Engineering Guide For Development July 2020
Engineering Guide For Development July 2020
Development- 2005
Amendment History
Amendment Date
February 2005
Original issue
June 2009
Plans A(BS)101M,106M,124M,131M,134S
November 2009
New clause 5.19 added – Road Names
December 2009
OSD map revised
December 2009
OSD in Appendix D relocated to Appendix B
February 2010
Pedestrian refuge guideline added to Append ix C
March 2010
Section 10.1 of Appendix D: list of programmes
September
New Clause (e) to positive covenants OSD
2010
October 2010
Path paving Policy updated
October 2010
New plan A(BS)M 152 added
Section 5.18 amended to include reference to Boom gates and Council Plan October 2010
A(BS)152M
Section 3.1 amended to reflect latest versions of acceptable design manuals October 2010
November 2012
Section 10.1 Appendix D list of program amended
November 2012
Pedestrian refuge policy deleted
November 2012
OSD map updated
November 2012
Various external reference manuals updated I.e. Austroad publications
November 2012
Standard Plan A(BS) 113M updated
November 2012
Standard Plan A(BS) 114M deleted
i
Blacktown City Council Engineering Guide for Development - 2005
Date
Amendment
June 2017
Certified stockpile definition (Glossary)
February 2018
Amended Appendix F standard recitals
October 2018
Amended 15. standard drawings A(BS) 113M standard street signs and post
June 2017
Certified stockpile definition (Glossary)
July 2020
Amended entries in Glossary – additions and changes to reflect industry updates
Section 1 General Procedures July 2020
1.3 Private Accredited Certifier amended to Accredited Certifier
1.4.A Deletion of Acceptance of Works Certificate – no longer issued by Council
1.6 Amend triplicate to duplicate
1.10 Tree Preservation – amendments made
1.14.3 $5,000 amended to $6,000 as per current goods and services schedule
1.17.5 Slope Junction amended to Inter-allotment Drainage
Section 2 Engineering Drawings
2.12 Kerb Return Cul-de-Sac, Splay Corner and Bend Details – amendments
made
2.16 Drainage Calculations – A1 amended to A3
2.18.6 Other Drainage Details – amendments made
2.21 Retaining Walls – amendments made
2.24 Adjoining Owners Permission – amendments made
2.25.2.3 Slope Junction Plan amended to Inter-allotment Drainage Plan
2.27 Addition of A3 plans
Section 3 Road Design
3.4 Community Title Roads & Private Access – addition
3.5 Turning Heads – addition
3.6 Utility Services – addition
3.7 Half Width Roads – amendments made
3.9 Pavement Design – amendments made
3.10 Pavement Surfacing – amendments made
ii
Blacktown City Council Engineering Guide for Development - 2005
iii
Blacktown City Council Engineering Guide for Development - 2005
Addition of Subdivision Works Certificate references throughout where applicable July 2020
July 2020
Amendment of Council branding and job titles throughout Guide
July 2020
Amend all references to DCP 1992 to DCP 2015
July 2020
Amend all references to Section 94 to Section 7.11
Appendix A: Cover Sheet July 2020
Vehicular crossing width at kerb and gutter – amended from 4.5m to 4m
Pit depth requiring step irons – amended from 1.2m to 0.9m
Reference to Occupational Health & Safety Act replaced by: Work Health and July 2020
Safety Act 2011
iv
Blacktown City Council Engineering Guide for Development - 2005
2005
FOREWORD
This Guide, and its accompanying document, Council's Work Specification - Civil, have been
prepared to provide engineering guidelines for the subdivision and development of land within
the Blacktown City Council area.
The aim of the Guide is to facilitate the efficient processing of engineering plan submissions,
and to ensure that infrastructure associated with any development is designed and constructed to
be safe, serviceable, economical to maintain and meets community expectations.
Applicants should be aware that each development is required to be treated on its merits, and
that approval is dependant on the overall impact of the development and not solely on compliance
with minimum engineering standards.
Nothing in this Guide is to be construed as limiting, in any way, Council's rights to impose
differing conditions when approving development proposals, nor limiting the discretion of
Council's Coordinator Engineering Approvals or his nominated representative to vary any
necessary engineering requirements in respect of a particular development, having regard to
good engineering practice.
Council wishes to acknowledge the assistance freely given by other Councils, Consultants and
Contractors who suggested matters that required updating, new processes and products that may
be adopted or provided assistance in this latest revision to ensure that this document represents
current "best practice".
v
Blacktown City Council Engineering Guide for Development - 2005
GLOSSARY
vi
Blacktown City Council Engineering Guide for Development - 2005
GLOSSARY continued
vii
Blacktown City Council Engineering Guide for Development - 2005
TABLE OF CONTENTS
SUMMARY
1. GENERAL PROCEDURES
2. ENGINEERING DRAWINGS
3. ROAD DESIGN
4. DRAINAGE DESIGN
5. MISCELLANEOUS REQUIREMENTS
6. APPENDICES
I. STANDARD DRAWINGS
viii
Blacktown City Council Engineering Guide for Development - 2005
TABLE OF CONTENTS
FOREWORD ..................................................................................................... i
GLOSSARY ....................................................................................................... ii
1 GENERAL PROCEDURES
1.1 Scope ........................................................................................................... 1 – 1
1.2 Aim .............................................................................................................. 1 – 1
1.3 Engineering Plans, Inspections & Accredited Certifiers ............................. 1 – 1
1.4 Overview of Engineering Process for the Applicant ................................... 1 – 2
1.5 Engineering Survey & Bench Marks ........................................................... 1 – 5
1.6 Engineering Drawings ................................................................................. 1 – 5
1.7 Persons Qualified ........................................................................................ 1 – 6
1.8 Consultation................................................................................................. 1 – 6
1.9 Inspection of Works .................................................................................... 1 – 6
1.10 Tree Preservation ......................................................................................... 1 – 7
1.11 Street Trees .................................................................................................. 1 – 8
1.12 Erosion & Sediment Control ....................................................................... 1 – 8
1.13 Road Safety Audit and WH&S Requirements ............................................ 1 – 8
1.14 Bonds ........................................................................................................... 1 – 8
1.15 Contributions/Monetary Payments .............................................................. 1 – 9
1.16 Works-As-Executed (WAE) Plans .............................................................. 1 – 10
1.17 Certificates and Inter-allotment Drainage Plans .......................................... 1 – 10
1.18 Written Consents ......................................................................................... 1 – 11
1.19 Street Lighting ............................................................................................. 1 – 11
2 ENGINEERING DRAWINGS
2.1 Scope ........................................................................................................... 2 – 1
2.2 Aim .............................................................................................................. 2 – 1
2.3 General Requirements ................................................................................. 2 – 1
2.4 Road & Drainage Drawings ........................................................................ 2 – 1
2.5 On-site Stormwater Detection Drawings..................................................... 2 – 2
2.6 Title Blocks ................................................................................................. 2 – 2
2.7 Title Sheet/Layout Plan ............................................................................... 2 – 2
2.8 Detail Plan ................................................................................................... 2 – 3
2.9 Road Long Section(s) .................................................................................. 2 – 4
ix
Blacktown City Council Engineering Guide for Development - 2005
3 ROAD DESIGN
3.1 Scope ........................................................................................................... 3 – 1
3.2 Aim .............................................................................................................. 3 – 1
3.3 Planning Standards ...................................................................................... 3 – 1
3.4 Community Title Roads & Private Access ................................................. 3 – 3
3.5 Half Width Roads ........................................................................................ 3 – 4
3.6 Construction Specification .......................................................................... 3 – 4
3.7 Pavement Design ......................................................................................... 3 – 4
3.8 Pavement Surfacing..................................................................................... 3 – 6
3.9 Geometric Design - General Principles (including designing for salinity) .......... 3 – 6
3.10 Design Speed ............................................................................................... 3 – 7
3.11 Sight Distance.............................................................................................. 3 – 8
3.12 Horizontal Alignment .................................................................................. 3 – 9
3.13 Transitions & Widening on Curves ............................................................. 3 – 9
3.14 Longitudinal Gradient ................................................................................. 3 – 9
3.15 Vertical Curves ............................................................................................ 3 – 10
3.16 Super-Elevation ........................................................................................... 3 – 11
3.17 Carriageway Crossfall ................................................................................. 3 – 11
3.18 Kerb & Gutter .............................................................................................. 3 – 11
3.19 Full Width Path Paving ............................................................................... 3 – 12
ix
Blacktown City Council Engineering Guide for Development - 2005
4 DRAINAGE DESIGN
5 MISCELLANEOUS REQURIEMENTS
x
Blacktown City Council Engineering Guide for Development - 2005
6 APPENDICES
A. Checklist for Engineering Plans A–1
B. On-site Detention General Guidelines & Checklist B–1
C. Councils Policies and Guidelines C–1
• Path paving policy
• Pedestrian Refuge Guideline
D. Drainage Design Manual D–1
E. Bond Documents, Format & Instructions E–1
F. Standard Recital for Terms of Easements, Covenants & Restrictions F–1
G. Example of a Lot Fill Plan G–1
H. Example Easement Certificate H–1
I. Standard Drawings I–1
xi
Blacktown City Council Engineering Guide for Development - 2005
1. GENERAL PROCEDURES
1.1 Scope
This section of the Engineering Guide sets out Council's general procedures
and practices in respect of engineering requirements for subdivision and
development of land within the Council area.
1.2 Aim
To provide an Applicant with an outline of Council's engineering procedures
for subdivisions and developments.
1.3 Engineering Plans, Inspections & Registered Certifiers
In this Guide, whenever the term "Engineering Plan" is used, this is deemed to
also be a reference to engineering plans associated with C o n s t r u c t i o n
C e r t i f i c a t e s o r Subdivision Works Certificates issued by Council or
Registered Certifiers under the EP&A Act 1979, and Engineering Approvals
issued by Council under the Roads Act 1993 and Local Government Act 1993.
Registered Certifiers may issue Subdivision Works Certificates for subdivision
and development works in accordance with the requirements of the EP&A Act
1979. Any reference made in this Guide to approvals or inspections by
Council’s Engineers or Development Inspectors for works under the EP&A Act
1979 shall also be deemed to be a reference to certificates issued and inspections
carried out by Registered Certifiers under the EP&A Act 1979.
Note: Compliance Certificates may be issued by Certifiers only with the prior
written agreement of Council.
Registered Certifiers do not have any authority to issue Engineering Approvals
or carry out inspections for works on Public Roads under the Roads Act 1993.
It should also be noted that Subdivision Works Certificates cannot be
issued for works on sites that are not part of the "subject land" for which
the Development Consent has been issued.
An example is interallotment drainage through adjacent lots that are not
included in the "subject land". In this case, a separate Section 68 Local
Government Act 1993 Approval would be required for the drainage works. This
form of approval can only be issued by Council.
Registered Certifiers have no authority to vary the requirements of this Guide.
They must comply with all of the Guide’s requirements prior to issuing any
Subdivision Works or Compliance Certificates under the EP&A Act 1979.
1-1
Blacktown City Council Engineering Guide for Development - 2005
1-2
Blacktown City Council Engineering Guide for Development - 2005
1-3
Blacktown City Council Engineering Guide for Development - 2005
M. Final inspection:
When all the defects, identified in the Preliminary Final Inspection, are
rectified the Applicant shall request a Final Inspection. Council's
Engineer/Development Inspector will re-inspect the work to confirm
that all the defects have been rectified.
1-4
Blacktown City Council Engineering Guide for Development - 2005
1-5
Blacktown City Council Engineering Guide for Development - 2005
1-6
Blacktown City Council Engineering Guide for Development - 2005
1-7
Blacktown City Council Engineering Guide for Development - 2005
1-8
Blacktown City Council Engineering Guide for Development - 2005
Path Paving
Path paving construction in accordance with Council's Path Paving
Policy (see Appendix "C") shall be deferred for a period following
practical completion of the road works.
Two options are available to the Applicant:-
* Bond the Works, by lodging an appropriate security with a Deed
of Agreement.
* Monetary Payment, where Council will use the monies for
construction of paths at a later, appropriate time.
Maintenance
Prior to the issue of a Subdivision Certificate (for subdivisions) or at
practical completion of works (for other developments), a Bank
Guarantee or Cash Security, to the amount of 5% (with a minimum
amount of $6,000) of the value of the whole of the works to be
constructed, must be lodged with Council. This is to provide for the
satisfactory performance of works and the replacement of any failed or
unsatisfactory work and any repairs required, inclusive of the
maintenance of any traffic control facilities.
The bond will be held by the Council for a period of at least 12 months
from the date of issue of the Subdivision Certificate/release of the Plan
of Subdivision or the date of completion of the works, whichever is the
latter. During this time the Applicant is responsible for maintenance of
the works. Any failure on his behalf may lead to call-up of all or part of
the security to enable remedial works to be undertaken by Council.
1.15 Contributions/Monetary Payments
Contributions and/or monetary payments for certain outstanding items must be
lodged prior to the issue of the Subdivision Certificate, or upon practical
completion of ½ width road works associated with developments as detailed in
the Consent.
A.C. Sealing
Subdividers are required to lodge a cash payment to cover the cost of the
final 25mm layer of Asphaltic Concrete (A.C.) following installation of
services by the various authorities. Such payment is assessed by Council
after submission of Work-As-Executed plans and is based on
Council's current construction rates.
Street Trees
A cash contribution in accordance with Section 7.11 (EP&A Act)
Contributions Plan No.10 is required in respect of each new lot towards
Council's provision of street trees at a suitable time in the development
of the area.
1-9
Blacktown City Council Engineering Guide for Development - 2005
Path Paving
As detailed in Council's Path Paving Policy (Appendix C), a cash
contribution may be lodged as an alternative to the bonding of these
works.
1.16 Works-As-Executed (WAE) Plans
Following the completion of engineering works of a subdivision or
development, a "Work-As-Executed" plan is required to be prepared by a
Registered Surveyor or "Persons Qualified" (See Section 1.7) and forwarded to
Council prior to the final inspection.
The WAE plans must show the matters listed below and as detailed in Section
2.25 - Engineering Drawings, of this Guide:
* all works have been completed generally in accordance with
the approved plans and specification,
* any departure from the approved plans,
* any additional/deleted work,
* the location of conduits, subsoil lines, stub mains and
interallotment drainage lines,
* pipeline long sections showing the constructed invert levels of
each pipe at each pit and pipe dimensions,
* details of overland flow provisions,
* site regrading areas by new contours, and
* all other details which have a bearing on the extent of works
and their acceptance by Council.
1.17 Certificates and Interallotment Drainage Plans
Prior to issue of a Subdivision Certificate, Occupation Certificate or upon
completion of works, the following Certificates and Plans must be lodged:
Compaction Certificates
The final submission requires lodgement of the road pavement
compaction certificates for all stages of the road pavement construction,
lot filling and lot classification which have been prepared
by a N.A.T.A. laboratory.
A lot fill diagram, an example of which can be found in Appendix "G",
must be provided where lots have been filled. The diagram will apply
to all lots that have been filled in excess of 250mm.
1 - 10
Blacktown City Council Engineering Guide for Development - 2005
Easement Certificates
The final submission requires lodgement of the Surveyor's Certificate in
the form shown in Appendix "H" of this Guide. This is to certify that
all pipes and drainage structures are located within the proposed
drainage easements.
Material Compliance Certificates
Material Compliance Certificates for all road pavement materials will
be required to be submitted prior to issue of the Subdivision Certificate
or upon completion of the works.
Engineer's Certificate
Where structural work has been undertaken on a project a certificate
from a Registered Engineer must be lodged certifying the adequacy of
the structure for the imposed loads.
For OSD systems, a Hydraulic Certificate from "Persons Qualified"
(See Section 1.7) shall be lodged with Council certifying that the system
will function hydraulically as per design requirements.
Interallotment Drainage Plan
A plan indicating location and depth of all interallotment drainage pits
shall be prepared by the project engineer/surveyor and submitted to
Council.
1.18 Written Consents
Where work has been carried out on adjoining properties, or a claim made
by an affected property owner, a written clearance that all outstanding claims
have been met, must be lodged with the final document submission.
1.19 Street Lighting
General
Council requires all new lighting levels to be in accordance with AS/NZ
1158 in its various parts and to comply with all the requirements of
Integral Energy's document "General terms and
Conditions for the Connection of Public Lighting Assets".
Arterial and Sub-Arterial Roads
The lighting of arterial and sub-arterial (Traffic Route Lighting) roads
must comply with AS/NZS 1158.Part1.1 – Vehicular Traffic (Category
V) Lighting – Performance and Installation Design Requirements 2005,
using the appropriate lighting categories.
1 - 11
Blacktown City Council Engineering Guide for Development - 2005
1 - 12
Blacktown City Council Engineering Guide for Development - 2005
1 - 13
Blacktown City Council Engineering Guide for Development - 2005
2. ENGINEERING DRAWINGS
2.1 Scope
This section of the Engineering Guide sets out Council's general requirements
for the preparation of Engineering Drawings.
2.2 Aim
To provide comprehensive details to facilitate the assessment of plans and
construction of works in a safe, efficient and effective manner.
Also to ensure that Engineering Drawings provide sufficient information in a
consistent format to allow Council to maintain a permanent record of
subdivision and development works.
2.3 General Requirements
All engineering drawings are to ensure that all relevant conditions of consent
have been addressed by the details shown.
2.4 Road and Drainage Drawings
Plans for Road and Drainage works shall be presented to Council generally in
the following format:
* Title Sheet,
* Detail Plan(s),
* Road Longitudinal Section(s),
* Road Cross Sections,
* Typical Road Cross Section(s),
* Kerb Return Details,
* Traffic Calming Devices, Pathways and Other Miscellaneous
Road Details,
* Permanent Traffic Warning and Regulatory Details (i.e.
Linemarking, Stop/Give Way Signs, Curve Signs etc.)
* Drainage Catchment Plan,
* Drainage Calculations,
* Drainage Longitudinal Section(s),
* Other Drainage Details,
* Erosion and Sediment Control Measures, and
* Traffic Control Measures
2-1
Blacktown City Council Engineering Guide for Development - 2005
2-2
Blacktown City Council Engineering Guide for Development - 2005
For small developments, where all of these details can be shown on the detail
plan, the layout plan may be omitted.
The title sheet should also include construction notes and an index of the sheets
provided in the set of drawings.
Council's File number shall be shown in letters 25mm high in the top right
corner of the sheet, e.g., CC-04-1000.
2.8 Detail Plan
Detail plans should include the following:
* Scale 1:500 or 1:200 for small sites (with Scale Bar),
* North point,
* Lot details including boundaries, numbers, easements and any road
widenings,
* Existing contours (at least two across each lot) extending beyond the
boundary of the site for a distance sufficient to show any constraints,
with a minimum distance of 10 metres,
* Existing natural features including: native vegetation, trees, ditches,
dams, mounds, creeks, etc. These details are not to be limited to the
proposed subdivision but shall include any features which have an
impact on the development,
* Existing constructed features including: fences, kerb and gutter, pipes,
pits, road pavements, buildings, road furniture, adjacent subdivisions,
etc. These details are not to be limited to the site and are to include
any feature which has an impact on the Development,
* Existing services: sewer, water, telephone, gas mains, electricity, etc.,
including all associated pits, poles and other structures, must be shown
on plan and plotted on Longitudinal Sections,
* Road centrelines showing chainages, bearings and intersection points,
* Extent of proposed works (using shading to aid in clarity) including:
- road names,
- carriageway and footway widths,
- chainages,
- tangent points,
- kerb type,
- path paving, cycleways, pram ramps,
- berms,
- batters,
- cut and fill areas clearly indicated by shading, clearly
identifying depths
2-3
Blacktown City Council Engineering Guide for Development - 2005
2-4
Blacktown City Council Engineering Guide for Development - 2005
2-5
Blacktown City Council Engineering Guide for Development - 2005
2-6
Blacktown City Council Engineering Guide for Development - 2005
2-7
Blacktown City Council Engineering Guide for Development - 2005
2-8
Blacktown City Council Engineering Guide for Development - 2005
• lead in,
• pipeline junctions, and
• details of utility services to be shown along with the level
where they cross pipelines.
Longitudinal sections shall be designed for interallotment drainage lines. Where
more than 5 lots shall be served, a hydraulic analysis is required to ensure lots
are not affected by surcharge.
2-9
Blacktown City Council Engineering Guide for Development - 2005
2 - 10
Blacktown City Council Engineering Guide for Development - 2005
Site Developments
For site developments, e.g., medium density development, an overland
flowpath shall be provided through the site to cater for the 100 year ARI
event flows from the upstream catchment. These flows must be safely
conveyed through the site to Council's road and/or drainage system.
Restrictions/Positive Covenants
Restrictions and positive covenants shall be provided over all
constructed overland flowpaths. The wording shall be in accordance
with Appendix F "Standard Recital for Terms of Easements, Covenants
and Restrictions" of this Guide.
2.21 Retaining Walls
Retaining walls adjacent to roads, pathways, public reserves as well as between
private lot boundaries shall be constructed in reinforced concrete or masonry
with an attractive finish. They shall not be constructed from any timber
products.
The Applicant must provide full engineering details of the proposed structure,
including elevation, typical cross-section and structural certification.
The design of the retaining wall must be prepared by a Registered Engineer.
A certificate of structural adequacy from a Registered Engineer for the finished
product shall also be submitted to Council on completion of the works.
2.22 Erosion and Sediment Control Measures
A plan prepared in accordance with the requirements of Section 5.165 shall be
provided showing relevant site characteristics and design criteria of erosion and
sediment controls and should include but not be limited to the following:
* Existing and design contours,
* Existing site drainage and vegetation,
* Limit of clearing, grading and filling,
* Grades/Slopes of site,
* Critical natural areas (natural watercourses, swamps, cliffs, etc.),
* Location of topsoil stockpiles, roads and all impervious surfaces,
* Distance to nearest natural watercourse or drainage line,
* Catchment area boundaries,
* Sediment basin calculations,
* Erosion and sediment controls, including diversions,
* Construction/Revegetation notes, and
* Outline of program for maintenance of erosion and sediment controls.
2 - 11
Blacktown City Council Engineering Guide for Development - 2005
2 - 12
Blacktown City Council Engineering Guide for Development - 2005
Minor ancillary works are considered to be works that tie the design levels back
to existing levels on adjoining land. Typically this would be a maximum of 0.5m
of cut/fill and batters at 1:5 and works not extending beyond 3mts from the
property boundary.
Where the extent of works on the adjoining land is considered by council to be
more than minor, then the development application must include all affected
property as part of the application. It may also be necessary to obtain
appropriate easements over such works. E.g. Easements for access, support,
drainage etc.
2.25 Works-As-Executed Plans (WAE) for Engineering Works
General
(a) In order to have a permanent record of construction which
incorporates amendments completed site regarding, etc. Works-
As-Executed Plans shall be lodged for Council’s records, with
W.A.E. figures (where there is a variation from the design)
shown boxed, in red colour, on plan and longitudinal sections.
(b) Works-As-Executed Plans must be submitted to Council prior
to final inspection by the Development Inspector.
(c) Subdivision Certificate (Plan of Subdivision) will not be
processed until the Works-As-Executed Plans have been
received and verified.
(d) The Works-As-Executed Plans must be certified by a Registered
Surveyor or Engineer responsible for the preparation of the
Works-As-Executed Plan.
(e) The Surveyor responsible for the Plan of Subdivision, or where
easements are registered, covering the subdivision /
development, shall supply a signed certificate stating that all
pipes and associated structures are located wholly within the
respective easements (see Appendix “H” for example of
Easement Certificate).
(f) The following certificate shall be appended to each sheet of the
plans and signed by the Registered Surveyor or Engineer:
“I hereby certify that engineering works shown on this plan have
been constructed in accordance with Construction Certificate /
or Subdivision Works Certificate issued by ……. OR the plans
and specification approved by Blacktown City Council.”
Name …………………………..
Signature ………………………
Capacity ……………………….
Date ………………………….…
2 - 13
Blacktown City Council Engineering Guide for Development - 2005
Information To Be Shown
2.25.2.1 Kerb & Gutter
(i) Footway widths, gutter invert/nominal kerb line to
property boundary.
(ii) All T.P.’s.
(iii) Centre of curves.
(iv) Beginning and end of construction.
(v) Intermediate points on long straights no more that
100m intervals, where variation exceeds 10% from
the approved width.
2.25.2.2 Gutter invert levels
(i) All T.P.’s.
(ii) Crest Points.
(iii) Sag Points.
(iv) End of straight grades.
(v) As required on flat grades.
(vi) Location of all Vehicular Crossings to be shown.
2 - 14
Blacktown City Council Engineering Guide for Development - 2005
2 - 15
Blacktown City Council Engineering Guide for Development - 2005
2.27 Scales
The following scales shall be used for the following plans and sections, unless
varied by the Coordinator:
* Engineering Detail Plan 1:1000, 1:500 or 1:200,
* Road Longitudinal Section 1:100 (vertical) to 1:500 (horizontal),
* Road Cross Section 1:100 Natural or 1:100 (vertical) to
1:200 (horizontal),
* Intersection Details 1:250, 1:200 or 1:100,
* Layout Plan 1:500, 1:1000, 1:2000 or 1:4000,*
Catchment Plan 1:500, 1:1000, 1:2000 or 1:4000 (for
external catchment),
* Locality Plan 1:500, 1:1000, 1:2000 or 1:4000,
* Kerb Return Plan 1:200,
* Kerb Return Longitudinal 1:100 (vertical) to 1:200
Section (horizontal), and
* Details 1:10, 1:20, 1:50 or 1:100 as required.
2.28 Dimensions
Linear dimensions on all engineering plans shall be in metres, with the
exception of detail plans which may be in millimetres. Methods of
dimensioning will be in accordance with the current Australian Standard.
Chainage shall be expressed to the nearest 0.01m, levels shall be reduced to
Australian Height Datum (AHD) and expressed to the nearest 0.005m (except
Bench Marks, PM’s and SSM’s which will be expressed to the nearest 0.001m).
2 - 16
Blacktown City Council Engineering Guide for Development - 2005
3. ROAD DESIGN
3.1 Scope
This section of the manual sets out Council’s requirements for the design of
urban and rural roads. It is in no way a comprehensive design manual and it is
intended to be read in conjunction with and as a supplement to:
* AUSTROADS (2020) – Guide to Traffic Management
* AUSTROADS (2020) – Guide to Road Design- suite of design
manuals- as amended
* AUSTROADS (2019) – Guide to Pavement Technology – Part 2
Pavement structural Design
* ARRB, Transport Research (2005) Sealed Local Roads Manual –
Guidelines to Good Practice for the Construction, Maintenance and
Rehabilitation of Pavements and
* Council’s relevant Development Control Plans.
3.2 Aim
The design and construction of a road system that provides the following:
* a high level of safety for all users,
* acceptable levels of amenity and protection from the impact of traffic,
* a reasonable level of convenience for all users, and
* economy of construction and maintenance.
3.3 Planning Standards
The road hierarchy has been developed to cater for various functions that need
to be performed by roads within Council’s road network. The road hierarchy
and relevant road widths are listed in Table 3.1 a n d 3 . 3 of this Guide
and are also embodied in Council’s Blacktown Development Control Plan 2015
(Part A).
New road layouts and widths must conform to that shown in Table 3.1 and 3.3
and any other relevant Development Control Plans. The precise location of any
proposed roads are subject to the detailed site assessment carried out during
the subdivision application process. In areas not covered by a Development
Control Plan the layout and width will be determined by Council on their
merits.
Kerb return and cul-de-sac details are contained within Section 2.12 of this
guide.
3-1
Blacktown City Council Engineering Guide for Development - 2005
3-2
Blacktown City Council Engineering Guide for Development - 2005
3-3
Blacktown City Council Engineering Guide for Development - 2005
Utility Services
Utility Services for lots served by the community road should be located within
the footway area and not under rigid pavements. The arrangement for the
installation and provision of services shall be generally in accordance with the
requirements of this guide and the relevant utility provider.
3.5 Half Width Roads
Council does not encourage the construction of half width roads, however in
certain circumstances this may be permitted. A minimum 4.5m width pavement
must be fully constructed.
Where half widths roads are approved, the applicant is required to provide
sufficient details regarding the extent of works to ensure operational
effectiveness and safety. This will involve a full design together with sufficient
details to ensure adequate transitions to the standard road pavements inclusive
of full width cross sections.
Where there are level differences between the design levels and adjoining land
they should transition with batters. Council will not permit retaining structures
within the road reserve. Council will require written consent from adjoining
owners for minor works, refer section 2.24.
Where there are significant level differences and/or retaining walls are
proposed, suitable safety barriers and or fencing must be shown on the plans.
Any such barriers should not reduce the trafficable lane width. A road safety
audit must be submitted with the application and the recommendations of the
audit incorporated into the design.
3.6 Construction Specification
Council's Works Specification - Civil complements this Guide and shall be
referred to for all construction details.
3.7 Pavement Design
A preliminary pavement design shall be prepared by a suitably qualified NER
engineer. A preliminary design may be based on an assumed California
Bearing Ratio (CBR) value not greater than 3.
A final pavement design shall be prepared by a Geotechnical Engineer and/or
registered N.A.T.A. laboratory based on a suitable site investigation. This
investigation shall include logging of test holes to a depth of not less than 1m
below subgrade (unless rock is encountered). Samples of material for testing
shall be taken from the site along the proposed road alignment at the design
subgrade level.
Details of the pavement design, together with results of subgrade testing
(including 4 day soaked CBR's) are to be submitted to and approved by Council
prior to commencement of pavement construction.
Note: Notwithstanding the above testing requirements, a maximum CBR value
of 7 shall be used for the pavement design.
3-4
Blacktown City Council Engineering Guide for Development - 2005
The design shall be based on Traffic Loading Criteria specified in the Consent
for the proposed works, which is based on the Design Traffic Loadings shown
in Table 3.3.
The structural design of the pavement must be in accordance with the following
procedures and shall have a confidence factor of 95%:-
(i) For N values equal to or less than 5x105 ESA
* Pavements should be designed using the general principals of
Austroads (2019) “Guide to Pavement Technology – Part 2
Pavement Structural Design ” – chapter 12
* Asphaltic concrete pavements shall have two layers of AC10
totaling a minimum thickness of 50mm.
(ii) For N Values greater than 5x105 ESA
* Pavements should be designed using the general principles of
Austroads (2019) “Guide to Pavement Technology – Part 2
Pavement Structural Design ”,
* It is anticipated that the pavement shall contain at least one
bound layer of either asphaltic concrete or portland cement
concrete, and
* Asphaltic concrete pavements shall have two layers of AC10
totalling a minimum thickness of 50mm.
(iii) Alternate Designs
* Alternate designs may be submitted accompanied by supporting
evidence from a geotechnical engineer as to the bearing capacity
of the subgrade and the structural adequacy of the
proposed pavement
(iv) Private
Community Title roads shall be constructed using rigid pavements. The
initial 5m of these roads shall be constructed using:
(a) Contrasting coloured concrete with arrows and a dividing line
incorporated in a complimentary colour scheme, or
(b) paving bricks laid on a reinforced concrete base with similar
contrasting signage as above to A(BS)112M.
(v) Minimum Pavement Thickness
In all cases of flexible pavement design the minimum pavement
thickness allowed shall be 300mm, excluding the thickness of the final
wearing course.
(vi) Use of Hawkesbury Sandstone in Industrial Roads
Sandstone shall not be used in pavements for Industrial Roads unless it
has been augmented by a process approved by Council.
3-5
Blacktown City Council Engineering Guide for Development - 2005
INDUSTRIAL
* Collector & - 1 x 107 150mm kerb & gutter
Heavy Duty
* Light Duty - 5 x 106 150mm kerb & gutter
RESIDENTIAL
*Major Collector 4,000 - 10,000 1 x 106 150mm kerb & gutter
* Minor Collector 2,000 - 4,000 5 x 105 150mm kerb & gutter
* Local Street 500 - 2,000 5 x 105 Roll top kerb & gutter
* Cul-de-sac 0 - 500 5 x 104 Roll top kerb & gutter
* Access Street 0 - 500 5 x 104 Roll top kerb & gutter
*Private/
Community Title 0 - 500 5 x 104 Mountable/Rigid Pavement
Roads
Note #:Kerb types to conform with Council's standard (refer Council Plan A(BS)101M)
3.8 Pavement Surfacing
All roads shall be surfaced with an initial course of 25mm thickness AC10.
The final wearing course of 25mm thickness of AC10 will be laid by Council
at a later date and paid for by the Applicant as a monetary payment. (This does
not apply to roundabouts.)
Roundabouts shall have an AC wearing course thickness of a m i n i m u m
75mm of SBS Polymer Modified AC14. The full 75mm thickness shall be
constructed by the Applicant at one time and shall extend on each leg a
minimum of 10m or to the end of the splitter islands (including linemarked)
whichever is the greater.
3.9 Geometric Design - General Principles (including designing for salinity)
Principles which are to be adopted in the engineering design are:-
(a) The assessment of geometric design in release areas must consider the
Indicative Layout Plan (ILP) road pattern as set out in the Growth
Centres DCP in particular for future roads in the vicinity of the site. In
particular sight distance and horizontal geometry.
(b) Carriage ways are to provide a smooth, safe trafficable alignment and
surface. The use of dish crossings is to be avoided.
3-6
Blacktown City Council Engineering Guide for Development - 2005
3-7
Blacktown City Council Engineering Guide for Development - 2005
3-8
Blacktown City Council Engineering Guide for Development - 2005
3-9
Blacktown City Council Engineering Guide for Development - 2005
Every effort should be made to provide vertical curves as long as possible for
improved appearance, however, surface drainage should be maintained in
proximity to sag points. The design of vertical curves shall be in accordance
with the Austroads (2020) “Guide to Road Design” and the following:
* A minimum design speed of 60 km/h shall be adopted even if the
horizontal alignment is not satisfactory for that speed,
* The minimum length of a sag vertical curve is that governed by sight
distance requirements,
* The desirable minimum length of a sag vertical curve is that providing
minimum headlight sight distance and this length should be provided
wherever possible,
* The absolute minimum length of a sag vertical curve is based on the
consideration of riding comfort and shall be such that the maximum
vertical acceleration is 0.1G, and
* In addition to the minimum length requirements mentioned above, from
a consideration of appearance the minimum length of a vertical curve
in urban areas shall not be less than that shown in Table 3.8.
3 - 10
Blacktown City Council Engineering Guide for Development - 2005
3 - 11
Blacktown City Council Engineering Guide for Development - 2005
3 - 12
Blacktown City Council Engineering Guide for Development - 2005
3.22 Batters
Batters shall be designed at stable slopes at the edge of the berm in accordance
with table 3.10.
Table 3.10 - Maximum Batter Slopes
Desirable Maximum Absolute Maximum
Batter Type
Slope (V:H) Slope (V:H)
Earth 1:5 1:4
Rock 1:0.5 1:0.25
The abovementioned slopes for rock batters refer only to cut batters in solid
rock with few clay bands.
Where the abovementioned slopes cannot be reasonably attained, variances
may be permitted subject to approval being obtained from the Coordinator.
The need for constructing retaining walls should be avoided wherever possible.
Should a retaining wall be necessary the Applicant must provide full
engineering details of the proposed structure, including elevation, typical cross-
section and structural certification by a Registered Engineer. Refer to Section
2.21.
3.23 Intersections
The design of intersections or junctions shall be in accordance with
AUSTROADS - Guide to Traffic Management (2020), Austroads (2020)
“Guide to Road Design”, various parts and/or the requirements of Councils
Coordinator Engineering Approvals.
Intersections should generally be located so that streets intersect at right angles
and at not less than 70°. Adequate stopping and sight distances should be
provided on each of the approach legs of an intersection and for any horizontal
or vertical curves.
Turning movements shall be accommodated by using AUSTROADS Design
Vehicles and Turning Templates as follows:
* For turning movements involving collector streets, the "design semi-
trailer" with turning path radius 12.5 metres shall be used to enable
turns to be made in a single forward movement,
* For turning movements involving local streets and collector streets, the
"design single unit" truck with turning path radius 12.0 metres shall be
used to enable turns to be made in a single forward movement, and
* For turning movements on access streets and cul-de-sac, the "design car"
with turning path radius 7.5 metres shall be used.
3 - 13
Blacktown City Council Engineering Guide for Development - 2005
3 - 14
Blacktown City Council Engineering Guide for Development - 2005
line. The locations of easements or pathways may not be flexible and regrading
may be necessary to ensure safe overland flow.
3.26 Roundabouts
The design of roundabouts shall be in accordance with AUSTROADS - Guide
to Traffic Engineering Practice, Part 6, Roundabouts and AUSTROADS- Guide
to Road Design Part 4B: Roundabouts shall be approved by the Council and/or
the Roads and Maritime Services.
3.27 Temporary Turning Heads
A temporary turning head will be required for all dead end roads.
On part road construction the turning head shall be offset to meet the above
criteria. This will usually require an appropriate temporary easement over the
affected lot(s).
The turning heads must provide for the safe movement for vehicular and
pedestrian traffic. The design of the turning heads shall include but not limited
to the following requirements:
• turning area radius shall be a minimum of 9.0m.
• The location of the turning head must be clear of drainage pits, light
poles, street signs or similar obstructions.
• The pavement beyond the formed section of road shall be a minimum
150mm of compacted DGB on a compacted subgrade with a minimum
25mm layer of asphalt.
• All signage and linemarking necessary, including parking restrictions,
to indicate the traffic conditions and ensure the safe operation of the
turning area.
• Appropriate traffic barriers shall be installed adjacent to batters steeper
than 1V in 5H. Such barriers shall be a minimum 300mm clear of the
required turning area.
• Details for all necessary works for the removal the temporary facility
and restoration to provide the permanent road formation.
Council may require higher or additional requirements to the above subject to
consideration of the nature and volume of traffic anticipated and expected
timeframe for the use of the turning head.
3.28 Traffic Calming Devices
The design of traffic calming devices shall be in accordance with
AUSTROADS - Guide to Traffic Management, Part 8, Local Area Traffic
Management and shall be approved by Council.
3 - 15
Blacktown City Council Engineering Guide for Development - 2005
4. DRAINAGE DESIGN
4.1 Scope
This section of the Guide sets out Council's requirements for the design of
stormwater drainage for urban and rural areas. It is in no way a comprehensive
design manual and it is intended to be read in conjunction with, and as a
supplement to, the 1998 edition of Australian Rainfall and Run- off 1998
(AR&R).
4.2 Aim
The design and construction of a drainage system that provides the following:
* a high level of safety for all users,
* acceptable levels of amenity and protection from the impact of flooding,
and
* economy of construction and maintenance.
4.3 General Requirements
All drainage, whether internal or external to the site, relevant or reasonably
required in respect of the proposed development shall be provided to Council's
requirements at the Applicant's cost.
Pipe infrastructure to be dedicated to Council shall have a minimum cover of
600mm.
Detailed drainage investigation and designs shall be undertaken by an
experienced designer and submitted in accordance with Council's Drainage
Design Manual - Appendix "D" and general provisions of Australian Rainfall
and Runoff - 1998.
4.4 Trunk Drainage Designs
Trunk drainage designs have been prepared for most major drainage systems
within the City and are available, for reference, at Council's Civic Centre.
Applicants must ensure compatibility of their proposal with the Trunk Drainage
Designs.
4.5 Extent of Works
Engineering plans are required to define the extent of works, clearly delineating
all inlet and outlet works, both on adjoining private or public lands. Applicants
shall undertake detailed field checks of existing drainage facilities to which a
connection is proposed.
4–1
Blacktown City Council Engineering Guide for Development - 2005
4–2
Blacktown City Council Engineering Guide for Development - 2005
4–3
Blacktown City Council Engineering Guide for Development - 2005
4–4
Blacktown City Council Engineering Guide for Development - 2005
Special Requirements
In addition to the requirements of the WSUD Drawings, temporary basins shall
meet the following criteria:
• All diversion and blocking structures shall be designed and constructed
to withstand the hydraulic loads of the system.
• Maximum retaining wall height of 2.4m and
• Walls and top of batters shall be located a minimum of 1m from the
adjoining lot boundary and/or road reserve.
• Maximum internal batters of 1V:3H
• Minimum 1.8m high chain wire or similar perimeter fence and
Lockable gates.
• Suitable access for maintenance including ramps for vehicles with all-
weather surface, minimum 4m (ABS175M) wide and a maximum grade
of 1V:5H.
Decommissioning Temporary Basins
The decommissioning of temporary basins will usually require a Roads
Act Approval together with a subdivision works certificate (SWC). A
new SWC may not be required if the full detail of the decommissioning
works was shown on the original SWC.
The decommissioning works shall ensure that all public and private land
affected by temporary works is rehabilitated to a state that will not cause
adverse effects to council’s infrastructure or the current and future
owners of the land.
Prior to decommissioning of any temporary infrastructure, written
approval must be obtained from Council. Approval will not be given
until all the following criteria have been satisfied:
a) the regional basin is operational, and
b) an appropriate water quality system is available within the
regional basin, and
c) there is a legal and contiguous stormwater connection, capable of
appropriately and safely conveying stormwater from the site to the
regional facility for all flows up to and including the 100 year
ARI.
The civil engineering and earthworks associated with the
decommissioning shall be undertaken in accordance with the
requirements of this Guide and Council’s Civil Works Specification.
In particular:
• All blockages and diversions in pits and pipes shall be removed
and/or reinstated as necessary.
4–5
Blacktown City Council Engineering Guide for Development - 2005
4–6
Blacktown City Council Engineering Guide for Development - 2005
5. MISCELLANEOUS REQUIREMENTS
5.1 Scope
This section of the engineering guidelines provides miscellaneous engineering
requirements not covered in the previous sections.
5.2 Aim
To provide the Applicant with an understanding of other Council engineering
requirements that may be required in the development of land.
5.3 Kerbs, Laybacks and Kerb Ramps
Kerb and gutter shall be constructed along all new roads and existing roads to
which the development has frontage and access.
Kerb type (i.e. 150mm barrier or roll type) is dependant on road classification,
and shall be in accordance with that shown in table 3.3. Note Only barrier kerb
is permitted adjacent to public or drainage reserves.
Where an Access Street connects into the head of a cul-de-sac, the height of
the cul-de-sac kerb may be reduced by 50mm to facilitate vehicular movement
into the Access Street.
Laybacks in 150mm barrier kerb should generally be provided to the low side
of each allotment, 1m from the side boundary prolongation. Provision must be
made for disposal of stormwater from each high-side lot into the kerb. For
details see Standard Drawing A(BS)101M.
Kerb ramps shall be provided at all intersections, whether path paving will be
constructed to that intersection or not. The position and layout of the kerb
ramp shall conform to that shown on standard drawing A(BS)104M "Path
Paving at Intersections and Kerb Ramp Details".
5.4 Path Paving
Council requires that the footways be cleared and graded to a crossfall of 4%
and provided with concrete path paving 1.5m wide in Growth Centres and 1.2m
wide in other areas. Paving shall be minimum 75mm thick, except at crossings
and where adjacent to Roll Top Kerb, where the thickness shall be increased
to 125mm. The path paving shall be constructed in accordance with Council's
Path Paving Policy (See Appendix "C" of this Guide). Within the Growth
Centres, the pathway location, width and type shall be in accordance with the
relevant DCP for the area.
Council requires that path paving construction be delayed until building
operations have been substantially completed to minimise damage to the path.
For residential lots this requires a minimum of 75% of dwellings to be
completed. Accordingly the paths to be bonded or alternatively a cash payment
be lodged with Council. A copy of the Bond Proforma is included at Appendix
"E" of this Guide.
5–1
Blacktown City Council Engineering Guide for Development - 2005
5–2
Blacktown City Council Engineering Guide for Development - 2005
5–3
Blacktown City Council Engineering Guide for Development - 2005
5–4
Blacktown City Council Engineering Guide for Development - 2005
5–5
Blacktown City Council Engineering Guide for Development - 2005
specific soil and water management plans for each development site.
These plans will outline staging of works, sediment and erosion control
measures, rehabilitation strategies and other processes/works to be
implemented to address the above concerns.
Designs/Plans
Preparation of Soil and Water Management Plans shall be in accordance
with Council's Works Specification - Civil (Section 3), this Guide and
relevant requirements and recommendations of the NSW Department of
Environment and Conservation (DEC). For works and control measures not
covered by Council's Guide or Works Specification - Civil, the Applicant
may follow the DEC’s "Managing Urban Stormwater - Urban Design"
guidelines, or Landcom's "Managing Urban Stormwater - Soil Sand
Construction - Volume 1" 4th Edition (2004).
Disturbance of Sites
Sites must only be disturbed where it is essential for the installation of
infrastructure.
All disturbed areas shall have ground cover re-established by topsoil
placement and sowing with an approved grass seed mix, as soon as
practical upon completion of the road works.
All steps must be taken to prevent, as far as possible, the creation of a dust
nuisance. The Applicant must provide appropriate water carts, with spray
apparatus, to keep the soil moist at all times during construction.
Implementation of Soil and Water Management Plan
Measures outlined in the Soil and Water Management Plan must be
implemented prior to, and maintained during and after the construction
works, in accordance with the requirements of Section 3, Council's Works
Specification - Civil.
5.16 Landscaping of Roundabouts and Median Strips
Description
The need for appropriate landscaping of civil infrastructure works on large
collector roads should be considered to enhance the appearance of public areas and
thoroughfares. The Applicant shall submit details of any proposed landscaping of
roundabouts and median strips for the consideration to Council with the
Development Application.
Design Requirements
(i) In proposing the landscaping of civil works the following issues need to
be considered:
* The potential damage to pavement from water and root
system infiltration,
5–6
Blacktown City Council Engineering Guide for Development - 2005
5–7
Blacktown City Council Engineering Guide for Development - 2005
5–8
Blacktown City Council Engineering Guide for Development - 2005
5–9
Blacktown City Council Engineering Guide for Development - 2005
5 – 10
Blacktown City Council Engineering Guide for Development - 2005
PPENDIX
Blacktown City Council Engineering Development Guide – 2005
COVER SHEET
- Locality Plan. ☐
- Index of drawings sheets. ☐
- Legend. ☐
PLAN
- Benchmarks and datum shown. ☐
- Reduction ratio, bar scales, north point. ☐
- Lot boundaries and numbers. ☐
A-2
Blacktown City Council Engineering Development Guide – 2005
Road Detail
- kerb radii 8.5m residential, 12.0m industrial. ☐
- cul-de-sac radii 9.0m residential, 13.5m industrial. ☐
- chainages. ☐
- tangent points. ☐
- bearings. ☐
- curve radii (bus routes min 76m). ☐
- dimensions (check for conformity with hierarchy). ☐
- half road construction min. width 4.5m. ☐
- vehicular crossing if required (lm from low side
boundary). ☐
- check that vehicular crossings do not clash with drainage
pit. ☐
- ramps required at pathways and all kerb returns (no lip). ☐
- lots to be contoured (existing and proposed). ☐
- roads intersect at right angles. ☐
- check for sight distance across intersection. ☐
- splay corners 5x5 (residential); 8 x 8 (industrial). ☐
- path paving shown conforms with Council Path Paving
Policy. ☐
- pathways, width / location. ☐
- extent of construction. ☐
- pavement splays shown at end of works.
- street sign location. No through road signs as required. ☐
- concrete pathways, extend to kerb. ☐
- bus bay provided at school site. ☐
- classification and name of road. ☐
- guide posts - white, reflectorised. ☐
- pipe baulkheads in pathways. ☐
- smooth junction with all existing work. ☐
- Only barrier kerb permitted adjacent to public or drainage
reserves. ☐
A-3
Blacktown City Council Engineering Development Guide – 2005
A-5
Blacktown City Council Engineering Development Guide – 2005
- Pipe baulkheads. ☐
- Continued to kerb or pedestrian path paving. ☐
- Restrictions on adjacent lots to ensure finished floor
levels 500mm above 100 year ARI level. ☐
INTERSECTION/CUL-DE-SAC DETAIL AND KERB PROFILES
- Plan drawn to scale 1:250 or 1:200 or 1:100. ☐
- Profiles drawn at 10 to 1 exaggeration. ☐
- Plan to be contoured. ☐
- Tangent points and radii shown. ☐
- Kerb returns to be numbered or lettered. ☐
- Top of kerb levels shown at 1/4 points and V.C. ☐
- Returns to grade out except sag points (i.e. no trapped
low points. ☐
- Sag point to be at least 1m beyond kerb TP. ☐
- Check for length of kerb less than 0.3% (should be less
than 5m). ☐
- Check splay corner details. ☐
- Check cross fall centreline to lip. ☐
- Check riding comfort around return. ☐
- Reduction ratios and bar scales.
ROUNDABOUT DESIGN (to Austroad Standards)
- Check size conforms with Austroads standards. ☐
- Check for adequate deflection through RAB. ☐
- Check vehicular turning circles (dependant on location). ☐
- Ensure compliance with Council requirements. ☐
* SBS Modified AC14 to kerb return TP’s (75mm thick). ☐
* centre island and annulus to be reinforced concrete. ☐
* painting (reflectorised) and stenciled concrete as
required. ☐
* lighting to Integral Energy satisfaction. ☐
* note re: provision of water tap in central island. ☐
* agricultural lines within central island. ☐
* reduction ratios and bar scale.
BRIDGE DESIGN
- The design has been performed by a competent
practising Civil or Structural Engineer. ☐
- Geotechnical data has been adequate and is held on
the design file. ☐
- The type and functional dimensions of the bridges meet
the current requirements of Austroads Bridge Design
Code, AS 3600, AS 1684, AS 1170, AS 4100. ☐
- The type and class of all materials are indicated on the
drawings. ☐
- Records of all significant design calculations are
available for audit. ☐
- The design complies with any Conditions of
Development consent. ☐
A-6
Blacktown City Council Engineering Development Guide – 2005
A-7
Blacktown City Council Engineering Development Guide – 2005
OUTLET CONDITIONS
- Extent of tail-out (depth will determine pipe length). ☐
- 100 yr ARI and PMF flood extents. ☐
- Erosion control/turfing. ☐
- Energy dissipaters. ☐
- Capacity of channels/existing pipeline. ☐
- Headwall detail. ☐
- In pathways extend pipe 3m beyond boundary (access). ☐
A-8
Blacktown City Council Engineering Development Guide – 2005
INTER-ALLOTMENT DRAINAGE
- Longitudinal sections provided. ☐
- Easements shown on plan. ☐
- Pipe size shown. ☐
- Minimum 150mm diameter. ☐
- Adequate pipe size. ☐
- Pipe cover (Min. 300). ☐
- Grade (Min. 1%, absolute 0.5%). ☐
- Type of pipe (RCP V.C.P. PVC etc). ☐
- Stubs to be provided for industrial, commercial and
medium density lots. ☐
- Connections to stormwater drainage (angle satisfactory). ☐
- Pits at bends and inside property boundary. ☐
- Pipes across Council footways to be RCP or RHS only. ☐
- Hydraulic check required for > 5 lots. ☐
A-9
Blacktown City Council Engineering Development Guide – 2005
TRAFFIC MATTERS
- Do plans need to be referred to Traffic Committee for
line marking, sign posting, street lighting? ☐
- If yes, 3 copies of plan required showing line marking,
signposting and lighting and report. ☐
- Check street sign location is to Council requirements. ☐
- Traffic controls comply with AS 1742.3-2002. ☐
- Certified by RTA accredited work site traffic. ☐
- Have pedestrians been catered for. ☐
- Has "after hours" traffic control through the worksite
been addressed? ☐
GEOTECHNICAL
- Notes to be shown on plans where filling is proposed. ☐
* all sediment control measures to be installed prior to
commencement of works. ☐
* fill compaction as Spec. ☐
* all testing controlled and certified by NATA registered
lab. ☐
* strip and stockpile topsoil prior to filling; respread on
completion of earthworks. ☐
* residential lots to be individually classified. ☐
COMMENTS
A - 10
Blacktown City Council Engineering Guide for Development - 2005
PPENDIX
ON-SITE DETENTION
GENERAL GUIDELINES &
CHECKLIST
Blacktown City Council Engineering Guide for Development - 2005
B-1
Blacktown City Council Engineering Guide for Development - 2005
iii. Pre to post development modeling within the growth centres using DRAINS or RAFTS
will not generally be accepted and the Council’s OSD spreadsheet used instead based on
the discharges/volumes above. Such electronic models can only be used where pre-
approved by Council and only in exceptional circumstances. Where such modeling is
agreed to then for pre-development allow for 15mm depression storage and large travel
times (typically 14 min) in DRAINS, or a 15mm initial loss and a single catchment with
high Mannings n (>0.06) for RAFTS. For post development use Council’s standard
parameters.
iv. Maximum ponding depths shall be as follows:
Pedestrian Areas 50 mm
Driveways and Parking 200 mm
Gardens 600 mm
In all cases, safety issues shall be addressed with provision of warning signs (including
Confined Space Entry signs), and if necessary, safety fencing.
v. Provision shall be made for flows greater than the 100 year ARI flow through the structure
via an overflow spillway and/or overland flow path (see also Section 2.14 -
Pathways, of this Guide).
vi. Freeboard for any building adjacent to the detention structure shall be in accordance with
Section 1.5 of appendix D of this Manual. The depth of spillway overflow shall be based
on the assumption that at commencement of the design storm, the detention outlet is fully
blocked.
vii. Structural components of on-site detention systems within the Hawkesbury River
Catchment shall be designed in accordance with the guidelines provided in the UPRCT
handbook.
viii. The drainage concept plan (to be submitted by the Applicant with the Development
Application) shall identify undrained areas and include a hardcopy printout of the OSD
Spreadsheet or S3QM certificate together with an electronic version of the spreadsheet OR
the on-line S3QM certificate submitted directly to Council detailing design parameters
such as pit levels, orifice levels/diameters, weir levels/flow rates, etc.
B. GENERAL REQUIREMENTS
All existing services which need to be relocated (if any) to facilitate the construction of OSD
storage areas, pits or drainage pipelines, shall be relocated at full cost to the developer.
(This should be a note on the plan).
B-2
Blacktown City Council Engineering Guide for Development - 2005
D. STORAGE
1) The invert of the below ground storage tank shall be graded at a minimum of 2% toward the
outlet. Above ground systems shall be graded at a minimum of 1% toward the outlet.
2) At least the 1 in 1.5 ARI year storm shall be underground or in low nuisance areas such as
passive landscaped or paved entertainment area. All storage within the rear yard or private
courtyard for residential development shall be 100% below ground.
B-3
Blacktown City Council Engineering Guide for Development - 2005
B-4
Blacktown City Council Engineering Guide for Development - 2005
E. TRASH RACK
1) The trash rack shall be constructed of hot dipped galvanized mesh, "Lysaght Maxi mesh
Rh3030" (or an approved equivalent), for orifices of less than 150mm diameter. For orifices
greater than 150mm diameter "WELDLOK (F40/203)" type mesh (or approved equivalent) shall
be used. The cross sectional area of the screen shall not be less than 50 times the orifice cross
sectional area for the Maxi mesh or 20 times for “WELDLOK”.
The use of any equivalent must be approved by Council’s Engineer prior to installation. Any
gaps between the trash rack and the pit wall shall be no greater than 3mm. The Trash Rack
shall be easily removable to allow cleaning of the orifice plate.
F. OUTLET SYSTEM
1) The orifice plate shall consist of a stainless steel plate 3mm thick for orifice holes up to 150mm
diameter, and 5mm thick for larger orifice sizes. (See Council Plan A(BS)175M).
2) A galvanized Rolled Hollow Steel (RHS) section shall be provided between the boundary
inspection pit and a kerb and gutter discharge point.
3) Reinforced concrete pipes (rubber ring joint type) line shall be used between the boundary pit
and any Council drainage pit
G. MAINTENANCE SCHEDULE
A maintenance schedule is to be prepared in accordance with the guidelines in the WSUD
inspection and Maintenance Guidelines available on Council’s website.
https://www.blacktown.nsw.gov.au/Plan-build/Stage-2-plans-and-guidelines/Developers-
toolkit-for-water-sensitive-urban-design-WSUD/WSUD-maintenance-resources
B-5
BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005
PPENDIX
OUNCILS OLICIES
ND UIDELINES
March, 2009
Path Paving Policy
Aim ............................................................................................................................................ 3
General ....................................................................................................................................... 3
1.1 Residential & Industrial ..................................................................................... 3
1.2 Road Hierarchy .................................................................................................. 4
1.3 Explanations....................................................................................................... 6
1.3.1 Pedestrians ............................................................................................. 6
1.3.2 Desire Line ............................................................................................. 6
1.3.3 Sub-Arterial Roads................................................................................. 6
1.3.4 Collector Roads ...................................................................................... 6
1.3.5 Local Roads ........................................................................................... 6
1.3.6 Cul-de-sacs ............................................................................................. 6
1.3.7 Access Roads ......................................................................................... 7
1.3.8 Industrial Collector Roads ..................................................................... 7
1.3.9 Industrial Access Roads ......................................................................... 7
1.3.10 Pathways ................................................................................................ 7
1.3.11 Parks ....................................................................................................... 7
1.3.12 Schools ................................................................................................... 7
1.3.13 Commercial/Retail Areas ....................................................................... 7
1.3.14 Bike Paths are ........................................................................................ 7
2. Implementation .............................................................................................................. 8
2.1 Developing Areas ............................................................................................... 8
2.1.1 Option 1 ................................................................................................. 8
2.1.2 Option 2 ................................................................................................. 8
2.2 Established Areas ............................................................................................... 9
2.2.1 Developer Construction ......................................................................... 9
2.2.2 Provision of Path Paving by Council ..................................................... 9
Aim
To provide a path paving network where it is needed most so that pedestrians have a safe and
effective, all weather surface on which to walk.
General
1.1 Residential & Industrial
Path Paving is generally 1.2m wide and laid 900mm off the property boundary on the
footway of public roads in new release areas. However, in established areas the Path
Paving is generally 1.1m wide and laid 900mm off the property boundary.
Council’s Path Paving Policy is outlined below:
(i) All new path paving shall be 1.2m w ide and l aid 900m m off the property
boundary.
(ii) In established areas, where the existing path paving is generally 1.1m wide, the
Manager Maintenance Services and Coordinator Engineering Approvals have
delegated authority to either maintain the status quo or apply 1.1 (i) on a case by
case basis.
(iii) For new subdivisions adjacent to established areas, where the existing path
paving has been constructed on both sides, but new path paving is required on
one side, the Director Environmental & Planning Services and Coordinator
Engineering Approvals have delegated authority to determine the transition point.
(iv) The Director Technical & Transport Services and Director Environmental &
Planning Services have delegated authority to change the width of path paving
from the standard width of 1.2m to any other width depending on the particular
situation.
Path paving shall generally be constructed of 75mm thick concrete. Its provision is
usually delayed until approximately 75 percent of the dwellings are constructed in the
street. However, in the case of integrated housing, the concrete path paving shall be
125mm thick to enable road and building works to commence concurrently. Refer to the
Table outlined below.
The three types of path paving allowed by Council are outlined below:
Type 1 - Grey concrete a s per the width and offset di stance off the property
boundary outlined above. Expansion joints shall be placed at intervals
not exceeding six (6) metres with dummy joints provided every one point
two (1.2) metres. The Director Technical & Transport Services, Director
Environmental & Planning Services, Manager Maintenance Services and
Coordinator Engineering Approvals have delegated authority to vary the
surface texture or finish, and colour of the concrete path paving.
Type 2 - Grey concrete with cl ay segmental p avers as per the width and offset
distance off the property boundary outlined above. Segmental pavers
shall be set in 75mm thick concrete at every third dummy joint.
Residential
Industrial
Other
Notes: (i) The above Table should be read in conjunction with Section 1.3 of the
Policy document.
(ii) 1.2* It should be noted that the majority of existing path paving in
established areas are 1.1m wide.
1.3 Explanations
1.3.1 Pedestrians has been used throughout this Policy, however it is recognised that users of
path paving include wheelchair users and young cyclists.
1.3.2 Desire Line is the preferred route which pedestrians would use to reach their destination,
such as a school, shops, park, place of worship, bus stop, train station, sporting facilities
and community facilities etc.
1.3.3 Sub-Arterial Roads need path paving on both sides due to higher vehicle speeds and
traffic volumes, and the need to limit road crossing points to reduce the potential for
pedestrian/vehicle contact. Sub-Arterial roads are marked on Plan No. A(BS)76R, which
shows the road hierarchy.
1.3.4 Collector Roads need path paving on both sides due to the higher traffic volumes and the
need to limit road crossing points to reduce the potential for pedestrian/vehicle contact.
Collector roads are marked on Plan No. A(BS)76R, which shows the road hierarchy, and
for new subdivision roads with 11 metres wide carriageway.
1.3.5 Local Roads generally need path paving on one side only. Local roads will sometimes be
provided with path paving on both sides of the road if desire lines are identified along
both sides of the road.
1.3.6 Cul-de-sacs generally need path paving on one side only. I n new subdivisions, path
paving shall be provided along at least one side of the Cul-de-sac. For existing Cul-de-
sacs with less than 30 dwellings, the residents must be consulted to ascertain whether or
not they require path paving, prior to construction.
1.3.7 Access Roads are narrow residential streets which have very low traffic volumes and path
paving would only be provided along one side.
1.3.8 Industrial Collector Roads are generally heavily trafficked with high usage by heavy
vehicles. Although the pedestrian generation is generally low, it is essential that path
paving is provided on both sides to encourage road crossings at intersections.
1.3.9 Industrial Access Roads have only minor pedestrian movements, but due its usage by
heavy vehicles and the longer distances that pedestrians need to walk. Path paving would
be provided on one side.
1.3.10 Pathways generally link streets with streets or streets to recreational and/or community
facilities. In many instances, Pathways are also utilised to cater for overland flows. As
such, they are generally constructed with 3 percent cross-fall and kerbed on one side.
Pathways in new release areas are 4m wide and in established areas they are generally 3m
wide. Pathways shall be constructed full width with 150mm thick concrete.
1.3.11 Parks provide aesthetic pedestrian routes that are usually linked to the adjacent street
path paving network. They provide pedestrian access to recreational and/or community
facilities located within the Park. The width of path paving in Parks are generally 1.5m
wide and constructed in 150mm thick concrete to cater for mowing tractors.
1.3.12 Schools need full width concrete path paving around the main entrance, adjacent to bus
bays and drop off and pick up areas caters for the high pedestrian numbers, particularly
during the drop off and pick up times. The full width concrete paved areas are usually
linked directly to the adjacent path paving network.
1.3.13 Commercial/Retail Areas are generally paved with segmental pavers full width to cater
for the high pedestrian usage and to enhance the aesthetics of these areas. Segmental
pavers shall be laid on 25mm sand over 75mm thick concrete base.
1.3.14 Bike Paths are generally 2.5m wide and constructed in concrete. If standard path paving
is proposed to be provided between two bike paths or where it forms part of Council’s
Bike Plan, then the proposed path paving should be upgraded to 2.5m wide to provide
continuity.
2. Implementation
Developer Construction
Developers are required to provide path paving on roads created by subdivisions and
along roads adjacent to their subdivisions. The provision of path paving by developers
should be delayed until approximately 75 percent of the dwellings have been constructed
along the street frontage. This is to minimise damage to the path paving during house
construction.
The developer has 2 options to facilitate the delay of path paving provision:
2.1.1 Option 1 Lodgement of Security Deposit in the form of a Bank Guarantee or Cash
Deposit can be lodged with Council together with the execution of
Council’s standard Deed. The amount of the security is 1.5 times the
value of the work which is calculated using Council’s short term contract
rates. When approximately 75 percent of the allotments created have
been built upon, the developer may then notify Council of their intention
to construct the path paving. Following Council’s approval to proceed
with the work, the work is then carried out by the developer’s contractor
and upon satisfactory completion the Security Deposit will be released.
2.1.2 Option 2 Monetary Payment towards the provision of path paving may be made
by the developer. The amount of payment will be calculated using
Council’s Goods & Services P ricing Schedule. I n addition, a n
administration fee of 1 percent of the value of the path paving works with
a minimum of $250 is paid to Council. The amount due is payable prior
to release of the plan of subdivision, but may be paid at a later date to
release a Security Deposit. The path paving will then be constructed by
Council at a later date. This opt ion relieves t he developer of t heir
obligations to provide path paving much earlier than Option 1 and frees
the developer from servicing a Bank Guarantee and other administrative
commitments.
The extent of path paving works proposed in accordance with this Policy must be shown
on the Engineering Plans required by the Development Consent. The extent of works
approved by Council will then form part of the road and drainage works that the
developer is required to provide.
Generally, Council do not construct path paving in developing areas as the developer will
be required to provide it as a condition of development approval. However, situations
may arise whereby the property owners when it does to meet the needs of the community,
Council will seek to recover half the construction cost of providing the path paving from
the owners of properties fronting the work. Particularly when the subject properties are
capable of further development or undertake commercial activities. Council has the
legislative power to enforce the recovery of half the construction costs of providing path
paving from the owners of properties fronting the work in accordance with the Local
Government Act 1993.
Where a development site fronts a road which is identified by this Policy as requiring
path paving, the developer is responsible for its construction along the full frontage of the
site. The fulfilment of this responsibility is by:
Council allocates funding for path paving projects through its Annual Works
Improvement Program. Projects are prioritised on merit in accordance to the Selection
Criteria outlined below:
Pedestrian Generators
Pedestrian Safety
Development Potential
Road Hierarchy
Remaining or Incomplete Sections
Requests Received by Council
APPENDIX C
APPENDIX D
DRAINAGE DESIGN
MANUAL
APPENDIX D
Prepared by:
Revised 2005
D-1
BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005
INTRODUCTION
This document outlines Blacktown City Council's recommended practice for urban drainage
design. All urban drainage design for Council shall be carried out in accordance with this
document. It is in no way a comprehensive "Design Manual" and is intended to be read in
conjunction with and as a supplement to the 1998 Reprinted edition of "Australian Rainfall and
Runoff" (referred to as "AR&R"). The Design coefficients defined in the Tables and Figures
within this Manual are applicable only to the City of Blacktown.
The "Major/Minor" concept is adopted for urban drainage design. The "Minor" system refers
to the underground pipes system, designed to an Average Recurrence Interval as determined in
Section 1 of this Manual. The "Major" system refers to overland flow paths which shall be
designed to convey major storm flows when the capacity of the minor system is exceeded.
The Manual has been divided into Sections in accordance with the design procedures outlined
in Section 1.5.2, Book 8 of AR&R (page 9). The appendices detail several design techniques
which may be applicable to different aspects of Urban Drainage Design.
General requirements for the design of trunk drainage systems in new release areas are detailed
in Section 9 of this Manual. Where these designs are carried out by Consultants, a separate
Design Brief shall be written for each new design.
NOTE: Although the parameters and techniques for Flow Estimation in urban catchments as
set out in the Manual, generally refer to the Rational Method, it may, depending on catchment
characteristics, be more appropriate to use Time/Area or Non-Linear-Runoff-Routing Model.
Urban Hydrograph Models such as RAFTS and DRAINS employ rigorous, as well as
contemporary techniques for determining catchment discharge and response and should be
used wherever possible. Council has already modelled some catchments using the DRAINS
and RAFTS computer models and on request, these data files can be made available to facilitate
catchment analysis.
D-2
BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005
DESIGN PROCEDURE
Listed below is the suggested procedure for urban stormwater drainage design. A detailed
explanation of the procedures is contained within each Section. The steps refer to the general
order in which a drainage design proceeds.
8. Culvert Design
D-3
BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005
Commercial 20 years
Industrial 20 years
Local/Collector 5 years
Sub-Arterial 20 years
Arterial 100 years
Access to Emergency Facilities 100 years
A check shall be undertaken to ensure that the 100 years ARI flow rate has a safe
"escape route" when the minor system fails. Major system drainage shall not be
confused with trunk drainage, as explained in the introduction. The "escape route"
shall follow a public pathway or road system, developed as part of the
subdivision/development being created.
D-4
BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005
All trunk drainage systems shall be designed to a 100 year ARI flow rate for the
Critical Storm, with freeboard requirements as shown in Section 1.5. Major retention
structures should be checked for Half Probable Maximum Flood flows so that
damage, resulting from failure of the structure, does not occur. Refer to Section 9 of
this Manual.
NOTE: Modification of these values will depend on individual cases e.g. Freeboard
may be increased or reduced where waterway area is such that the sensitivity of the
floodway to changes in the flow parameters, is indicative of a corresponding large or
small change in flow depth and velocity; additionally, it may be necessary for a
structure to be checked for a Full Probable Maximum Flood in areas where failure
could significantly increase the danger to life and property.
The extent of "trunk drainage" in a catchment will be defined by areas shown as SP2
Drainage in the LEP, and/or flood extents mapping as defined on Council's
Geographical Information System.
Industrial/
Residential
Commercial
Drainage System Land Habitable Garage Land
Floor
Level Floor Floor Level
(#) Level Level Level
(#)
Trunk Drainage
0.5 m 0.5 m 0.1 m 0.5 m 0.5 m
Creeks and open channels
Overland Flow N/A 0.3 m 0.1 m N/A 0.3 m
Onsite Detention (*) N/A 0.2 m 0.1 m N/A 0.2 m
Road Drainage - Minor Systems
(Gutter & Pipe Flow) 0.15 m below top of grate
Road Drainage - Major Systems
(Road capacity) See Figure 1.1
Detention Basins 0.5 m below top of embankment (100 year ARI)
D-5
BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005
Piped drainage
easement with
flow
overland flow
X
Land level beyond building setback
shall be at least:
Y
- 0.5 m for residential areas
- 0.3 m for Industrial & Commercial areas drainage
B B above the 100 year ARI flood level. easement
A BDY BDY
225 (min)
225 (min)
Ar
100 (min)
ea
FFL FFL
Building Setback
(min)
300
overland
flow
ROAD piped
flow
Note:
Finished floor levels shall be designed taking into
consideration the most critical water surface level
adjoining the buildings. Generally, this level will be
in line with the upstream most building wall as shown
'X' and 'Y' in the plan.
SECTION B-B
flow flow
DRAINAGE RESERVE
flood extent
100 year ARI
A PLAN
BDY
BDY
DRAINAGE RESERVE ROAD RESERVE Building Setback
225 (min)
FFL FFL
0.5 m (minimum) - Residential
0.3 m (minimum) Industrial/Commercial Major Systems (100 Year ARI)
2000 ard)
4 % (standa (stand
rd) (max) 4%
(max)
200
100 year ARI flood level
D-6
BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005
An assessment of the topography will determine the location of proposed drainage paths.
Once the location of a proposed network is defined, trial pit locations should be arranged.
Generally, pits should be spaced with minimal bypass flows. An approximate procedure for
locating pits is detailed in "Technical Note 2" in Book 8 (page 11) of AR&R. The final
design criteria for location of pits is described in Section 4.1 of this Manual.
Catchment areas to each pit shall be determined from contour information and proposed
property boundaries. A site inspection shall always be made to check the contour
information and assess the likelihood of any flow path deviations which may occur as a
consequence of existing or proposed developments. Changes to flow paths can occur as a
result of the construction of fences, retaining walls, buildings etc. after the construction phase
of the subdivision. The impact of these changes shall be considered at the design stage.
Sub-area discharges can be calculated using the procedures detailed in Section 3. Major
system flow paths should be defined at this stage, and analysed according to the procedures
detailed in Section 5.
Rainfall intensities adopted for design are those issued by the Bureau of
Meteorology for Minchinbury, and these shall apply for the Blacktown City Council
Area. A copy of the IFD table (Table 3.0) is on the following page.
Time of concentration for each sub catchment shall be determined using the
Kinematic Wave Equation, as detailed in Technical Note 3 (Pages 12-13) of Book 8
of AR&R.
The Kinematic Wave equation is very sensitive to slope and the Retardance
Coefficient "n*", these should be estimated carefully. Recommended Retardance
Coefficients are listed below in Table 3.1. (see next page)
D-7
BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005
Table 3.1
Surface Retardance Coefficients (n*)
D-8
BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005
TABLE 3.0
RAINFALL INTENSITY FREQUENCY DURATION FOR BLACKTOWN NSW
D-9
BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005
The rainfall intensities shown above are calculated in accordance with Chapter 2, Australian
Rainfall and Runoff - 1987 Edition.
D - 10
BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005
Cy = Fy x C10
Runoff coefficients shall be estimated separately for each land use, see Table 3.3.
Table 3.4 is a quick reference table giving runoff coefficients in Blacktown for
the land uses listed in Table 3.3.
Past experience and information from DIPNR suggests that major flooding in
Blacktown occurs part way through a much longer storm event. Thus the
catchment is already saturated and the Loss Rates are negligible.
Table 3.2
Recurrence Intervals Fy
1 0.80
2 0.85
5 0.95
10 1.00
20 1.05
50 1.15
100 1.20
D - 11
BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005
Table 3.3
Land Use f
Table 3.4
D - 12
BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005
Discharge for each sub catchment may be calculated using the Rational Method
formula:
Q = C x I x A/0.36 (l/s)
"Hydrological Design Sheet 1" (A copy is on the following page) sets out the
preferred format for these calculations. Technical Note 6 (page 24) of Book 8 of
AR&R details a worked example for these calculations. The following points should
be noted:
* The rainfall intensity adopted (column 8) is for the total flow time,
* A "C" valve (column 9) and sub area (column 10) is calculated for each land use
type, and
* The discharge for the subcatchment (column 13) is calculated by summing the
CA's (column 12) and multiplying by (I/0.36).
"Hydrological Design Sheet 2" (copy attached) can then be used to calculate the flows
along each reach of the pipe system. Where calculations are proposed to be presented
as a computer hardcopy, it shall be necessary to obtain approval from Council's
Engineer prior to doing so. Hand calculations shall be submitted in the format shown
on the enclosed Sheets.
In areas where this may be critical, such as industrial or high density residential
development, a partial area check, based on times of concentration of impervious areas
directly connected to the pipe system, is necessary. However, for routine urban
drainage design this may not be appropriate.
D - 13
BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005
D - 14
BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11)
Pipe Time Intensity ΣCA Q= Time Intensity ΣCA Q=CIA Adopted Remarks
to I (ha) CIA to I (ha) (l/s) Flow Rate
(min) (mm/h) (l/s) (min) (mm/h) [7]x[8] (l/s)
[3]x[4] /0.36 Greater
/0.36 of [5] &[9]
FULL AREA PARTIAL AREA
D - 15
BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005
The following criteria governs the location of pits in roadways, for the design average
recurrence interval:
Technical Note 4 (pages 16-17) of Book 8 of AR&R details a method for calculating
gutter and road flows.
Most existing grates within the city area are Durham (RMS A190) type grates with bars
parallel to the kerb. In some circumstances these pit configurations have less capacity
than the welded steel ("Weldlok") type grates. Any analysis of existing drainage systems
shall therefore account for inlet capacities appropriate to the type of grate/inlet
configuration.
Once the sub catchment flows are known, pit inlets can be designed in accordance with
the charts contained on the following pages. All new pit inlets shall be constructed using
welded steel ("Weldlok") type or equivalent grates with appropriate skirts. On grade,
percentage capture by grates is mainly dependent on lintel size, tests show that the two
types of grates mentioned above have similar performance characteristics on grade when
in combination with a lintel. The charts for the sag inlets are based on tests conducted
by the RTA N.S.W., Water Research Laboratory and the West Australian Institute of
Technology (see Ref. 6, 10 & 14) and incorporate the following blockage factors:
Alternatively inlet capacities can be calculated from first principles using formulas as
detailed in Section 1.5.4(iii), Book 8 (page 15) of AR&R. If using these formulae, the
D - 16
BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005
blocking factors adopted on the previous page, shall be applied. Where it is proposed
to use a grate not conforming to these requirements, it is necessary to submit a detailed
investigation from an accredited laboratory establishing the performance of the grate
prior to it being accepted or rejected by Council.
Hand calculations for the design of pit inlets shall be tabulated on "Hydrological
Design Sheet 1" (column 16 to 20). Computer analyses shall conform to the inlet
capacities graphed on Figs. 4.1 to 4.5, unless prior approval has been received from
Council's Development Services Engineer.
Sag pits shall be designed based on a depth of ponding, up to the top of the kerb.
Ponding depths can be calculated using design charts, Figures 4.2 - 4.5 of this Manual.
Lintel sizes shall be commensurate with inflow requirements.
A nominal internal lintel size of 0.9m shall be placed on junction pits along kerb and
gutter in public roads. The minimum nominal internal lintel size for grated gully pits
in public roads shall be 1.8m, unless the pit's main function is to facilitate a change in
direction or grade of the stormwater pipe, in which case the nominal internal lintel size
may be reduced to 1.2m. The minimum nominal internal lintel size for grated gully
pits in "sags" shall be 2.4m.
D - 17
BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005
Many of the flooding problems in older areas of Blacktown have occurred, due to inadequate
provision of overland flow paths. Thus, all urban drainage designs shall incorporate an
assessment of major system flows. The aim of this check is to ensure that a safe and
adequate "Escape route" is achieved for storm events above that of the pipe system design.
This route should be a properly sized over-land flow path preferably along a road and
pathway system.
The Rational Method may be used to estimate major system flows for critical points in the
drainage system. An ARI of 100 years shall be used for this and the difference between the
minor system flow and the 100 year ARI flow shall be the basis upon which the major system
flow path shall be designed.
The roads and pathways will generally form the flow path by which the major system flows
are routed, either to the Trunk Drainage system or to a lowpoint with sufficient hydraulic
capacity to capture the flows. Special consideration shall be given to Trapped Lowpoints
where the overland flowpath may divert surcharge into properties. This is especially
important when designing "Downhill" cul-de-sac and Kerb returns adjacent to a sag vertical
curve. In the former case the overland flow path shall incorporate a depressed pathway with
reverse crossfall in the footway. In the latter case consideration shall be given to grading the
Kerb Return such that water flows around the Return and away before it breaks over the top
of kerb at the lowpoint. Table 5.1 overpage gives approximate capacities of full width
carriageways based on the following criteria:
If the roadway capacity is inadequate, an estimate shall be made of the capacity of the pipe
system under major flow conditions. Pit capacities shall be calculated using the appropriate
blocking factors, and pipe capacities estimated with trial diameters and head levels no greater
than 150mm below the surface levels / invert of kerb (applicable up to the design ARI for the
respective pipeline reach).
The major flows must have an overland flow path such that all floor levels have
minimum freeboards in accordance with Section 1.5 of this Manual. The freeboard
requirement may be varied on consideration of the sensitivity of the floodway
parameters to the flows. Subject to approval by the Manager Investigation and Design.
D - 23
BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005
TABLE 5.1
CARRIAGEWAY CAPACITIES (m3/s)
Longitudinal
Carriageway Width (m)
Slope
% 5 5.5 6.5 7.5 8 9 10.3 11 13.5 15.5
0.5 0.64 0.68 0.76 0.82 0.84 0.87 0.87 0.86 0.42 0.42
1 0.90 0.97 1.08 1.16 1.19 1.23 1.23 1.22 0.60 0.60
2 1.27 1.37 1.53 1.64 1.69 1.74 1.75 1.72 0.85 0.85
3 1.56 1.68 1.87 2.01 2.07 2.13 2.14 2.11 1.04 1.04
4 1.80 1.94 2.16 2.33 2.39 2.46 2.47 2.44 1.20 1.20
5 2.02 2.17 2.42 2.60 2.67 2.75 2.76 2.73 1.34 1.34
6 2.21 2.37 2.65 2.85 2.92 3.01 3.02 2.99 1.47 1.47
7 2.38 2.56 2.86 3.08 3.16 3.25 3.27 3.23 1.58 1.58
8 2.55 2.74 3.06 3.29 3.37 3.48 3.49 3.45 1.69 1.69
9 2.70 2.91 3.24 3.49 3.58 3.69 3.70 3.66 1.80 1.80
10 2.85 3.06 3.42 3.68 3.77 3.89 3.91 3.85 1.89 1.89
Longitudinal
Carriageway Width (m)
Slope
% 5 5.5 6.5 7.5 8 9 10.3 11 13.5 15.5
0.5 0.85 0.91 1.03 1.12 1.16 1.22 1.26 1.27 0.62 0.62
1 1.20 1.29 1.45 1.59 1.64 1.72 1.78 1.80 0.87 0.87
2 1.69 1.83 2.06 2.24 2.32 2.44 2.52 2.54 1.23 1.23
3 2.08 2.24 2.52 2.75 2.84 2.98 3.09 3.11 1.51 1.51
4 2.40 2.58 2.91 3.17 3.28 3.45 3.57 3.59 1.74 1.74
5 2.68 2.89 3.25 3.55 3.67 3.85 3.99 4.01 1.95 1.95
6 2.94 3.16 3.56 3.88 4.02 4.22 4.37 4.40 2.13 2.13
7 3.17 3.42 3.85 4.20 4.34 4.56 4.72 4.75 2.31 2.31
8 3.39 3.65 4.11 4.48 4.64 4.87 5.05 5.08 2.46 2.46
9 3.59 3.87 4.36 4.76 4.92 5.17 5.35 5.39 2.61 2.61
10 3.79 4.08 4.60 5.01 5.18 5.45 5.64 5.68 2.76 2.76
Notes: 1. Maximum flow depth = 200mm
2. Velocity Depth relationship V.dg < 1.0.
3. Manning's n: Pavement = 0.014; Gutter = 0.012; Footway = 0.025.
4. Carriageway crossfall = 3%; Footway crossfall = 4%
5. Shaded figures indicate half road capacity only.
6. Linear interpolation may be used for other longitudinal carriageway slopes
7. Capacities based on profile for Major systems shown on Section A-A, Figure
1.1, Section 1.5 of this Manual.
Technical Note 6 Book 8 (page 28) of AR&R details a procedure for checking major system
flows. A copy of "Hydrological Design Sheet 3", the preferred format for checking major
systems, is on the following page.
D - 24
BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005
D - 25
BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005
6. HYDRAULIC DESIGN
The Hydraulic Grade Line method shall be used for pipeline design. It is not the purpose of
this document to give a detailed explanation of the method, but important points are
mentioned below:
The tailwater to be adopted will depend on the outflow conditions. Where determination of a
tailwater level is in doubt, it shall be necessary to confirm the value with Council's Manager
Investigation and Design.
* Pit loss factors (k) shall be calculated using the Tables from ARRB SR 34, 1986
(Tables 6.5 and 6.6); a copy of these are on the following pages. Where the pit
configuration is not covered by these tables, the Missouri Charts or Hare Charts should
be used. (Refer to reference (1), (6), (7)),
* The top pit in the system must have sufficient depth to generate sufficient head to
charge the pipe. This can be calculated by using co-efficients derived from the
Missouri Charts. The k value of 4.5 should not automatically be assigned to all starter
pits but each pit shall be assessed on its merits, and
D - 26
Discharge and velocity graph
Colebrook-White formula k = 0.60mm
For circular pipes running full but not under head.
Engineering Guide For Development - 2005
Computed by:
HYDRAULIC GRADIENTS
DISHARGE Q, l/s
* Pit Loss factors for drop pits shall be calculated in accordance with the charts
previously mentioned. An allowance shall be made relative to the drop through
the pit. When the obvert of the outlet pipe is at or greater than Do/4, below the
invert of the upstream pipe, the inflow shall be regarded as grate flow. That is,
when the obvert of the outlet pipe is 1/4 of its diameter or greater, below the
invert of the upstream pipe then the pipe loss factor (k) shall be no less than 4.5.
Intermediate cases may be determined by linear interpolation of pit loss factor
(k) up to 4.5. Because of the high losses in these pits, it may be preferable to
design a mitre bend or a steeper section of pipe.
Where pipe grades are in excess of 15%, Concrete Thrust Blocks shall be placed at every
third collar. Pipe grades >20% are NOT permitted, except where approved by Council in
special unavoidable circumstances.
Desirable Full Flow Pipe Velocity shall fall between 0.6m/s and 6.0m/s.
An allowance of 150mm shall be adopted below the lowest point of the pit inlet/kerb invert,
to allow such inlets to act efficiently. Where this cannot be achieved it will be necessary to
obtain the concurrence of Council before proceeding.
Where a pipe section is operating under 500mm or more of head (above pipe obvert) that
Section shall be constructed using pipes without lifting holes.
Technical Note 9 Book 8 (pages 42-45) of AR&R detail the recommended procedures for
Hydraulic Grade Line calculations (HGL). A copy of the "Hydraulic Design Sheet" is
attached and this shall be used for manual calculations. Computer analyses will be accepted
where prior approval from Council's Engineer has been received. The HGL shall be checked
using the Hydraulic Checking Sheet (copy enclosed) and the Water Levels so determined
plotted on the pipeline Longitudinal Sections.
D - 28
Blacktown City Council ENGINEERING GUIDE FOR DEVELOPMENT-2005
[1] [2] [3] [4] [5] [6] [7] [8] [9] [10] [11] [12] [13] [14] [15] [16] [17] [18] [19] [20] [21] [22] [23] [24] [25]
Pipe Length Design Trial Full V2 U/S U/S Pit Pit k.V2 HGL at HGL Pipe HGL at D/S Pit D/S Pit Hydraulic Cover U/S Adopted Hydraulic Cover Adopted Pipe Remarks
L Flow Pipe Pipe 2g Surface Water Pressure 2g U/S Slope Sf Friction D/S Surface Water [11]-[14] [7]-Cover, Pipe [23]- Lowest [16]-[4] [15]- Lowest Slope
(m) Rate Diameter Vel. (m) Level Level Change (m) Pit (m/m) Loss Sf.L Pit Level Level Wall Drop of Cover of [21] Sf
Q (l/s) (m) V (m) Limit * Coeff. [9]x[6] (m) [12]x[2] (m) (m) Limit** thickness [17],[18] and [22] [20]-[23]
(m/s) AHD (m) Ku or Kw [8]-[10] AHD AHD (m) and [19] [2]
[11]-[13]
U/S Invert Levels (m) U/S Invert Levels (m)
D-29
BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005
D - 30
BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005
3. Inlet/Junction Pits with Gutter Flow 4. Part-Full Outflow from Junction Pits
Code Description Qu Ql ≈ Qg ≈ Kw
≈ =
1-1 Inlet pipe - - Qo 4.0
with single
pipe
outflow
inlet on
through
pipeline
1-2A . Qu ≈ Qg Qo/2 - Qo/2 2.0
1-2B . Qu ≈ Qo Qo - some 0.5
inlet on
through Situations frequently arise, particularly in upper-basin
pipe with catchments of moderate/steep grade, where pipes operate
lateral(s) part-full. Water level build-up in pits supplying these
1-3A .Qu > Qo Qo some some 0.5
1-3B .Qu > Ql Qo/2 some Qo/2 1.5 pipes, is, typically above obvert level (see sketch).
1-3C .Qu ≈ Ql Qo/2 Qo/2 some 1.5 Bannigan and Morgan (1981) have suggested for such
1-3D .Qu < Ql some Qo some 2.0 situations that the hydraulic grade line be set at (discharge)
1-3E .Qu < Ql some Qo/2 Qo/2 2.5
1-4 Inlet on 'L' - Qo some 2.5
pipe obvert level and the height, hw, fixed in the same
pipe manner as other cases considered in Tables 6.5 and 6.6.
junction The value of Vo required in the calculation of hw is given
i.e. Qu ≈ O by Vo = Qo /Ao where Ao is discharge pipe full area.
Inlet on "T"
pipe
junction i.e. No experimental or field validation of this has to date been
Qu ≈ O
. opposed
presented. Results of a pilot study carried out at S.A.
1-5A laterals - Qo some 3.0 Institute of Technology show water level build-up can be
1-5B . offset - Qo some 2.5 significantly recommended that the Bannigan and Morgan
laterals approach be adopted with hw fixed by:
hw = 1.5 kw V2o
2g
The results of current research will in time yield a more
accurate relationship.
D - 31
BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005
Examples
<45 situation:
D - 32
ENGINEERING GUIDE FOR DEVELOPMENT - February 2005
BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005
8. CULVERT DESIGN
Culverts shall be designed in accordance with culvert hydraulics theory i.e. the culvert capacity
is determined by the flow conditions, depending on whether inlet control or outlet control
governs.
Recommended design procedures are contained in Section 3 of the Concrete Pipe Association
of Australia's publication: "Hydraulics of Precast Concrete Conduits - Hydraulic Design
Manual". A suggested tabulation of the design calculations is contained on the following page.
There a number of Computer programmes available for the design of culverts. Council's
Engineer should be consulted regarding the suitability of individual programmes
D - 34
BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005
Culvert Control Check. Concrete Pipe Association of Aust. Hydraulic Design Manual.
D - 35
BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005
Release areas or very large infill developments will require the design of trunk drainage
infrastructure. Council's basic philosophy is that natural creek lines and watercourses must
remain largely intact and continue to function as viable ecological systems. Where the
existing riparian environments are largely degraded, Council expects that the trunk drainage
design will address this issue and restore ecological and habitat systems to mimic the natural
condition of Western Sydney creek lines as closely as is practicable.
Council recognises that urbanisation of natural or rural developed catchments will inevitably
alter creek hydrologic and geomorphologic regimes. However, the design of any trunk
drainage system must recognise and address these constraints whilst proposing
solutions/designs that integrate with Water Sensitive Urban Design principles and mimic
natural flow regimes and restore/enhance/maintain the existing riparian environment and
floodplain.
The following information is for general guidance only and does not in any way constitute
the only acceptable approach for trunk drainage design. Council is primarily interested in
superior aesthetic, environmental and recreational outcomes for riparian corridors, which are
a very valuable community resource. Leading edge or innovative trunk drainage design
strategies will be assessed on their merits.
Further information and more detailed technical advice and assistance may be obtained
by contacting Council's Manager - Investigation and Design.
9.1 HYDROLOGY
D - 36
BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005
for fish passage where appropriate. Landscaping must reflect indigenous flora representative
of the natural riparian environment of Western Sydney creek lines. The design should aim to
achieve a slow moving, steady flow regime to minimise scouring potential and maximise safety
outcomes. Rock drop structures, incorporating low flow riffle zones, and dense (increasing
floodplain roughness) riparian plantings may help achieve these outcomes on steeper sections
of some watercourses.
The floodplain of all natural or constructed watercourses must be hydraulically analysed using
appropriate software such as HEC-RAS. Flood levels and extents for the 5yr, 20yr, 100yr ARI
events and the PMF are to be provided in a digital format suitable for importation to Council's
GIS. Model input data files in electronic format must be provided to Council for checking and
future reference.
On-line retarding basins and/or wetlands are to be avoided whenever possible. Council's
philosophy is that retarding basins, wherever possible, should incorporate a landscaped
wetland, designed with water quality improvements as a primary objective. Grass lined,
generally trapezoidal basins with low flow pipe systems and little landscaping will not be
approved. Basins/wetlands should be designed as a community passive recreational facility as
well as providing an essential flow retarding function. Where saline soils are identified as a
development issue, strategies to minimise the impacts a wetland may have on water tables or
movement of saline groundwater must be explored. This may include, but not limited to, lining
of wetlands or restrictions on cut-fill of the proposed urbanised catchment.
Spillways of basins shall be designed to safely pass extreme storm events without structural
failure of the embankment. Landscape plans must not include placement of deep-rooted trees
or shrubs where roots may promote piping or structural failure of engineered embankments,
should they be uprooted during major storm events. The basin design must be subject to a
detailed risk assessment, for all events up to and including the PMF, where the downstream
floodplain is urbanised. The risk assessment must include an assumption of catastrophic
structural failure; i.e. a dam break scenario.
D - 37
BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005
Council encourages the use of computer models by Professional Civil Engineers for
drainage design. Data input and output files of any program used shall be submitted in
electronic format to Council. Council's Asset design Services Section is familiar with
the following commercially available programs and recommends their use subject to the
comments below. Should Consultants wish to use a program not listed below, then all
costs incurred by Council, associated with the independent assessment of the submitted
drainage modelling, are to be borne by the applicant who is required to make satisfactory
prior arrangements with Council for the payment of all expenses incurred by Council in
its assessment of the drainage submission
* RAFTS: Runoff routing model for trunk drainage and retention basin design.
Flow rates should be checked against those calculated by other methods.
D - 38
BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005
D - 39
BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005
REFERENCES
1. ARGUE, J. (1986) "Storm Drainage Design in Small Urban Catchments" Special Report
No 34. Australian Road and Research Board.
9. NICHOLS, P.S. & GRIFFIN, P.L "Modern Methods of Urban Drainage." Hydrology &
Water Resources Symposium, Hobart, 8th-10th November, 1983.
10. "Preliminary Survey of the Hydraulics of Gully Pits". Manly Hydraulics Laboratory.
Report No. 263, July, 1980
11. SANGSTER, W.M.; WOOD, H.W.; SMERDON, E.T.; BOSSEY, H.G.; "Pressure
Changes at Storm Drain Junctions - Design Methods". Engineering Series Bulletin No. 41.
University of Missouri.
12. Landcom's "Managing Urban Stormwater - Soils and Construction - Volume 1" 4th Edition
(2004).
14. HYDRAULIC MODEL TESTING OF GULLY PITS (May, 1984); Grate efficiency
analysis for C.I. & D. Cast Iron Products by the West Australian Institute of Technology.
(unpub.)
15. WOLLONGONG CITY COUNCIL (1984) "Stormwater Drainage - Hydraulic Design of
Underground Pipe Networks
D - 40
BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005
APPENDIX E
BOND DOCUMENTS
FORMAT & INSTRUCTIONS
APPENDIX E
A. DEEDS OF AGREEMENT
B. BANK GUARANTEE
C. CASH SECURITY
1. Cash deposits can be paid to Council using cash or Bank Cheque. Personal or
Company Cheques will only be accepted for amounts of $10,000 or less.
E-1
BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005
1. The Applicant will carry out and complete the works required to satisfy the Notice/s of
Determination held on Council files shown in Part 1 of the Third Schedule and
described in Part 2 of the Third Schedule ("the Works") to the satisfaction of Council by
the date set out in Part 3 of the Third Schedule or by any extended date fixed by the
Council in writing ("the Completion Date").
2. The Applicant will upon the execution of this deed pay or provide the security
stipulated in the Fourth Schedule ("the Security") for the performance of its obligations
under clause 1.
3. The Council may request the Applicant in writing to delay the execution of the Works
or any part of the Works to a date or any extended date fixed by the Council and the
Applicant must comply with any such request.
4. If the Applicant fails to comply with its obligations under clause 1 the Council may call
in the Security and use it to carry out or complete the Works and for this purpose the
Council may enter upon the land whereon the Works are or are to be situated.
5. (a) A certificate signed by the General Manager or other authorised employees and
given to the Applicant as to the cost to the Council of carrying out or completing
the Works shall be conclusive.
(b) The cost to the Council of completing the Works, and of any other uncompleted
works treated as part of the Works pursuant to Clause 8, shall include, but not be
limited to:
(i) All fees and charges necessarily or reasonably incurred by the Council in
order to have the Works carried out and completed properly and
expeditiously;
(ii) The reasonable cost to the Council of any supervision of the Works
which exceeds the supervision normally undertaken by the Council in
relation to work of a similar nature; and
(iii) Without limiting the generality of paragraph (i) all legal costs and
expenses reasonably incurred by the Council by reason of the Applicant's
failure to complete the Works, or of the calling in or expenditure of
money under this deed or generally in the carrying out of the Council's
powers and duties under this deed.
E-2
BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005
6. If the cost of completing the Works as certified is greater than the total amount of
money held by or available to the Council under this deed, then the Applicant will pay
to the Council the amount of that deficiency; and failing payment of the same forthwith,
the Council may recover that amount from the Applicant as a liquidated sum due and
owing by him to the Council.
7. Subject to clause 8, the Security, or so much of it as has not been used in accordance
with clause 4, shall be returned or refunded to the Applicant within 30 days of
completion of the Works.
8. The Council shall not be obliged to comply with its obligations under clause 7 if at the
time of completion of the Works the Applicant has not carried out his obligations under
any contract or deed between him and the Council in similar terms to this deed relating
to the development to which the Works relate, or to any other development. In that
event, the Council shall be entitled to retain any money or guarantees held by it under
this deed until all such obligations have been completed to the satisfaction of the
Council and to apply, call in and deal with the same as if such obligations were part of
the Works.
9. Any notice, certificate or request required or permitted to be given this deed shall be
sufficiently served or given if:
10. In the interpretation of this deed, unless the context otherwise requires:
(a) Words importing the singular include the plural and vice versa;
(b) Words importing any gender include any other gender and in particular a
reference to a "person" includes a corporation;
(c) Covenants given, obligations assumed, by more than one party shall bind those
parties and each of them jointly and severally.
ENGINEERING GUIDE FOR DEVELOPMENT - February 2005
E-3
BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005
Address:
(Applicant to complete)
E-4
BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005
APPENDIX F
APPENDIX F
F-1
BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005
ORIGINAL VERSION
PREPARED BY: PROUST & GARDNER
CONSULTING SURVEYORS & PLANNERS
406 PACIFIC HIGHWAY
LINDFIELD NSW 2070
IN CONSULTATION WITH
AND REVISED BY: BLACKTOWN CITY COUNCIL'S
DEVELOPMENT SERVICES UNIT
F-2
BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005
CONTENTS:
3. Positive Covenants
● On-site Stormwater Detention
● Overland Flowpath
● Stormwater Quality Improvement Device
● Maintenance & Repair of Shared Access
F-3
BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005
The Conveyancing Act 1919 has been amended by the Property Legislation
Amendment (Easements) Act 1995 which commenced on 1 August 1996. Parts of the
Acts that affect easement terms are as follows:
Easements in Gross
These easements have not been repealed and can be used, the terms of which
are deemed to be incorporated in the Instrument (see Schedules 4A and 8,
Parts 1-4) and variations thereof by addition, exception, qualification or
omission is now permitted.
The terms of the abovementioned easements (see Schedule 4A Parts 5-11) are
deemed to be incorporated in the Instrument and variations thereof by
addition, exception qualification or omission is now permitted.
ENGINEERING GUIDE FOR DEVELOPMENT - February 2005
F-4
BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005
3. The Amendment Act 1995 provides for terms of 10 additional easements that
benefit a lot. These easements do not require description in Part 2 of an
Instrument.
The terms of the abovementioned easements (see Schedule 8 Parts 5-14) are
deemed to be incorporated in the Instrument and variations thereof by
addition, exception, qualification or omission is now permitted.
4. The Amendment Act 1995 also provides for Positive Covenants for
Maintenance and Repair to be created over the site of an easement (or shared
accessway), or to benefit the site of an easement (or shared accessway). Lots
can now be burdened and benefited with a covenant which affects the owners
from time to time. The terms of the covenant can state that the registered
proprietors for the time being of the lots must maintain the site of the easement
(or shared accessway), or structure within it, and must share costs in some
proportion relating to the maintenance (see page B-11 for example).
5. The Amendment Act 1995 also provides for the creation of Cross Easements
for Party Walls automatically under a new Section 88BB of the Conveyancing
Act. The plan must show a boundary passing through the whole or part of a
wall and the wall is identified as a "Party Wall". No other information is
required for this automatic process.
Whilst the terms of the easements, etc., mentioned in Sections 1, 2 and 3 do not have
to be recited in Part 2 of any relevant 88B instrument (since their title in Part 1 will
impart the standard terms unless otherwise stated), their recitals are nevertheless
included in this document at Section D.
All terms of easements, covenants and restrictions shall have a clause referring
to the relevant authority e.g. Blacktown City Council, Sydney Water, Integral
Energy etc, as having the power to "release, vary or modify" those terms.
F-5
BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005
Full and free right for the body in whose favour this easement is created and
every person authorised by it from time to time and at all times thereafter to
enter go upon return pass and repass with or without vehicles in through along
and over the burdened lot and to use the burdened lot for the purpose of
placing thereon all such earth soil cement sand clay and other material or the
removal therefrom all such earth soil clay and other material as shall in the
opinion of the Council of the City of Blacktown be necessary or desirable for
the purpose of constructing reconstructing and forever maintaining on the
burdened lot a batter to serve as a support for the said land burdened and to do
all such incidental acts and things that may be necessary in the premises for
the purpose of constructing maintaining repairing altering or doing any work
on the land comprised in the said easement and for all or any of the said
purpose to remove and re-erect any fences or other posts on the land
comprised in the said easement.
F-6
BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005
have a tendency to affect the stability of the said batter as a support for the
said road and lots benefited as aforesaid or which may injure or damage the
said batter or in any way impair its efficiency and if the proprietor for the time
being of the burdened lot should do or suffer to be done any act or thing which
may in any way injure damage or impair the said batter he shall be liable at his
own expense to properly and substantially repair and make good all such
injury and damage. Where herein used, words importing the singular number
or plural number shall include the plural and singular number respectively and
words importing the masculine gender shall include the feminine or neuter
gender.
The proprietor of the lot benefited and persons authorised by him may:
(a) enter upon the burdened lot but only within the site of this easement.
(b) do anything reasonably necessary for the purpose of renewing,
replacing, painting, repairing and maintaining the dwelling adjacent to
this easement.
(c) remain on the site of this easement for any reasonable time for the said
purposes.
the proprietor of the burdened lot shall not erect any building or other structure
of any kind on or over the site of the easement.
The proprietor of the benefited lot and every person authorised by him may
go, pass and repass at all times and for all purposes with or without animals or
vehicles or both to or from the site of the easement provided that this right of
carriageway is a temporary right.
F-7
BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005
(a) not exceed a speed of 20 kph whilst driving a vehicle over the site of
this easement.
(b) not drive a vehicle of Tare weight in excess of ( )kg over the site of
this easement.
(c) not park a vehicle or leave a vehicle standing or otherwise allow an
obstruction to remain on the site of this easement."
No building shall be erected on the lot hereby burdened being a filled lot
unless constructed on pier and beam footings to safe and uniform strata or
alternatively on footings or slab designed and certified by a Chartered
Professional Engineer to the requirements and satisfaction of the Council of
the City of Blacktown.
Fencing Responsibility
F-8
BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005
Access Prohibited
The burdened lot shall not be used nor shall any part thereof be used as a
means of vehicular or pedestrian access or route to or from any part of #
(insert road name) and no owner of such a lot shall pass or repass nor shall
that owner permit or authorise any of his employees visitors or authorised
persons to pass or repass across the boundary between (insert road name) and
the burdened lot without consent of the Council of the City of Blacktown
(which consent may at any time be revoked by the said Council at its absolute
discretion).
The burdened lot shall not be further developed unless it is developed and/or
resubdivided with adjoining land to the satisfaction of the Council of the City
of Blacktown.
No building shall be occupied on any hereby burdened lot unless the vehicular
footway and gutter crossing serving that lot is constructed to Council's
specification in accordance with development consent having Notice of
Determination No. # issued by the Council of the City of Blacktown on #.
F-9
BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005
(a) Do any act, matter or thing which would prevent the system from
operating in a safe and efficient manner.
(b) Make or permit or suffer the making of any alterations or additions to
the system.
(c) Allow any development within the meaning of the Environmental
Planning and Assessment Act 1979 to encroach upon the system.
This restriction shall bind all persons who are or claim under the registered
proprietor(s) as stipulated in Section 88E(5) of the Conveyancing Act 1919.
For the purposes of this restriction, "the system" means the on-site stormwater
detention system constructed on the land as detailed on the plans approved by
………. as Construction Certificate No. ………. on ………., including all
ancillary gutters, pipes, drains, walls, kerbs, pits, grates, tanks, chambers,
basins and surfaces designed to temporarily detain stormwater, as well as all
surfaces graded to direct stormwater to the temporary storage. (Include the
following for Private CC's only) A copy of this Construction Certificate is
held on Council File No. …..
This following version is only used when construction of the OSD system is
being deferred, which will only be permitted by Council in exceptional
circumstances.
"The registered proprietor shall not erect or suffer the erection of any dwelling
house or other structure on the lot(s) hereby burdened unless the registered
proprietor has first constructed or has made provision for the construction of
an on-site stormwater detention system on the said lot(s), in accordance with
the design, construction and/or provision requirements of, and to the
satisfaction of Blacktown City Council.
Overland Flowpath
(a) Do any act, matter or thing which would prevent the overland
flowpath from operating in a safe and efficient manner.
ENGINEERING GUIDE FOR DEVELOPMENT - February 2005
F - 10
BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005
This restriction shall bind all persons who are or claim under the registered
proprietor(s) as stipulated in Section 88E(5) of the Conveyancing Act 1919.
For the purposes of this restriction "overland flowpath" means the works
constructed on the land (including all access pavements, pipes, drains, kerbs,
pits, grates and surfaces designed to convey stormwater through the site)
shown on plans approved by ………. as Construction Certificate No. ……….
on ………. and contained within the aforementioned Easement to Drain Water
variable width/…..m wide. (Include the following for Private CC's only) A
copy of this Construction Certificate is held on Council File No. …..
1. Do any act, matter or thing which would prevent the device from
operating in a safe and efficient manner.
2. Make or permit or suffer the making of any alterations or additions to
the device.
3. Allow any development within the meaning of the Environmental
Planning and Assessment Act 1979 to encroach upon the device.
This restriction shall bind all persons who are or claim under the registered
proprietor(s) as stipulated in Section 88E(5) of the Conveyancing Act 1919.
For the purpose of this restriction, "the device" means the ………. (e.g.
"Humeceptor") stormwater quality improvement device constructed and/or
installed on the land as detailed on the plans approved by ………. as
Construction Certificate No. ………. on ………., including all ancillary
gutters, pipes, drains, walls, kerbs, pits, grates, tanks, chambers, basins and
surfaces designed to treat stormwater, as well as all surfaces graded to direct
ENGINEERING GUIDE FOR DEVELOPMENT - February 2005
F - 11
BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005
Floor Level
The floor level of any building erected on the burdened lot shall be a minimum
of ….. metres above the designed 1% Annual Exceedance Probability top
water level in the overland flowpath/open channel/ drainage easement (delete
where non applicable) on lot …../within the site.
3. POSITIVE COVENANTS
(a) Keep the system clean and free from silt, rubbish and debris.
(b) Maintain and repair at the sole expense of the registered
proprietor(s) that part of the system contained within the
registered proprietor's own lot, so that it functions in a safe and
efficient manner, in accordance with the "On-Site Detention
Maintenance Schedule" as approved by ………. on ………., a
copy of which is attached, and also held on Council File
……….. A copy of this Schedule is available to all owners and
occupiers of the burdened lot(s).
(c) For the purpose of ensuring observance of this covenant, permit
Blacktown City Council or its authorised agents (hereinafter
referred to as "the Council") from time to time and upon giving
reasonable notice (but at any time and without notice in the
case of an emergency) to enter the land and inspect the
condition of the system and the state of construction,
maintenance or r epair of t he s ystem, f or c ompliance w ith t he
requirements of this covenant.
(d) Comply with the terms of any written notice issued by the
Council to attend to any matter and carry out such work within
the time stated in the notice, to ensure the proper and efficient
performance of the system and to that extent Section 88F(2)(a)
of t he C onveyancing A ct 1919 ( hereinafter r eferred t o a s " the
Act") is hereby agreed to be amended accordingly.
(e) Notify Council after each programmed maintenance inspection.
2. Pursuant to Section 88F (3) of the Act the Council shall have the
following additional powers pursuant to this covenant:
ENGINEERING GUIDE FOR DEVELOPMENT - February 2005
F - 12
BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005
(a) In the event that the registered proprietor fails to comply with
the terms of any written notice issued by the Council as set out
above, the Council may enter the land with all necessary
equipment and carry out any work considered by Council to be
reasonable to comply with the said notice referred to in 1(d)
above.
(b) The Council may recover from the registered proprietor in a
court of competent jurisdiction:
3. This covenant shall bind all persons who are or claim under the
registered proprietor(s) as stipulated in Section 88E(5) of the Act.
For the purposes of this covenant, "the system" means the on-site stormwater
detention system constructed on the land as detailed on the plans approved by
………. as Construction Certificate No. ………. on ………., including all
ancillary gutters, pipes, drains, walls, kerbs, pits, grates, tanks, chambers,
basins and surfaces designed to temporarily detain stormwater, as well as all
surfaces graded to direct stormwater to the temporary storage. (Include the
following for Private CC's only) A copy of this Construction Certificate is
held on Council File No. …..
Overland Flowpath
(a) Keep the overland flowpath clean and free from silt, rubbish
and debris.
(b) Maintain and repair at the sole expense of the registered
proprietor(s) that part of the overland flowpath contained
ENGINEERING GUIDE FOR DEVELOPMENT - February 2005
F - 13
BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005
3. This covenant shall bind all persons who are or claim under the
registered proprietors as stipulated in Section 88E(5) of the Act.
F - 14
BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005
For the purposes of this covenant, "overland flowpath" means the works
constructed on the land (including all access pavements, pipes, drains, kerbs,
pits, grates and surfaces designed to convey stormwater through the site)
shown on plans approved by ………. as Construction Certificate No. ……….
on ………. and contained within the aforementioned Easement to Drain Water
variable width/…..m wide. (Include the following for Private CC's only) A
copy of this Construction Certificate is held on Council File No. …..
(a) Keep the device clean and free from silt, rubbish and debris
(b) Maintain and repair the device at the sole expense of the
registered proprietor(s), so that it functions in a safe and
efficient manner, in accordance with the manufacturer's
recommended requirements and/or the "Maintenance Schedule"
prepared by ………. on ………., a copy of which is held on
Council File ……….. A copy of this Schedule is available to
all owners and occupiers of the burdened lot(s).
(c) For the purpose of ensuring observance of this covenant, permit
Blacktown City Council or its authorised agents (hereinafter
referred to as "the Council") from time to time and upon giving
reasonable notice (but at any time and without notice in the
case of an emergency) to enter the land and inspect the
condition of the device and the state of construction,
maintenance or repair of the device, for compliance with the
requirements of this covenant.
(d) Provide to the Council each year on or before 1 September
an annual maintenance report ("Report") outlining all
maintenance undertaken on the Device in accordance with the
Maintenance Schedule or industry best practice. Copies are to
be provided with the Report of all cleaning reports and tipping
dockets to demonstrate that all material removed was disposed
of in an approved manner.
(e) Comply with the terms of any written notice issued by the
Council to attend to any matter and carry out such work within
the time stated in the notice, to ensure the proper and efficient
performance of the device and to that extent Section 88F(2)(a)
of the Conveyancing Act 1919 (hereinafter referred to as "the
Act") is hereby agreed to be amended accordingly.
F - 15
BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005
2. Pursuant to Section 88F(3) of the Act the Council shall have the
following additional powers pursuant to this covenant:
(a) In the event that the registered proprietor fails to comply with
the terms of any written notice issued by the Council as set out
above, the Council may enter the land with all necessary
equipment and carry out any work considered by Council to be
reasonable to comply with the said notice referred to in 1(e)
above.
(b) The Council may recover from the registered proprietor in a
court of competent jurisdiction:
I. Any expense reasonably incurred by it in exercising its
powers in sub-paragraph 2(a) above. Such expense
shall include reasonable wages for employees engaged
in effecting, supervising and administering the said
work, together with costs, reasonably estimated by
Council, for the use of materials, machinery, tools and
equipment used in conjunction with the said work.
II. Legal costs on an indemnity basis for issue of the said
notices and recovery of the said costs and expenses
together with the costs, charges, and expenses of
registration of a covenant charge pursuant to Section
88F of the Act or providing any certificate required
pursuant to Section 88G of the act or obtaining any
injunction pursuant to Section 88H of the Act.
3. This covenant shall bind all persons who are or claim under the
registered proprietor(s) as stipulated in Section 88E(5) of the Act.
For the purposes of this covenant, "the device" means the
………. (e.g. "Humeceptor") stormwater quality improvement
device constructed and/or installed on the land as detailed on
the plans approved by ………. as Construction Certificate No.
………. on ………., including all ancillary gutters, pipes, drains,
walls, kerbs, pits, grates, tanks, chambers, basins and surfaces
designed to treat stormwater, as well as all surfaces graded to direct
stormwater to the device. (Include the following for Private CC's
only) A copy of this Construction Certificate is held on Council File
No. …..
F - 16
BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005
The proprietor of the lot hereby burdened will in respect of the right of
carriageway within the benefited lot #ly referred to in the abovementioned
plan:
(a) maintain the driveway surface and any associated drainage system in
reasonable working condition and
(b) repair and/or restore any or all of the driveway surface and associated
drainage system as nearly as practicable, to its former condition and
(c) share the costs of the abovementioned works equally (or proportionally
to usage) with all other proprietors of other lots similarly burdened by
this covenant.
F - 17
BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005
1. The recitals for the above easements required by Integral Energy Australia are
quite lengthy and therefore subject to typographical errors in the preparation
of 88B instruments.
2. In an effort to minimise the potential for errors and also to simplify the
creation of these easements, Integral Energy Australia have had the recitals
registered with the Land and Property Information NSW.
5. Please note therefore, that the following inclusions in Part 2 of an 88B are now
acceptable:
F - 18
BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005
6. Of course, the inclusion of the full recital as set out by Integral Energy
Australia will also continue to be acceptable, however, over time its use will
most likely decline.
F - 19
BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005
PART 1
TERMS OF RIGHT OF CARRIAGEWAY .…. REFERRED TO IN ABOVEMENTIONED
PLAN:
Full and free right for the body in whose favour this easement is created, and every person
authorised by it, to go, pass and repass at all times and for all purposes with or without
animals or vehicles or both over the land indicated herein as the servient tenement.
PART 2
TERMS OF RIGHT OF FOOTWAY ….. REFERRED TO IN ABOVEMENTIONED
PLAN:
Full and free right for the body in whose favour this easement is created and every person
authorised by it, to go, pass and repass at all times and for all purposes without animals or
vehicles over the land indicated herein as the servient tenement.
PART 3
TERMS OF EASEMENT TO DRAIN WATER ….. REFERRED TO IN
ABOVEMENTIONED PLAN:
Full and free right for the body in whose favour this easement is created, and every person
authorised by it, from time to time and at all times to drain water (whether rain, storm, spring,
soakage, or seepage water) in any quantities across and through the land herein indicated as
the servient tenement, together with the right to use, for the purposes of the easement, any
line of pipes already laid within the servient tenement for the purpose therefore and where no
such line of pipes in replacement or in substitution therefore and where no such line of pipes
exists, to lay, place and maintain a line of pipes of sufficient internal diameter beneath or
upon the surface of the servient tenement, and together with the right for the body in whose
favour this easement is created and every person authorised by it, with any tools, implements,
or machinery, necessary for the purpose, to enter upon the servient tenement and to remain
there for any reasonable time for the purpose of laying, inspecting, cleansing, repairing,
maintaining, or renewing such pipe line or any part thereof and for any of the aforesaid
purposes to open the soil of the servient tenement to such extent as may be necessary
provided that the body in whose favour this easement is created and the persons authorised by
it will take all reasonable precautions to ensure as little disturbance as possible to the surface
of the servient tenement and will restore that surface as nearly as practicable to its original
condition.
F - 20
BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005
PART 4
TERMS OF EASEMENT TO DRAIN SEWAGE ….. REFERRED TO IN
ABOVEMENTIONED PLAN:
Full and free right for the body in whose favour this easement is created, and every person
authorised by it, from time to time and at all times by means of pipes to drain sewage and
other waste material and fluid in any quantities across and through the land herein indicated
as the servient tenement, together with the right to use, for the purposes of the easement, any
line of pipes already laid within the servient tenement for the purpose of draining sewage or
any pipe or pipes in replacement or in substitution therefore and where no such line of pipes
exists, to lay, place and maintain a line of pipes of sufficient internal diameter beneath or
upon the surface of the servient tenement, and together with the right for the body in whose
favour this easement is created and every person authorised by it, with any tools, implements,
or machinery, necessary for the purpose, to enter upon the servient tenement and to remain
there for any reasonable time for the purpose of laying, inspecting, cleansing, repairing,
maintaining, or renewing such pipe line or any part thereof and for any of the aforesaid
purposes to open the soil of the servient tenement to such extent as may be necessary
provided that the body in whose favour this easement is created and every person authorised
by it will take all reasonable precautions to ensure as little disturbance as possible to the
surface of the servient tenement and will restore that surface as nearly as practicable to its
original condition.
PART 5
TERMS OF EASEMENT FOR REPAIRS ….. REFERRED TO IN ABOVEMENTIONED
PLAN:
(a) at the expiration of at least one week's notice served on the owner or occupier
of a lot burdened, use the lot for the purpose of carrying out necessary work on
any surface used by that body which cannot otherwise reasonably be carried
out, and
2. In exercising those powers, the body having the benefit of this easement must:
(a) ensure all work on the lot benefited is done properly and carried out as quickly
as is practicable, and
(b) cause as little inconvenience as is practicable to the owner and any occupier of
the lot burdened, and
F - 21
BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005
(c) cause as little damage as is practicable to the lot burdened and any
improvement on it, and
(d) restore the lot burdened as nearly as is practicable to its former condition, and
PART 6
TERMS OF EASEMENT FOR DRAINAGE OF SEWAGE ….. REFERRED TO IN
ABOVEMENTIONED PLAN:
(a) drain sewage, sullage and other fluid wastes in pipes through each lot
burdened, but only within the site of this easement, and
2. In exercising those powers, the body having the benefit of this easement must:
(b) cause as little inconvenience as is practicable to the owner and any occupier of
the lot burdened, and
(c) cause as little damage as is practicable to the lot burdened and any
improvement on it, and
(d) restore the lot burdened as nearly as is practicable to its former condition, and
PART 7
TERMS OF EASEMENT FOR DRAINAGE OF WATER ….. REFERRED TO IN
ABOVEMENTIONED PLAN:
(a) drain water from any natural source through each lot burdened, but only
within the site of this easement, and
(b) do anything reasonably necessary for that purpose, including:
F - 22
BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005
2. In exercising those powers, the body having the benefit of this easement must:
(b) cause as little inconvenience as is practicable to the owner and any occupier of
the lot burdened, and
(c) cause as little damage as is practicable to the lot burdened and any
improvement on it, and
(d) restore the lot burdened as nearly as is practicable to its former condition, and
PART 8
TERMS OF EASEMENT FOR ELECTRICITY PURPOSES ….. REFERRED TO IN
ABOVEMENTIONED PLAN:
(a) transmit electricity through each lot burdened, but only within the site of this
easement, and
2. In exercising those powers, the body having the benefit of this easement must:
(b) cause as little inconvenience as is practicable to the owner and any occupier of
the lot burdened, and
(c) cause as little damage as is practicable to the lot burdened and any
improvement on it, and
ENGINEERING GUIDE FOR DEVELOPMENT - February 2005
F - 23
BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005
(d) restore the lot burdened as nearly as is practicable to its former condition, and
PART 9
TERMS OF EASEMENT FOR SERVICES ….. REFERRED TO IN ABOVEMENTIONED
PLAN:
(a) provide domestic services supplied by that body through each lot burdened,
but only within the site of this easement, and
2. In exercising those powers, the body having the benefit of this easement must:
(b) cause as little inconvenience as is practicable to the owner and any occupier of
the lot burdened, and
(c) cause as little damage as is practicable to the lot burdened and any
improvement on it, and
(d) restore the lot burdened as nearly as is practicable to its former condition, and
PART 10
TERMS OF EASEMENT FOR WATER SUPPLY ….. REFERRED TO IN
ABOVEMENTIONED PLAN:
F - 24
BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005
2. In exercising those powers, the body having the benefit of this easement must:
(b) cause as little inconvenience as is practicable to the owner and any occupier of
the lot burdened, and
(c) cause as little damage as is practicable to the lot burdened and any
improvement on it, and
(d) restore the lot burdened as nearly as is practicable to its former condition, and
PART 11
TERMS OF RIGHT OF ACCESS ….. REFERRED TO IN ABOVEMENTIONED PLAN:
(a) by any reasonable means pass across each lot burdened, but only within the
site of this easement, for the purpose of exercising or performing any of its
powers, authorities, duties or functions and
(b) do anything reasonably necessary for passing across each lot, including:
2. In exercising those powers, the body having the benefit of this easement must:
(b) cause as little inconvenience as is practicable to the owner and any occupier of
the lot burdened, and
(c) cause as little damage as is practicable to the lot burdened and any
improvement on it, and
F - 25
BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005
(d) restore the lot burdened as nearly as is practicable to its former condition, and
F - 26
BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005
PART 1
TERMS OF RIGHT OF CARRIAGEWAY … REFERRED TO IN ABOVEMENTIONED
PLAN:
Full and free right for every person who is at any time entitled to an estate or interest in
possession in the land herein indicated as the dominant tenement or any part thereof with
which the right shall be capable of enjoyment, and every person authorised by him, to go,
pass and repass at all times and for all purposes with or without animals or vehicles or both to
and from the said dominant tenement or any such part thereof.
PART 2
TERMS OF RIGHT OF FOOTWAY ….. REFERRED TO IN ABOVEMENTIONED
PLAN:
Full and free right for every person who is at any time entitled to an estate or interest in
possession in the land herein indicated as the dominant tenement or any part thereof with
which the right shall be capable of enjoyment, and every person authorised by him, to go,
pass and repass at all times and for all purposes without animals or vehicles or both to and
from the said dominant tenement or any such part thereof.
PART 3
TERMS OF EASEMENT TO DRAIN WATER … REFERRED TO IN
ABOVEMENTIONED LAND:
Full and free right for every person who is at any time entitled to an estate or interest in
possession in the land herein indicated as the dominant tenement or any part thereof with
which the right shall be capable of enjoyment, and every person authorised by him, from time
to time and at all times to drain water (whether rain, storm, spring, soakage, or seepage water)
in any quantities across and through the land herein indicated as the servient tenement,
together with the right to use, for the purposes of the easement, any line of pipes already laid
within the servient tenement for the purpose therefore and where no such line of pipes in
replacement or in substitution therefore and where no such line of pipes exists, to lay, place
and maintain a line of pipes of sufficient internal diameter beneath or upon the surface of the
servient tenement, and together with the right for the grantee and every person authorised by
him, with any tools, implements, or machinery, necessary for the purpose, to enter upon the
servient tenement and to remain there for any reasonable time for the purpose of laying,
inspecting, cleansing, repairing, maintaining, or renewing such pipe line or any part thereof
and for any of the aforesaid purposes to open the soil of the servient tenement to such extent
as may be necessary provided that the grantee and the persons authorised by him will take all
reasonable precautions to ensure as little disturbance as possible to the surface of the servient
tenement and will restore that surface as nearly as practicable to its original condition.
ENGINEERING GUIDE FOR DEVELOPMENT - February 2005
F - 27
BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005
PART 4
TERMS OF EASEMENT TO DRAIN SEWAGE ….. REFERRED TO IN
ABOVEMENTIONED PLAN:
Full and free right for every person who is at any time entitled to an estate or interest in
possession in the land herein indicated as the dominant tenement or any part thereof with
which the right shall be capable of enjoyment, and every person authorised by him, from time
to time and at all times by means of pipes to drain sewage and other waste material and fluid
in any quantities across and through the land herein indicated as the servient tenement,
together with the right to use, for the purposes of the easement, any line of pipes already laid
within the servient tenement for the purpose of draining sewage or any pipe or pipes in
replacement or in substitution therefore and where no such line of pipes exists, to lay, place
and maintain a line of pipes of sufficient internal diameter beneath or upon the surface of the
servient tenement, and together with the right for the grantee and every person authorised by
him, with any tools, implements, or machinery, necessary for the purpose, to enter upon the
servient tenement and to remain there for any reasonable time for the purpose of laying,
inspecting, cleansing, repairing, maintaining, or renewing such pipe line or any part thereof
and for any of the aforesaid purposes to open the soil of the servient tenement to such extent
as may be necessary provided that the grantee and the persons authorised by him will take all
reasonable precautions to ensure as little disturbance as possible to the surface of the servient
tenement and will restore that surface as nearly as practicable to its original condition.
PART 5
TERMS OF EASEMENT FOR REPAIRS ….. REFERRED TO IN ABOVEMENTIONED
PLAN:
(a) at the expiration of at least one week's notice served on the owner or occupier
of a lot burdened, use the lot burdened for the purpose of carrying out
necessary work on, or on any structure on, the lot benefited which cannot
otherwise reasonably be carried out,
2. In exercising those powers, the body having the benefit of this easement must:
(a) ensure all work on the lot benefited is done properly and carried out as quickly
as is practicable, and
(b) cause as little inconvenience as is practicable to the owner and any occupier of
the lot burdened, and
F - 28
BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005
(c) cause as little damage as is practicable to the lot burdened and any
improvement on it, and
(d) restore the lot burdened as nearly as is practicable to its former condition, and
PART 6
TERMS OF EASEMENT FOR BATTER ….. REFERRED TO IN ABOVEMENTIONED
PLAN:
(a) construct and maintain on the lot burdened, but only within the site of this
easement, whatever batter or embankment is reasonably necessary to support
the surface or subsurface of the lot benefited or any part of it, or any structure
or works on the lot benefited, and
(b) use the site of this easement, or any other part of the lot burdened, or any other
land, in a way which may detract from the stability of or the support provided
by the batter or embankment.
3. If the owner of the lot burdened does or allows anything to be done which damages
the batter or embankment or impairs its effectiveness, the owner of the lot benefited
may serve no less than 14 days notice on the owner of the lot burdened requiring the
damage to be repaired or the impairment removed.
If the owner of the lot burdened does not comply with the notice, the owner of the lot
benefited may enter and repair the damage or remove the impairment and may
recover any reasonable costs from the owner of the lot burdened.
4. In exercising those powers, the body having the benefit of this easement must:
(b) cause as little inconvenience as is practicable to the owner and any occupier of
the lot burdened, and
F - 29
BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005
(c) cause as little damage as is practicable to the lot burdened and any
improvement on it, and
(d) restore the lot burdened as nearly as is practicable to its former condition, and
PART 7
TERMS OF EASEMENT FOR DRAINAGE OF SEWAGE ….. REFERRED TO IN
ABOVEMENTIONED PLAN:
(a) drain sewage, sullage and other fluid wastes in pipes through each lot
burdened, but only within the site of this easement, and
(b) cause as little inconvenience as is practicable to the owner and any occupier of
the lot burdened, and
(c) cause as little damage as is practicable to the lot burdened and any
improvement on it, and
(d) restore the lot burdened as nearly as is practicable to its former condition, and
PART 8
TERMS OF EASEMENT FOR DRAINAGE OF WATER ….. REFERRED TO IN
ABOVEMENTIONED PLAN:
(a) drain water from any natural source through each lot burdened, but only
within the site of this easement, and
F - 30
BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005
(b) cause as little inconvenience as is practicable to the owner and any occupier of
the lot burdened, and
(c) cause as little damage as is practicable to the lot burdened and any
improvement on it, and
(d) restore the lot burdened as nearly as is practicable to its former condition, and
PART 9
TERMS OF EASEMENT FOR ELECTRICITY PURPOSES ….. REFERRED TO IN
ABOVEMENTIONED PLAN:
(a) transmit electricity through each lot burdened, but only within the site of this
easement, and
2. In exercising those powers, the body having the benefit of this easement must:
(b) cause as little inconvenience as is practicable to the owner and any occupier of
the lot burdened, and
(c) cause as little damage as is practicable to the lot burdened and any
improvement on it, and
(d) restore the lot burdened as nearly as is practicable to its former condition, and
F - 31
BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005
PART 10
TERMS OF EASEMENT FOR OVERHANG ….. REFERRED TO IN
ABOVEMENTIONED PLAN:
(a) insist that the parts of the structure (the overhanging structure) on the lot
benefited which, when this easement was created, overhung the lot burdened
remain, but only to the extent they are within the site of this easement, and
(b) must keep the overhanging structure in good repair and safe condition, and
2. In exercising those powers, the body having the benefit of this easement must:
(b) cause as little inconvenience as is practicable to the owner and any occupier of
the lot burdened, and
(c) restore the lot burdened as nearly as is practicable to its former condition, and
3. The owner of the lot burdened may insist that this easement be extinguished when the
structure on the lot benefited is removed.
4. The owner of the lot burdened must not do or allow anything to be done to damage or
interfere with the overhanging structure.
PART 11
TERMS OF EASEMENT FOR SERVICES ….. REFERRED TO IN ABOVEMENTIONED
PLAN:
(a) use each lot burdened, but only within the site of this easement, to provide
domestic services to or from each lot burdened, and
F - 32
BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005
2. In exercising those powers, the body having the benefit of this easement must:
(b) cause as little inconvenience as is practicable to the owner and any occupier of
the lot burdened, and
(c) cause as little damage as is practicable to the lot burdened and any
improvement on it, and
(d) restore the lot burdened as nearly as is practicable to its former condition, and
3. For the purpose of this easement, domestic services includes supply of water, gas,
electricity, telephone and television and discharge of sewage, sullage and other fluid
wastes.
PART 12
TERMS OF EASEMENT FOR WATER SUPPLY ….. REFERRED TO IN
ABOVEMENTIONED PLAN:
(a) run water in pipes through each lot burdened, but only within the site of this
easement, and
2. In exercising those powers, the body having the benefit of this easement must:
(b) cause as little inconvenience as is practicable to the owner and any occupier of
the lot burdened, and
F - 33
BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005
(c) cause as little damage as is practicable to the lot burdened and any
improvement on it, and
(d) restore the lot burdened as nearly as is practicable to its former condition, and
PART 13
TERMS OF EASEMENT TO PERMIT ENCROACHING STRUCTURE TO REMAIN …..
REFERRED TO IN ABOVEMENTIONED PLAN:
(a) insist that the parts of the structure (the encroaching structure) on the lot
benefited which, when this easement was created, encroached on the lot
burdened remain, but only to the extent they are within the site of this
easement, and
(b) must keep the encroaching structure in good repair and safe condition, and
2. In exercising those powers, the body having the benefit of this easement must:
(b) cause as little inconvenience as is practicable to the owner and any occupier of
the lot burdened, and
(c) restore the lot burdened as nearly as is practicable to its former condition, and
3. The owner of the lot burdened may insist that this easement be extinguished when the
structure on the lot benefited is removed.
4. The owner of the lot burdened must not do or allow anything to be done to damage or
interfere with the encroaching structure.
F - 34
BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005
PART 14
TERMS OF RIGHT OF ACCESS ….. REFERRED TO IN ABOVEMENTIONED PLAN:
(a) by any reasonable means pass across each lot burdened, but only within the
site of this easement, to get to or from the lot benefited, and
2. In exercising those powers, the body having the benefit of this easement must:
(b) cause as little inconvenience as is practicable to the owner and any occupier of
the lot burdened, and
(c) cause as little damage as is practicable to the lot burdened and any
improvement on it, and
(d) restore the lot burdened as nearly as is practicable to its former condition, and
F - 35
BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005
APPENDIX G
EXAMPLE OF A
LOT FILL PLAN
APPENDIX H
EXAMPLE
EASEMENT CERTIFICATE
APPENDIX H
EXAMPLE CERTIFICATE
Council Ref:
General Manager
Blacktown City Council
DX 8117
BLACKTOWN
Dear Sir,
Our final Plan of Subdivision bearing the abovementioned description and reference intends
to create the following easements over the specified lots.
Drainage pipes and associated structures are laid wholly within the easements to be created
by registration of the accompanying linen plan.
Yours faithfully,
Signature
Name of Surveyor
(Please Print)
H-1
BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005
APPENDIX I
STANDARD
DRAWINGS
APPENDIX I
STANDARD DRAWINGS
I-1
BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005
A(BS)124M Typical locations for signs and markings associated with Wombat Crossings
A(BS)128S Specification for Bus Shelter Concrete Base/Apron - with Path Paving
A(BS)129S Specification for Bus Shelter Concrete Base/Apron - without Path Paving
A(BS)136S Removed
A(BS) 143M Pedestrian Refuge Guideline (currently under review see AS 1742.10 or RMS
Technical directive 2011-01A)
I-2
BRACKET ALUMINIUM
3mm THICK MIN. LENGTH 500 END MOUNTED
MAX. LENGTH1200 END MOUNTED
PRE-PRINTED UV INK ON MAX. LENGTH 1800 CENTRE MOUNTED
LAMINATE LOGO.
15
10
SEE SHT. 3 FOR DETAIL
WILLIAM LAWSON DR
200
180
185
15
Blacktown
City Council
10
BLADE AND BRACKET SUPPLIED AND ORDER NUMBER. BOLTS, NUTS AND WASHERS SHALL BE GALVANISED AND OF
6
SUITABLE SIZE.
2.0 SIGN BLADE
2.1 SIGNS SHALL BE MANUFACTURED FROM AN APPROVED 5.0 TOLERANCE
12
MARINE GRADE HIGH TENSILE STRENGTH ALUMINIUM MANUFACTURING TOLERANCES OF SIGNS SHALL BE SPECIFIED IN SECTION
EXTRUSION WITH SQUARE END. 4 - MANUFACTURING AND MATERIALS OF A.S. 1743:2018 SPECIFICATIONS.
2.2 THE LENGTH OF THE SIGNS SHALL NOT BE MORE THAN 6.0 PROTECTION AND PACKAGING
1800mm. PROTECTION AND PACKAGING OF ALL BLADES, BRACKETS AND
ASSOCIATED FITTINGS FOR DELIVERY TO COUNCIL SHALL BE THE
2.3 THE FLANGES SHALL BE 18mm MINIMUM WIDTH AND NO RESPONSIBILITY OF THE SUPPLIER. SIGNS ARE TO BE PROTECTED 2
200
LESS THAN 6mm THICK, THE FILLET SHALL BE NOT LESS FROM DAMAGE DURING TRANSIT BY APPROVED WRAPPING PRIOR
THAN 5mm WIDE AND 7mm MINIMUM THICKNESS AND THE TO DELIVERY.
WEB SHALL BE 2mm MINIMUM THICKNESS (REFER DETAIL A)
2.4 THE BLADES SHALL BE PRE-DRILLED TO COINCIDE WITH 7.0 WARRANTY
THE POSITION AND DIAMETER OF THE BRACKETS. ALL STREET SIGN BLADES SHALL CARRY A 8 YEAR PERFORMANCE
THE BLADES SHALL BE 200mm BLADES. WARRANTY FROM THE RETRO-REFLECTIVE MATERIAL
MANUFACTURER. DETAILS OF THE PERFORMANCE WARRANTY
10
SHALL BE SUBMITTED WITH THE QUOTATION/TENDER.
THIS DRAWING MAY BE PREPARED IN COLOUR AND MAY BE INCOMPLETE IF COPIED
6
VINYL SHEETING BONDED TO THE PREPARED ALUMINIUM AND SPECIFICATIONS FROM COUNCIL.
EXTRUSION BLADE BY THE APPROVED METHOD TO MEET
AS/NZ 1906.1:2017 APPLICABLE FOR A 8 YEAR DURABILITY/WARRANTY. 2. END MOUNTED SIGNS MUST HAVE STREET NAME ON BOTH
THE SHEETING SHALL EXTEND FOR THE FULL LENGTH OF THE SIDES. DETAIL A
BLADE AND BE UNSPLICED ALONG ITS ENTIRE LENGTH. N.T.S.
THE MINIMUM WIDTH OF THE BACKGROUND MATERIAL SHALL 3. DOUBLE ENDED SIGNS (CENTRE MOUNTED) HAVE STREET NAME
BE 175mm FOR 200mm BLADES. ON ONE SIDE ONLY.
----
REV DATE DESCRIPTION CHECKED APPROVED DATE SCALE DO NOT SCALE FROM DRAWING DRAWINGS / DESIGN PREPARED BY TITLE NAME DATE PROJECT
SURVEYED B.C.C. STANDARD DRAWINGS A1
DESIGNED ---- SHEET
DRAWN KC STANDARD STREET NAMES & POSTS
CHECKED
Blacktown TITLE
1
City Council OF
ACCEPTED
STREET NAME BLADE SPECIFICATION
N.T.S. Lic No.QAC/R61/0103
3
G NOV. '18 REDRAWN - NEW SIGN, NEW LOGO & NOTES REVISED XX XX DD.MM.YY MANAGER ASSET DESIGN
DATE COUNCIL CHAMBERS: 62 FLUSHCOMBE ROAD, BLACKTOWN, NSW 2148
CO-ORDINATE SYSTEM HEIGHT DATUM ASSET DESIGN
DRAWING FILE LOCATION / NAME
I:\TTSHARE\STANDARD DRAWINGS\A(BS)113MStSignPosts\A(BS)113M.dwg
PLOT DATE / TIME
13.02.2019 / 11:52 AM
PLOT BY
cleggk MGA ZONE 56 AHD
ALL MAIL: GENERAL MANAGER, PO BOX 63, BLACKTOWN, NSW 2148
TELEPHONE: (02) 9839 6000 FAX: (02) 9831 1961 DX : 8117 BLACKTOWN
CAD FILE
A(BS)113M.dwg
FILE No
----
PLAN No
A(BS)113M REV
G
MINIMUM LENGTH 500 MAXIMUM LENGTH 1800
35 MAXIMUM LENGTH 1200
ALUMINIUM BRACKET
Blacktown
City Council
WILLIAM LAWSON DR Blacktown
City Council
WILLIAM LAWSON DR
GALVANISED BOLTS,
NUTS AND WASHERS.
DETAIL 1
SINGLE ENDED SIGN DOUBLE ENDED SIGN BRACKET FOR ATTACHING
SIGN PLATE FOOTING DETAILS AS PER SINGLE ENDED SIGN SINGLE SIGN TO STEEL POST
2400 MIN.
FOR DETAILS REFER SHT. 1.
SIGN PLATE
DETAILS GENERALLY AS FOR SINGLE ENDED
SIGN UNLESS OTHEWISE SPECIFIED.
REFER SHT. 1 AND BRACKET DETAIL FOR
CENTRE MOUNTING.
560 MAX. DETAIL 3
BRACKET FOR ATTACHING
TOP OF KERB THREE SIGNS TO STEEL POST
DETAIL 2
220
STANDARD
KERB NORMAL BACKFILL BRACKET FOR ATTACHING
MATERIAL. GALVANISED
AND END CAP.
GUTTER 13Ø HOLES FOR TWO SIGNS TO STEEL POST
ANCHOR ROD.
380
330
CENTRALLY MOUNTED.
REFER DETAIL 5. REFER DETAIL 4.
DETAIL 4
CHEVRON "HAZARD" BARRIER
BENJAMIN CR DAV
ID R
OAD
TO BE ERECTED WHERE DIRECTED. RID
GE
ROA
D BRACKET FOR ATTACHING
SINGLE SIGN TO TIMBER POST
D
ROA
GE
BRID
2400 MIN
D
ROA
HAM
ING
B IRM
A D
MINO R O NETA
DRIVE
2400 MIN.
GEOR
GE DR
SUSAN IVE
DRIVE
AD
RO
VID
DA
THIS DRAWING MAY BE PREPARED IN COLOUR AND MAY BE INCOMPLETE IF COPIED
ROA
D GROOVE ON SIGN
PLATE FOR BOLTS
O R ATTACHED TO BRACKET.
J DETAIL 5
MA END MOUNTED. BRACKET FOR ATTACHING
REFER DETAIL 2.
REFER DETAIL 1.
STREET SIGNS MOUNTED EXTRA LENGTH SIGN TO MULTIPLE
ON TIMBER POWER POLES POSTS OR CENTRE MOUNTED
STREET SIGNS AT INTERSECTION STREET SIGNS AT JUNCTIONS DOUBLE ENDED SIGN
----
REV DATE DESCRIPTION CHECKED APPROVED DATE SCALE DO NOT SCALE FROM DRAWING DRAWINGS / DESIGN PREPARED BY TITLE NAME DATE PROJECT
SURVEYED B.C.C. STANDARD DRAWINGS A1
DESIGNED ---- SHEET
DRAWN KC STANDARD STREET NAMES & POSTS
CHECKED
Blacktown TITLE
2
City Council OF
ACCEPTED
DETAILS
N.T.S. Lic No.QAC/R61/0103
3
G NOV. '18 REDRAWN - NEW SIGN, NEW LOGO & NOTES REVISED XX XX DD.MM.YY MANAGER ASSET DESIGN
DATE COUNCIL CHAMBERS: 62 FLUSHCOMBE ROAD, BLACKTOWN, NSW 2148
CO-ORDINATE SYSTEM HEIGHT DATUM ASSET DESIGN
DRAWING FILE LOCATION / NAME
I:\TTSHARE\STANDARD DRAWINGS\A(BS)113MStSignPosts\A(BS)113M.dwg
PLOT DATE / TIME
13.02.2019 / 11:52 AM
PLOT BY
cleggk MGA ZONE 56 AHD
ALL MAIL: GENERAL MANAGER, PO BOX 63, BLACKTOWN, NSW 2148
TELEPHONE: (02) 9839 6000 FAX: (02) 9831 1961 DX : 8117 BLACKTOWN
CAD FILE
A(BS)113M.dwg
FILE No
----
PLAN No
A(BS)113M REV
G
THIS DRAWING MAY BE PREPARED IN COLOUR AND MAY BE INCOMPLETE IF COPIED
----
REV DATE DESCRIPTION CHECKED APPROVED DATE SCALE DO NOT SCALE FROM DRAWING DRAWINGS / DESIGN PREPARED BY TITLE NAME DATE PROJECT
SURVEYED B.C.C. STANDARD DRAWINGS A1
DESIGNED ---- SHEET
DRAWN KC STANDARD STREET NAMES & POSTS
CHECKED
Blacktown TITLE
3
City Council OF
ACCEPTED
LOGO DETAILS
N.T.S. Lic No.QAC/R61/0103
3
G NOV. '18 REDRAWN - NEW SIGN, NEW LOGO & NOTES REVISED XX XX DD.MM.YY MANAGER ASSET DESIGN
DATE COUNCIL CHAMBERS: 62 FLUSHCOMBE ROAD, BLACKTOWN, NSW 2148
CO-ORDINATE SYSTEM HEIGHT DATUM ASSET DESIGN
DRAWING FILE LOCATION / NAME
I:\TTSHARE\STANDARD DRAWINGS\A(BS)113MStSignPosts\A(BS)113M.dwg
PLOT DATE / TIME
13.02.2019 / 11:52 AM
PLOT BY
cleggk MGA ZONE 56 AHD
ALL MAIL: GENERAL MANAGER, PO BOX 63, BLACKTOWN, NSW 2148
TELEPHONE: (02) 9839 6000 FAX: (02) 9831 1961 DX : 8117 BLACKTOWN
CAD FILE
A(BS)113M.dwg
FILE No
----
PLAN No
A(BS)113M REV
G