MD Asib Hossain Exp7 PDF
MD Asib Hossain Exp7 PDF
MD Asib Hossain Exp7 PDF
Experiment No : 07
Experiment Name : Power system network
Submitted To:
Abu Tareq
Lecturer
Department of EEE
Bangladesh University of Business & Technology (BUBT)
Submitted By:
NAME: Md Asib Hossain
ID : 17181108006
INTAKE : 22
SECTION : 01
PROGRAM : B.Sc. in EEE
1|Page
Objectives
The main objectives of this experiments is given below:
1. To introduce about per unit system
2. To introduce about end to end power network system
3. To analyze the parameters at different point in system network
4. To design the low loss cost effective power system network and analyze it
Firstly the value of base power and the base voltage are selected, and their choice
automatically fixes the other base values.
So
Putting the value of base current from the equation (1) in equation (2) we get
2|Page
Putting the value of base current from the equation (1) in the equation (3) we get
3|Page
To change base values, the following expression is used:
Generating Substation
In generating station the fuel (coal, water, nuclear energy, etc.) is converted into
electrical energy. The electrical power is generated in the range of 11kV to 25kV, which
is step-up for long distance transmission.
Transmission Substation
The transmission substation carries the overhead lines which transfer the generated
electrical energy from generation to the distribution substations. It only supplies the
large bulk of power to bulk power substations or very big consumers. The transmission
voltage is operating at more than 66kv and is standardized at 69kv, 115KV, 138KV,
161KV, 230KV, 345KV, 500KV, and 765KV, line-to-line. The transmission line above
230KV is usually referred to as extra high voltage (EHV).
4|Page
Distribution Substation
The component of an electrical power system connecting all the consumers in an area
to the bulk power sources is called a distribution system. The bulk power stations are
connected to the generating substations by transmission lines. They feed some
substations which are usually situated at convenient points near the load centers.
Methodology
1. Open ETAP--> File ---> New Project--->Save Project Name
2. Open ETAP Library and browse the components
3. Connect the components as per circuit diagram
4. Set the desired voltage and required frequency
5. Simulate the diagram using ETAP
6. Alalyze and plot the waveforms
5|Page
ETAP Circuit Diagram