Project Standard Specification: Condensers) (Integral Air-Cooled Condensers)
Project Standard Specification: Condensers) (Integral Air-Cooled Condensers)
Project Standard Specification: Condensers) (Integral Air-Cooled Condensers)
PART 1 - GENERAL
A. Drawings and general provisions of the Contract, including Conditions of Contract and
Division 1 Specification Sections, apply to this Section.
0.2 SUMMARY
A. This Section includes packaged air-conditioning units with refrigerant compressors and
controls, intended for indoor installations, with [externally mounted air-cooled
condensers] [integral air-cooled condensers].
0.3 SUBMITTALS
A. Product Data: Include rated capacities; shipping, installed, and operating weights; furnished
specialties; and accessories for each type of product indicated.
B. Shop Drawings: Diagram power, signal, and control wiring and differentiate between
manufacturer-installed and field-installed wiring.
C. Samples for Initial Selection: Manufacturer's color charts consisting of units or sections of
units showing the full range of colors available for units with factory-applied color finishes.
D. Field Test and Commissioning Reports: As specified in "Field Quality Control" and
"Commissioning" Articles in Part 3 of this Section. Indicate and interpret test results for
compliance with performance requirements.
SELF-CONTAINED AIR-CONDITIONING UNITS (15 TONS AND SMALLER) 15736 - Page 1/6
STD-SPC-DCA(A1)-ME-DCA REV A
<Project Title>
A. Electrical Components, Devices, and Accessories: Listed and labeled as defined in latest
and relevant IEC standard, by a testing agency acceptable to the Engineer.
B. Paint finish shall be suitable for hot and humid climates. Unit shall be capable and suitable
of working at outdoor ambient temperature of 50 deg. C .
0.5 COORDINATION
A. Coordinate size and location of concrete bases for units. Cast anchor-bolt inserts into bases.
Concrete, reinforcement, and formwork are specified in Division 3 Section "Cast-in-Place
Concrete."
B. Coordinate size, location, and connection details with roof curbs, equipment supports, and
roof penetrations specified in Division 7 Section "Roof Accessories."
0.6 WARRANTY
B. Warranty Period: [Five] <Insert other number> years from date of Substantial
Completion.
A. Furnish extra materials described below that match products installed and that are packaged
with protective covering for storage and identified with labels describing contents.
PART 2 - PRODUCTS
0.1 GENERAL
SELF-CONTAINED AIR-CONDITIONING UNITS (15 TONS AND SMALLER) 15736 - Page 2/6
STD-SPC-DCA(A1)-ME-DCA REV A
<Project Title>
0.3 CABINET
A. Frame and Panels: Structural-steel frame with galvanized steel panels with factory applied,
baked-enamel finish in color selected by the Engineer from manufacturer's standard range,
and with access doors or panels.
B. Insulation: Minimum 13 mm thick, acoustic duct liner on cabinet interior and control panel.
C. Drain Pan: Stainless steel, with connection for drain; insulated with polystyrene..
C. Drive: [Belt, with fan mounted on permanently lubricated bearings] [Direct, with fan
and motor resiliently mounted].
D. Fan Sheaves: Steel sheaves, dynamically balanced, bored to fit shafts and keyed.
E. Motor Sheave: Variable and adjustable pitch selected so that required rpm are obtained
when set at midposition.
0.5 COMPRESSOR
A. Description: Hermetically sealed, 3600 rpm maximum, and resiliently mounted with
positive lubrication and internal motor protection.
SELF-CONTAINED AIR-CONDITIONING UNITS (15 TONS AND SMALLER) 15736 - Page 3/6
STD-SPC-DCA(A1)-ME-DCA REV A
<Project Title>
B. Refrigeration Circuit: A separate circuit for each compressor, with externally equalized
thermal-expansion valve, filter-dryer, and charging valves.
A. Description: Factory assembled and tested; consisting of condenser coil, fans and motors,
and operating controls; suitable for roof mounting.
1. Condenser Coil: Aluminum-fin copper tube with integral subcooler; leak tested to
2930 kPa.
2. Condenser Fans: Direct-drive propeller type with permanently lubricated motors
with built-in thermal-overload protection.
3. Refrigerant Line Kits: Annealed-copper suction and liquid lines that are factory
cleaned, dried, pressurized, and sealed; insulated suction line; flared fittings at
evaporator end, no fitting at condenser end; and service valves for both suction and
liquid lines.
4. Corrosion-Resistant Treatment: Phenolic coating applied in multiple dips and baked.
Corrosion treatment for condenser coils shall be factory applied.
A. Description: Factory assembled and tested; consisting of condenser coil, fans and motors,
and cabinet.
1. Condenser Coil: Aluminum-fin copper tube with integral subcooler; leak tested to
2930 kPa.
2. Condenser Fan: Direct-drive propeller type with permanently lubricated motor with
built-in thermal-overload protection.
3. Corrosion-Resistant Treatment: Phenolic coating applied in multiple dips and baked.
Corrosion treatment for condenser coils shall be factory applied.
0.10 CONTROLS
A. Control Package: Factory wired, including contactor, high- and low-pressure cutouts,
internal-winding thermostat for compressor, control-circuit transformer, and noncycling
reset relay. Control system shall be factory equipped with all necessary interface
communication to BMS on Bacnet protocol.
1. Supply fan.
2. Compressor.
3. Condenser.
4.
SELF-CONTAINED AIR-CONDITIONING UNITS (15 TONS AND SMALLER) 15736 - Page 4/6
STD-SPC-DCA(A1)-ME-DCA REV A
<Project Title>
PART 3 - EXECUTION
0.1 INSTALLATION
D. Isolation: Mount cabinet and remote air-cooled condenser on [rubber-in-shear pads for
mounting under base of unit] [spring isolators for mounting under base of unit].
0.2 CONNECTIONS
C. Unless otherwise indicated, connect piping with unions and shutoff valves to allow units to
be disconnected without draining piping. Refer to piping system Sections for specific valve
and specialty arrangements.
D. Ground equipment.
SELF-CONTAINED AIR-CONDITIONING UNITS (15 TONS AND SMALLER) 15736 - Page 5/6
STD-SPC-DCA(A1)-ME-DCA REV A
<Project Title>
B. Leak Test: After installation, charge system and test for leaks. Repair leaks and retest until
no leaks exist.
C. Operational Test: After electrical circuitry has been energized, start units to confirm proper
motor rotation and unit operation. Remove malfunctioning units, replace with new
components, and retest.
D. Test and adjust controls and safeties. Replace damaged and malfunctioning controls and
equipment.
0.4 COMMISSIONING
B. Verify that units are installed and connected according to the Contract Documents.
0.5 DEMONSTRATION
SELF-CONTAINED AIR-CONDITIONING UNITS (15 TONS AND SMALLER) 15736 - Page 6/6
STD-SPC-DCA(A1)-ME-DCA REV A