PP1-2M90-1043-006 - B - Inspection Test Plan - CODE B PDF

Download as pdf or txt
Download as pdf or txt
You are on page 1of 5
At a glance
Powered by AI
The document outlines the inspection and test plan for a silo, including various inspections, tests, and acceptance criteria that must be met.

Dimensional checks, visual inspections, mechanical/chemical property tests, leakage tests, cleaning checks, and others are required at various stages of fabrication and assembly as outlined on pages 1-3.

Acceptance criteria include conformance with applicable specifications and approval drawings as well as requirements for things like material identification, weld quality, dimensions, leakage, and cleanliness as specified.

SAMSUNG

ENGINEERING CO., LTD

Received
Contracct No. : LSP-C
CA-131 PP Plan
nt Page 1 of 5 EPC P
Project No. : SC0353
S 14 Oct 2020

EPC Doc.Noo.:SC0353
3-
LSP Doc.No.:: INSPE
ECTION AN
ND TEST
Rev. B MFD110P--01-J1ITP001- Rev. B
PP1-2M90-1
1043-006 PLAN 006

IN
NSPEC
CTION
N AND TEST PLAN
N

REQUISIT
TION NO. : MF
FD110P
PURCHAS
SE ORDER
R NO. : 50
000052162
VENDOR’’S DOCUME
ENT NO. : PP
P1-2M90-104
43-006
Add the applicable Tag Nos or Items No.
ITEM & TA
AG NO. : Co
ommon
ITEM DES
SCRIPTION
N : SIL
LO Package

Approved PM
B 13/10/20 Is
ssue For Apprroval CK Choi CW K
Kim SH Park
✔ Approved with comment
A 19/12/19 Is
ssue For Apprroval CKwith
Approved Choi CW K
comment / ResubmitKim SH Park
REV D
DATE(DD/MM//YY) DESCRIPTIO
ON RejectPREPARED
/ Resubmit CHEC
CKED AP
PPROVED
PE ETROCHEM
Reviewed MICAL
/ Information Only CO OMPLEX 14 Oct 2020
IN SOUTH
Reviewed with H OF
Comment VIET
/ ResubmitTNAM SAMSUNG

TỔỔ HỢP HÓA A DẦU MIỀ


This approval or review does not relieve the
ỀN
vendor / subcontractor of his responsibilities to NAM
ENGINEERING CO., LTD

Long So
on Petrochem
micals Co., Ltd
L Meet all requirements VIỆ ỆT
of the NAM
purchase order.

ORIGINAL CHECKED

SIGN.
SAMS
SUNG ENG
GINEERING
G CO., LTD
D.
DATE 14 Oct 2020 14 Oct 2020

SAMSUNG ENGINEERING CO., LTD

DYPNF CO., LT
TD

2020-10-13 17:53:24 송마리아-PC


LSP[PP Silo] Project ITP No.: SC0353-MFD110H-01-J1ITP001-006

Revision No. : B
Inspection & Test Plan for Silo
Date: 2020.10.13

Applicable Spec./ Inspection By


Description of Record /Report No.
No Inspection Detail Acceptance Remark
Inspection and Test (Verifying Document) DONG YANG SEC OWNER
Criteria

1 PIM - - MOM H H R

2 Anchor Bolt Dimensional and Visual Check with Packing Approval Drawings' Test Report WS/W SS/W R

Raw Material -Mechanical and Chemical Properties


Receiving Inspection -Identification of Materials
3 ASME SEC II Mill Certificated
(Metarial for -Transfer of Material Marking WR R R
(Material, Heat No., etc.)
Category"A"B"C"D"Weld Joint )

Non-destructive ASME.SEC.V
4 Examination - Liquid Penetration Examination ASME.SEC VIII DIV.1 Test Report W R R
(Caterory "D"100%) ASME. SEC IX

Intermediate Dimensional
Dimensional and Visual Check
and Visual Inspection for
5 Approval Drawings' Inspection Report W W
Top Nozzle to Roof and
- Tie-in Nozzle Position, Size Rating, etc
- Connection Check of Plateform to Roof
WR
Platform Pre-Assembly

6 Leak Test of Reinforcement Pad - Pad Leak Check Approval Procedure Test Report W SW R

Dimensional and Visual Check


Fit-up Inspection - Root Gap
7 Approval Drawings' - H SW R
For Final Shell("Category"B") Joint - Total Length
- Orientation

Non-destructive
ASME.SEC.V
Examination
8 - Liquid Penetration Examination ASME.SEC VIII DIV.1 Test Report W R R
(Shell L&C Weld Cross Seam 100%)
ASME. SEC IX
150mm x 150mm
One Point Per Each Lot For
Category"A"B"C"D"Weld Joint with
9 Positive Material Identification Approval Procedure Test Report W R R
Flange, Plate, Pipe, Fitting
[Except: Support, Clip, Base, Structure]

Final Dimensional Dimensional and Visual Check


10 Approval Drawings' Inspection Report H W W R
and Visual Inspection - Total Length

- Pressure Check 300mmaq


11 Pneumatic Test Approval Procedure Pneumatic Test Report H HW HW
- Leak Check

Visual
12 Acid Cleaning Approval Drawings' - W R R
-Cleaning

NOTE: R : Document Review S/W : Spot Witness (10) % W : Witness Point M : Manufacturer Inspection H : Hold Point
LSP[PP Silo] Project ITP No.: SC0353-MFD110H-01-J1ITP001-006

Revision No. : B
Inspection & Test Plan for Silo
Date: 2020.10.13

Applicable Spec./ Inspection By


Description of Record /Report No.
No Inspection Detail Acceptance Remark
Inspection and Test (Verifying Document) DONG YANG SEC OWNER
Criteria

Approval Drawings' & Data Sheet


13 Buffing Inspection Approval Drawings' Buffing Report W
[If Applicable Part] WR WR
Surface Preparation & Salt/Dust/Profile check
- Cleaning & Surface Preparation Check
13 Approval Drawings' Painting&Coating Report W
Painting - Coating Thickness Check
Adhesion test SS/W R

- Mark No.
- Process Condition
- Connection. Size, Rating
14 Packing Inspection - Name of Manufacturer Packing List Packing List W W R
- To clean and free from all defects before packing.
- To protect from any damage by plywood, tape,
or other suitable means before shipping.

SQR review SQR R R

IRC R R

NOTE: R : Document Review S/W : Spot Witness (10) % W : Witness Point M : Manufacturer Inspection H : Hold Point
Non-Destructive Examination Plan for Silo

DESCIPTION PT PMI

1 Nozzle to Roof&Shell&Cone 100% One Point Per Each Lot

2 Lifting Lug 100% N/A

10%
3 Circumferential Strength Weld of Roof&Shell&Cone One Point Per Each Lot
(T-Cross 150mm x 150mm x 150mm)

10%
4 Junction of Cone to Skirt One Point Per Each Lot
(T-Cross 150mm x 150mm x 150mm)

* PT shall be performed to the repaired area & defect area