Open navigation menu
Close suggestions
Search
Search
en
Change Language
Upload
Sign in
Sign in
Download free for days
100%
(1)
100% found this document useful (1 vote)
544 views
6 pages
Case Study 3 - Production and Cost
Hi
Uploaded by
Lavan Satha
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content,
claim it here
.
Available Formats
Download as PDF or read online on Scribd
Download
Save
Save Case Study 3 - Production and Cost For Later
Share
100%
100% found this document useful, undefined
0%
, undefined
Print
Embed
Report
100%
(1)
100% found this document useful (1 vote)
544 views
6 pages
Case Study 3 - Production and Cost
Hi
Uploaded by
Lavan Satha
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content,
claim it here
.
Available Formats
Download as PDF or read online on Scribd
Carousel Previous
Carousel Next
Download
Save
Save Case Study 3 - Production and Cost For Later
Share
100%
100% found this document useful, undefined
0%
, undefined
Print
Embed
Report
Download
Save Case Study 3 - Production and Cost For Later
You are on page 1
/ 6
Search
Fullscreen
‘Edwin Mansfield and Harold H. Wein A Managerial Application of Cost Functions by a Railroad ‘There have been numerous studies where ithe relationship between cost and output has ‘een estimated for manufacturing plants, ‘These studies fail generally into’ two cate- gories. In the first category, the chief pur- [pose of the work has been to accumulate -evidence concerning various cost curves that occupy an important place in econ- ‘omics, In the second category, the work has ‘been done primarily with a view toward ‘the direct usefulness of the relationship of. cost and output to industrial managers. This paper falls into the second category. ‘We give an illustration here of how such a relationship may be used to formulate a simple control chart for costs, a topic which should be of interest to many applied statisticians and industrial man- agers. The problem of controlling per- formance and costs is important in almost every sector of industry and trade. Our data, and hence our specific results, per- -- tain to the American railroad industry, but the statistical techniques that are used ‘may be applicable to other industries as well. FREIGHT YARDS AND COST CONTROL Freight yards differ greaily in size, layout, and type, but they have certain physical characteristics and functions in common. Physical Characteristics. AU yards contain. sets of tracks. In large yards they are generally of three types: receiving tracks where incoming freight cars are stored, classification tracks where cars are switched, and outbound tracks where cars that were situated on a classification track are stored until a locomotive hauls them away as a train, ' Functions. Freight yatds switch cars. That is, they sort incoming cars by putting them on the appropriate classification tracks, and in this way they break up incoming trains to form new trains. Most yards also deliver-and pick up cars. Engines are as- signed to deliver cars to industrial sidings and other yards and to pick them up there. Finally, many yards bill and inspect freight cars and perform such ancillary services as maintenance, repair, and storage. This case is taken ftom an article in Applied Statistics. Reprinted with permission. 151CASE FOUR The importance of freight yards to a railroad is illustrated by the fact that about one-third of its total operating costs may arise in these yards. In view of this, it is clearly important that proper control be maintained over the performance of the yards. However, this problem of main: taining adequate control is made difficult by their number and their distribution over a large area..(For example, in the railroad we studied, about 200 freight yards are scattered along approximately 12,000 miles of track.) It is virtually impossible for any team of managers to have each day a rea- sonably complete knowledge of what hap- pened at each yard. They must examine selected data concerning the performance of the yards during the day, and from these data they must somehow evaluate a yard’s performance. In evaluating performance, ‘one piece of information that is used is the costs. incurred in the yard during the day. At present, the data and techniques used by most railroads do not seem well suited for their purpose. Judging by the opinions of the railroad management with which we worked, their purpose is to detect those days when the costs at a yard are unusu- ally:high for the output produced and those seties of days when the costs are repeatedly higher than would be expected. Detection of either of these would result in an inquiry concerning the causes ofthe apparent deteri- oration of yard performance. In addition, the management is interested in detecting days when costs are unusually low or when they are repeatedly lower than would be expected. In this case there would also be an inquiry, but the intention would be to encourage the responsible factors rather than to remedy them, In this paper we discuss a control chart based on the relationship between cost and output that may be useful for these pur- poses. Before discussing the chart, it seems worthwhile to describe the measures of freight-yard output and costs that are used. The two most important services performed at a yard are switching and de- 152 livery; and it seems reasonable to use the number of “cuts” switched and the number of cars delivered during a particular period: as a measure of output. A “cut” is a group of cars that rolls as a unit on to the same... : classification track; it is often used as measure of switching output. The number of cars delivered includes both the cars ” delivered to sidings and other yards and’ those that are picked up. This output measure is not ideal, one difficulty being that it conceals considerable heteroge- neity. For example, two groups of cars. may be delivered but one may be hauled.a greater distance than the other. Some of this heterogeneity could be eliminated b3 further refinements in the output measure, but the extra complexity with regard to: data collection and computation migh result in a loss of feasibility. The costs used here include all money’ costs incurred in the yard except fixed + charges, repair costs, maintenance and stor- age costs, and vacation costs. Only money.” costs are included; the costs that may be.” imputed to car delay are not taken into account. Fixed charges are excluded, but some of the included costs are essentially. fixed in the very short run, THE CONTROL CHART ‘The control chart contains the deviation 6 actual cost from the cost that would be ex: pected on the basis of the average relation ship between cost and output. ‘These de ations are used to detect days when costs. are suspiciously high or low. The model. that underlies the chart is as follows: for a particular yard, the expected cost on the’. i'th day (C)) is assumed to be a linear function of the number of cuts switched on the i’th day (S;) and the number of cars = delivered on the i’th day (D,). * When the railroad management refer to unusually. high or low costs, it seems clear” that they mean costs that are unusual if the cost-output relationship and effects of «: ' numerous small disturbances remain at their previous, satisfactory levels. That is, they are interested in detecting those C; that are unusually high or low if the average jrelationship between cost and output is unchanged. Similarly, when they refer to a sequence of days when costs are higher or lower than would be expected, it seems clear that they mean a run of the C; that is unlikely if this relationship is unchanged. If the model is adequate and if the aver- age relationship between cost and output is known, it is a simple matter to set up a control chart that will aid the manage- ment. Each day, the deviation of actual cost from the cost that would be expected on the basis of this relationship can be plotted on a chart that has two sets of con- trol limits. The outer control limits can be set so that, if this relationship remains the same, the probability that a point lies out- side them is small; The inner control firnits can be set so that, if this relationship re- mains the same, the probability that two consecutive points lie outside them (in one direction) is small, When a point lies out- side the outer limits or a pair of points lies outside the inner limits, there is evidence that the relationship may have changed and that an inquiry should be made, SETTING UP THE CHART ‘A control chart was set up at a freight yard located at Toledo, Ohio. This yard consti- tutes one of the largest and most impor- tant links in the railroad we studied. The chief types of freight that pass through the yard are livestock, perishables, coal, and automobiles. Table 1 shows the number of cars switched, the number of cuts switched, the number of cars delivered, the number of crews employed, the number of engine hours used, and the costs at the yard, for a sample one-week period. The first step-in setting up the chart was to gather historical data concerning cost and output. Data similar to those in Table 1 were collected for sixty-one days, and the average relationship between cost and output was estimated. The resulting relationship was C,=4,914 + 0.425; + 2.44D; aw ‘The second step was to test some of the assumptions underlying the chart, Some of these tests are quite similar to those used in quality control to determine if the process is “in control.” Taken together, the results of these tests did not cast any great sus- TABLE 1 . Output, Cost, and Employment, Freight Yard, Toledo, 7 Days* ITEM FRI-SAT. SUN. MON. = TUES. WED. THURS. Number of cuts switched 869 792 762 586 669 732 © 659 Number of cars switched 2534 2303. «2521 «1849 «2090 2114 1979 Number of cars delivered* 1015 1003 820. 548-877, 706 1038 Number of crews used. 45 45 40 38 46 46 46 Number of engine hours 372 369 329 309 385 381 386 Money costs ($) 7523 7464 6932 6550 7606 7757 7701 *Taken from records of cooperating railroad tincludes number of cars picked up, 153°,‘CASE FOUR picion on the assumptions underlying the chart. Indeed, the results seemed to be quite compatible with these assumptions. The third step was to draw the inner and outer control limits on the chart. The outer control limits were set at $804, and the inner control limits were set at + $410, ‘These limits (designated by ICL and OCL) are included in Figure 1. If there were no errors in the assumptions, the probability would be 0.05 that a point would lie out- side the outer limits if the relationship remained fixed. Similarly, the probability would be about 0.03 that two consecutive points would lie outside the-same inner control limit. After setting the control limits, an attempt was made to determine if any assignable cause could be found for the days FIGURE 1 Deviation of Actual Cost from Expected Cost Based on Average Relationship © Between Cost and Output: Freight Yard, 61 Days Source: Records of cooperating railroad. 154 that were “out of control.” None could be found, and it was assumed that they were due to “chance.” The number of such days was almost precisely what one would expect on a chance basis. PERFORMANCE OF THE CHART This section describes the performance of. the chart during a six-week period that was several months subsequent to the time when the chart was set up. The results apply to the» freight yard described above. On each day. during the period data were collected con- cerning the money costs (C), the number’ of cuts switched (S), and the number of cars: delivered (D) on the previous day. Thert the deviation of actual cost from expected DayDeviation ($) ————r FIGURE 2 Control Chart for Costs: Freight Yard, 42 Days Source: Records of cooperating railroad. cost based on the average relationship in equation (1) was computed and plotted on the chart.’ The deviations that were plotted are shown in Figure 2. During the six-week period, four days seemed to be out of control, and in every case there seemed to be an assignable cause. One of these days was Labor Day. The exceptionally high costs on Labor Day can be attributed to the punitive wage-rates that were paid because it was a holiday. On the other days that were out of control (all of them Sundays) the exceptionally low costs can be attributed in part to the fol- Sowing circumstances: (1) Cars delivered to other yards constituted a large propor- ~ tion of all cars delivered, and since such cars are relatively easy to deliver, costs were depressed. (2) More efficient methods were used to handie incoming cars. (34Some work ordinarily performed by the yard was done by another yard; hence costs were reduced somewhat. ‘The basic data were’ collected by rail- road employees and the points on the chart were computed by officials of the railroad. From their evaluation of the performance of the yard it appeared that the chart pro- vided a reasonably faithful picture of the level of performance. Moreover, the chart stimulated some inquiries that indicated: where improvements in yard performance might be made. 4 Actually, the relationship was recomputed as mote and more data became available. 155,1. Do managers often find it difficult to minimize costs? If so, why? 2. Can control charts of the sort de- scribed in this case help managers to minimize costs? If so, how? 3. Is equation 1 a short-run or long-run cost function? Why? 156 . What is the marginal cost of delivering © .. Does the average cost per cut switched. . In what ways can these estimates of acar? exceed the marginal cost of switching acut? marginal and average cost be useful to railroad managers? Explain.
You might also like
Controlling
PDF
No ratings yet
Controlling
80 pages
Transportation Problem
PDF
100% (1)
Transportation Problem
53 pages
Chapter 1-5 PDF
PDF
100% (1)
Chapter 1-5 PDF
180 pages
Managerial Economics Chapter 5 Presentation
PDF
0% (1)
Managerial Economics Chapter 5 Presentation
27 pages
Lecture 2 - Introduction To Management
PDF
No ratings yet
Lecture 2 - Introduction To Management
52 pages
Functional Relationship: Total, Average and Marginal
PDF
No ratings yet
Functional Relationship: Total, Average and Marginal
21 pages
Introduction To Introduction To Econometrics Econometrics Econometrics Econometrics (ECON 352) (ECON 352)
PDF
100% (2)
Introduction To Introduction To Econometrics Econometrics Econometrics Econometrics (ECON 352) (ECON 352)
12 pages
Chapter 4
PDF
No ratings yet
Chapter 4
26 pages
Managerial Accounting - Mid Term Exam PDF
PDF
No ratings yet
Managerial Accounting - Mid Term Exam PDF
4 pages
Chap 6 Competitie Dynamics
PDF
100% (1)
Chap 6 Competitie Dynamics
43 pages
Internal Sources of Finance
PDF
No ratings yet
Internal Sources of Finance
10 pages
Optimal Decisions Using Marginal Analysis
PDF
No ratings yet
Optimal Decisions Using Marginal Analysis
9 pages
Economics For Managers GTU MBA Sem 1 Chapter 13
PDF
No ratings yet
Economics For Managers GTU MBA Sem 1 Chapter 13
41 pages
Mid Sem 1sem Exam Paper Oct2015
PDF
100% (1)
Mid Sem 1sem Exam Paper Oct2015
26 pages
Location Working 5
PDF
No ratings yet
Location Working 5
63 pages
Chapter 1 An Overview of Financial Mangement
PDF
No ratings yet
Chapter 1 An Overview of Financial Mangement
47 pages
PTE Mikro - 6 - Production and Business Org
PDF
100% (1)
PTE Mikro - 6 - Production and Business Org
23 pages
IE 113 Unit 9
PDF
No ratings yet
IE 113 Unit 9
40 pages
Globalization of Indian Automobile Industry
PDF
100% (2)
Globalization of Indian Automobile Industry
25 pages
CIMA E1 - OM - Chapter - 6
PDF
No ratings yet
CIMA E1 - OM - Chapter - 6
50 pages
Topic 9 - Multidimensional Scaling, Conjoint Analysis
PDF
No ratings yet
Topic 9 - Multidimensional Scaling, Conjoint Analysis
46 pages
Ens192 3.2 Controlling
PDF
No ratings yet
Ens192 3.2 Controlling
62 pages
College Project
PDF
100% (1)
College Project
14 pages
SCM 302 Ratcliffe - 04 - Forecasting
PDF
No ratings yet
SCM 302 Ratcliffe - 04 - Forecasting
63 pages
Case Study 3 Railroad - Answers
PDF
100% (1)
Case Study 3 Railroad - Answers
7 pages
Case Study of Managerial Economics
PDF
No ratings yet
Case Study of Managerial Economics
10 pages
Impact Curve AND Experience Curve
PDF
No ratings yet
Impact Curve AND Experience Curve
16 pages
Gemini Electronics Inc: Sfad Case#01
PDF
No ratings yet
Gemini Electronics Inc: Sfad Case#01
18 pages
N. Gregory Mankiw: Macroeconomics
PDF
No ratings yet
N. Gregory Mankiw: Macroeconomics
62 pages
Business Economics Chapter 2 - Demand Analysis
PDF
No ratings yet
Business Economics Chapter 2 - Demand Analysis
44 pages
Case Study 2 - How HP Used Tactics of The Japanese To Beat Them at Their Game
PDF
100% (1)
Case Study 2 - How HP Used Tactics of The Japanese To Beat Them at Their Game
6 pages
Economics For Managers GTU MBA Sem 1 Chapter 13
PDF
No ratings yet
Economics For Managers GTU MBA Sem 1 Chapter 13
41 pages
Lab #2 Chapter 2 - The Economic Problem
PDF
100% (1)
Lab #2 Chapter 2 - The Economic Problem
14 pages
Statistics SPSS Project
PDF
No ratings yet
Statistics SPSS Project
12 pages
Demand Analysis
PDF
No ratings yet
Demand Analysis
18 pages
Managerial Accounting Assign C1 062112na
PDF
No ratings yet
Managerial Accounting Assign C1 062112na
17 pages
Assignment Economics
PDF
100% (1)
Assignment Economics
4 pages
Case 7
PDF
100% (2)
Case 7
2 pages
Case Study 1 - Is Coca-Cola The Perfect Business
PDF
100% (1)
Case Study 1 - Is Coca-Cola The Perfect Business
5 pages
Synd - 7 Business Eco EMBA 59A Decision Time at The Aromatic Coffee Co
PDF
No ratings yet
Synd - 7 Business Eco EMBA 59A Decision Time at The Aromatic Coffee Co
18 pages
MN 5227 Business Economics: Group Assignment
PDF
No ratings yet
MN 5227 Business Economics: Group Assignment
24 pages
Our Assignment
PDF
No ratings yet
Our Assignment
31 pages
Mefa Unit 2
PDF
No ratings yet
Mefa Unit 2
28 pages
Assumptions of Kinked Demand Curve
PDF
No ratings yet
Assumptions of Kinked Demand Curve
2 pages
Assignment 8
PDF
No ratings yet
Assignment 8
3 pages
Economics For Managers GTU MBA Sem 1 Chapter 16
PDF
No ratings yet
Economics For Managers GTU MBA Sem 1 Chapter 16
24 pages
Capacity: 4 Credit Units Semester: 1 Course Description: Managerial Economics
PDF
No ratings yet
Capacity: 4 Credit Units Semester: 1 Course Description: Managerial Economics
4 pages
Lecture 6 - Employee Satisfaction and Motivation
PDF
No ratings yet
Lecture 6 - Employee Satisfaction and Motivation
22 pages
NTPC Financial Statement Analysis
PDF
No ratings yet
NTPC Financial Statement Analysis
19 pages
2000 AE Coelli - Technical Efficiency of European Railways A Distance Function Approach
PDF
No ratings yet
2000 AE Coelli - Technical Efficiency of European Railways A Distance Function Approach
11 pages
Time Value of Money
PDF
No ratings yet
Time Value of Money
28 pages
Case Study 1 Amcott
PDF
100% (1)
Case Study 1 Amcott
1 page
Case Study Rail Road 2
PDF
No ratings yet
Case Study Rail Road 2
6 pages
Quantification of Dell S Competitive Advantage
PDF
50% (2)
Quantification of Dell S Competitive Advantage
3 pages
Lavan Sathananthan - Individual Assignment - MN 5227 - Business Economics
PDF
No ratings yet
Lavan Sathananthan - Individual Assignment - MN 5227 - Business Economics
11 pages
Mba ZC416
PDF
No ratings yet
Mba ZC416
12 pages
Production Function: Short-Run and Long-Run Production Theory
PDF
No ratings yet
Production Function: Short-Run and Long-Run Production Theory
13 pages
Economies of Scale & Diseconomies of Scale
PDF
No ratings yet
Economies of Scale & Diseconomies of Scale
17 pages
Comparative Characteristics of PERT and CPM
PDF
No ratings yet
Comparative Characteristics of PERT and CPM
27 pages
Indian Railways Industry-Report
PDF
No ratings yet
Indian Railways Industry-Report
8 pages
The Marketing and Accounting Departments of Pharmed Caplets, Inc. Have Provided You With The Following
PDF
No ratings yet
The Marketing and Accounting Departments of Pharmed Caplets, Inc. Have Provided You With The Following
6 pages
Economics For Managerial Decision Making
PDF
No ratings yet
Economics For Managerial Decision Making
3 pages
PGDM (2017-19) Term-II: End Term Examination - Operations Management - I
PDF
No ratings yet
PGDM (2017-19) Term-II: End Term Examination - Operations Management - I
6 pages
What Is Cost Control
PDF
No ratings yet
What Is Cost Control
9 pages
Cost Output Relationship in The Short Run
PDF
No ratings yet
Cost Output Relationship in The Short Run
5 pages
MBA PT - 2010-2013 - HP Case Study - Sidharth Jaiswal (Roll No. 30)
PDF
No ratings yet
MBA PT - 2010-2013 - HP Case Study - Sidharth Jaiswal (Roll No. 30)
3 pages
Case 3-Tanaka Komuten-Questions
PDF
No ratings yet
Case 3-Tanaka Komuten-Questions
1 page
Pillsbury
PDF
No ratings yet
Pillsbury
13 pages