ConstructionSafety PDF
ConstructionSafety PDF
ConstructionSafety PDF
December 2007
1.0 Introduction
This document covers the legislative frame work for construction safety,
management issues, safety measures in various construction activities,
guidelines on personal protective equipment and selected case studies of
accidents from which important lessons can be learnt.
1
2.0 Legislative Framework
2
The above issues should be addressed by the project management during the
entire life cycle of the project. Few measures are listed below for a
comprehensive safety management of the project.
! Safety organization shall comply with all the requirements such as safety
surveillance, safety training, safety enforcement measures, safety audit
etc. related to all works.
3
3.3 Surveillance Programme
3.4 Training/Orientation
Safe place of working and safe system of working are the two important
requirements in reducing accidents in construction site. Though safe place of
working can be provided, safe system of working can only be provided through
proper training to the workmen. Safety training should be made a part of all
construction jobs. It should include
4
3.5 Certification of Construction Workers
In order to ensure safety in all hazardous jobs such as excavation, work at height,
work in confined spaces, working with chemicals, welding and gas cutting etc.,
safety work permit should be taken. The permit procedures should be well
established and practiced. The importance of permit system should be impressed
upon the line management. The record of permits should be maintained in a
systematic manner and should be verified periodically by safety officials.
It is found that about 60% of fatalities are caused due to fall of persons from
height. A system of issuing height passes to persons detailed to work at height is
introduced in construction sites. It is to be ensured that an established procedure
for issue of height passes is in place. The height pass is issued after conducting
medical examination of persons and rig walk test to ensure the physical fitness to
work at height. The height pass issued is made available with persons for all
works at height. This serves as a mechanism to check that only medically fit
workers are deployed for jobs at height.
3.9 Documentation
The documents that need to be prepared at any construction site are, construction
safety manual, job hazard analysis reports, checklists and supporting documents
like procedures for vehicle control movement, training manual, safety work
permit system etc. Which are need based and specific to each site.
5
3.9.1 Construction Safety Management Manual (CSMM)
Job hazard analysis is one of the best methods for identifying all possible hazards
associated with a job and the safety measures to be taken for each possible
identified hazard. Before start of construction activity, detailed job hazard
analysis (JHA) should be carried out for all critical jobs starting from excavation
to equipment erection and a checklist should be prepared based on the job hazard
analysis carried out. In job hazard analysis, first a job is selected and then it is
broken into different steps. For each step, hazards are identified and accordingly
safety measures to be taken for each hazard are brought out.
It is a fact that the accidents can be eliminated by providing safe working place
and establishing safe ways of working at the construction site. A brief description
of different types of construction activities, their associated hazards and safety
measures to be taken for prevention of accidents are highlighted. AERB's
6
stipulations through notifications wherever issued are provided for reference in
this monograph.
4.1 Blasting
The blasting works involve use of explosives. A safety work permit is issued for
carrying out this job. The blasting jobs should be well planned. The hazards
involved during blasting are damage to adjacent property, injuries to nearby
personnel etc.
i) The blaster should be a qualified and competent person for carrying out
blasting work. He should know about the dangers involved.
ii) Blasting in the open site shall only be carried out during the fixed hours
every day / fixed day in the week. Workers & residence of adjacent
property been informed about the blasting so they will not be
unnecessarily disturbed by it.
iii) No loose material such as tools, drilling implements etc. shall be left on
the rock surface to be blasted.
vi) The grit blaster should wear facial respirator with clean air supply to
avoid inhalation of free silica.
7
viii) Care should be taken that the blasting point is free of detonating gas,
inflammable objects, sparking or damage wiring system, stray currents
4.2 Excavation
i) Means for rapid access and egress should be provided. All trenches 120
cm or more in depth shall at all times be supplied with at least one ladder
for every 30 m along the trench. Ladder shall be extended from bottom
of the trench to at least 1 metre above the surface of the ground.
iii) Measures shall be taken to prevent persons who are not engaged in
excavation work, from approaching excavation areas by placing
warning signals, barricades etc. near the site of the excavation.
iv) Excavated material shall not be dumped within 1.5 metres of the edges.
v) Excavated area shall have illumination level of at least 20 lux for night
work.
4.2.1 Trench
The hazards associated with trench work are collapsing of the sides /caving in
and burying / partially burying those in the trench. Trench provides confined
space to work & collapse occurs quickly without warning. The probability of
locating & rescuing a person in time is very low which increases the severity of
the hazard. Main hazards associated with trench work are:
8
ii) Worker being struck by falling materials;
ii) Shoring (supporting the sides of the trench) and /or proper slopes to the
trench walls should be provided.
iv) Trench sides in the work should be thoroughly inspected before start of
work.
vi) Ladder access at suitable intervals with proper support in the trench
should be provided and ladder should extend above the ground level.
vii) Vehicles should be prevented from approaching too close to the edge of
the trench by providing suitable stops.
viii) Clearance should be taken from electrical section before carrying out
trench work.
9
4.2.2 Shaft
Hazards mentioned for trench work are also applicable to the work related to
shafts along with one additional & potential hazard called “ Dangerous Working
Atmosphere”.
i) Test for oxygen level inside the shaft before start of work everyday.
ii) In case of fuel operated machines, frequent monitoring of the air along
with a proper ventilation system for the shaft should be ensured to
provide a healthy working atmosphere.
iii) Effective communication system between the ground staff & the
persons working in the shaft should always be there to ensure safe
working environment.
4.3.1 Scaffold
ii) Fall of materials: Materials/tools may slip & fall from working
platform and can injure persons working below.
iii) Scaffold collapse: This is one of the potential hazards associated with
work at height, which can result in multiple casualties.
10
Measures to be taken to prevent the above hazards are:
ii) The platform should be strong enough to bear the loads of workmen &
materials.
iii) The ground should be checked for firmness & if necessary base plates
should be used for support.
iv) Toe board should be fitted on the working platform to arrest fall of
materials /tools.
v) Frequently used tools should be tied to the worker else kept inside a
covered & secured toolbox on the platform.
vi) Persons should not be allowed to work under the scaffold and if at all it is
necessary to carry out work, then safety net should be provided to arrest
the fall of materials & tools.
ix) Scaffold should not be over loaded with excess manpower or materials.
xii) All persons while working at height should use personal protective
equipment like safety belt with full body harness, helmet etc.
11
xvi) Width of the platform should be sufficient (about one meter) enough to
accommodate the personnel and material required for the specific job.
xvii) The platform /walkways should not have any openings /gaps.
The H-Form work popularly known as DOKA, is a mould used to shape the
concrete and support the concrete until it attains sufficient strength. It is an
engineered system used for concreting works. The hazards associated with this
system are falling of members, fall of persons from the platform etc. A typical
H-Form used for wall concreting is shown in the photograph. The hazards are
mainly associated during shuttering and de-shuttering operations. Accidents
leading to death are mainly caused due to improper usage, lack of quality
assurance, use of non-standard components etc.
12
iii) Quality assurance programmes for non-standard components should be
in place.
iv) Mock-up exercises should be carried out before actually installing at work
spot.
vi) The shuttering /de-shuttering works should be carried out under strict
supervision.
4.3.3 Ladder
i) Slip of ladder: This is the most common form of hazard associated with
13
the ladder as it may slip while the person is climbing on it or working
from it at a height.
ii) Fall of person: A person may fall while climbing on the ladder due to
loss of balance while carrying materials or due to missing a rung in the
ladder.
iii) Ladder Collapse: The ladder may give away under the load of the
person resulting in severe injuries.
iv) Electrocution: The metallic ladder may come in contact with live
electrical lines and the person working on it may get electrocution.
i) The ladder should stand evenly on its stiles on a firm and level surface.
ii) Ladder should be securely tied near its upper end grouted at lower end to
the permanent structure when used for access to platforms.
0
iii) Ladder should be placed approximately at an angle of 75 to the
horizontal when it is used for access as well as working platform.
vi) Ladders should be inspected thoroughly for any defects before start of
work and on regular intervals.
vii) Use of metallic ladders or wooden ladders with metallic parts should be
prohibited in the areas where live electric lines are available.
ix) Rungs & footwear of persons should be free from slippery materials
such as oil/mud to avoid slipping from the ladder.
xi) Persons should face the ladder while climbing up or getting down.
14
A Ladder for access to height with secure working platform
The most serious accidents that occur during erection work of structures are due
to fall of workers from the structures, fall of materials from structures on persons
working below and collapse of the structure or a part of the structure.
ii) Properly inclined ladders secured at the top should be used for
vertical movements.
iii) A suitable working platform with guard rails & toe guards should be
provided.
iv) If work is to be carried out for a short time and where working platform is
not feasible, then the workmen should use safety belts secured to a
permanent member of the structure to prevent fall. Where a rigid
member is not available for securing the safety belt hook, proper
lifelines should be provided for the purpose, with the lifelines firmly
attached to nearby strong structures.
vi) Frequently used tools should be tied to the worker else kept inside a
15
covered & secured toolbox on the platform.
i) All open sides of structure above a height of 3.5 metres from which a
worker might fall and openings into which a worker might fall should be
adequately covered or barricaded. Every opening in the floor of a
building, or in a working platform shall be provided with suitable means
to prevent fall of persons or materials by providing suitable
fencing/railing of 1 metre.
ii) Where barricades could not be installed, safety net should be installed
close to the level at which there is a danger of a fall. During erection of
tall buildings/structures above 3.5 metres height, nylon nets shall be
provided to prevent fall from height in case it is not possible to provide
barricades.
v) Scaffolding or staging 3.5 metres above the ground floor shall have a
guard rail properly attached, bolted, braced or otherwise secured at least
1 metre high above the floor/ platform.
16
vi) Where the platform is more than 3.5 metres above ground floor for
working/ standing on the platform, the width should be minimum 1
metre.
Openings are needed to be kept in the constructed floor of the building for
material movement or equipment erection. If these openings are not
covered/barricaded properly, man or material may fall through these. Thus either
the man falling through the opening gets serious injury or any person working
below the opening gets injury due to fall of material through the opening.
To prevent fall of person or material through opening, every opening in the floor
of a building shall be provided with suitable fencing/railing of 1 metre height
with toe guard. Where barricades can not be installed, safety net should be
installed close to the level at which there is a danger of a fall.
Good practice used to arrest the fall through floor opening with metal gratings
17
4.6 Use of Material Handling Equipment
i) No lifting machine, chain, rope or lifting tackle shall be taken into use for
the first time unless it has been tested and examined by a competent
person and a certificate of such a test and examination specifying the
safe working load and signed by the person making the test and the
examination is kept available for inspection.
ii) Cranes shall be operated only by authorised persons who are well trained
and experienced.
iv) Standard signals shall be used so that the operator and user are able to
synchronise their communication.
vi) The load to be lifted should not exceed the Safe Working Load (SWL).
vii) The load to be lifted should be secured tightly to prevent falling during
lifting.
18
4.7 Use of Portable Electrical Equipment
19
4.8 Working in Confined Space
During construction, different works are required to be carried out inside the
confined spaces like boiler, pipeline, pit, reaction or process vessel, storage tank
etc. Conditions like oxygen deficiency, toxic atmospheres, high temperatures
etc. may occur inside the confined space and these conditions may lead to serious
health hazard of the people working inside the confined space. So all employees
required to enter into confined or enclosed spaces shall be instructed about the
hazards involved, the necessary precautions to be taken, and the use of protective
and emergency equipment. No person should enter in any confined space like
tank, pit chamber etc. in which gas, fumes, vapours, dust are likely to be present
to such extent that it may endanger his/her health without safety work permit.
ii) The oxygen content inside the confined space should also be measured
along with arrangement for forced air supply inside the confined space.
No permit should be issued if the oxygen content is below 19%.
iii) The person while entering the confined space should wear Self
Contained Breathing Apparatus (SCBA) set. if hazardous substance is
likely to be present or oxygen deficiency is likely to occur during the
course of work.
vi) No single person should be allowed to enter into the confined space.
Buddy system should be followed for working inside confined space.
Persons entering inside the confined space should work as a team of two.
Backup persons should also be available outside to assist whenever
required.
20
vii) Authorized persons entering a confined space must wear a chest or full
body harness with a retrieval line attached to the center of their backs
near shoulder level or above their heads. The other end of the retrieval
line should be held by a rescue person outside or attached to a
mechanical device outside the confined space.
Cutting and welding operations (commonly referred to as hot work) are widely
performed during construction activities. Potential health, safety, and property
hazards result from the fumes, gases, spark, hot metal and radiant energy
produced during hot work. Hot work equipment, which utilizes electricity or
compressed gases, requires special awareness and training on the part of the
worker to be used safely. Welding and Cutting operations present a variety of
hazards, not only to those carrying out the operation but in many instances to
others in the vicinity. The hazards associated with hot work can be reduced
through the implementation of effective control programs. Cutting and welding
job should be controlled by permit to work system. The possibility of electric
shock is one of the most serious risks encountered by a welder. Accidental
contact with the 'live' electrical components, including the electrode and the
work piece, can result in serious a burn injury or more seriously electric shock.
Electric shock can kill either by direct action on the body or by a resultant fall, if
working at height.
21
Safety Measures during Gas Cutting
i) The gas cylinders should be kept well away from any fire or hot areas.
Welding hose, gas torches, valve connections should be checked for
leakage of gas.
ii) The gas cutter should use personal protective equipment like goggles,
hand gloves, safety shoes etc.
iii) Proper routing of welding hose should be done before the start of the
work to avoid damage due to other personnel/equipment movements.
iv) Before starting any gas cutting, a written permit clearance should be
obtained from authorised agency indicating special precautions
including the fire fighting details.
i) Correct and proper electric earthing should be done for the welding
machine, the casing and the job to be welded. An authorised and trained
electrician should check all connections.
ii) The welding cable should be in good condition without any insulation
damage. The welding cable connections should be tight. The cable
should not be laid on wet surface.
iii) All welding work should be started only after obtaining welding permit
from authorised agency indicating special precautions including the
availability of fire fighting measures near the job.
iv) During carrying out welding, welder should use personal protective
equipments like welding screen, hand gloves etc.
22
vi) For welding in confined areas like inside of tanks, pipes etc., proper
ventilation should be provided.
vii) For welding work on overhead equipment such as crane etc. a separate
earth cable should run upto the work place and should be connected to
work place.
5.1.3 Enforce the usage of PPE by workman through proper training and
awareness programmes .
23
6.0 Suggestions for improvement in Accident Prevention Programme
Brief Description:
During the cleaning of the belt at the tail pulley area of conveyor of sand
screening section of batching plant, one worker was trapped between the
tail end pulley belt roller and ground. The trapped person sustained
multiple injuries.
Brief Description:
During gasket replacement job in the down stream flange of the two
24
Atmospheric Steam Discharge Valves (ASDV), one of the ASDV popped up
2
and lot of saturated steam at 49 Kg/cm pressure and about 260 deg C came
out through the downstream flange of ASDV. One of the helpers engaged in
the work got serious steam burns.
Brief Description:
During lifting of a pipe spool of 20 inches in diameter and weighing about
260 kgs by a chain pulley block of capacity 2 ton, the load hook of the chain
pulley block suddenly got detached from the swiveling block. The pipe spool
fell down and the elbow of the pipe spool hit the rigger.
25
Lessons learnt to prevent such accident:
- Checklist for inspection of chain pulley block should be made
incorporating all critical parameters like availability of grub screw,
punching marks etc.
- Person should not stand below the hanging load or come close to it.
Brief Description:
A bundle of reinforcement rods weighing about 205 kg were being lowered
to ground (Elevation 12000 mm) by Tower Crane. A Fitter was in that
location for unloading the bundle from the crane. During the lowering
process, an ISMB 100 beam, about 2 metre long, weighing abut 23 kg, that
was kept on two climbing brackets at the Elevation 20400 mm level, was
dislodged by the hook block of the Tower Crane. It fell on the fitter, causing
injury on right forehead.
Brief Description:
One worker fell from El 108 m to El 100 m through a hatch block opening of
length 2.2 m x width 0.5 m.
26
Probable Cause of the accident:
The hatch block opening was covered by one old 12 mm thickness plywood sheet
of length 2.4 m X width 0.4 m. Below the plywood 4 nos. of 10 mm rods were
kept loosely. When the worker kept his feet on the plywood, due to his weight,
plywood sheared and he fell down through the opening. The opening was not
barricaded by any guardrail, which could have prevented the fall of the victim.
Also multiple agencies were using that opening for material lifting and lack of
communication was there among the contractors.
8.0 Conclusion
Acknowledgements
The authors are grateful to Shri S.K.Sharma, Chairman, AERB and Shri
S.K.Chande, Vice -Chairman, AERB for their suggestions in preparation of this
monograph and constant encouragement & guidance.
27
Sincere thanks are also due to Dr P.C.Basu, Director, C&SED and his staff, Shri
R.I.Gujarathi, Director, NPSD, Dr. Om Pal Singh, Director, ITSD, Smt.S.
Bhattacharya, formerly of NPSD, Shri K.Ramprasad, IPSD, Shri L. N. Valiveti,
IPSD and Shri Nidhip Chodankar, IPSD for their review and expert comments.
References
28
Published By : Atomic Energy Regulatory Board
Niyamak Bhavan
Anushaktinagar
Mumbai 400 094
INDIA
GOVERNMENT OF INDIA
CONSTRUCTION SAFETY
A MONOGRAPH