Site Test Report

Project: Supply of Control Relay & Metering Panel


Including Installation, Testing & Commissioning
of 33kV GIS at Bindur Mor, Rajshahi Substation.

Contractor: Energypac Engineering Ltd. Relay Model P-632


Substation: Bindur Mor 33/11kV GIS Feeder/Circuit: Tr-01 Main Protection
Relay Manufaucterar Scheneider Electric Page: 1 of 3

Inspection Testing and Secondary Injection of Differential Protection Relay Type


P-632

FROM 33kV GIS POST CT TO 11kV GIS POST CT

1) - General data:
Relay secondary current IN: 5A 5A Built-in rated auxiliary voltage :(110-250)V AC/DC
Software Used: Easergy Studio Software Version: 651.00
CT ratio: HV: 400/5 A LV:1200 /5 A

2) - Configuration of protection functions:

Description Relay Description Enabled Disabled


Differential Protection DIFF
Restricted Earth Fault Protection-1 REF_1
Restricted Earth Fault Protection-2 REF_2
Definite-time overcurrent protection-1 DTOC1
Definite-time overcurrent protection-2 DTOC2
Inverse-time overcurrent protection-1 IDMT1
Inverse-time overcurrent protection-2 IDMT2
Thermal overload protection 1 THRM1
Time-voltage protection V<>
Over/ under frequency protection f<>
Overfluxing protection V/f
Measuring-circuit monitoring -1 MCM_1
Measuring-circuit monitoring -2 MCM_2
Circuit breaker failure protection - 1 CBF_1
Circuit breaker failure protection- 2 CBF_2
Limit value monitoring-1 LIM_1
Limit value monitoring-2 LIM_2

Tested By: Witness By: NWZPDC Representetive (BPDB)


Energypac Design-2 Chief Engr. XEN, Energy Audit
Signature:
Md. Mohsin, Senior Engineer,
T & C, EEL
Test Equipment: SMRT-410 Date: 22nd April 2017
Site Test Report

Project: Supply of Control Relay & Metering Panel


Including Installation, Testing & Commissioning
of 33kV GIS at Bindur Mor, Rajshahi Substation.

Contractor: Energypac Engineering Ltd. Relay Model P-632


Substation: Bindur Mor 33/11kV GIS Feeder/Circuit: Tr-01 Main Protection
Relay Manufaucterar Scheneider Electric Page: 2 of 3

3) - General inspection & testing:

S NO B-General inspection & testing: Checked


1 Installation & wiring correct to relevant drawings Yes
2 Relay case connected to local earth bar Yes
3 Measured value check Yes
4 Relay binary input and output checked Yes
5 Visual inspection of unit Yes
6 Fault recorder Yes

4) – Transformer Data:
Transformer Data Primary Winding Secondary Winding
Voltage Rating 33 kV 11 kV
Capacity – P 16/20MVA 16/20 MVA
Load Current – In 280/350 A 840/1050 A
CT Ratio (In) 400/5A 1200/5A
Percentage Impedance (Z%) 10.66 % 10.66 %

5) - Differential relay setting 1:


I diff > : I/ IN : 0.2I/InO t diff > delayed 0.0 s
I diff >> : I/ IN 7.5In/InO t diff >> delayed 0.0 s
I diff >>> : I/ IN 7.5In/InO t diff >>> delayed 0.0 s
2nd. Harmonic: 15% Slope 1: 30%
5th. Harmonic : 25% Base Point 2: 4
Vector Group:  Dyn11        Slope 2: 70%
CT Star Point HV: towards line: towards Object: CT Star Point LV: towards line: towards Object:

Tested By: Witness By: NWZPDC Representetive (BPDB)


Energypac Design-2 Chief Engr. XEN, Energy Audit
Signature:
Md. Mohsin, Senior Engineer,
T & C, EEL
Test Equipment: SMRT-410 Date: 22nd April 2017
Site Test Report

Project: Supply of Control Relay & Metering Panel


Including Installation, Testing & Commissioning
of 33kV GIS at Bindur Mor, Rajshahi Substation.

Contractor: Energypac Engineering Ltd. Relay Model P-632


Substation: Bindur Mor 33/11kV GIS Feeder/Circuit: Tr-01 Main Protection
Relay Manufaucterar Scheneider Electric Page: 3 of 3

6) Slope Test:

Slope 1: 30% Slope


Current injection from HT & LT both side
Injected phase RYB & ryb

Current Measured Current From Relay Calculated Slope


Injection Idiff1 Ibias1 Idiff2 Ibias2
HT side LT side Id1 Ib1 Id2 Ib2 ∆Id/∆Ib
5.396 3.343 0.473 1.002 --- ---
10.42 7.057 --- --- 0.783 2.083 29.9%

Slope 2: 70% Slope


Current injection from HT & LT both side
Injected phase RYB & ryb

Current Measured Current Calculated Slope


Injection Idiff1 Ibias1 Idiff2 Ibias2
HT side LT side Id1 Ib1 Id2 Ib2 ∆Id/∆Ib
20.47 14.48 1.396 4.076 --- ---
23.42 15.906 --- --- 1.747 4.578 =69.92%

Tested By: Witness By: NWZPDC Representetive (BPDB)


Energypac Design-2 Chief Engr. XEN, Energy Audit
Signature:
Md. Mohsin, Senior Engineer,
T & C, EEL
Test Equipment: SMRT-410 Date: 22nd April 2017