This document appears to be a work schedule for various construction projects overseen by Mr. Cho. It lists the names of site supervisors and the specific work each is responsible for, including finishing works on different floors, landscaping, plastering and more. Subcontractors are also listed along with the scope of works they will handle, such as waterproofing, roofing, drywall, flooring and other tasks. A surveyor and various foremen are identified along with their responsibilities for supporting survey works, scaffolding, masonry, tile works and more.
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0 ratings0% found this document useful (0 votes)
46 views1 page
CCM - Mr. Cho
This document appears to be a work schedule for various construction projects overseen by Mr. Cho. It lists the names of site supervisors and the specific work each is responsible for, including finishing works on different floors, landscaping, plastering and more. Subcontractors are also listed along with the scope of works they will handle, such as waterproofing, roofing, drywall, flooring and other tasks. A surveyor and various foremen are identified along with their responsibilities for supporting survey works, scaffolding, masonry, tile works and more.
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 1
CCM - MR.
CHO
AHMED RONEL
RAMA ZAFAR MOAMAR MASHKOOR JAMES
- 1F extension all finishing works - 1F orig. scope all finishing works - BF all finishing works - GF all finishing works - Landscaping works - 1F extension stone coping - External plaster (touch-up) - CEP finishing works (4 buildings) - Hyundai direct works - 1F plant rooms & medical gas rm - Glass balustrade (1.6 & full height) - 2F all works (inside & outside) - 3 nos. staircase Zone 4 5 6 - To follow ceramic tile repair works
MARVIN (SURVEYOR) MR. KIM (FOREMAN) SUBCON SCOPE OF WORKS
- All survey works to support James AL BAWAKIR - External & toilet waterproofing - External & internal survey works Tarsem (General foreman) DSP - Roofing, sst handrails, DRAGONI - All finishing works & 1F ext drywall & ceiling Delwar (Scaffolding foreman) FALCON - Cold room basement GCS - All screed works Habib (Mason foreman) IMAR - Vinyl, metal ceiling, blinds, corridor handrails JASCON - drywall, gyp ceiling & paint Nazim (External Civil foreman) LIVART - Doors, caseworks, LANDWORX - Landscaping works - All ceramic tile works MODERN - Floor epoxy paint - Basement wall painting works NORWOOD - Metal screen, metal doors - Control direct workers PAC - Spider, curtain wall, internal glazing - All temporary works QMEDIC - Bed head unit SING MARBLE - All stone works SHARQ - Patient lifts TONACO - Curtain track TADMUR - Roof waterproofing