4.1 Pert and CPM
4.1 Pert and CPM
Scheduling
UNIT - 4
Introduction- CPM
•What are the critical activities which could delay the entire
project if they were not completed on time?
Activity: An activity is an effort that requires resources and takes a certain amount
of time for completion. Examples of activities are: studying for an examination,
designing a part, connecting bridge girders, or training an employee.
Critical activity: A critical activity is an activity that, if even slightly de-layed, will
hold up the scheduled completion date of the entire project.
Path: A path is a series of adjacent activities leading from one event to another.
Critical path: A critical path is the sequence of critical activities that forms a
continuous path between the start of a project and its completion.
The Project Network Concurrent Activities
AOA Network
AON Network
A Sample Set of Project Activities
and Precedences
Task Predecessor
a --
b --
c a
d b
e b
f c, d
g e
Figure 1 Stage 1 of a Sample AON
Network
Figure 2 Stage 2 of a Sample AON
Network
Figure 3 A Completed Sample
AON Network
Figure 4 Stage 1 of a Sample AOA
Network
Figure 5 Stage 2 of a Sample AOA
Network
Figure 6a A Completed Sample
AOA Network
Figure 6b A Completed Sample AOA
Network Showing the Use of a Dummy Task
Event: An event is the beginning or end of an activity .Events do not
have a time duration. Event is indicated by circle in network diagram
A
15
A B
C D
C
A
B D
17
Situations in network diagram
B
A A must finish before either B or C can
start
C
A
C both A and B must finish before C can
start
B
A
C both A and B must finish before either of
C or D can start
B D
A
B
A must finish before B can start
C
D
Slack time & critical path :
20
Example
1. Construct the CPM Network using the details below and
determine the critical path
A
1 2
CPM NETWORK
D
A
1 2 7
C
3
CPM NETWORK
5
E
4
F
D 6
A
1 2 7
C
3
CPM NETWORK
5
E
G
4
F
D 6
H
A
1 2 7
C
3
CPM NETWORK
5
E
G
4
F
D 6
H
A I 8
1 2 7
C
3
CPM NETWORK
5
E
G
4
F
D 6
H
A I 8
1 2 7
C
B
J
3
CPM NETWORK with duration of each activity
5
E(3)
G(2)
4 F(3)
D(2) 6 H(1)
A(1) I(3) 8
1 2 7
C(2)
B(4)
J(2)
3
To find the Critical Path LFT
EST
5
E(3)
G(2)
4
F(3)
0
D(2) 6
H(1)
0
A(1) I(3) 8
1 2 7
C(2)
B(4)
J(2)
3
To find the Critical Path LFT
EST
5
E(3)
G(2)
4
F(3)
0 0
D(2) 6
H(1)
0 1
A(1) I(3) 8
1 2 7
C(2)
B(4)
J(2)
3
To find the Critical Path LFT
EST
5
0 E(3)
3 G(2)
4
F(3)
0 0
D(2) 6
H(1)
0 1
A(1) I(3) 8
1 2 7
C(2)
B(4)
J(2)
3
To find the Critical Path LFT
EST
0
5 6
0 E(3)
3 G(2)
4
F(3)
0 0
D(2) 6
H(1)
0 1
A(1) I(3) 8
1 2 7
C(2)
B(4)
J(2)
3
To find the Critical Path LFT
EST
0
5 6
0 E(3)
3 G(2)
4
F(3)
0 0
D(2) 6
0 H(1)
0 1 8
A(1) I(3) 8
1 2 7
C(2)
B(4)
J(2)
3
To find the Critical Path LFT
EST
0
5 6
0 E(3)
3 G(2)
4
F(3)
0 0
D(2) 6
0
0 H(1)
0 1 8 9
A(1) I(3) 8
1 2 7
C(2)
B(4)
J(2)
3
To find the Critical Path LFT
EST
0
5 6
0 E(3)
3 G(2)
4
F(3)
0 0
D(2) 6
0
0 H(1)
0 1 8 9
A(1) I(3) 8
1 2 7
C(2)
B(4)
0 J(2)
5
3
To find the Critical Path LFT
EST
0
5 6
0 E(3)
3 G(2)
4
F(3)
0 0
D(2) 6
0
0
0 H(1) 12
0 1 8 9
A(1) I(3) 8
1 2 7
C(2)
B(4)
0 J(2)
5
3
To find the Critical Path LFT
EST
0
5 6
0 E(3)
3 G(2)
4
F(3)
0 0
D(2) 6
0
12
0 H(1) 12
0 1 8 9
A(1) I(3) 8
1 2 7
C(2)
B(4)
0 J(2)
5
3
To find the Critical Path LFT
EST
0
5 6
0 E(3)
3 G(2)
4
F(3)
0 0
D(2) 6
9
12
0 H(1) 12
0 1 8 9
A(1) I(3) 8
1 2 7
C(2)
B(4)
0 J(2)
5
3
To find the Critical Path LFT
EST
0
5 6
0 E(3)
3 G(2)
4
F(3)
0 0
D(2) 6
9
12
8 H(1) 12
0 1 8 9
A(1) I(3) 8
1 2 7
C(2)
B(4)
0 J(2)
5
3
To find the Critical Path LFT
EST
6
5 6
0 E(3)
3 G(2)
4
F(3)
0 0
D(2) 6
9
12
8 H(1) 12
0 1 8 9
A(1) I(3) 8
1 2 7
C(2)
B(4)
0 J(2)
5
3
To find the Critical Path LFT
EST
6
5 6
3 E(3)
3 G(2)
4
F(3)
0 0
D(2) 6
9
12
8 H(1) 12
0 1 8 9
A(1) I(3) 8
1 2 7
C(2)
B(4)
0 J(2)
5
3
To find the Critical Path LFT
EST
6
5 6
3 E(3)
3 G(2)
4
F(3)
0 1
D(2) 6
9
12
8 H(1) 12
0 1 8 9
A(1) I(3) 8
1 2 7
C(2)
B(4)
0 J(2)
5
3
To find the Critical Path LFT
EST
6
5 6
3 E(3)
3 G(2)
4
F(3)
0 1
D(2) 6
9
12
8 H(1) 12
0 1 8 9
A(1) I(3) 8
1 2 7
C(2)
B(4)
10 J(2)
5
3
Critical Path
6
5 6
3 E(3)
3 G(2)
4
F(3)
0 1
D(2) 6
9
12
8 H(1) 12
0 1 8 9
A(1) I(3) 8
1 2 7
C(2)
B(4)
10 J(2)
5
3
Critical Path Critical Path
1-2-4–5–6–7-8 A–D-E–G–H-I
CPM NETWORK
c 4
2
7
G
A 5 D 8
7
1 B H K
4 3
E C6 7 8
8 11 11
F I2 J
5 12
5
Critical Path
1-3-6–7-8 45
Event TL T E Slack time
1 0 0 0
2 19 5 14
3 4 4 0
4 26 12 14
5 10 9 1
6 12 12 0
7 23 23 0
8 34 34 0
46
PERT
ACTIVITY DURATION
C(4) G(5)
4 6
E(7)
6-0 13-0
C(4) G(5)
4 6
E(7)
6-12 13-19
Identifying potential problem areas: The critical activities are also more
likely to become problem areas. Once identified, contingency plans may be
devised.