Lecture Unit Commitment - Numericals

This document discusses optimal system operation for power plants through a multistage process of load forecasting, unit commitment, and economic dispatch. It is not economical to run all power plant units at all times, so unit commitment determines which plants should be online to meet a given load in the most cost-effective way, taking into account the type of plants, maintenance schedules, and other factors. Economic dispatch then determines the optimal output levels of the committed plants. This multistage process aims to ensure reliable and cost-efficient electricity supply.

Uploaded by

champion 88
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
40 views

Lecture Unit Commitment - Numericals

This document discusses optimal system operation for power plants through a multistage process of load forecasting, unit commitment, and economic dispatch. It is not economical to run all power plant units at all times, so unit commitment determines which plants should be online to meet a given load in the most cost-effective way, taking into account the type of plants, maintenance schedules, and other factors. Economic dispatch then determines the optimal output levels of the committed plants. This multistage process aims to ensure reliable and cost-efficient electricity supply.

Uploaded by

champion 88
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 10

Problem formulation and examples on unit

commitment, and economic dispatch


Optimal System Operation
 Not economical to run all the units at all times

 For a given load to determine which units should be On is UCP.

 Important for thermal power plants

Multistage process:
Load forecasting,
Type of power plants
Availability of plant; if under maintenance
Unit commitment
Economic Dispatch
Optimal System Operation
Optimal System Operation
Optimal System Operation
Optimal System Operation
Optimal System Operation
Optimal System Operation
Optimal System Operation
Optimal System Operation