BI-10-02126– (REPLACE CRUDE OIL SAMPLERS AT YANBU NORTH TERMINAL)- 530074
PD&T PROJECTS AND TECHNICAL SUPPORT DEPARTMENT
CAPITAL PROGRAM MANAGEMENT
BI-10-02126
REPLACE CRUDE OIL SAMPLERS AT YANBU NORTH TERMINAL
Weekly Progress Report # 32
(Week Ending August 29,
2020)
Revision 00
Prepared by:
Page 1 of 4
BI-10-02126– (REPLACE CRUDE OIL SAMPLERS AT YANBU NORTH TERMINAL)- 530074
TABLE OF CONTENTS
1.0 WEEKLY PROGRESS REPORT ACTIVITIES WEEKENDING (AUGUST 29, 2020) .................... 3
1.1 ENGINEERING ................................................................................................................................ 3
1.1.1 PROCESS ........................................................................................................................................ 3
1.1.2 INSTRUMENTATION ...................................................................................................................... 3
1.1.3 PIPING ............................................................................................................................................. 3
1.1.4 COMMUNICATION .......................................................................................................................... 3
1.1.5 STRUCTURAL/CIVIL ...................................................................................................................... 3
1.1.6 ELECTRICAL .................................................................................................................................. 3
1.1.7 FIRE PROTECTION (OSB) ............................................................................................................. 4
1.1.8 CORROSION MANAGEMENT PROGRAM (CMP) ........................................................................ 4
1.1.9 MECHANICAL ................................................................................................................................. 4
2.0. AREAS OF CONCERN ................................................................................................................... 4
3.0. ATTACHMENTS .............................................................................................................................. 4
Page 2 of 4
BI-10-02126– (REPLACE CRUDE OIL SAMPLERS AT YANBU NORTH TERMINAL)- 530074
1.0 WEEKLY PROGRESS REPORT ACTIVITIES WEEKENDING (August 29, 2020)
1.1 ENGINEERING
1.1.1 PROCESS
• Replies for 90% E review for disagreed and implemented reviewer comments
• Incorporation of 90% closed comments for IFB
• Interdisciplinary Inputs to Mechanical
1.1.2 INSTRUMENTATION
• Implemting 90% batch-2 comments required for implementation as proof
1.1.3 PIPING
Prepare the IFB package
Update the piping plans based on approved proposal of Manual sample connection routing
Discussion and meetings
1.1.4 COMMUNICATION
• No activity
1.1.5 STRUCTURAL/CIVIL
• Continued closing SA disputed comments on 90% Package
• Updated Plot Plan for the eyewash/shower location
• Continued revising Civil/Structural IFB documents and drawings
1.1.6 ELECTRICAL
• Incorporate agreed 90% comments
• Started preparation of IFB Package.
Page 3 of 4
BI-10-02126– (REPLACE CRUDE OIL SAMPLERS AT YANBU NORTH TERMINAL)- 530074
1.1.7 FIRE PROTECTION (OSB)
• Response provided to 90% E review comments
• Provided Interdisciplinary Inputs to Piping on Emergency Eyewash and Safety Showers
• Updated Basis of Design Document with the requirement of Emergency Eyewash and Safety Showers
• Weekly progress update
1.1.8 CORROSION MANAGEMENT PROGRAM (CMP)
• Comments implementation of SA on 90% Package.
• Generating proof of implementation of SA comments
▪ MECHANICAL
• Working on 90% comments implementation
• Working on vendor quotations LOG
• Working on the impact of relocating Skid of berth 64
AREAS OF CONCERN
2.0
. • There is impact of COVID-19 Safety & Health Measures on the project progress.
3.0 ATTACHMENTS
. • Weekly Progress Summary
• Weekly Overall discipline progress
• Weekly Progress Report Details
• Weekly Progress overall S-Curve
Page 4 of 4