Bill of Materials and Estimates: ' ' Leona Bonghanoy Yuko
Bill of Materials and Estimates: ' ' Leona Bonghanoy Yuko
Bill of Materials and Estimates: ' ' Leona Bonghanoy Yuko
ITEM NO. ITEM OF WORK QTY UNIT Material Cost Total Cost
I EARTHWORKS
1.1 Excavation 7.56 m3 139.77 1,056.66
Sub Total 1,056.66
II MASONRY WORKS
2.1 100mm THK CHB Wall 119.70 m2 449.33 53,784.80
2.3 10mm diameter Deformed Bar, Grade 40 251.86 kg 41.55 10,464.98
2.4 12mm diameter Deformed Bar, Grade 40 272.16 kg 41.55 11,308.33
2.5 Cement Plastering, Smooth Finish on Concrete 239.40 m2 34.90 8,355.06
2.6 #16 Tie Wire 15.72 kg 75.00 1,179.06
Sub Total 85,092.23
III STRUCTURAL WORKS
3.1 Structural Concrete, 3000 psi, 4" Slump, 3/4 aggregate 9.11 m3 4,290.00 39,090.48
3.2 100mm x 50mm x 6mm THK C-purlins 24.00 lengths 339.56 8,149.44
3.3 2" Wire Mesh 331.86 m2 400.00 132,744.00
Sub Total 179,983.92
IV PAINT
4.1 Epoxy Primer 8.24 gal 1,000.00 8,240.00
4.2 Enamel Paint Semi-Gloss Finish (yellow) 8.24 gal 1,000.00 8,240.00
Sub Total 16,480.00
Total Amount 282,612.81
ITEM NO. ITEM OF WORK QTY UNIT Material Cost Total Cost
I EARTHWORKS
1.1 Excavation 7.56 m3 139.77 1,056.66
Sub Total 1,056.66
II MASONRY WORKS
2.1 100mm THK CHB Wall 119.70 m2 449.33 53,784.80
2.2 10mm diameter Deformed Bar, Grade 40 251.86 kg 41.55 10,464.98
2.3 12mm diameter Deformed Bar, Grade 40 272.16 kg 41.55 11,308.33
2.4 #16 Tie Wire 15.72 kg 75.00 1,179.06
Sub Total 76,737.17
III STRUCTURAL WORKS
3.1 cement 125 bags 200.00 25,020.00
3.2 sand 6.95 m3 250.00 1,737.50
3.3 gravel 9.11 m3 350.00 3,189.20
3.4 100mm x 50mm x 6mm THK C-purlins 24.00 lengths 339.56 8,149.44
3.5 2" Wire Mesh 331.86 m2 400.00 132,744.00
Sub Total 170,840.14
IV PAINT
4.1 Epoxy Primer 8.24 gal 1,000.00 8,240.00
4.2 Enamel Paint Semi-Gloss Finish (yellow) 8.24 gal 1,000.00 8,240.00
Sub Total 16,480.00
V CONSUMABLES 1.00 lot 5,000.00 5,000.00
Sub Total 5,000.00
Total Amount 270,113.97
` `
Engr. Raymund John J. Jusayan Leona Bonghanoy Yuko
ENGINEER OWNER
Client : Leona Bonghanoy Yuko
Project : Proposed Perimeter Fence
1 SPECIFICATIONS:
10 mm reinf. bars
masonry wall
ties
horizontal bars
Cement Plastering
cement
sand
Structural Concrete
concrete fence column
concrete fence footing
cement
sand
gravel
total;
cement
sand
gravel
steel matting W
2.4
C-purlins
PAINT
PURLINS
wire mesh
m3 per mesh footing no. of posts total m3 for mesh footing
0.036 70 2.52
L H Area
3 2 6
2.8 2.25 6.3
L W H
3 2
0.2 0.2 2
L W H
2.56
qty
15.7208 kg
L H Thickness
2.8 2.25 0.02
82.008 bags
4.556 m3
9.112 m3
125.1 bags
6.95 m3
9.112 m3
7756.56
598.5
8355.06 34.9
NO. OF COLUMN QTY
20 1.6 m3
1.8 m3
NO. OF WALL
19 3.192 m3
70 2.52 m3
total qty 9.112 m3
m2
Total Area
114 m2
119.7 m2
total length
4.5 4.005 kg 80.1
no. of posts say (posts) (pcs) bend total length of vertical bars
70.1375 70 0.05 1.2
no. of layers total length of horizontal bars
3 1.8
TOTAL QTY.
kg
kg
qty
1.068 kg
1.602 kg
272.162 KG
524.02666667 kg