Ciclo Di Verniciatura: Proprieta' Tecniche Vedi Schede Tecniche Allegate

This document provides specifications for a 3-coat painting cycle. It lists a zinc-rich inorganic primer, acrylic silicone intermediate coat, and acrylic silicone finish coat to achieve a total dry film thickness of 135 μm. The painting cycle is applicable for carbon steel ball valves that operate between 149°C and 204°C according to Specification S-02-140-K-ESP-701 System 9B.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
97 views1 page

Ciclo Di Verniciatura: Proprieta' Tecniche Vedi Schede Tecniche Allegate

This document provides specifications for a 3-coat painting cycle. It lists a zinc-rich inorganic primer, acrylic silicone intermediate coat, and acrylic silicone finish coat to achieve a total dry film thickness of 135 μm. The painting cycle is applicable for carbon steel ball valves that operate between 149°C and 204°C according to Specification S-02-140-K-ESP-701 System 9B.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Doc. No.

PC 3152
CICLO DI VERNICIATURA
Painting Cycle Sheet 1 of 1

PROPRIETA’ TECNICHE VEDI SCHEDE TECNICHE ALLEGATE


Technical Properties See attached technical sheet

PREPARAZIONE SUPERFICIE Cleanliness: ISO 8501-1 Sa 2 ½


Surface preparation Roughness: ISO 8503 Grade Medium G

DESCRIZIONE DEL CICLO


Cycle description

COAT PAINTING TYPE PRODUCT SUPPLIER M.D.F.T. (µm)

Primer Zinc Rich Inorganic Primer Carbozinc 11 Carboline 75 µm

Intermediate Acrylic Silicone Thermaline 4900R Carboline 30 µm

Finish Acrylic Silicone Thermaline 4900R Carboline 30 µm

TOTAL MINIMUM DRY FILM THICKNESS (µm) 135 µm

Aluminium
FINAL COLOUR
(Ral 7035)

CONTROLLI RICHIESTI / Inspection requirements


CONTROLLO RUGOSITÀ PREPARAZIONE SUPERFICIALE IN ACCORDO ALLA ISO 8501‐1
Surface Preparation according to ISO 8501‐1
CONTROLLO VISIVO DELLA SUPERFICIE SABBIATA IN ACCORDO ALLA ISO 8502-3
Visual Control of blast cleaned according to ISO 8502-3
CONTROLLO SPESSORE TOTALE IN ACCORDO ALLA SSPC PA 2
Check of total DFT According to SSPC‐PA 2
TEST DI ADESIONE IN ACCORDO ALLA ASTM D 3359: CRITERIO DI ACCETTABILITA’ LIVELLO 3-4
Adhesion test according to ASTM D 3359: Acceptance criteria: Level 3- 4

REMARK
Painting cycle applicable on carbon steel ball valves with temperature between 149°C and 204°C
according to Spec. S-02-140-K-ESP-701 System 9B

Q.C. Q.A.
2 10.07.2014 Inserito test di adesione / Added adhesion test
S.Frazzi L.Ripoldi
Q.C. Q.M.
1 08.03.2013 Inserita specifica cliente / Added client specification
S.Frazzi D.Morelli
Q.C. Q.M.
0 22.01.2013 Prima emission / First Issue
S.Frazzi D.Morelli
Rev: Date: Prepared: Approved: Description: