Section 14 PDF PDF
Section 14 PDF PDF
Section 14 PDF PDF
14.1.1 General
The capital cost estimates have been prepared for the Phase 1 development of the project.
These are based on the project descriptions and drawings given under the relevant sections of
the present report. The drawings were prepared after carrying out basic engineering of various
components of the project. The quantities have been calculated from the drawings for cost
estimation purpose. The basis of the costing is as follows:
- The cost estimates of civil works have been prepared on the basis of current rates for
various items of work prevailing in the region and also on the past costs for similar works
elsewhere.
- The costs of equipment and machinery are based on budgetary quotations and discussions
held with the manufacturers and also in-house data. The costs include all taxes and duties.
- The price level used for the estimates is as of the third quarter of 2004.
- All costs towards overheads, labour, tools, materials, insurance, financing costs, etc., are
covered in the rates for individual items.
- The costs towards plant and machinery include manufacture, supply, installation and
commissioning of the respective items.
- The exchange rate has been assumed as 1 US $ = Rs. 44.00/-, 1 Euro = Rs. 59.00/-
- Provision towards contingencies, engineering and establishment has been included
separately.
An abstract of the capital cost estimates for the Phase 1 development of the project is furnished
below in Table 14.1. The detailed capital cost estimates are presented in Table 14.2.
- Hinterland connections
- Road Bridge outside the port boundary
- Crude Oil Handling and associated facilities
- Financing Costs
14.2.1 General
Operation and maintenance costs have been calculated under various heads, as described in
the subsequent paras. These costs do not include the following items:
The following norms have been used for estimating the annual maintenance and repair costs:
It is estimated that number of personnel required for the Phase 1 port operations and
maintenance shall as below:
Managerial - 50 Nos.
Supervisors/Labours - 350 Nos.
The average total cost per annum per person has been estimated as Rs. 5,00,000/- for the
managerial staff and Rs. 1,00,000/- for the supervisors/labours.
The operation costs includes the fuel, water and power costs. These have been considered as
below:
Power - Rs. 4.50 per unit plus Rs. 200 per kVA of demand rate per month
Water Charges - Rs. 25 per kilolitre as indicated by GPL
The operation costs for the equipments run by electrical power have been calculated based on
the maximum throughput and utilisation of the equipment. Further the operation costs of the
following items have been estimated as a percentage of their capital cost, as given below:
The summary of the annual operation and maintenance costs of the phase 1 facilities is
presented in Table 14.3 below:
B. MANPOWER COSTS
1. Managerial 50 No. @ Rs. 500,000/- per annum 25.00
2. Supervisors/ Labours 350 No. @ Rs. 100,000/- per annum 35.00
Total M anpow e r Costs 60.00
C. OPERATION COSTS
1. Electricity
Electricity Consumption 41,000,000 units @ Rs 4.50 per unit 184.50
Fixed Charges on Demand Rate 30 MVA @ Rs. 200/- per kVA per month 72.00
2. Water Charges 375,000 kL per annum @ Rs. 25/- per kL 9.38
3. Marine Crafts Rs. 924 million @ 10 % per annum 92.40
4. Diesel Driven Equipments Rs. 803 million @ 5 % per annum 40.15
5. Firef ighting, Pollution Control & misc. w orks Rs. 237 million @ 3 % per annum 7.11
Total Operation Costs 405.54
Based on the estimated port facilities required over the time horizon of the master plan, the
Block Capital Cost Estimates as well as the O&M cost estimates have been worked out as
presented in Table 14.4 below:
5. BUILDINGS 180 49 64 42 57 42 85
6. STACKYARDS 203 0 51 35 40 8 48
Increm ental O&M Costs (Rs. In Million) 1,202 248 263 257 442 59 400