Cadangan Pembaikan Cerun Dan Kerja-Kerja Berkaitan Di SK Kauluan Ranau, Sabah
Cadangan Pembaikan Cerun Dan Kerja-Kerja Berkaitan Di SK Kauluan Ranau, Sabah
Cadangan Pembaikan Cerun Dan Kerja-Kerja Berkaitan Di SK Kauluan Ranau, Sabah
Project Name:
CADANGAN PEMBAIKAN CERUN DAN KERJA-KERJA
BERKAITAN DI SK KAULUAN RANAU, SABAH
Document Title:
METHOD STATEMENT
FOR
WALER BEAM
Submission Record
15/09/2020
Reviewed by CHARNOLD BIN MIOL Date
TABLE OF CONTENTS
Items
Title Page
No.
1.0 INTRODUCTION 3
2.0 OBJECTIVE 3
3.0 WORKS METHODOLOGY 3
4.0 HEALTH, SAFETY AND ENVIRONMENT REQUIREMENT 5
5.0 QUALITY ASSURANCE & CONTROL REQUIREMENT 5
6.0 PLANT, MACHINERY AND EQUIPMENT 6
7.0 MANPOWER – KEY PERSONNEL 6
8.0 MATERIALS 6
9.0 REFERENCES 7
10.0 REQUEST FOR INSPECTION 7
11.0 ANNEXURES 7
Method Statement for Waler Beam
1.0 INTRODUCTION
Under the scope of work for Cadangan pembaikan cerun dan kerja-kerja berkaitan di
SK Kauluan Horizontal Drains and its associated works need to be carried out.
2.0 OBJECTIVE
The Horizontal Drain work is to provide proper stabilization in slope works wherever
necessary and to be carried out shall be in accordance with the requirements of the
specification and drawings.
a) The Engineer on site shall determine the location of the Horizontal drains.
a) Temporary Staging:
The types of drilling machine used shall be dependent on the slope profile, height, spacing and
the availability of working pltafrom. Temporary staging shall be erected along the slope side so as
to enable drilling of the soil by small portable drilling machine and also as a platform for workers.
Temporary staging shall be erected from bracing enhances rigidity of the whole frame and
firmness of the ground on which the supports stand must be ensured.
b) Drilling:
Generally, minimum 75mm nominal diameter borehole is drilled at the required location with either rotary or rotary
percussive drilling machines to the required depth and inclinations. Temporary casings are to be used if necessary to
stabilize the boreholes. Temporary casings to be removed after installations of horizontal drains.
The quality assurance & control requirements shall be in accordance with this method
statement. In carrying this works the following documents & forms and procedures shall
be implemented before commencement of work;
1 Soil nail machine Rotary machine with down hole hammer with bit or
drag bit depending on soil formation.
2 Air compressor 100 psi and 300 to 700 CFM
8.0 MA TERIAL
i) PVC pipe with 75mm x 6mm slots at 200mm centers (staggered) on the upper half of
the horizontal pipe.
ii) Non-woven geo-textile.
Method Statement for Waler Beam
9.0 REFERENCES
The work is carried out in accordance to the following: -
(i) Bill of Quantities.
(ii) Approved Project Construction Drawing.
11.0 ANNEXES
(i) Request for Inspection (RFI) Form
(ii) Checklist Form