0% found this document useful (0 votes)
331 views5 pages

5.3.1.1 BQ Preparation: Practice Example (Site Clearance) : Contract Documentation For Civil Engineering Projects 249

1) The document discusses the process for preparing a bill of quantities (BQ) for a civil engineering project. It involves measuring quantities from design drawings and specifications. 2) A 4-step process is outlined: 1) collate drawings and specs, 2) identify a standard measurement method, 3) take off and input quantities and dimensions, 4) finalize the unpriced BQ. 3) An example of preparing a BQ item for a site clearance is provided, walking through each step. This includes using the CESMM3 reference and measuring the land area to calculate the quantity in hectares.

Uploaded by

Calvinhaowei
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
331 views5 pages

5.3.1.1 BQ Preparation: Practice Example (Site Clearance) : Contract Documentation For Civil Engineering Projects 249

1) The document discusses the process for preparing a bill of quantities (BQ) for a civil engineering project. It involves measuring quantities from design drawings and specifications. 2) A 4-step process is outlined: 1) collate drawings and specs, 2) identify a standard measurement method, 3) take off and input quantities and dimensions, 4) finalize the unpriced BQ. 3) An example of preparing a BQ item for a site clearance is provided, walking through each step. This includes using the CESMM3 reference and measuring the land area to calculate the quantity in hectares.

Uploaded by

Calvinhaowei
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 5

Contract documentation for civil engineering projects  249

Prior to detailed cost estimation (Section 2.2.3) of a civil engineering


job, reference must be made to all available drawings and specifications to
allow a detailed measurement of the works and a systematic description of
the items.
Section 5.3.1.1 (acknowledging texts by Ivor Seeley and others188) pro-
vides a structured method for ‘taking-off’ quantities (traditionally take-
offs from drawings) in preparing project BQs.

5.3.1.1 BQ preparation: Practice example (site clearance)


After the preparation of their design drawings (and related specifica-
tions), the civil engineer needs to take-off and itemise the quantities of
the work under the contract. Four steps to prepare the project’s BQs are
as follows:

Step 1: Collate and review the available design drawings and specifications
Step 2: Identify a standard method of measurement consistent with require-
ments; refer to SMM in checklist fashion, to itemise/­measure all
parts of the design
Step 3: Prepare to ‘take off’ (manually or by Excel spreadsheet/software186)
to input
• SMM references
• Works descriptions in words
• Unit quantities (and respective dimensions) generated by both
default volumes/quantities from CAD design software and
remote measurement where default quantification is unavailable
• Retain ‘take off draft’ for future cost-control cross-check of
dimensions
Step 4: Transpose take-off draft items and finalise unpriced BQs

A scenario might involve the need to measure and prepare a BQ item for
a future land site clearance.

Step 1
The land to be measured for a future general site clearance is a nonuniform
rectangle depicted on a general arrangement drawing of approximately less
than 85 × 50 m; with no discernable trees, stumps, buildings, other struc-
tures or pipelines.

Step 2
The standard method of measurement to be used in this case is CESMM3;
specifically, class D, demolition and site clearance (as shown in Table 5.17).
250  Integrated design and cost management for civil engineers

CESMM3
Class D: Demolition and site clearance
Includes: Demolition and removal
Excludes: Removal below the original surface
Second Third Measurement Definition Coverage Additional
First division division division rules rules rules rules
C1… A1…
1 Site clearance ha D1… C2… A2…
2 Trees nr 1 girth: D2… C3… A3…
500–1 m
2 1–2 m…
3… … … … … … …
Adapted from CESMM3 published by Thomas Telford, 1991.

Step 3
Take-off ‘paper’ is prepared to facilitate description (Figure 5.4) and is
divided into six columns:

• ‘SMM reference’ column on the left


• A large second ‘item description’ column, followed by
• A columns on the right to allow the input of units (m, m 2 , m3 or ha)
• Additions (for the input of area dimensions length × width)
• Deductions (to allow omission of voids)
• A final quantities column

• The CESMM3 reference is D100


• The works description in words:
• Class D: Demolition and Site Clearance
• General Clearance
• The unit of measurement is ha (hectares)
• Remote measurement add dimensions:
• 78 × 45 (shown linearly)
• 3362 m 2 (with take-off diagram)
• Quantification in the final column:
• 0.34 ha
• Side note rules state C2 and D1 apply to hedges and fences to be
included in this case.

Step 4
The finalised transposed BQ item is shown below alongside, for clarity,
unit-rate and total; albeit rates and totals usually remain blank to facilitate
bids by prospective tenderers.
Contract documentation for civil engineering projects  251

Figure 5.4  Take-off.

Demolition and site


clearance Unit Quantity Unit rate Total
D100 General clearance ha 0.34 $1800 $612

5.3.1.2 BQ practice example (concrete strip foundation)


Measurement and itemisation of a concrete strip foundation.

Step 1: Drawings show strip foundation of grade 25 of some 30 m × 2.4 m ×​


0.9 m.
252  Integrated design and cost management for civil engineers

Step 2: CESMM3 class F, in situ concrete is shown next:

Class F: In situ concrete


Excludes: In situ concrete for boreholes, etc.
Second Measurement Definition Coverage Additional
First division division Third division rules: M1–2 rules rules rules
Provision
1 Standard m3 1… 1.10 mm D1–D4 A1…
2 Designed m3 1 C7.5 aggregate
… …
5 C25 7. 20 mm
aggregate
… … … … … … …
Placing
5 Mass m3 1 1 thick
blinding <150 mm
2 base …
footings 4 thick
>500 mm
Source: Adapted from CESMM3 published by Thomas Telford, 1991.

Step 3a: Prepare quantities to ‘take off’ (Figure 5.5). Take-off ‘paper’ from
six columns

• The CESMM3 reference is F257 (Figure 5.5).


• The work’s description in words: Class F: In situ Concrete, Provision
of concrete Designed mix Grade 25; as AS1379; 20 mm aggregate.
• Unit m3.
• Remote measurement dimensions are 30 × 2.4 × 0.9 linearly = 64.80 m2.

with take-off-diagram of strip-founds supporting a grade C30 retaining wall

Step 3b:

• The CESMM3 reference is F524 (Figure 5.6).


• Works description: Class F: In situ Concrete.
• Placing of concrete.
• Mass, bases, footings.
• Thickness, >500 mm.
• Unit is m3.
• Dimensions as previous item F257 (Figure 5.5).

Step 4: Prepare finalised BQ item. The finalised BQ items are shown below
with unit-rate and total to be completed by the various tenderers
bidding for the job.
Contract documentation for civil engineering projects  253

Figure 5.5  Placing ‘take-off’.

Figure 5.6  Final item.

Unit
In situ concrete Unit Quantity rate Total
F257 Provision of concrete m 3 64.80
Designed mix, Grade C25, AS1379, 20 mm
aggregate
F524 Placing of concrete m3 64.80
(mass, bases and footings; thickness >500 mm)

You might also like