Rectification Order: Project Name: Cambodia China Polytechnic University (CPPU)
Rectification Order: Project Name: Cambodia China Polytechnic University (CPPU)
Rectification Order: Project Name: Cambodia China Polytechnic University (CPPU)
Diameter: 675 mm
Concrete cover: 35 mm
Chipped edge: 35 mm
To make it as formal rectifying, contractor need to repair those structural elements which have
mentioned above with report.
Technical or design team should prepare method statement and submit to relevant parties in order
to have correct repairing procedure at site with good result.