 MW / Hz
f i Rgi fr
P 400
0.01 Hz
f 40000
PA A f 13000 0.01 130 MW
PB B f 16000 0.01 160 MW
PC C f 11000 0.01 110 MW
ACE A (130 0) 13000(0.01) 0 MW
ACE B (260 500) 16000(0.01) 240 160 400 MW
ACEC (390 (500)) 11000(0.01) 0 MW
Three Bus Case on AGC
-40 MW 40 MW
Bus 2 8 MVR -8 MVR Bus 1
1.00 PU
266 MW
133 MVR
1.00 PU
101 MW
5 MVR
-77 MW -39 MW
150 MW AGC ON
25 MVR 12 MVR 100 MW
166 MVR AVR ON
78 MW 39 MW
-21 MVR -11 MVR
Bus 3 1.00 PU
Home Area
133 MW
67 MVR
250 MW AGC ON
34 MVR AVR ON
Generation
is automatically Net tie flow is
changed to match close to zero
change in load
Multiple Generator Governor Response
Consider an isolated power system with three generators on-line and operating at
60Hz. The load is 360 MW and the generator outputs for units #1, #2 and #3 are
80MW, 120MW and 160MW, respectively.
A load of 21MW (P) is added. What frequency does the system settle at? How
much does each unit pick-up (MW)?
Since R(p.u.)=( f(Hz)/60)/( P(MW)/Capacity),
then (P/f)=(1/R) X Capacity/60).
A B
83
Example: Frequency Calculation
84
Example: ACE Calculation
ACE A PAB
1
9.091
1
0.0136 10 MW
RA 0.015
ACEB PBA
1
9.091
1
0.0136 0 MW
RB 0.0015
85
Example: Control Action
86
Three generators serving 360MW
Three generators serving 367MW
Three generators serving 374MW
Three generators serving 381MW
Load of 367MW and 60Hz SPs increased
by 7 MW
Illustration of typical governor dead
band
Dynamics of the Governor
and AGC Control
of System Frequency
Schematic diagram of LFC and AVR of a
synchronous generator
Turbine-governor block diagram
Block diagram for a simple steam turbine governor commonly known as
the TGOV1 model.
The block models the delays associated with the turbine; for
nonreheat turbines T2 should be zero.
The time delays Typical values are R=0.05 pu, T1 =0.5 seconds, T3=0.5 for a
associated with the non-reheat turbine or T2=2.5, and T3=7.5 seconds otherwise.
governor
96
Speed-Power Relationship
From synchronous turbine-governor: small
signal analysis model,
PM GM s PC
1
R
At steady state (s → 0,GM s → 1), we
have
1
PM PC
R
97
Block diagram of turbine–
governor system; (a) non-
reheat steam unit, (b)
reheat steam
unit and (c) hydraulic unit
Block diagram model of
governor with frequency
control loops for a non-reheat
steam generator unit
Dynamic response of
the closed-loop system
with (solid) and without
(dotted) supplementary
control
Addition of a speed changer
Turbine speed governing system
Block diagram representation of speed governor
system
Turbine transfer function model
Block diagram representation of generator-load
model
Block diagram model of load frequency control
(Isolated power system)
Proportional plus integral load frequency control
Dynamic response of load frequency controller
with an without integral control action
Power system equipped for
supplemental control
Two generators equipped with
governors having output feedback
Schematic of a governor with output
feedback
AGC for 2-Area with Tie-line Bias Control :
Static Speed-Power Curve
Load in area 2 increases.
Frequency of both area
drops.
ACE makes Control 0
power of area 2 2’
2
increases.
1
Steady state is reached = Change in load 2
+
when frequency is back
at the operating point and
PM
generator in area 2 take
its own load. PM 1 PM 1 PM 2 PM 2 PM 2
PM 1
111
AGC for 2-Area with Tie-line Bias Control: Block Diagram
ACE 1 = 0
↓, try to ↑ mechanicalR
1 PL1 Frequency 1 ↓
+ power
ACE1 K PC1 PM 1 -
1 GM1 s + GP1 s s
s + 1 1
P+12
- -
P1 P12Different phase angle ↓ +
Transfer power 12 ↓
T12
Transfer power 12 ↑
-1 Setting control power 2 ↑ -1 Different phase angle ↑
-
P21+ P2 P21
ACE2 K PC 2 PM 2 - 2 2
2
s
GM 2 s + GP2 s s
+ + Frequency 2 ↓
ACE 2 < 0 - -
B2
Governor 2 sense speed 1 PL 2 Load 2 ↑ Frequency 2 ↑
↓, try to ↑ mechanical
2 power
Governor 2 sense
R2 Steady state:
112
Generator Voltage
Control
113
Automatic Generation and Voltage Control
In modern large interconnected systems, manual regulation is not
feasible and therefore automatic generation and voltage regulation
equipment is installed on each generator. Figure below gives the
schematic diagram of load frequency and excitation voltage regulators of
a turbo-generator.
The controllers are set for a particular operating condition and they take
care of small changes in load demand without frequency and voltage
exceeding the prescribed limits. With the passage of time, as the change
in load demand becomes large, the controllers must be reset either
manually or automatically.
Excitation voltage control is fast acting in which the major time constant
encountered is that of the generator field; while the power frequency
control is slow acting with major time constant contributed by the turbine
and generator moment of inertia – this time constant is much larger than
that of the generator field. Thus, the transients in excitation voltage
control vanish much faster and do not affect the dynamics of power
frequency control.
Schematic diagram of LFC and AVR of a
synchronous generator
The Automatic Voltage Regulator (AVR)
system of a generator
Schematic diagram of load frequency and
excitation voltage regulators of a turbo-generator
Schematic diagram of alternator voltage regulator
scheme
Block diagram of alternator voltage regulator
scheme
Generation oscillations at the dead band
frequency