Unit Three Sewage and Sewerage Systems
Unit Three Sewage and Sewerage Systems
Unit Three Sewage and Sewerage Systems
e) The water loss, through leakage in water distribution system and house connections,
does not reach consumers and hence, not appear as sewage. Also certain amount of
water is used for such purposes, e.g. boiler feed water, water sprinkled over the roads,
streets, lawns, and gardens, water consumed in industrial product, water used in air
coolers, etc. may not reach the sewers
Net quantity of sewage = Accounted quantity of water supplied from the waterworks +
Addition due to unaccounted private water supplies + Addition due to infiltration –
Subtraction due to water losses - Subtraction due to water not entering the sewerage
system
Manning’s Formula
This is most commonly used for design of sewers. The velocity of flow through sewers can be
determined using Manning’s formula as below:
Where,
V = velocity of flow in the sewer, m/sec
R = Hydraulic mean depth of flow, m = A/P
A = Cross section area of flow, m2
P = Wetted perimeter, m
n = Rugosity coefficient, depends upon the type of the channel surface i.e., material and
lies between 0.011 to 0.015. For brick sewer it could be 0.017 and 0.03 for stoneware.
S= Hydraulic gradient, equal to invert slope for uniform flows
Design of Sanitary Sewers
The sewers are designed to flow under gravity with 0.5 to
0.8 full at designed discharge, i.e. at the maximum
estimated discharge when a velocity of about 1 -1.6 m/s
is desirable
It is necessary that a minimum velocity (i.e., about 1/3 of
the average discharge) of about 0.45 m/s and an average
velocity of about 0.9 m/sec develops in sewers too.
However even if the minimum velocity ensues in the
sewer once a day the sewer gets flushed and remains
clean.
Example:
= 1.479 m/s
Note that the design and analysis becomes complex when sewer
is running part full for which proportional discharge curves are
used.
Hydraulic Elements Chart
Example
• Calculate the velocity of flow and corresponding discharge in a sewer of
circular section having diameter equal to 1 m, laid at a slope of 1 in 500.
Sewer runs at a depth of 0.6 depth. Use Manning’s n = 0.012
= 1.162 cumecs
Average sewage flow per day = (100000) (200) (0.8)/(24x3600x1000) = 0.185 cumecs.
Peak flow = (3) (0.185) = 0.555 cumecs
This is q at 0.7 depth; Now from graph for d/D = 0.7, q/Q is 0.85 and v/V is 1.12
So Q = 0.555/0.85 = 0.6536
Major factors affecting the quantity of storm water flow are as below:
i. Area of the catchment
ii. Slope and shape of the catchment area
iii. Porosity of the soil
vi. Intensity and duration of rainfall
Measurement of Rainfall
The rainfall intensity could be measured by using rain gauges and recording the
amount of rain falling in unit time. The rainfall intensity is usually expressed as
mm/hour or cm/hour. The rain gauges used can be manual recording type or
automatic recording rain gauges.
Estimation of Quantity of Storm
Water
Rational Method
The quantity of storm water is considered as function of intensity of
rainfall, duration and coefficient of runoff.
Time of Concentration: The period after which the entire catchment
area will start contributing to the runoff is called as the time of
concentration.
The rainfall with duration lesser than the time of concentration will
not produce maximum discharge.
The runoff may not be maximum, even when the duration of the
rain is more than the time of concentration. This is because in such
case the intensity of rain reduces with the increase in its duration.
The runoff will be maximum, when the duration of rainfall is equal
to the time of concentration and is called as critical rainfall
duration.
Estimation of Quantity of Storm
Water Contd.
The time of concentration is equal to sum of inlet time and time of travel.
Inlet Time: The time required for the rain in falling on the most remote
point of the tributary area to flow across the ground surface along the
natural drains or gutters up to inlet of sewer is called inlet time.
Time of Travel: The time required by the water to flow in the drain
channel from the mouth to the point under consideration or the point
of concentration is called as time of travel.
Q = 0.278 C.I.A
Where, Q is m3/sec; I is mm/hour, and A is area in square kilometer
Example
Determine designed discharge for a combined system serving population of 50000 with rate
of water supply of 135 LPCD. The catchment area is 100 hectares and the average coefficient
of runoff is 0.60. The time of concentration for the design rainfall is 30 min and the relation
between intensity of rainfall and duration is I = 1000/(t + 20).
Solution
Estimation of sewage quantity
Considering 80% of the water supplied will result in wastewater generation,
the quantity of sanitary sewage = 50000 x 135 x 0.80/1000 = 5400 m3/day = 0.0625 m3/sec
Considering peak factor of 2.5, the design discharge for sanitary sewage = 0.0625 x 2.5
= 0.156 m3/sec
Calculate the runoff coefficient and quantity of storm water runoff, if intensity of rainfall is
30 mm/h for rain with duration equal to time of concentration. If population density in the
area is 350 persons per hectare and rate of water supply is 200 LPCD, calculate design
discharge for separate systems and combined system.
Solution
Estimation of sanitary sewage quantity
Considering 80% of the water supplied will result in wastewater generation,
the quantity of sanitary sewage = 350 x 300 x 200 x 0.80/1000 = 16800 m3/day =
0.194 m3/sec
Considering peak factor of 2.5, the design discharge for sanitary sewage = 0.194 x
2.5
= 0.486 m3/sec
R = A/P = 1.314 m
Example
• A rectangular river channel 4.6 m wide carries has a bed slope of 1:400
and a Manning’s n value of 0.040 s/m1/3. Calculate the depth of flow, D,
that corresponds to a discharge of 2.83 m3/s.