Method Statement for Waler Beam

Cadangan pembaikan cerun dan kerja-kerja


berkaitan di SK Kauluan Ranau, Sabah
MS/2019 - 01 Rev.: 00 Page 1 of 8

Project Name:
CADANGAN PEMBAIKAN CERUN DAN KERJA-KERJA
BERKAITAN DI SK KAULUAN RANAU, SABAH

Document Title:
METHOD STATEMENT
FOR
WALER BEAM

Submission Record

Revision Date Revision Information

00 15/09/2020 First issue.

Prepared by Date 15/09/2020


ASDIA FATHIYA SIMUDAH

15/09/2020
Reviewed by CHARNOLD BIN MIOL Date

Approved by KHAMIRUL ALMY BIN AMINUDDIN Date 15/09/2020

APPROVED APPROVED WITH COMMENTS REJECTED,


Proceed with the works Proceed with the works and to comply (pls. specify): REVISE AND
RESUBMIT

Note: Please tick the appropriate box


Method Statement for Waler Beam

Cadangan pembaikan cerun dan kerja-kerja


berkaitan di SK Kauluan Ranau, Sabah
MS/2019 - 01 Rev.: 00 Page 2 of 8

TABLE OF CONTENTS

Items
Title Page
No.
1.0 INTRODUCTION 3
2.0 OBJECTIVE 3
3.0 WORKS METHODOLOGY 3
4.0 HEALTH, SAFETY AND ENVIRONMENT REQUIREMENT 5
5.0 QUALITY ASSURANCE & CONTROL REQUIREMENT 5
6.0 PLANT, MACHINERY AND EQUIPMENT 6
7.0 MANPOWER – KEY PERSONNEL 6
8.0 MATERIALS 6
9.0 REFERENCES 7
10.0 REQUEST FOR INSPECTION 7
11.0 ANNEXURES 7
Method Statement for Waler Beam

Cadangan pembaikan cerun dan kerja-kerja MS/2019 - 01 Rev.: 00 Page 3 of 8


berkaitan di SK Kauluan Ranau, Sabah

1.0 INTRODUCTION

Under the scope of work for Cadangan pembaikan cerun dan kerja-kerja berkaitan di
SK Kauluan Horizontal Drains and its associated works need to be carried out.

2.0 OBJECTIVE

The Horizontal Drain work is to provide proper stabilization in slope works wherever
necessary and to be carried out shall be in accordance with the requirements of the
specification and drawings.

3.0 WORKS METHODOLOGY

3.1 Preparation Stage

a) The Engineer on site shall determine the location of the Horizontal drains.

b) The installation of horizontal drain, including drilling, installation and stressing


shall be carried out in accordance with the specifications and drawings.

3.2 Construction Procedure

a) Temporary Staging:
 The types of drilling machine used shall be dependent on the slope profile, height, spacing and
the availability of working pltafrom. Temporary staging shall be erected along the slope side so as
to enable drilling of the soil by small portable drilling machine and also as a platform for workers.
 Temporary staging shall be erected from bracing enhances rigidity of the whole frame and
firmness of the ground on which the supports stand must be ensured.

b) Drilling:
 Generally, minimum 75mm nominal diameter borehole is drilled at the required location with either rotary or rotary
percussive drilling machines to the required depth and inclinations. Temporary casings are to be used if necessary to
stabilize the boreholes. Temporary casings to be removed after installations of horizontal drains.

c) Installation of Horizontal Drain:


 The Horizontal drain shall be spaced at 4.0 m center to center or as directed by the S.O.
 The locations of horizontal drain shall be determined by the engineer on site if the exact locations of ground water
seepage is known.
 If the locations of groundwater seepage area is known, horizontal drain shall be added horizontally both side until
there is no water coming out from the last one installed.
 The PVC Pipe shall be wrapped with non-woven geo textile approved by the engineer.
 Th e length of the horizontal drain shall be as shown in the drawing or as determined by the engineer.
 A 75mm wide “u” – channel drain shall be constructed to chute.
Method Statement for Waler Beam

Cadangan pembaikan cerun dan kerja-kerja


berkaitan di SK Kauluan Ranau, Sabah MS/2019 - 01 Rev.: 00 Page 5 of 8

4.0 HEALTH & SAFETY REQUIREMENT

4.1 Health & Safety Requirement

4.1.1 All personnel involve with the event shall have;


a) Compulsory to provide and wearing Personal Protective Equipment
(PPE) at all times during commencement of works at site;

(i) Safety vest.


(ii) Safety shoes.
(iii) Safety helmet (if required).

4.1.2 Housekeeping need to maintain at all time.

5.0 QUALITY ASSURANCE & CONTROL REQUIREMENT

The quality assurance & control requirements shall be in accordance with this method
statement. In carrying this works the following documents & forms and procedures shall
be implemented before commencement of work;

(i) Request for Inspection (RFI) form.


(ii) Inspection Checklist.
Method Statement for Waler Beam

Cadangan pembaikan cerun dan kerja-kerja


berkaitan di SK Kauluan Ranau, Sabah MS/2019 - 01 Rev.: 00 Page 6 of 8
.

6.0 PLANT, MACHINERY AND EQUIPMENT


The equipment involved in the Micropiling work (but not limited to), according to type
and suitability: -

No Equipment / Plant / Tools Description

1 Soil nail machine Rotary machine with down hole hammer with bit or
drag bit depending on soil formation.
2 Air compressor 100 psi and 300 to 700 CFM

7.0 MANPOWER – KEY PERSONNEL


Typical manpower involved in Micropiling work (but not limited to) are as follows: -

Item Type of Manpower Job Function

1. Project Engineer Supervising work in progress at site

2 Site Supervisor Standing supervision at site

3 Competent Person Implementing site safety procedures

4 Machinery Operator Operating the soil nail machine

5 General Worker Carrying out works on the ground

6 Surveyor & Chainman Setting out of point, alignments and levels.

8.0 MA TERIAL
i) PVC pipe with 75mm x 6mm slots at 200mm centers (staggered) on the upper half of
the horizontal pipe.
ii) Non-woven geo-textile.
Method Statement for Waler Beam

Cadangan pembaikan cerun dan kerja-kerja


berkaitan di SK Kauluan Ranau, Sabah MS/2019 - 01 Rev.: 00 Page 7 of 8

9.0 REFERENCES
The work is carried out in accordance to the following: -
(i) Bill of Quantities.
(ii) Approved Project Construction Drawing.

10.0 REQUEST FOR INSPECTIONS


The Contractor shall submit the request for work inspection (RFI) form to the Supervising
Engineer, or his representative with all the relevant attachment, to allow inspection being
conducted before any subsequent work start.

11.0 ANNEXES
(i) Request for Inspection (RFI) Form
(ii) Checklist Form