Replace Crude Oil Samplers at Yanbu North Terminal

This weekly progress report discusses engineering work for the project to replace crude oil samplers at the Yanbu North Terminal in Saudi Arabia. Activities during the week included addressing reviewer comments on the 90% design package, finalizing civil/structural and electrical drawings and documents for the invitation for bid package, and coordinating among engineering disciplines like piping and instrumentation. One area of concern is the potential impact of COVID-19 safety measures on project schedule and progress.

Uploaded by

Muhammad Salman
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
45 views4 pages

Replace Crude Oil Samplers at Yanbu North Terminal

This weekly progress report discusses engineering work for the project to replace crude oil samplers at the Yanbu North Terminal in Saudi Arabia. Activities during the week included addressing reviewer comments on the 90% design package, finalizing civil/structural and electrical drawings and documents for the invitation for bid package, and coordinating among engineering disciplines like piping and instrumentation. One area of concern is the potential impact of COVID-19 safety measures on project schedule and progress.

Uploaded by

Muhammad Salman
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 4

BI-10-02126– (REPLACE CRUDE OIL SAMPLERS AT YANBU NORTH TERMINAL)- 530074

PD&T PROJECTS AND TECHNICAL SUPPORT DEPARTMENT


CAPITAL PROGRAM MANAGEMENT

BI-10-02126

REPLACE CRUDE OIL SAMPLERS AT YANBU NORTH TERMINAL

Weekly Progress Report # 32


(Week Ending August 29,
2020)
Revision 00

Prepared by:

Page 1 of 4
BI-10-02126– (REPLACE CRUDE OIL SAMPLERS AT YANBU NORTH TERMINAL)- 530074

TABLE OF CONTENTS

1.0 WEEKLY PROGRESS REPORT ACTIVITIES WEEKENDING (AUGUST 29, 2020) .................... 3
1.1 ENGINEERING ................................................................................................................................ 3
1.1.1 PROCESS ........................................................................................................................................ 3
1.1.2 INSTRUMENTATION ...................................................................................................................... 3
1.1.3 PIPING ............................................................................................................................................. 3
1.1.4 COMMUNICATION .......................................................................................................................... 3
1.1.5 STRUCTURAL/CIVIL ...................................................................................................................... 3
1.1.6 ELECTRICAL .................................................................................................................................. 3
1.1.7 FIRE PROTECTION (OSB) ............................................................................................................. 4
1.1.8 CORROSION MANAGEMENT PROGRAM (CMP) ........................................................................ 4
1.1.9 MECHANICAL ................................................................................................................................. 4
2.0. AREAS OF CONCERN ................................................................................................................... 4
3.0. ATTACHMENTS .............................................................................................................................. 4

Page 2 of 4
BI-10-02126– (REPLACE CRUDE OIL SAMPLERS AT YANBU NORTH TERMINAL)- 530074

1.0 WEEKLY PROGRESS REPORT ACTIVITIES WEEKENDING (August 29, 2020)

1.1 ENGINEERING

1.1.1 PROCESS

• Replies for 90% E review for disagreed and implemented reviewer comments
• Incorporation of 90% closed comments for IFB
• Interdisciplinary Inputs to Mechanical

1.1.2 INSTRUMENTATION

• Implemting 90% batch-2 comments required for implementation as proof

1.1.3 PIPING
 Prepare the IFB package
 Update the piping plans based on approved proposal of Manual sample connection routing
 Discussion and meetings

1.1.4 COMMUNICATION

• No activity

1.1.5 STRUCTURAL/CIVIL

• Continued closing SA disputed comments on 90% Package


• Updated Plot Plan for the eyewash/shower location
• Continued revising Civil/Structural IFB documents and drawings

1.1.6 ELECTRICAL

• Incorporate agreed 90% comments


• Started preparation of IFB Package.

Page 3 of 4
BI-10-02126– (REPLACE CRUDE OIL SAMPLERS AT YANBU NORTH TERMINAL)- 530074

1.1.7 FIRE PROTECTION (OSB)

• Response provided to 90% E review comments


• Provided Interdisciplinary Inputs to Piping on Emergency Eyewash and Safety Showers
• Updated Basis of Design Document with the requirement of Emergency Eyewash and Safety Showers
• Weekly progress update

1.1.8 CORROSION MANAGEMENT PROGRAM (CMP)

• Comments implementation of SA on 90% Package.


• Generating proof of implementation of SA comments

▪ MECHANICAL
• Working on 90% comments implementation
• Working on vendor quotations LOG
• Working on the impact of relocating Skid of berth 64
AREAS OF CONCERN
2.0
. • There is impact of COVID-19 Safety & Health Measures on the project progress.

3.0 ATTACHMENTS
. • Weekly Progress Summary
• Weekly Overall discipline progress
• Weekly Progress Report Details
• Weekly Progress overall S-Curve