CCPU-Defect List #010-17.jan.2019

Download as doc, pdf, or txt
Download as doc, pdf, or txt
You are on page 1of 5

Mega Asset Management Co., Ltd.

DEFECT LIST Canadia Tower, 10F, No.315, Ang Duong Street


(corner of Monivong Blvd), Phnom Penh, Cambodia

PROJECT NAME: Cambodia China Polytechnic University (CCPU)


LOCATION: Chroy Chongvar Satellite City, Phnom Penh, Cambodia
PREPARED BY: Chhem Sophea (Mr.)
PHONE / EMAIL: 010 384 758/ [email protected]
REFERENCE NUMBER: CCPU-DFL-010
DATE: January 17, 2019
ATTENTION: KPCC
CC: Mega Asset Management Co., Ltd.

ID COMMENTS/ DESCRIPTION ACTION STATUS


A Rebar and concrete work of pile caps
1 Installed rebar and cast concrete for 12 pile caps without inspection KPCC Disapproved

Please refer the ID in the table to the ID in Photo Report below:

Additional Comments (if any)

Status of concrete casting is Disapproved due to:

- No schedule of concrete casting submitted/informed

- No inspection record from actual rebar and concrete work

- No site engineer standby during concreting

- No report photo of concrete casting

ID LOCATION ON DRAWING (RED ZONE) PHOTO DESCRIPTION ON SITE

Mega Asset Management Co.,Ltd.


Mega Asset Management Co., Ltd.
Canadia Tower, 10F, No.315, Ang Duong Street
(corner of Monivong Blvd), Phnom Penh, Cambodia

12 Pile caps cast on Jan 16, 2019 night are 1E,


1B, 2A, 2B, 2D, 2E, 3D, 4A, 4B, 11D, 11E and 12E

 Element: Pile caps


 Location: BF at twelve grids: 1E, 1B, 2A, 2B, 2D, 2E, 3D, 4A, 4B, 11D, 11E and 12E

Mega Asset Management Co.,Ltd.


Mega Asset Management Co., Ltd.
Canadia Tower, 10F, No.315, Ang Duong Street
(corner of Monivong Blvd), Phnom Penh, Cambodia

 Issue: Installing rebar and concrete casting for 12 pile caps as mention in Location was done without
inspection; on informing. Cast in early morning (1:25 to 4:30) on Jan 17, 2019, contractor finished rebar
installation in the midnight and instantaneously concreted.
Status: MAM disapproved for the 12 pile caps concrete casting.
 Date: 17.January.2019
Report Photo

(Photo of PC1b at grid 4-B)


- No inspection record for pile cap rebar arrangment and concrete casting
- No inspection record for post installed rebar of structural column

(Photo of PC2 at grid 3-D)


- 30 mm as cover from main bar of pile cap is not less than designed cover, 40 mm from side stirrup

Mega Asset Management Co.,Ltd.


Mega Asset Management Co., Ltd.
Canadia Tower, 10F, No.315, Ang Duong Street
(corner of Monivong Blvd), Phnom Penh, Cambodia

(Photo of PC1b at grid 2-B)


- No inspection record for post installed rebar of basement wall, no signed drawing attach with
inspection form

(Photo of PC1b at grid 2-A)


- No inspection record for post installed rebar of capping beam, no signed drawing attach with
inspection form

Mega Asset Management Co.,Ltd.


Mega Asset Management Co., Ltd.
Canadia Tower, 10F, No.315, Ang Duong Street
(corner of Monivong Blvd), Phnom Penh, Cambodia

Concrete delivery slip as reference; but not informed in internal group Telegram

Mega Asset Management Co.,Ltd.