Pozo Direccionales 27farah
Pozo Direccionales 27farah
Pozo Direccionales 27farah
ABSTRACT
Djibouti plans to drill 4 new geothermal wells for its future production in the Lava
Lake or Fialé, within the Asal Rift segment. These wells are planned to be
directionally drilled and the targets are based on six previous wells (Asal 1 - 6) drilled
in the late 1980s in this rift segment. These 6 wells were drilled in an area which
has high temperature potential, but problems of low permeability and high salinity
were encountered. This paper presents directional well planning for these new wells
and calculations for: (a) the trajectory and survey, (b) the well path, (c) the vertical
depth. Two case studies are presented for Fialé and the resulting well path, using the
build and hold type of directional wells. A simple BHA with two-stabilizers is
proposed with an optimal weight on bit. Based on the casing plan, the kick-off point
should be lowered to 430 m depth rather than 350 m as proposed by the pre-
feasibility study, which is about 30 m below the casing shoe of the intermediate
casing. Another option is drilling vertical wells, which would provide the same
subsurface information as directional wells. However, a thorough cost analysis of
drilling, survey tools, and equipment is needed to determine whether directional or
vertical drilling is financially advantageous for the exploration wells. Directional
drilling would not require new permitting or much geological and geophysical
studies as such studies were done in the pre-feasibility phase in 2008. Drilling pads
and targets for vertical drilling would, however, require further studies and a permit
to drill inside of Fialé crater.
1. INTRODUCTION
Directionally drilled wells represent an efficient way to reach special targets that are difficult to reach
using vertically drilled wells. A drawback of directional drilling is higher cost, but the advantage is that
surface construction may be minimized while still reaching the intended targets. The main factor in the
cost of a directional well is the horizontal distance to the target. The objective of the present study is to
present the calculations that show the well path in a 3D space, and to develop the model that gives the
minimum drilling length for these wells. The project of constructing and operating a geothermal power
plant is divided into four phases from the exploration phase to production. The Asal project is currently
in the exploration phase, which involves drilling four exploration and appraisal wells, followed by a
625
Farah Omar 626 Report 27
resource appraisal period, and finally by drilling seven to nine additional production wells. Information
attained through the drilling of the exploration wells and during the appraisal of the second phase will
be used for the conceptual design of the power plant. The true vertical depth (TVD) departure from the
end of the built section, and the well path in a build and hold well profile is calculated.
Although the focus of this work is directional drilling, vertical drilling should not be excluded as a
perfectly viable option. Therefore, this topic is also presented in a separate section and compared with
directional drilling.
1.1 Background
The objective of steering a well trajectory in the right direction and hitting a geological target many
kilometers downhole has forced the drilling industry to really focus on tools and methods to identify
wellbore location and its path during drilling. In the early days of drilling exploration, it was common
to set the drilling rig right above the target and drill a vertical well into it. Later, it became necessary to
drill wells to reach targets that were deviated from the reference location at the surface. Throughout the
years, many tools and methods have been developed for directional drilling. There are several
companies offering tools to deflect and steer wellbores in the right direction and to measure wellbore
inclination and azimuth.
The directional survey measurements are given in terms of inclination, azimuth and 3D coordinates,
TVD, northing and easting at the depth of the survey station. For many applications, the accurate
position and direction of the borehole should be determined at depths which may not coincide with the
depth of survey stations. A mathematical tool for interpolating between survey stations is then required.
1.2 Objective
The objective of this paper is to show the calculation methods needed for directional well path design
and to show the usage of trajectory and survey calculation methods by designing the well path of two
wells in Asal Fialé. The emphasis is on the following:
Calculate the true vertical depth (TVD) and departure from the vertical, at the end of the build-up
(EOB) section and the total depth (TD) to the bottom of the hole, in a build and hold well profile.
Calculate directional coordinates.
Describe formulas used to describe and calculate the well trajectory for different methods:
Tangential; balanced tangential; average angle; radius of curvature; and minimum curvature.
Outline the procedure for calculating survey results.
Calculate the northing, easting, TVD, vertical section and dogleg severity of a survey station using
the minimum curvature method.
Determine the exact bottom hole location of the well.
Monitor the actual well path while drilling to ensure the target is reached.
Orient deflection tools (such as directional drilling assemblies) in the required direction when
making corrections to the well path.
Design the bottom hole assembly (BHA) including the buoyed weight (or hook load) in a vertical
hole and the required BHA weight in air.
1.3 Scope
The minimum curvature method was chosen for trajectory calculations of the well. The scope of this
work is based on:
Report 27 627 Farah Omar
The following directional drilling methods are covered in the following books: Applied drilling
engineering by Bourgoyne, Millhem, Chenevert, and Young (1991); Directional drilling and deviation
control technology by the French Oil and Gas Industry Association (1990); and Directional drilling by
Inglis (1987). Other references are indicated where used. It is pertinent to note that this literature is
focused towards petroleum drilling practices. Other sources are:
- Tangent section: Section of a well where the well path is maintained at a certain inclination, with
the intent of advancing in both TVD and vertical section. Short tangential sections are built for
housing submersible pumps for example.
- True-vertical depth (TVD): Vertical distance between kelly bushing (KB) and survey point.
- Vertical Section (VS): Pre-defined azimuth angle along which the VS is calculated, usually the
angle between north and a line uniting the wellhead and the total depth, measured on a plan view.
- Well path: The trajectory of a directionally drilled well in three dimensions.
2.1.2 Application
c) Inaccessible locations. Vertical access to a producing zone is often obstructed by some obstacle at
the surface (e.g. river estuary, mountain range, city). In this case, the well may be directionally drilled
into the target from a rig site some distance away from the point vertically above the required point of
entry into the reservoir.
d) Side-tracking and straightening. It is, in fact, quite difficult to control the angle of inclination of any
well (vertical or deviated) and it may be necessary to ‘correct’ the course of the well for many reasons.
For example, it may be necessary in the event of the drillpipe becoming stuck in the hole to simply drill
around the stuck pipe (or fish), or plug back the well to drill to an alternate target.
Report 27 629 Farah Omar
e) Salt dome drilling. Salt domes (called diapirs) often form hydrocarbon traps in what were overlying
reservoir rocks. In this form of trap, the reservoir is located directly beneath the flank of the salt dome.
To avoid potential drilling problems in the salt (e.g. severe washouts, moving salt, high pressure blocks
of dolomite) a directional well can be used to drill alongside the diapir (not vertically down through it)
and then at an angle below the salt to reach the reservoir.
f) Relief wells. If a blow-out occurs and the rig is damaged, or destroyed, it may be possible to kill the
“wild” well by drilling another directionally drilled well (relief well) to intercept or pass within a few
feet of the bottom of the “wild” well. The “wild” well is killed by circulating high density fluid down
the relief well, into and up the wild well.
There are several types of wellbore profiles. Below there is a description and an illustration of the most
common profiles:
- Build and hold profile (Type 1) is the most common and simplest. The well is vertical until the
KOP where it is kicked off and an angle is built. When the desired inclination is reached, the well
path is kept tangent or straight until the target is reached.
- Build, hold and drop profile (Type 2), also called shaped wells, is the same in the upper section
as the build and hold well profile. The well is kept vertical until KOP and an inclination is built
and the tangent section is drilled. After the tangent section, a drop-off section is drilled where the
inclination is reduced and the well path is almost vertical as it hits the target.
- Deep build/kick-off (Type 3) is a type of wellbore drilled when there is a hindrance, such as a salt
dome, or when the well has to be side-tracked. The well is drilled vertically to a deep KOP and
then inclination is built quickly to the target. Horizontal well profile and Horizontal Drain hole
well profile are other types of wellbore trajectories. Theoretically, there are more than ten types
of wellbore profiles.
There are three specific parameters which must be considered when planning one of the trajectories
shown in Figure 3. These parameters combine to define the trajectory of the well:
- Kick-off point, is the long hole measured depth at which a change in inclination of the well is
initiated and the well is oriented in a particular direction (in terms of north, south, east and west).
In general, the most distant targets have the shallowest KOPs in order to reduce the inclination of
the tangent section of the well (Figure 3). It is generally easier to kick off a well in shallow
formations than in deep formations. The kick-off should also be initiated in formations which are
stable and not likely to cause drilling problems, such as unconsolidated clays.
- Build-up and drop off rate (in degrees of inclination) are the rates at which the well deviates from
the vertical (usually measured in degrees per 30 m or 100 ft). The build-up rate is chosen on the
basis of previous drilling experience in the location and the tools available, but rates between 1°
and 3° per 30 m or 100 ft of hole drilled are most common in conventional wells. Since the build-
Farah Omar 630 Report 27
up and drop off rates are constant, these sections of the well, by definition, form the arc of a circle.
Build up rates in excess of 3°/30 m are likely to cause doglegs when drilling conventional deviated
wells with conventional drilling equipment. The build-up rate is often termed the dogleg severity
(DLS).
- Tangent angle of the well (or drift angle) is the inclination (in degrees from the vertical) of the
long straight section of the well after the build-up section of the well. This section of the well is
termed the tangent section because it forms a tangent to the arc formed by the build-up section of
the well. The tangent angle will generally be between 10° and 60° since it is difficult to control
the trajectory of the well at angles below 10° and it is difficult to run wire line tools into wells at
angles greater than 60°.
The depth of a particular point on the well path, referred to as true vertical depth (TVD) is expressed in
metres (feet) vertically below a reference (datum) point. The northerly and easterly displacement of the
point horizontally from the wellhead is reported as Northing/easting or longitude/latitude.
Having fixed the target and the rig position, the next stage is to plan the geometrical profile of the well
to reach the target. The most common well trajectory is the build and hold profile, which consists of 3
sections - vertical, build-up and tangent. The trajectory of the wellbore can be plotted when the
following points have been defined:
Since the driller will only be able to determine the long hole depth of the well, the following information
will also be required:
- A long hole depth (AHD) of the KOP (same as TVD of KOP);
- Build up rate for the build-up section (selected by engineer);
- Direction in which the well is to be drilled after the KOP in degrees from north (defined by
position of rig and target);
- AHD at end of build (EOB) and the tangent section commences; and
- AHD of the target.
Report 27 631 Farah Omar
These depths and distances can be defined by a simple geometrical analysis of the well trajectory.
2.3.1 Build-and-hold
The choice of slot depends on a number of factors including target location and the proximity of other
wells. The target coordinates and depth are selected by the geologist. The choice of KOP and build-up
rate has to be made by the directional engineer (Bourgoyne, at al., 1991):
Figures 5 and 6 show a build-and-hold wellbore trajectory intersecting a target at a true vertical depth
(TVD) of TVD3 and at a horizontal departure of Dh (point D). The kickoff point is at a TVD of depth
TVD1, where the rate of inclination angle build-up is q in degrees per unit length.
For the following formula, note that TVD3 =TVDAG, TVD2 =TVDAC, TVD1 =TVDAB. The radius of
curvature, R, is thus:
180° 1
∗ (1)
π
where q is the build-up rate in °/30 m.
Farah Omar 632 Report 27
tanτ (3a)
3 2
and
τ (3b)
3 1
Angle Ω can be found by considering ODC, where:
sin Ω (4)
and
3 1
Substituting OP into Equation 4 gives:
sin Ω (5)
3 1
The maximum inclination angle, θ, for the build-and-hold case where Dh< R is:
θ
2 2 3 1 (6)
3 1
The length of the trajectory path, CD, at a constant inclination angle can be determined from triangle
DCO as:
(9)
and
(10)
The total measured depth, DM, for a true vertical depth of TVD3 is:
1 (11)
where DM equals the vertical section to kickoff plus build section plus constant inclination section
(Figures 6 and 7).
Report 27 633 Farah Omar
The horizontal departure GF (DE) at the end of the build can be determined by considering D’CO, where:
1 (12)
To find the measured depth and horizontal departure along any part of the build before reaching
maximum angle θ, consider the intermediate inclination angle θ’, the inclination angle at C’, which will
yield a new horizontal departure, Dn.
The preceding derivation is valid only when Dh < R. Another way of expressing the maximum
inclination angle, θ, in terms of R, TVD1, TVD3, and Dh for Dh ˃ R is:
3 1
θ
3 1 (13)
∗
3 1
The following equations are used to calculate the maximum inclination angles for R+R1 ˃ Dt and R+R1
< Dt:
4 1
1 (14)
1 3 1
∗
4 1 1
Farah Omar 634 Report 27
4 1
180°
1
(15)
1 3 1
∗
4 1 1
Sidetrack is when a new well path is to be obtained out of a previous one. The main sidetrack methods
used in directional drilling are:
Whipstocks, the retrievable, open-hole whipstock is only used in special applications, e.g. rigs
with small pumps, and sidetracks in deep, very hot holes. The whip-stock is pinned to a limber
BHA which includes a small bit. A typical BHA is:
- Motors, in this method, a bent sub is run directly above a PDM. A typical BHA is as follows:
Bit + PDM + bent sub + float sub + orienting sub (UBHO) + non-magnetic DCs + HWDP +
DP.
- Whip-stock + pilot bit + stabilizer + shearpin sub + 1 joint of drill pipe + UBHO + non-
magnetic DC.
Jetting, this technique is used to deviate the wellbore in soft and friable formations. The well can
be kicked off and built up to maximum inclination using one BHA. A typical jetting BHA is:
Report 27 635 Farah Omar
- Bit + near-bit stab. + UBHO (universal bottom hole orientation) + MWD + NMDC (non-
magnetic drill collar) + stab + DC + stab., etc.
During drilling it is close to impossible to make the actual trajectory precisely match the designed well
path. For that reason, it is important to monitor the well trajectory and take corrective actions as the
well is being drilled. To achieve this goal there must be reliable survey measurement tools and
techniques that determine inclination, azimuth and perhaps the tool face orientation at different points
along the well path. Survey tools only provide an incremental departure from a known starting point.
The known point is referred to as the tie-on, or ties line. The first survey station is recorded deeper than
the tie-on. The tools measure inclination and azimuth, the MD is known. The points of measurements
are called survey stations. The measured parameters are then used to calculate the wellbore position in
terms of the 3D coordinates N, E and TVD. Inclination angle is measured with respect to the vertical
while azimuth is measured with respect to either magnetic or true north. But azimuth is typically
reported in reference to true or grid north. As a result, the azimuth needs to be corrected before being
reported or used in calculations. True north is the absolute north reference. Magnetic Declination is the
angle from true north to magnetic north, and Grid Convergence is the angle from true north to grid north.
2.5.1 Application
When planning a 3D well trajectory, one of the most important considerations is torque and drag. If the
torque and drag are not carefully considered, the drill string might fail. The torque and drag model used
makes special assumptions that simplify the analysis and are used to model real drill strings. The most
important factor influencing the torque and drag forces is the hole curvature. The well path should be
redesigned with a smaller build-up rate if the drill string seems to fail when simulating these forces
during the design stage. There are many causes for excessive torque and drag such as: sliding friction,
tight hole, collapsing or swelling clay/shale, key seats, differential sticking and cuttings build-up. The
minimum curvature method assumes the bending part in the equilibrium equation used to calculate
torque and drag is discontinuous at survey stations. Some authors mean this is one of the main
weaknesses of using the minimum curvature method. Due to the missing bending stresses, the method
might not represent the real drill string configuration.
data of inclination, azimuth, and measured depth. The following paragraphs are a description of these
methods (Sperry-Sun, 2001).
1 2 1 2
∆ ∆ ∗ ∗ (17)
2 2
1 2
∆ ∆ ∗ cos (18)
2
where MD = Measured depth between surveys (m);
I1 = Inclination (angle) at upper survey (°);
I2 = Inclination (angle) at lower survey (°);
Az1 = Azimuth direction at upper survey (°); and
Az2 = Azimuth direction at lower survey (°).
B. Tangential method
The tangential method (Figure 11) uses the inclination and azimuth at the lower end of the course length
to calculate a straight line that represents the well bore, and passes through the lower end of the course
length. The wellbore is assumed to be a straight line throughout the course length. This method is the
most inaccurate of the methods discussed and should not be used in the determination of survey results
unless the course lengths are not longer than the length of the survey tool.
FIGURE 10: Average angle method FIGURE 11: Tangential angle method
Tangential calculations:
∆ ∆ ∗ 2∗ 2 (19)
Report 27 637 Farah Omar
∆ ∆ ∗ 2∗ 2 (20)
∆ ∆ ∗ 2 (21)
where MD = Measured depth between surveys (m);
I2 = Inclination (angle) of lower survey (°); and
Az2 = Azimuth direction of lower survey (°).
∆ ∗ 1∗ 2 1∗ 2
∆ (23)
2 1 ∗ 2 1
∆ ∗ 2 1
∆ (24)
2 1
Farah Omar 638 Report 27
When drilling a directional well, the actual trajectory of the well must be regularly checked to ensure
that it is in agreement with the planned trajectory. This is done by surveying the position of the well at
regular intervals. These surveys will be taken at very close intervals (~12 m, or every connection) in
the critical sections (e.g. in the build-up section) of the well. While drilling the long tangential section
of the well, surveys may only be required every 36 m (or every third connection). The surveying
programme will generally be specified in the drilling programme. If it is found that the well is not being
drilled along its planned course, a directional orientation tool must be run to bring the well back on
course. In general, the earlier such problems are recognised the easier they are to correct. Surveying
therefore plays a vital role in directional drilling.
Report 27 639 Farah Omar
of the pre-feasibility
phase identified Fialé in
the Asal Rift as a
favourable production
sector due to its
impressive faulting,
massive magma
deposition and active
steam fumaroles on the
surface (Figure 14); the
production section of well
A5 of the former Asal
drilling project is located
within the sector. Well
A5 was unproductive and
penetrated both cold and
hot formations. This
resource behaviour
suggests firstly that there
are active flow channels
of fresh seawater that
recharge a deep reservoir.
These faults should
provide pressure support
and more favourable fluid
chemistry than observed
in the old well (field
sector A). The high
downhole temperature
confirms a large heat
reserve. Based on these
results, four new wells
(AA to AD) from four
drill pads were suggested
by REI (REI, 2009),
aiming at targets within
and in the immediate
FIGURE 15: Well path of four targets inside and outside of the Lava Lake surroundings of Fialé
(Fialé) for directional drilling, as suggested by REI (2009) (Figure 15).
3.1 Objective
The geothermal wells planned by REI are to be drilled down to 2500 m depth and they are all to be
directional. In order to reach the drilling targets, the drill sites were chosen to be located where discharge
brine could be disposed of and where disturbances to the pristine environment would be at a minimum.
If the geothermal resource proves accessible, it is expected that more wells, perhaps as many as 5, will
be drilled from the same drill pads. In this way, the roadwork and surface piping could be kept to a
minimum. A storage place will be set up at the drill site, most likely between sites AC and AD. This is
a flat area where drilling material and equipment are stored after having been shipped to Djibouti and
transported to the Fialé drilling area. Part of the storage area will be fenced and a part of it will be roofed
for protection against the sun. The four wells (AA to AD) are planned to be drilled vertically using
percussion and rotary drilling assemblies, as applicable, to a kick off point (KOP) at approximately 350
Report 27 641 Farah Omar
m depth (Rotary Kelly Bushing). Inclination is to be built at a uniform rate of 3°/30 m to an inclination
of 30°, with a specified nominal azimuth, which shall be maintained to the final well depth. The kick-
off and initial build will be achieved with a mud motor and MWD equipment until the desired inclination
and direction have been achieved. Once inclination and direction have been achieved, rotary assembly
and electronic multi-shot measurement tools will be utilised. However, vertical drilling should be
considered as an option, and its technical and cost aspects are briefly discussed in Section 3.5.
The four planned wells are within the Asal Rift segment, which is one of the five rift segments in
Djibouti. The other four are Alol, Gaggade, Hanle, and Goba’ad, all with geothermal potential. The
five rift segments have a NNW to WNW strike. They are narrow elongated depressions, surrounded by
elevated plateau and massifs. Their altitudes vary from 0 to 300 m a.s.l., except for the Asal segment
which, at its northwest tip, drops to –150 m b.s.l. in the Asal Lake. These segments are among the major
tectonic elements of the Afar depression. They have a complex geology since the Miocene period
(Varet, 1978; Gaulier and Huchon, 1991) that includes: (a) successive volcano tectonic events related
to the opening of the Red Sea, East African Rifts and Aden Ridge; (b) the shift of a rift from the Red
Sea to the Afar Depression; (c) westward propagation of the Aden-Tadjourah ridges; (d) rift jumps and
simultaneous activity of several rift segments; (e) the rotation of the Danakil Horst; and (f) complex
kinematics and relative plate motion. Successive rifting since Miocene resulted in the accumulation of
a vast basaltic trap and rhyolites in Afar, deposition of thick intercalated marine sediments as well as
thinner lacustrine sediments filling the five rift segments. Magmatic and tectonic processes of the plate
boundaries are the origin of geothermal activity in this part of Africa.
The Asal Rift itself (Figure 14) extends from the Gulf of Ghoubet in the southeast to Lake Asal in the
northwest, bounded by major WNW striking normal faults. Due to its accessibility, this segment has
been studied quite extensively, demonstrating that the rift is bounded by WNW striking major normal
faults. The most active part of the Asal segment is the Inner Rift, which is about 3 km wide and is
located to the southeast. The Inner Rift hosts most of the recent volcanism, with the last eruption dating
from 1978. The most prominent feature of the Inner Rift is the Lava Lake, also called Fialé. The Lava
Lake is an apparent crater about 1.3 km wide whose floor is covered by recent basaltic lavas.
The high geothermal potential of the Asal Rift is known from high-temperature exploration wells drilled
over the past decades. While previous studies demonstrated the importance of the WNW normal faults
of the rift, the recent geological pre-feasibility study shows two additional pieces of information on
which grounds Fialé has been chosen as the target site (Khodayar, 2008): (a) there are more sets of
fractures than the WNW set present within the rift; (b) Fialé could be a caldera, hosting the most
significant surface geothermal manifestations of the Asal Rift segment.
Well Asal-5 (Figure 16) is the deepest well (2105 m) drilled in the Asal Rift and is unproductive as it
penetrates both cold and hot formations. Data from this well (Árnason and Flóvenz, 1995) indicate a
possible shallow hot reservoir (160°C) at 500-550 m depth, then a cold zone (about 60°C) down to 1200
m depth. Below 1200 m, temperature increases and the bottom temperature is about 333°C at 2105 m.
The well has never been discharged. This temperature profile suggests firstly that there are active flow
channels of fresh seawater recharging a deep reservoir. Secondly, the downhole high temperature
confirms a large heat reserve. After the well became unsuccessful, Icelandic scientists familiar with the
strategic research of similar geothermal fields joined the exploration of Asal Geothermal Field. The
geological investigations of the Asal Field (Saemundsson, 1988) indicated that Well Asal-5 was not
correctly sited as it would be about 700-1000 m from the geothermal up flow zone. Shortly thereafter,
resistivity studies were undertaken using the TEM method (Transient Electromagnetics) in the Inner
Rift (Árnason et al., 1988). The survey indicated the existence of an up flow zone of geothermal fluid
Farah Omar 642 Report 27
10% higher at the bottom) (Virkir-Orkint, 1990). This raises the question of the provenance of the saline
water and the subsurface hydrology through rocks and/or open fractures.
The pre-feasibility geological field studies focused on Fialé, but a short investigation was also made in
Korili/Gale le Kôma to the southwest of the Asal Lake (Khodayar, 2008). Results suggested both areas
as having high potential. The detailed mapping of geology, tectonic and surface geothermal
manifestations in Fialé identified three sub-areas (A, B, and C in Figure 18).
FIGURE 18: Location map of geothermal areas studied in the field (Khodayar, 2008)
The sub-area A to the west of Fialé has the highest potential as it has the most evidence of geothermal
activity. The first target zone there is an altered zone with fumaroles and hot wet soil up to 91°C along
an open NNW fracture. This fracture is seismically active and is monitored instrumentally. The second
target zone is adjacent to the NNW fracture on the inner slope of Fialé where the hot wet soil reaches
75.5°C. In sub-area B to the east of Fialé (Figure 18), most alterations are aligned in WNW and ENE
zones that coincide with the underlying WNW and ENE fractures. The WNW and ENE altered zones
are respectively parallel to the adjacent inner rift boundary fault and to the trace of a major fault
stretching from west-southwest of Fialé towards sub-area B. Sub-area C is high up on a rifted block
above the outer slope of Fialé to the west. Along with the WNW faults of the rift, sets of fractures
striking NNW, ENE and E-W were also mapped in and around the Lava Lake (Khodayar, 2008).
Evidence of these fractures is also seen in geophysical results, and constitutes some of the targets chosen
by REI for directional drilling (Figure 15). Finally, geological investigations suggested that Fialé might
be a caldera (Khodayar, 2008), which is likely since seismicity is highest under the Lava Lake (Figure
18) and could be indicative of a magmatic body at depth.
The proposed location of the four drill pads (shown in Figure 15) in Asal Fialé by REI (REI, 2008), are
the following:
Farah Omar 644 Report 27
a) Well AA is located on the outer slopes of the Lava Lake rim. The drilling target from drilling site
AA is the inner part of the Lava Lake, especially the intersections of various fault lines identified
by geological mapping. The horizontal distance from a drill pad is about 1000 m, making the
drilling targets within the Lava Lake reachable from Site AA. Facing the site to the northwest, at
the foot of the slope, is a flat area which could in the future be the location of a separation station
and/or power house.
b) The location of drill pad AB is on a flat plane bordered by low ridges with NW-SE directions. To
the southeast the plane connects to the Lava Lake through a depression in the crater rim. The
current track to the Ardoukoba crater ascends here from Lava Lake and traverses the drill site.
From Site AB the main fumarole area could be reached by directional drilling towards the east,
and by a southerly direction the main fault plane of the Fialé area could be penetrated.
c) Parallel to the plane of Site AB, but to the southwest, is another flat area, bordered by a low ridge
to the northeast and the high cliff of the main plane to the southwest. This plane is hidden from
view and is large enough to accommodate drill pads, a separation station and a power house.
Wells drilled from a pad in the southeast corner of the plain could reach drilling targets under
Lava Lake and the important fault planes of the Fialé area.
d) The location is farthest to the east, and is reserved as an option for the last exploration well if the
drilling of the first well shows that the Lava Lake target is less promising than the area between
the Lava Lake and the eastern fault boundary of the Inner Rift. This area could accommodate a
few wells aimed at the faults of the eastern border of the Inner Rift. This drill pad would only be
prepared if the other drill sites were found to be less suitable than currently anticipated.
Four drill pads have been planned by REI, based on recommendations from the recent geological and
geophysical studies from ISOR (Iceland GeoSurvey). The surface and target coordinates are shown in
Tables 1 and 2.
X Y Latitude/Longitude
Latitude/Longitude Elevation
Well (Easting) (Northing) (Degrees/Minutes/
(Degrees/ Decimal) (m)
m m Seconds)
11°35'25.31"N 11.590364 N
AA 227212.1 1282455 104
42°29'54.85"E 42.498569 E
11°34'59.63"N 11.583235 N
AB 227030.3 1281667 124
42°29'49.08"E 42.496967 E
11°34'51.64"N 11.581009 N
AC 226651.5 1281424 109
42°29'36.65"E 42.493515 E
11°35'6.27"N 11.585078 N
AD 226121.2 1281879 118
42°29'19.13"E 42.488619 E
Figure 19 shows the necessary parameters for the calculations. First the radius of the curvature is
calculated. Note, Dh ˃ R.
180 1
∗ ° 573 m
π
For this case, Dh ˃ R. A way of expressing the maximum inclination angle, θ, in terms of R, TVD1,
TVD3, and Dh for Dh ˃ R is:
3 1
θ 180° arctan
3 1 (30)
arccos ∗ sin arctan
3 1
2247 350
180° arctan
1015 573
573 2247 350
arccos ∗ sin arctan 30.21°
2247 350 1015 573
π∗θ∗ 3 1 ∗ sin θ
1 (32)
180° cos θ
π ∗ 30.12° ∗ 573 2247 350 573 ∗ sin 30.12°
350 2512 m
180° cos 30.12°
The total measured displacement depth to the target (maximum) is:
1 ∗ sin θ (33)
Calculations
Vertical Horizontal
Measured
depth displacement
depth (m)
(m) (m)
KOP 350 0 350
EOB 638 78 652
Target 2247 1085 2513
Maximum inclination θ°
Build up rate, BUR 3°/30
R=180/π*1/((3°)/
Radius of curvature, R
(30 m)) = 573 m
Line JD = Dh – R; JD = 442 m
Line JO = TVD3-TVD1; JO = 1897 m
Angle JOC = arctan(JD/JO);
Angle JOC = 13.11°
Geometry of build-and-hold type well path for Line OD = JO/cos(Angle JOC);
Dh ˃ R Line OD = 1947.76 m
Horizontal Angle COD = arccos(R/OD);
δ=Direction to
Angle COD = 72.89°
target
D3= E or W / Sinδ Angle COJ = Angle COD – Angle JOC;
= arc tan E or W / N or S Angle COJ = 59.78°
Maximum angle of well, θ = 90 – Angle COJ;
θ=30.21°
End of build:
Measured depth = TVD1 + (θ/BUR )
= 652.1 m
Vertical depth = TVD1+R sin θ = 638.31 m
Displacement (De) = R*(1 – cos θ) = 77.8 m
Declination
N/S E/W Target:
Measured depth = TVD1 + (θ/BUR) + CD
Grid target = 2513.7 m
The normal method for determining the well path is to ascertain the coordinates by using some survey
method to calculate the inclination and direction at various depths (stations) and then calculate the
trajectory. There are 18 or more calculation techniques for determining the trajectory of the wellbore.
The main difference in all these techniques is that one group uses straight line approximations and the
other assumes the wellbore is more of a curve and is approximated with curved segments. For this case,
the minimum curvature method will be used (Figure 21) which is the most accurate and commonly used.
Whilst drilling a deviated well, the measured depth, inclination and azimuth of the well are measured at
station 2 (see survey data below). The north and east co-ordinates, TVD, vertical section and dogleg
severity, of the next station are calculated according to the minimum curvature method.
This method smooths the two straight-line segments of the balanced tangential method using the ratio
factor, RF. The survey information of measured depth, inclination, and azimuth are entered in the
appropriate columns (i.e. measured depth-total, inclination, and azimuth-observed) in Table 3.
620 380
∆ ∗ sin 3° ∗ cos 325° sin 27° ∗ cos 325° ∗ 1.0631
2
51.15
The vertical (TVD) is obtained using Equation 27:
620 380
∆ ∗ cos 3° cos 27° ∗ 1.0631 233.5 m
2
For Well AB:
The parameters of Well AB are shown in Table 4.
The North:
620 380
∆ ∗ sin 3° ∗ cos 100° sin 27° ∗ cos 100° ∗ 1.0631 10.84
2
The vertical (TVD):
620 380
∆ ∗ cos 3° cos 27° ∗ 1.0631 233.5 m
2
Other calculation methods sometimes used are the balanced tangential method, the radius of curvature
method, and the average angle method. The three-dimensional geometrical representation of the
trajectory for Well AA is presented below, where the wellbore is deflected at point B. The well was
turned clockwise for the N325° and N100° target zone, presented in Table 5:
a) b) c)
FIGURE 22: a): Horizontal displacement (Dh); b) A view from the south on the TVD projected on
a vertical W-E plane; and c) A view from the east on the TVD projected on a vertical S-N plane
Report 27 649 Farah Omar
a) b) c)
FIGURE 24: a) Horizontal displacement; b) A view from the south on the TVD projected on a
vertical W-E plane; and c) A view from the east on the TVD projected on a vertical S-N plane
As to which method yields the most accurate results, Table 6 compares the four different calculation
methods using data taken from a planned well. An example for comparison is Well AA.
Note that the tangential method shows considerable difference. This is why the tangential method is
rarely used. The differences between the average angle, the minimum curvature, and the balanced
tangential methods are so small that any of the methods could be used for calculating the trajectory.
Several calculation methods are summarised in an excel worksheet for an overview (see Table 7).
Farah Omar 650 Report 27
Case 1: Well AA
Direction: Due north
Survey interval: 240 m
Rate of build: 3°/30 m
Total inclination: 30° at 650 m
Azimuth: 325°
Calculation method Total vertical depth (m) North displacement (m)
Minimum curvature 233.50 51.15
Balanced tangential 226.75 49.77
Angle-averaging 231.82 50.88
Tangential 213.84 89.25
Well AA
Measured Hole Dev Avg. tangential method Balanced tangential method
depth dev azi North East TVD North East Tvd
0 0 325 0 0 0 0 0 0
380 3 325 8.18 -5.72 379.87 8.17 -5.72 379.74
410 6 325 10.10 -7.07 409.78 10.10 -7.07 409.64
… … … … … … … … …
2510 30 325 832.23 -508.33 2247.20 832.21 -582.72 2246.98
Measured Hole Dev Minimum curvature Radius of curvature
depth Dev Azi North East TVD North East TVD
0 0 325 0 0 0 0 0 0
380 3 325 8.17 -5.72 379.83 0 0 379.74
410 6 325 10.10 -7.07 409.73 0 0 409.64
… … … … … … … … …
2510 30 325 832.22 -582.73 2247.13 0 0 2247.33
Well AB
Measured Hole Dev Avg tangential method Balanced tangential method
depth dev azi North East TVD North East TVD
0 0 100 0 0 0 0 0 0
380 3 100 -1.73 9.83 379.87 -1.73 9.83 379.74
410 6 100 -2.74 12.14 409.78 10.10 -7.07 409.64
… … … … … … … … …
2510 30 100 -176.42 872.78 2247.20 -176.42 1000.50 2246.98
Measured Hole Dev Minimum curvature Radius of curvature
depth dev azi North East TVD North East TVD
0 0 100 0 0 0 0 0 0
380 3 100 -1.73 9.83 379.83 0 0 377.84
410 6 100 -2.14 12.15 409.73 0 0 407.82
… … … … … … … … …
2510 30 100 -176.42 1000.52 2247.13 0 0 2247.33
There are four basic requirements which must be met when designing a drill string:
The burst, collapse and tensile strength of the drill string components must not be exceeded;
The bending stresses within the drill string must be minimised;
The drill collars must be able to provide all of the weight required for drilling; and
The BHA must be stabilised to control the direction of the well.
In order to design the BHA to hit the bottom target, the following will be determined:
Length of BHA necessary for a desired weight on bit (WOB);
Length of drill pipe and drill collar to be used with a specific bottom hole assembly; and
Design of a drill string for the conditions specified.
Design parameters:
Depth = 2510 m
Hole size = 8½"
Mud weight = 1.08
Desired MOP = 30.10³ daN = 30 600 kg
Safety factor in collapse = 1.15
Size and weight of drill collars = (6½ in. x 2¼ in.) = 147.92 kg/m
Weight on bit (WOB) = 10 tonnes
Farah Omar 652 Report 27
No drill pipes are used to apply weight on the bit. All the weight comes from the drill collars, 85% of
the DC weight, as shown before. Table 8 summarizes the BHA design for a depth of 2510 m.
Hole size Bit sizes Weight on bit Length of drill Weight of BHA for
(inches) (Inches) (kg) collar (m) tangent section (kg)
8½" 6½" OD 2¼" ID 10000 92 130258.18
Directional drilling is the same as vertical drilling until the kickoff point at 350 m depth, at which depth
the well is deviated gradually from the vertical (Figures 27 a and b). Vertical well drilling operations
differ from directional well drilling operations. A non-exhaustive comparison between these two types
of drilling methods highlights the main technical aspects such as engineering, environmental issues,
subsurface data collection, and costs (Table 9). Three main points can be taken from this correlation:
A target depth of 2000 m has been chosen in this comparison as an example, which is within the
depth range suggested by REI for directional drilling. This short comparison shows that each
type of drilling has its pros and cons. The costs of drilling alone are clearly higher for directional
drilling, due to the longer length of the well to reach the target. If the costs of survey tools and
equipment are added, then directional drilling may be up to 30% more expensive than vertical
Report 27 653 Farah Omar
TABLE 9: Non-exhaustive comparison between directional and vertical drilling for a target at a depth
of 2000 m as example; note that the differences between the two drilling types are presented in italics
drilling. On the other hand, the costs of multiple well pads can change the outcome. A detailed
cost analysis of multiple well pads is needed to see the total costs of each type of drilling and
which one would be financially sound.
From an environmental view point, the constructions related to multiple well pads, as well as the
water waste, chemical products, and mud from the wells are major concerns. Due to these main
concerns, drilling in the Lava Lake is not permitted at this point. Considering that vertical drilling
must be carried out above the target(s), i.e. inside the Lava Lake for potential targets there, the
Farah Omar 654 Report 27
existence of the permit is an issue that has to be dealt with should vertical drilling be revealed as
the preferred choice for targets inside the Lava Lake.
From geological and geophysical points of view, information regarding the subsurface can be
obtained equally from directional and vertical drilling (Table 9), but the ultimate choice depends
on the total costs for each type of drilling. As to the well production, cases are known worldwide
where directional drilling has been 2.5-7 times more productive than vertical drilling. This higher
production rate may partly be due to the fact that directional drilling intersects several fractures
or a wider broken zone with higher permeability (Figure 27a). But as indicated, pre-feasibility
studies are not precise enough to accurately locate potential targets for vertical drilling outside or
inside the Lava Lake of Fialé. Considering that knowledge of the dip direction of a target fracture
is critical for vertical drilling (Figure 27b), further geological studies are required to estimate the
potential fracture targets as well as the risks, especially concerning seismically active fractures
such as the NNW fault in the western part of Fialé.
Due to a lack of further geological and geophysical studies, at this stage the best suggestion for vertical
drilling would be to aim at the same targets as recommended by REI for directional drilling (Figure 28),
given that permission can be obtained to drill inside the Lava Lake. To offer more choices in the site of
well AA, a few fractures have been reported from the pre-feasibility study (Khodayar, 2008). According
to that study, these fractures were identified from aerial photographs only. Their exact locations on
maps may be more or less displaced due to distortions between the old aerial imageries and the old
topographical maps on which the fractures were reported at the time of that study. In general, vertical
drilling could be located on both sides of an individual fracture to obtain its dip direction, or at fracture
intersections. It is important to keep in mind that the above suggestion is, in no way, a thorough site
selection of targets for vertical drilling; further studies are necessary.
Based on the calculations in the case studies of directional drilling, the build and hold program is the
most attractive approach for the production wells in Asal Fialé. Simple two-stabilizer building
assemblies could be used with optimal WOB. Because the BHA could always be building the angle,
the effects of the formation forces could be controlled easily by adjustment of the second stabilizer,
either closer to or farther from the lead stabilizer. Drilling through the abrasive sandstone at the base of
the cretaceous would require 3-point roller reamers instead of stabilizers. These reamers would also be
necessary in hard limestone. To drill through these wells, regular spiral or straight-bladed stabilizers
could be used. The risk in the build and hold program is that the build might close in the harder limestone
and motors would be needed to complete the hole.
Farah Omar 656 Report 27
The foregoing approaches are only a few of the possibilities that could be deduced from the principles
presented in the report. There is no absolute way of drilling a directional well. However, there are
better, optimal ways to drill any well (good planning and careful selection of the bit, mud system, etc.)
that should minimize the risks. Assuming the previous results (trajectory and survey calculations), with
REI’s proposal to make the KOP at 350 m, it is proposed here that the kick off point should be at least
30 meters below the casing shoe. Thus, all directional wells in the future in Asal should have a kickoff
point at 430 m depth at least with a 400 m intermediate casing.
Vertical drilling is another option. Based on the results of the pre-feasibility studies, the best suggestions
for vertical drilling at this stage are to drill down to 2000 m into the targets recommended by REI (2009)
(Figure 28). Such vertical exploration wells would be best placed on both sides of individual fractures
or at their intersections. For potential targets inside of the Lava Lake of Fialé, a permit has to be
obtained. However, additional geological and geophysical surveys are required to accurately select the
targets for vertical drilling. Such studies should also estimate the risks related to seismic faults, in
particular for those target fractures inside the Lava Lake where shallow magmatic bodies could be
present at depth. Drilling inside the Lava Lake would have the advantage of determining whether that
area as a whole is indeed less saline than the two other target areas suggested by REI (Figure 17).
ACKNOWLEDGEMENTS
The success and final outcome of this project required a lot of guidance and assistance from many people
and I am extremely fortunate to have gotten this for the completion of my project work. That I have
done this is only due to such guidance and assistance and I will not forget to thank them. I wish to thank
Dr. Ingvar B. Fridleifsson, the outgoing director of the UNU Geothermal Training Programme, and Mr.
Lúdvík S. Georgsson, the present director of the UNU GTP, for their organization of the training and
the follow up of our learning. Many thanks to Mr. Ingimar Gudni Haraldsson, Ms. Málfrídur
Ómarsdóttir, Mr. Markus A. G. Wilde, and Ms. Thórhildur Ísberg for their support and help in the
programme. I wish also to thank my supervisors for their help in different parts of my report: Hannes
Sverrisson (from Mannvit) for directional well design, Sverrir Thórhallsson (from ÍSOR) for bottom
hole assembly, and Dr. Maryam Khodayar (from ÍSOR) for vertical drilling, and the insightful
discussions, valuable advice, and their support during the whole period of the study, and especially for
their patience and guidance during the writing process. I am grateful to the UNU Fellows for the
wonderful time we had together during this 6 months.
I hope my friends and colleagues, too numerous to thank individually, will forgive me for not compiling
a huge list here.
Lastly, I thank almighty, my parents, brother, and sisters for their constant encouragement without which
this assignment would not be possible. To the love of my life, Samia!
Above all, I praise God, the almighty for providing me this opportunity and granting me the capability
to proceed successfully.
Report 27 657 Farah Omar
REFERENCES
Aquater, 1989: Djibouti geothermal exploration project, Republic of Djibouti, final report. Aquater,
Italy, report, 159 pp.
Árnason, K., and Flóvenz, Ó.G., 1995: Geothermal exploration by TEM-Soundings in the Central Asal
Rift in Djibouti, East Africa. Proceedings of the World Geothermal Congress 1995, Florence, Italy,
933-938.
Árnason, K., Eysteinsson, H., and Vilhjálmsson, A.M., 2008: The Asal geothermal field, Djibouti.
Geophysical surface exploration, 2007-2008. ÍSOR - Iceland GeoSurvey, report ISOR-2008/019,
prepared for REI (confidential), 74 pp.
Árnason, K., Björnsson, G., Flóvenz, Ó.G., Haraldsson, E.H., 1988: Geothermal resistivity survey in
the Asal rift, volume 1: Main text. Orkustofnun, Reykjavík, report S-88031/JHD-05, prepared for the
UND-OPS and ISERST, 48 pp.
Baker Hughes INTEQ, 1995: Drilling engineering workbook. A distributed learning course. Baker
Hughes INTEQ Inc., 410 pp.
Bourgoyne, A.T., Millheim, K.K., Chenevert, M.E., and Young, F.S. Jr., 1991: Applied drilling
engineering. SPE Textbook Series, 2, 502 pp.
French Oil and Gas Industry Association, 1990: Directional drilling and deviation control technology.
Editions technic, Paris, France, 137 pp.
Gabolde, G., and Nguyen, J.P., 1991: Drilling data handbook. Gulf Publising Co., Houston, TX, United
States, 542 pp.
Gaulier J.M., and Huchon, P., 1991: Tectonic evolution of Afar triple junction. Bull. Soc. Géol. France,
126, 451-464.
Inglis, T.A., 1987: Directional drilling, vol. 2. Graham & Totman, Ltd., London, 260 pp.
Khodayar, M., 2008: Results of the 2007 surface geothermal exploration in the Asal Rift and transform
zones, Djibouti: Tectonics and geothermal manifestations (revised version, May 2008). Iceland
GeoSurvey, report ÍSOR-2008/008, prepared for REI (confidential), 81 pp + 5 maps.
REI, 2008: Drilling and testing of geothermal exploration wells in the Assal Area, Djibouti:
Environmental management plan. Reykjavik Energy Invest, report REI-2008/Assal 1, 58 pp.
REI, 2009: Geothermal pre-feasibility study in the Asal Rift, Djibouti: Project status after completions
of surface exploration studies and environmental impact assessment. Reykjavik Energy Invest,
confidential report, REI-2008, 20 pp.
Saemundsson, K., 1988: Djibouti geothermal project. Analysis of geological data pertaining to
geothermal exploration of Asal rift. UNDP, 18 pp.
Varet, J., 1978: Geology of central and southern Afar (Ethiopia and Djibouti Republic). Centre Natonal
de la Recherche Scientifique, Paris, France, 124 pp.
Farah Omar 658 Report 27
Virkir-Orkint, 1990: Djibouti geothermal scaling and corrosion study, final report. Virkir-Orkint
Consulting Group Ltd, Iceland, report prepared for Electricité de Djibouti, 273 pp.
APPENDIX I: Expected lithological profiles and designs for Wells AA and AB, Asal, Fiale