Mitsui Petrorabigh: Engineering & Ship Building Co

This document provides a Gantt chart showing the schedule for the Rabigh PC2 MEG Unit Storage project from July 2010 through July 2011. It involves demolishing an existing tank and constructing a new tank. Key activities include commencing demolition work in July 2010, erecting scaffolding in July-August 2010, cutting and releasing the shell courses from September-November 2010, and completing demolition by November 2010. Roof removal work was scheduled from November 2010 to April 2011. The new tank erection began in November 2010 and handover was planned for July 2011.

Uploaded by

faisal jasim
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
74 views3 pages

Mitsui Petrorabigh: Engineering & Ship Building Co

This document provides a Gantt chart showing the schedule for the Rabigh PC2 MEG Unit Storage project from July 2010 through July 2011. It involves demolishing an existing tank and constructing a new tank. Key activities include commencing demolition work in July 2010, erecting scaffolding in July-August 2010, cutting and releasing the shell courses from September-November 2010, and completing demolition by November 2010. Roof removal work was scheduled from November 2010 to April 2011. The new tank erection began in November 2010 and handover was planned for July 2011.

Uploaded by

faisal jasim
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

MITSUI ENGINEERING & SHIP BUILDING CO.

PETRORABIGH
Activity ID Activity Name Original Start Finish 2010 2011
Duration Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 6465
RABIGH PC2 MEG UNIT STORAGE 308.00 03-Jul-10 A 06-Jul-11 RABIGH PC2 MEG UNIT STORAGE

CONSTRUCTION 308.00 03-Jul-10 A 06-Jul-11 CONSTRUCTION

C000 Commence demolation work 0.00 03-Jul-10 A Commence demolation work


C001 Commence roof removal work 0.00 06-Nov-10 A Commence roof removal work
C003 Commence erection of new tank 0.00 27-Nov-10 A Commence erection of new tank
C004 Complete demolation work 0.00 27-Nov-10 A Complete demolation work
C005 Complete roof removal work 0.00 24-Apr-11 Complete roof removal work
C006 Handing over of Tank 0.00 06-Jul-11 Handing over of Tank
C01 Tank construction 307.90 03-Jul-10 A 06-Jul-11 Tank construction
C01D Demolition of existing tank 90.10 04-Jul-10 A 27-Nov-10 A Demolition of existing tank
DEMOLITION OF EXISTING TANK 118.20 04-Jul-10 A 27-Nov-10 A DEMOLITION OF EXISTING TANK
C01C-010 Removing of damaged scaffold 6.00 04-Jul-10 A 09-Oct-10 A Removing of damaged scaffold
C01C-020 Installation of fire wall 6.00 20-Jul-10 A 13-Oct-10 A Installation of fire wall
C01C-030 Erection of scaffold 12.00 24-Jul-10 A 17-Aug-10 A Erection of scaffold
C01C-040 Removing of accessories 4.00 14-Aug-10 A 04-Sep-10 A Removing of accessories
C01C-050 Removing of instullation 15.00 29-Aug-10 A 23-Sep-10 A Removing of instullation
C01C-110 Cutting / releasing of 9th shell cource 3.00 30-Sep-10 A 04-Oct-10 A Cutting / releasing of 9th shell cource
C01C-120 Cutting / releasing of 8th shell cource 3.00 04-Oct-10 A 07-Oct-10 A Cutting / releasing of 8th shell cource
C01C-130 Cutting / releasing of 7th shell cource 3.00 07-Oct-10 A 11-Oct-10 A Cutting / releasing of 7th shell cource
C01C-140 Cutting / releasing of 6th shell cource 3.20 11-Oct-10 A 14-Oct-10 A Cutting / releasing of 6th shell cource
C01C-150 Cutting / releasing of 5th shell cource 3.40 16-Oct-10 A 19-Oct-10 A Cutting / releasing of 5th shell cource
C01C-160 Cutting / releasing of 4th shell cource 3.70 19-Oct-10 A 24-Oct-10 A Cutting / releasing of 4th shell cource
C01C-170 Cutting / releasing of 3th shell cource 4.00 24-Oct-10 A 28-Oct-10 A Cutting / releasing of 3th shell cource
C01C-180 Cutting / releasing of 2th shell cource 4.40 28-Oct-10 A 02-Nov-10 A Cutting / releasing of 2th shell cource
C01C-190 Cutting / releasing of 1th shell cource 4.40 02-Nov-10 A 07-Nov-10 A Cutting / releasing of 1th shell cource
C01C-200 Cutting / releasing of bottom plate 6.00 03-Nov-10 A 10-Nov-10 A Cutting / releasing of bottom plate
C01C-210 Dismantle of scaffold 26.00 04-Oct-10 A 03-Nov-10 A Dismantle of scaffold
C01C-310 Foundation inspection & repair 6.00 10-Nov-10 A 20-Nov-10 A Foundation inspection & repair
C01C-320 Check & change damaged anchor bolt 12.00 10-Nov-10 A 27-Nov-10 A Check & change damaged anchor bolt
ROOF REMOVAL 144.00 06-Nov-10 A 24-Apr-11 ROOF REMOVAL
CRRC-010 Civil contractor mobilization 6.00 06-Nov-10 A 06-Dec-10 A Civil contractor mobilization
CRRC-020 Preparation of work area 2.00 13-Nov-10 A 14-Nov-10 A Preparation of work area
CRRC-030 Form work / inspection of foundations 9.00 20-Nov-10 A 07-Dec-10 A Form work / inspection of foundations
CRRC-040 Pouring of concrete / inspection of foundations 3.00 08-Dec-10 A 09-Dec-10 A Pouring of concrete / inspection of foundations
CRRC-050 Installation / alignment of temp. columns 3.00 11-Dec-10 A 03-Feb-11 A Installation / alignment of temp. columns
CRRC-060 Installation of bracing 2.00 14-Dec-10 A 03-Feb-11 A Installation of bracing
CRRC-070 Handling / cutting of roof 6.00 02-Apr-11 A 07-Apr-11 Handling / cutting of roof
CRRC-080 Releasing cut portions 2.00 09-Apr-11 10-Apr-11 Releasing cut portions
CRRC-090 Removing of temp. structure 2.00 11-Apr-11 12-Apr-11 Removing of temp. structure
CRRC-100 Removing of temp. concrete foundation 4.00 13-Apr-11 17-Apr-11 Removing of temp. concrete foundation
CRRC-110 Site cleaing 3.00 18-Apr-11 20-Apr-11 Site cleaing
CRRC-120 Civil contractor demobilization 3.00 21-Apr-11 24-Apr-11 Civil contractor demobilization
CONST. NEW TANK TK-2502-001 (FR 16.47M DIA X 19.70M H) 189.80 27-Nov-10 A 06-Jul-11 CONST. NEW TANK TK-2502-001 (FR 16.47M DIA X 19.70M H)
C01E Erection of tank 80.50 27-Nov-10 A 20-Apr-11 Erection of tank
C01H Hydro test of tank 15.20 18-Apr-11 05-May-11 Hydro test of tank
C01P Painting of tank 76.90 02-Apr-11 29-Jun-11 Painting of tank
C01V Handing over of tank 37.00 24-May-11 06-Jul-11 Handing over of tank
ERECTION 120.50 27-Nov-10 A 20-Apr-11 ERECTION
TANK BASE 52.00 27-Nov-10 A 28-Feb-11 A TANK BASE
Annular Plate 4.00 27-Nov-10 A 02-Dec-10 A Annular Plate
C01EB1-010 Erection / fit up of annular plate 1.50 27-Nov-10 A 29-Nov-10 A Erection / fit up of annular plate
C01EB1-020 Welding of annular plate 2.50 29-Nov-10 A 02-Dec-10 A Welding of annular plate
Bottom Plate 48.00 29-Dec-10 A 28-Feb-11 A Bottom Plate
C01EB2-010 Erection / fit up of bottom plate 5.00 29-Dec-10 A 28-Feb-11 A Erection / fit up of bottom plate
C01EB2-020 Welding of bottom plate 8.00 02-Jan-11 A 10-Jan-11 A Welding of bottom plate
C01EB2-030 Fit up bottom to annular 2.50 22-Jan-11 A 24-Jan-11 A Fit up bottom to annular
C01EB2-040 Welding bottom to annular 4.00 23-Jan-11 A 27-Jan-11 A Welding bottom to annular
TANK SHELL 102.80 04-Dec-10 A 05-Apr-11 TANK SHELL
1st Shell Cource 46.20 04-Dec-10 A 28-Feb-11 A 1st Shell Cource
C01ES1-010 Erection / fit up of 1st shell plates 1.30 04-Dec-10 A 28-Dec-10 A Erection / fit up of 1st shell plates
C01ES1-020 Welding vertical 1st shell joints 2.50 05-Dec-10 A 09-Dec-10 A Welding vertical 1st shell joints
C01ES1-030 Fit up annular to shell 2.00 22-Jan-11 A 30-Jan-11 A Fit up annular to shell
C01ES1-040 Welding annular to shell 4.50 23-Jan-11 A 28-Feb-11 A Welding annular to shell
2nd Shell Cource 32.00 25-Dec-10 A 11-Jan-11 A 2nd Shell Cource
C01ES2-010 Erection / fit up of 2nd shell plates 1.20 25-Dec-10 A 26-Dec-10 A Erection / fit up of 2nd shell plates
C01ES2-020 Welding vertical 2nd shell joints 2.40 01-Jan-11 A 04-Jan-11 A Welding vertical 2nd shell joints
C01ES2-030 Fit up for 1st Circumferential joint 1.80 05-Jan-11 A 06-Jan-11 A Fit up for 1st Circumferential joint
C01ES2-040 Welding of 1st Circumferential joint 4.00 06-Jan-11 A 11-Jan-11 A Welding of 1st Circumferential joint
3rd Shell Cource 6.90 16-Jan-11 A 20-Jan-11 A 3rd Shell Cource
C01ES3-010 Erection / fit up of 3rd shell plates 1.10 16-Jan-11 A 17-Jan-11 A Erection / fit up of 3rd shell plates
C01ES3-020 Welding vertical 3rd shell joints 2.30 18-Jan-11 A 19-Jan-11 A Welding vertical 3rd shell joints
C01ES3-030 Fit up for 2nd Circumferential joint 1.60 19-Jan-11 A 19-Jan-11 A Fit up for 2nd Circumferential joint
C01ES3-040 Welding of 2nd Circumferential joint 3.80 19-Jan-11 A 20-Jan-11 A Welding of 2nd Circumferential joint
4th Shell Cource 10.00 29-Jan-11 A 02-Feb-11 A 4th Shell Cource
C01ES4-010 Erection / fit up of 4th shell plates 1.00 29-Jan-11 A 29-Jan-11 A Erection / fit up of 4th shell plates
C01ES4-020 Welding vertical 4th shell joints 2.20 29-Jan-11 A 30-Jan-11 A Welding vertical 4th shell joints
C01ES4-030 Fit up for 3rd Circumferential joint 1.50 31-Jan-11 A 01-Feb-11 A Fit up for 3rd Circumferential joint
C01ES4-040 Welding of 3rd Circumferential joint 2.00 01-Feb-11 A 02-Feb-11 A Welding of 3rd Circumferential joint
5th Shell Cource 6.00 07-Feb-11 A 12-Feb-11 A 5th Shell Cource
MITSUI ENGINEERING & SHIP BUILDING CO. PETRORABIGH
Activity ID Activity Name Original Start Finish 2010 2011
Duration Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 6465
C01ES5-010 Erection / fit up of 5th shell plates 0.80 07-Feb-11 A 07-Feb-11 A Erection / fit up of 5th shell plates
C01ES5-020 Welding vertical 5th shell joints 2.10 08-Feb-11 A 08-Feb-11 A Welding vertical 5th shell joints
C01ES5-030 Fit up for 4th Circumferential joint 1.40 08-Feb-11 A 09-Feb-11 A Fit up for 4th Circumferential joint
C01ES5-040 Welding of 4th Circumferential joint 3.30 10-Feb-11 A 12-Feb-11 A Welding of 4th Circumferential joint
Wind Girder#1 13.00 15-Feb-11 A 20-Mar-11 A Wind Girder#1
C01ESW-010 Erection / fit up of wind girder 3.00 15-Feb-11 A 24-Feb-11 A Erection / fit up of wind girder
C01ESW-020 Welding of wind girder 4.00 24-Feb-11 A 20-Mar-11 A Welding of wind girder
6th Shell Cource 6.20 14-Feb-11 A 19-Feb-11 A 6th Shell Cource
C01ES6-010 Erection / fit up of 6th shell plates 0.70 14-Feb-11 A 15-Feb-11 A Erection / fit up of 6th shell plates
C01ES6-020 Welding vertical 6th shell joints 2.00 14-Feb-11 A 16-Feb-11 A Welding vertical 6th shell joints
C01ES6-030 Fit up for 5th Circumferential joint 1.30 17-Feb-11 A 17-Feb-11 A Fit up for 5th Circumferential joint
C01ES6-040 Welding of 5th Circumferential joint 3.20 17-Feb-11 A 19-Feb-11 A Welding of 5th Circumferential joint
7th Shell Cource 4.40 21-Feb-11 A 24-Feb-11 A 7th Shell Cource
C01ES7-010 Erection / fit up of 7th shell plates 0.60 21-Feb-11 A 22-Feb-11 A Erection / fit up of 7th shell plates
C01ES7-020 Welding vertical 7th shell joints 1.90 22-Feb-11 A 22-Feb-11 A Welding vertical 7th shell joints
C01ES7-030 Fit up for 6th Circumferential joint 0.80 23-Feb-11 A 23-Feb-11 A Fit up for 6th Circumferential joint
C01ES7-040 Welding of 6th Circumferential joint 2.90 23-Feb-11 A 24-Feb-11 A Welding of 6th Circumferential joint
Wind Girder#2 29.00 26-Feb-11 A 05-Apr-11 A Wind Girder#2
C01ESW-030 Erection / fit up of wind girder 3.00 26-Feb-11 A 15-Mar-11 A Erection / fit up of wind girder
C01ESW-040 Welding of wind girder 4.00 16-Mar-11 A 05-Apr-11 A Welding of wind girder
8th Shell Cource 7.00 28-Feb-11 A 07-Mar-11 A 8th Shell Cource
C01ES8-010 Erection / fit up of 8th shell plates 0.60 28-Feb-11 A 28-Feb-11 A Erection / fit up of 8th shell plates
C01ES8-020 Welding vertical 8th shell joints 1.90 01-Mar-11 A 02-Mar-11 A Welding vertical 8th shell joints
C01ES8-030 Fit up for 7th Circumferential joint 0.80 02-Mar-11 A 02-Mar-11 A Fit up for 7th Circumferential joint
C01ES8-040 Welding of 7th Circumferential joint 2.90 05-Mar-11 A 07-Mar-11 A Welding of 7th Circumferential joint
9th Shell Cource 6.20 21-Mar-11 A 28-Mar-11 A 9th Shell Cource
C01ES9-010 Erection / fit up of 9th shell plates 0.60 21-Mar-11 A 21-Mar-11 A Erection / fit up of 9th shell plates
C01ES9-020 Welding vertical of 9th shell joints 1.90 21-Mar-11 A 23-Mar-11 A Welding vertical of 9th shell joints
C01ES9-030 Fit up for 8th Circumferential joint 0.80 23-Mar-11 A 24-Mar-11 A Fit up for 8th Circumferential joint
C01ES9-040 Welding of 8th Circumferential joint 2.90 24-Mar-11 A 28-Mar-11 A Welding of 8th Circumferential joint
Curb Angle 5.60 28-Mar-11 A 05-Apr-11 Curb Angle
C01ESC-010 Erection / fit up of curb angle 2.00 28-Mar-11 A 30-Mar-11 A Erection / fit up of curb angle
C01ESC-020 Welding curb angle 3.50 30-Mar-11 A 05-Apr-11 Welding curb angle
TANK ROOF 102.20 14-Dec-10 A 10-Apr-11 TANK ROOF
C01R-010 Erection of temporary structure 6.00 14-Dec-10 A 02-Jan-11 A Erection of temporary structure
C01R-020 Erection of roof frames 4.00 14-Dec-10 A 17-Jan-11 A Erection of roof frames
C01R-030 Erection of secondary rafters & plates 3.00 18-Jan-11 A 22-Jan-11 A Erection of secondary rafters & plates
C01R-040 Welding top side 6.00 23-Jan-11 A 29-Jan-11 A Welding top side
C01R-050 Welding under side 8.00 25-Jan-11 A 01-Feb-11 A Welding under side
C01R-060 Installation of roof appurtenance & walkway 6.00 12-Feb-11 A 19-Feb-11 A Installation of roof appurtenance & walkway
C01R-070 Lifting and seal welding to curb angle 2.00 07-Apr-11 10-Apr-11 Lifting and seal welding to curb angle
TANK ACCESSORIES 48.50 19-Feb-11 A 16-Apr-11 TANK ACCESSORIES
C01EAD Drip ring 5.00 02-Apr-11 06-Apr-11 Drip ring
C01EAS-G1 Shell appurtenance 0.00 02-Apr-11 02-Apr-11 Shell appurtenance
C01EAS-G3 Stairway 0.00 26-Feb-11 A 16-Apr-11 Stairway
C01EAS-G4 Misc. 0.00 16-Mar-11 A 16-Mar-11 A Misc.
Shell Accessories 48.50 19-Feb-11 A 16-Apr-11 Shell Accessories
Shell Appurtenance 36.90 19-Feb-11 A 02-Apr-11 Shell Appurtenance
C01EAS-020 Manways 0.30 26-Feb-11 A 26-Feb-11 A Manways
C01EAS-030 Inlet Nozzle N1 - 8" 0.60 16-Mar-11 A 16-Mar-11 A Inlet Nozzle N1 - 8"
C01EAS-040 To P 2502 N2 - 6" 1.20 16-Mar-11 A 17-Mar-11 A To P 2502 N2 - 6"
C01EAS-050 Return P 2502 N3 - 4" 1.00 19-Feb-11 A 19-Feb-11 A Return P 2502 N3 - 4"
C01EAS-060 Drain Nozzle N4 - 3" 1.20 19-Feb-11 A 20-Feb-11 A Drain Nozzle N4 - 3"
C01EAS-070 Thermo wall K3 - 1 1/2" 0.80 02-Apr-11 02-Apr-11 Thermo wall K3 - 1 1/2"
C01EAS-080 Foam chamber N8 - 8" 0.60 02-Apr-11 02-Apr-11 Foam chamber N8 - 8"
Stairway 42.20 26-Feb-11 A 16-Apr-11 Stairway
C01EAS-210 Preparation of Stairway 5.00 26-Feb-11 A 06-Apr-11 Preparation of Stairway
C01EAS-220 Erection/welding of supports 3.00 26-Feb-11 A 04-Apr-11 Erection/welding of supports
C01EAS-230 Erection/welding of stringer/platform/brackets 4.00 07-Apr-11 11-Apr-11 Erection/welding of stringer/platform/brackets
C01EAS-240 Erection of grating 2.50 12-Apr-11 14-Apr-11 Erection of grating
C01EAS-250- Erection of handrail 3.50 12-Apr-11 16-Apr-11 Erection of handrail
Misc. 29.20 26-Feb-11 A 02-Apr-11 Misc.
C01EAS-420 Fire fighting bracket supports 4.00 26-Feb-11 A 12-Mar-11 A Fire fighting bracket supports
C01EAS-440 Insulating supports 3.00 28-Mar-11 A 31-Mar-11 A Insulating supports
C01EAS-450 Earthing lug/Name plate 0.20 28-Mar-11 A 02-Apr-11 Earthing lug/Name plate
Drip Ring 5.00 02-Apr-11 06-Apr-11 Drip Ring
C01EAD-010 Erection / fit up of drip ring 2.00 02-Apr-11 03-Apr-11 Erection / fit up of drip ring
C01EAD-020 Welding of drip ring 3.00 04-Apr-11 06-Apr-11 Welding of drip ring
TANK CLEANING 14.30 31-Mar-11 A 20-Apr-11 TANK CLEANING
C01EC-010 Shell internal cleaning 8.00 03-Apr-11 A 14-Apr-11 Shell internal cleaning
C01EC-020 Shell external cleaning 4.00 31-Mar-11 A 20-Apr-11 A Shell external cleaning
C01EC-040 Temorary blind flanges 1.00 16-Apr-11 17-Apr-11 Temorary blind flanges
C01EC-050 Temporary piping and hydrotest connections 1.00 16-Apr-11 17-Apr-11 Temporary piping and hydrotest connections
HYDRO TEST 15.20 18-Apr-11 05-May-11 HYDRO TEST
C13H-010 Filling water 7.20 18-Apr-11 26-Apr-11 Filling water
C13H-020 Draining water 6.00 26-Apr-11 03-May-11 Draining water
C13H-030 Washing and cleaning 2.00 03-May-11 05-May-11 Washing and cleaning
PAINTING 77.00 02-Apr-11 A 29-Jun-11 PAINTING
ROOF PAINTING 17.00 02-Apr-11 A 14-Apr-11 ROOF PAINTING
MITSUI ENGINEERING & SHIP BUILDING CO. PETRORABIGH
Activity ID Activity Name Original Start Finish 2010 2011
Duration Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 6465
C01P0 ROOF PAINTING 17.00 02-Apr-11 A 07-Apr-11 ROOF PAINTING
C01P0-010 Blasting & 1st primer coat for internal roof 4.00 02-Apr-11 A 05-Apr-11 A Blasting & 1st primer coat for internal roof
C01P0-020 2nd primer coat for internal roof 1.40 06-Apr-11 A 07-Apr-11 A 2nd primer coat for internal roof
C01P0-030 1st Intermediate coat for internal roof 2.20 07-Apr-11 A 10-Apr-11 A 1st Intermediate coat for internal roof
C01P0-040 2nd Intermediate coat for internal roof 1.00 10-Apr-11 A 11-Apr-11 A 2nd Intermediate coat for internal roof
C01P0-050 1st top coat for internal roof 2.00 11-Apr-11 A 13-Apr-11 A 1st top coat for internal roof
C01P0-060 2nd top coat for internal roof 0.90 13-Apr-11 A 14-Apr-11 A 2nd top coat for internal roof
C01P0-070 Stripe coat for external roof 4.50 02-Apr-11 06-Apr-11 Stripe coat for external roof
C01P0-080 Final inspection and touch up of roof 1.00 20-Apr-11 A 07-Apr-11
INTERNAL PAINTING 47.20 05-May-11 29-Jun-11 INTERNAL PAINTING
C01P1 Internal painting 47.20 05-May-11 29-Jun-11 Internal painting
C01P1-010 Erect internal scaffolding 10.00 05-May-11 17-May-11 Erect internal scaffolding
C01P1-020 Blasting & 1st primer coat for internal shell 5.00 17-May-11 23-May-11 Blasting & 1st primer coat for internal shell
C01P1-030 2nd primer coat for internal shell 3.00 23-May-11 26-May-11 2nd primer coat for internal shell
C01P1-040 1st Intermediate coat for internal shell 4.00 26-May-11 31-May-11 1st Intermediate coat for internal shell
C01P1-050 2nd Intermediate coat for internal shell 2.40 31-May-11 04-Jun-11 2nd Intermediate coat for internal shell
C01P1-080 1st top coat for internal shell 3.00 04-Jun-11 07-Jun-11 1st top coat for internal shell
C01P1-085 2nd top coat for internal shell 2.00 07-Jun-11 09-Jun-11 2nd top coat for internal shell
C01P1-090 Final inspection & touch up for internal roof & shell 1.00 09-Jun-11 11-Jun-11 Final inspection & touch up for internal roof & shell
C01P1-100 Dismantal of scaffolding 8.00 11-Jun-11 20-Jun-11 Dismantal of scaffolding
C01P1-110 Tank cleaning 2.00 20-Jun-11 22-Jun-11 Tank cleaning
C01P1-130 Blasting & 1st primer coat of bottom plate 1.80 22-Jun-11 23-Jun-11 Blasting & 1st primer coat of bottom plate
C01P1-135 2nd primer coat of bottom plate 1.00 23-Jun-11 25-Jun-11 2nd primer coat of bottom plate
C01P1-140 1st Intermediate coat of bottom plate 1.40 25-Jun-11 27-Jun-11 1st Intermediate coat of bottom plate
C01P1-145 2nd Intermediate coat of bottom plate 0.70 27-Jun-11 27-Jun-11 2nd Intermediate coat of bottom plate
C01P1-150 1st top coat of bottom plate 0.90 28-Jun-11 28-Jun-11 1st top coat of bottom plate
C01P1-155 2nd top coat of bottom plate 0.50 28-Jun-11 29-Jun-11 2nd top coat of bottom plate
C01P1-160 Final inspection of bottom plate 0.50 29-Jun-11 29-Jun-11 Final inspection of bottom plate
EXTERNAL PAINTING 16.00 05-May-11 24-May-11 EXTERNAL PAINTING
C01P2-010 Erection of external scaffolding 10.00 05-May-11 17-May-11 Erection of external scaffolding
C01P2-020 Stripe coat for external shell 10.00 12-May-11 24-May-11 Stripe coat for external shell
INSULATION / INSTALLATION / HANDING OVER 37.00 24-May-11 06-Jul-11 INSULATION / INSTALLATION / HANDING OVER
C01V-010 Tank calibration 1.00 29-Jun-11 30-Jun-11 Tank calibration
C01V-030 Instruments Installation 3.40 30-Jun-11 05-Jul-11 Instruments Installation
C01V-050 Tank insulation 30.00 24-May-11 28-Jun-11 Tank insulation
C01V-060 Dismantal of extenal scaffolding 8.00 25-Jun-11 04-Jul-11 Dismantal of extenal scaffolding
C01V-070 Box up 2.00 04-Jul-11 06-Jul-11 Box up

Actual Work Critical Remaining Work Summary Page 3 of 3 Date Revision Checked Approved
23-Oct-10 REV.10 UPD.1 Amir Hegazy Abdul Kadir Umar
Remaining Work Milestone
04-Dec-10 REV.10 UPD.2 Amir Hegazy Abdul Kadir Umar