Built-Up Rates Title/Project: Element/Trade/Work Category
Built-Up Rates Title/Project: Element/Trade/Work Category
OUTPUT (RM)
DATA MANIPULATION
Checklist :
1. Monthly Debris Clearance
i) Loading of Debris
ii) Removal of Debris
2. Final Clearance
3. Overhead
4. Profits
ASSUMPTION DATA :
Period of clearance work = 1 day/month
Period of final clearance work = 3 days
A. MONTHLY CLEARANCE
i) Debris clearance 3 unskilled labour = RM 70.00 x 3 x 16 months 3,360.00
B. FINAL CLEARANCE
10 unskilled labours x 3 days x RM70.00 2,100.00
10,260.00
C. PROFIT 5% 513.00
M2 0.00
OUTPUT (RM)
DATA MANIPULATION
Checklist :
1.Material
2.Plants
3.Labours
4. Overhead
5. Profits
MATERIAL
Supply and install
0 RM -
add. wastage 5% -
PLANT
Total plant
LABOUR
TOTAL COST :
TOTAL COST :