Engineering and Construction Subcontract
Engineering and Construction Subcontract
from the subcontract starting date until Completion of the whole of the
core
subcontract works.
Access and use is allowed on or before the later of its subcontract access
date and the date for access shown on the Accepted Programme.
main
Take over 35
secondary
35.1 The Contractor need not take over the subcontract works before the Sub-
contract Completion Date if it is stated in the Subcontract Data that he is not
willing to do so. Otherwise the Contractor takes over the subcontract works not
later than two weeks after Completion.
35.2 The Employer or the Contractor may use any part of the subcontract works
before Completion has been certified. If he does so, the Contractor takes over
components
the part of the subcontract works when the Employer or the Contractor begins
to use it except if the use is
cost
Acceleration 36
data
36.1 The Contractor may instruct the Subcontractor to submit a quotation for an
acceleration to achieve Completion before the Subcontract Completion Date.
The Contractor states changes to the Key Dates to be included in the
quotation. A quotation for an acceleration comprises proposed changes to the
Prices and a revised programme showing the earlier Subcontract Completion
Date and the changed Key Dates. The Subcontractor submits details of his
assessment with each quotation.
36.2 The Subcontractor submits a quotation or gives his reasons for not doing so
within the period for reply.
clauses
core
1 General . The conditions of contract are the core clauses and the clauses for main
Option . . . . . , dispute resolution Option . . . . . and secondary Options . . . . .
of the NEC3 Engineering and Construction Subcontract June 2005 (with
amendments June 2006).
. The works in the main contract are
option clauses
..............................................................
main
. The subcontract works are
..............................................................
. The Contractor is
option clauses
Name . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
secondary
Address . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
..............................................................
. The Employer in the main contract is
Name . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Address . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
components
..............................................................
cost
. The Project Manager in the main contract is
Name . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Address . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
subcontract
..............................................................
data
. The Supervisor in the main contract is
Name . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Address . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
..............................................................
. The Adjudicator in this subcontract is
Name . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Address . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
..............................................................
If the Contractor has decided the subcontract completion date for the whole of
the subcontract works
. The subcontract completion date for the whole of the subcontract works is
clauses
core
..............................................................
If the Contractor is not willing to take over the subcontract works before the
Subcontract Completion Date
option clauses
. The Contractor is not willing to take over the subcontract works before the
Subcontract Completion Date.
main
2 ......................... ...........................
cost
3 ......................... ...........................
If the period in which payments are made is not four weeks and Y(UK)2 is not
used
. The period within which payments are made is . . . . . . . . . . . . . . . . . . . . . . . .
subcontract
If Y(UK)2 is used and the final date for payment is not 21 days after the date
data